Procurement Schedule

Updated August 6, 2015
  • Issue Request for LOIs: January 8, 2015
  • Issue RFQ: February 26, 2015
  • Project briefing meetings: March 16 - March 27, 2015
  • Deadline for industry inquiries to RFQ: March 31, 2015
  • CDOT responses to industry RFQ inquiries: April 3, 2015
  • Final RFQ addendum issued: April 9, 2015
  • SOQ due date: April 23, 2015
  • Notify short-listed submitters: June 4, 2015
  • Debrief RFQ submitters: by request and appointment
  • Issue Draft RFP: August 31, 2015
  • Final RFP: November 30, 2015
  • Design-Build Team Selection: April 2016
  • Construction: Summer 2016