Business Center

Bid Tabs - 2018

2018 Bid Tabs by project name

Letting Date Project Description Low Bidder Bid Tabulation
Aug 23

BR 025A-028 (20407) ~ I25 Bridge Replacements over Butte Creek at Exit 59 - N-17-BN & N-17-S in Huerfano county.

TLM Constructors, Inc. Bid Tab
Jan 25

BR 0252-444 (20809) ~ On I-25 at Rockrimmon Boulevard from MP 146.727 to MP 148.874, work consists of detour pavement and removal, concrete milling, variable depth asphalt HMA overlay, bridge repairs, remove and replace bridge joints, removal and installation of guardrails, curb and gutter removal and replacement, modify/adjust structures and manholes, traffic control, signing and striping, erosion control, seeding and mulching in El Paso County.

Ralph L. Wadsworth Construction Company LLC Bid Tab
Oct 11

BR 1131-006 (20862) ~ This project consists of removing a timber structure, A-24-L, and replacing with a double cell precast CBC, A-24-AQ. There will be an on-site shoofly detour constructed to the east side of the structure in order to detour traffic around the structure work. The major components to the work will be detour construction, structure removal, dewatering and preparing the subbase for CBC placement, rip-rap lining the bottom of the CBC, construction of wingwalls, flattening roadway slopes, and rebuilding the roadway over this section of highway. This project is located in Logan County

TRICON 2, LLC Bid Tab
Sep 6

BR R200-228 (21020) ~ Bridge M-22-Z replacement on CO 10 east of La Junta. Work to include earthwork, bridge demolition and replacement, guardrail installation, and other items as included in the plans.  In Otero county

TLM Constructors Inc. Bid Tab
Nov 15

C 5502-098 (22086) ~ This project is in La Plata county on US 550 MP 21.5-24.0 US 160 MP 82.5-83.4.  Consists of installation of curb ramps at 19 locations within the city limits of Durango. 

Western Gravel Constructors, LLC Bid Tab
Nov 15

C 060A-023 (21876) ~ This project in Weld county entails the widening at SH60 and WCR40 to improve the safety of the corridor. Southbound SH60 will add a deceleration right turn lane and bubble left turn lane. Northbound SH60 will add a left turn lane. The existing CBC minor structure in Farmer's Independent Ditch will be extended on the existing channel alignment. The project will be completed with a 2 inch HMA overlay.

Mountain Constructors, Inc. Bid Tab
Feb 1

C 0703-440 (21686) ~ At US 40 near Berthoud Pass, I-70 near MM 213, and around the EJM Tunnel portal road, work consists of installation of avalanche exploder devices/systems and associated control shelters in Grand and Summit Counties.

Geovert Bid Tab
Aug 9

C 0853-109 (22441) ~ Upgrade of ADA ramps in various locations on US34 in Greeley and Weld county. 

Can Do Concrete Bid Tab
Dec 6

C 2873-192 (22442) ~ This project is in Larimer county.  US 34 and US 287 in Loveland ADA curb ramp repair and replacement to prowag standards.  

Can Do Concrete Construction Inc. Bid Tab
Nov 29

CR 500-198 (22120R) ~ Region 5 guardrail replacement in La Plata, Montezuma, and Saguache counties.

Cruz Construction Bid Tab
Mar 1

ER 007A-026 (21088) ~ On SH 7 at various locations, work consists of permanent flood repairs, shoulder widening, and ADA curb ramps, 2” mill and overlay from MP 0.0 to MP 12.0 and shoulder widening to accommodate bike lanes from MP 6.4 to MP 10.6, and culvert repairs in Boulder and Larimer Counties.

Flatiron Constructors Bid Tab
Mar 8

ER 144A-002 (20254) ~ On SH 144 from MP 5.08 to MP 6.65, work consists reconstructing 1.6 miles of two lane highway using Aggregate Base Course Class 6 with HMA and includes moving the alignment of the roadway away from the South Platte River in Morgan County.

Castle Rock Construction Co. Bid Tab
Jan 11

ER 0252-466 (22311) ~ On I-25 at MP 155, work consists of restoration of the Monument Creek Branch to include concrete box culvert and winged wall repairs, construction of concrete drop structures, channel armoring with boulders, riprap, grouted riprap, installation of embankment material, seeding, and Prebbles Mouse appurtenances in El Paso County.

SEMA Construction Inc. Bid Tab
Dec 13 ER 0252-467 (22312) ~ The South Douglas Creek box culvert (Structure Number 025A145120BL, MP 145.12) is a 400 feet long, 14 feet wide, 12 feet high concrete box culvert (CBC) conveying flows under all lanes of I-25. The structure was constructed in 1959. This site is needing repairs as a result of flood damage from 2013. The project is located in El Paso county.

American Civil Constructors, LLC Bid Tab
Nov 15

ER 052A-039 (20262) ~ This project is located in Boulder county. CO 170 MP 1.2 CBC Eldorado Canyon.

Concrete Works of Colorado 

Bid Tab
Jun 28 ER  055A-001 (21289) Near CO 55 at the South Platte River, permanent flood repairs in Logan County. Hamilton Construction Bid Tab
Jan 4 ER 0342-058 (20180) ~ On US 34D and 18th Street from MP 11.65 to MP 13.62 and MP 14.09 to MP 14.50, work consists of box culvert extensions, asphalt removal, asphalt overlay and pavement, shouldering, concrete pavement, hydro demolition, bridge deck repair, girder and corbel repair, bridge rail replacement, riprap installation, pavement marking, traffic control in Weld County. Hamilton Construction Co. Bid Tab
Nov 29 ER 0361-118 (20744) ~ This project consists of Re-wetting of Muggins gulch on US 36 from MM 7 to MM 8 in Larimer county.  It will include a concrete box culvert, a tunnel, specialized river and environmental considerations, rock blasting to facilitate a rockfall ditch, paving and rockfall mitigation in Larimer County. Rejected N/A
Jan 25

ER 1151-034 (21352) ~ On CO 115 at MP 34.7 and MP 40.5, and on US 24 at MP 294.2, work consists of permanent flood repairs of damaged curb, installation of trench drains with slope regrade, and replace damaged section of Montessori wall with grouted boulder wall in El Paso County.

American West Construction LLC Bid Tab
Nov 29

ER R400-329 (20285) ~ This project located in Larimer county on US 287 & SH 14 north of Fort Collins.  The work consists of placing rip rap along the highway embankment at various locations, temporary river channel diversion and reconstruction and cross culvert installations.

Duran Excavating, Inc. Bid Tab
Aug 9

ER M850-027 (22792) ~ Emergency box culvert repair in Manitou Springs in El Paso County.

Wildcat Construction Co. Bid Tab
Apr 12

FBR 069A-034 (22320) ~ Bridge replacement SH69 (M-6-P) in Huerfano County.

Lawrence Construction Company Bid Tab
Sep 20

FBR 071A-018 (21012) ~ Arkansas River bridge replacement project on SH 71. Work to include installation of construction access, grading, removal of existing structure, installation of new structure, earthwork, construction signing, striping, guardrail installation, and other items as indicated in the plans and specs. This project is located in Crowley and Otero counties.

Lobato Construction, LLC  Bid Tab
Jul 12

FBR 060A-022 (21146) ~ This project entails the demolition and replacement of structure C-17-B with structure C-17-FT; a 7 span, 790 foot bridge, 43 foot out to out with 1'-6" curbs, carrying SH60 over the South Platte river . This will require a new horizontal alignment westward of the existing structure and a 28 foot extension of culvert C-17-FM on the Southwest side of the project to accommodate the new roadway alignment and the realignment of WCR46. This project will include HMA, Bridge removal and replacement, Embankment Material (CIP), Erosion Control, Fencing, ABC, Signing, Striping, Traffic Control, Pipes, and culverts.

Hamilton Construction Co. Bid Tab
Apr 19

FBR 096A-047 (21011) ~ On CO 96 replace structure K-17-F with box culvert K-17-FF, work consists of building a detour, removing existing structure, installing box culvert, grading, removing detour, and traffic control in Pueblo County.

Kirkland Construction Bid Tab
Apr 19

FBR 0502-081 (22436) ~ On US 50 near the town of Sargents, work consists of removal of portions of existing bridge structure, removal of asphalt material, construction of precast concrete box culvert, cast in place wingwalls, toewalls, and aprons, HMA paving/patching and pavement markings in Saguache County.

Dietzler Construction Corporation Bid Tab
Jan 25

FBR 0701-242 (22170) ~ On I-70 at MP 56.77 Bridge G-03-Q over the Colorado River Overflow, work consists of bridge repairs in Mesa County.

Hamilton Construction Co. Bid Tab
Feb 15

FBR 0701-244 (22359) ~ On I-70 at MP 88.55 Bridge F-05-L over the Colorado River, work consists of bridge repairs in Garfield County.

Hamilton Construction Co. Bid Tab
Feb 1

FBR 0702-382 (22360) ~ On I-70 at MP 158.85 Bridge F-10-L, work consists of bridge repairs including mitigating fatigue cracks in structural steel girders by means of repairing cracks, drilling, welding, painting, deck repairs, replacement of bridge expansion joints, replacement of HMA and waterproofing membrane, replacement of bridge rail, roadway work including replacement of guardrail and construction of cross-overs for maintenance of traffic in Eagle County.

Lawrence Construction Company Bid Tab
Mar 8

FSA R200-247 (22167) ~ On US 287 from MP 0.00/State Line to MP 133, work consists of installing centerline rumble strips in Baca, Kiowa and Prowers Counties.

Diamond Surface Inc. Bid Tab
Oct 25 FSA 0142-063 (19664R) ~ This project consists of concrete pavement reconstruction on West Main Street and Division Ave.  New concrete pavement construction throughout the new S-curve, hot mix asphalt mill and fill work on US 138 and US 6, curb and cutter and sidewalk construction, curb ramp reconstruction, medians with median lighting, storm sewer installation, and striping and signing all located in Logan county in Sterling.  Rejected N/A
Dec 13 FSA 0142-063 (19664R) ~ This project consists of concrete pavement reconstruction on West Main Street and Division Ave.  New concrete pavement construction throughout the new S-curve, hot mix asphalt mill and fill work on US 138 and US 6, curb and cutter and sidewalk construction, curb ramp reconstruction, medians with median lighting, storm sewer installation, and striping and signing all located in Logan county in Sterling.  PARSONS Construction Group, Inc. Bid Tab
Nov 1

 FSA 052A-047 (21856) ~ This project is an intersection widening project. Salient features include new signals and caissons, street lighting, both overlay and full depth HMA, curb and gutter, raised median, and concrete drainage pipe. Located in Weld county. 

Asphalt Specialties Bid Tab
Mar 1

FSA 070A-029 (21906) ~ North of I-70 on Pecos Street at 48th Avenue, work consists of roundabout improvements in Denver County.

Jalisco International Bid Tab
Oct 18

FSA 076A-011 (22760) ~ This project includes work sites in Adams, Morgan, and Weld counties from MM 25.14 to MM 100. The project consists of removing and applying high contrast tape at designated locations.

Innovative Marking System, Inc. Bid Tab
Jan 4 FSA 145A-061 (19796) ~ On SH 145 in the Town of Dolores, work consists of removal and replacement of concrete flatwork, sign replacement and minor traffic control in Montezuma County. Medved Gloval Inc. Bid Tab
May 3

FSA 0711-020 (21864) ~ Intersection Safety Improvements at CO 71 and CO 94 Intersection in Lincoln County.

KECI Colorado Incorporated Bid Tab
Dec 6

IM 0253-268 (22703) ~ This project is located in Adams and Broomfield counties I-25: 120th(SH 128) to SH 66. Completion of the SB and NB tolled express lane from 120th to E470. Consisting of mainline overlay, new mash complain median barrier and lighting, and ITS and tolling. 

Graham Contracting LTD Bid Tab
Jan 18 ITS SW01-833 (21594) ~ On CO 265 near York Street, work consists of furnishing and installing over height detection systems, including detectors, blank out signs, cabinets, conduit and pull boxes in Denver County. Interface Communications Company Bid Tab
Nov 15 ITS 0242-088 (22503) ~ On US-24 from I-25 to Morning Sun Drive (Woodland Park), work consists of installation of fiber optic cable and conduit, which includes pull boxes, manholes, Ethernet switches, backbone fiber, lateral fiber, splicing fiber, terminating fiber, existing device integration, and testing ofthe fiber and network in El Paso and Teller Counties. PAONIA, Inc. Bid Tab
Jun 21

MP R200-251 (22534) ~ R2, removal and replacement of existing pavement markings all R2 counties.

Roadsafe Traffic Systems Bid Tab
Dec 20 

MP R200-252 (22535) ~ This project consist of removal and replacement of existing signs along various highways in Pueblo County. The work includes installation sign bases, post, and panels. 

PAONIA, Inc. Bid Tab
Dec 13 MTCE 0253-267 (22700) ~ This project is located on I25 in Larimer County from MP 269.0 to MP 281.0.  The work consists of removing and replacing concrete panels in the northbound and southbound drive lanes, with the majority of work in the southbound drive lane. Incorporated into this project is temporary traffic control with approval for extended lane closure in the southbound direction.

Ralph  L. Wadsworth Construction Co.  Bid Tab
Jan 11

MTCE R100-296 (22230) ~ On CO 72 and CO 74, work consists of signage removal and replacement using sign panels provided by CDOT and contractor furnished posts and footings, traffic and erosion control in Boulder, Gilpin and Jefferson counties.

CC Enterprises Bid Tab
Sep 27

MTCE R100-301(22322) ~ This signing project will replace, remove, or install sign panels and overhead sign structures on US 6, I-25, US 36, CO 58, I-70, I-76, I-225, I-270, US 285, CO 287, and C-470.  This project is located in Adams, Denver, and Douglas counties. 

PAONIA, Inc. Bid Tab
May 17 MTCE R100-312 (22471) ~ On CO 86 from MP 6.8 to MP 12.3 and on CO 119 from MP 12.5 to MP 16.1, work consists of asphalt chip sealing in Adams, Douglas and Gilpin Counties. A-1 Chip Seal Bid Tab
Jul 5

MTCE R100-313 (22499) ~ Replacement of pavement markings in Arapahoe, Clear Creek, Douglas, Gilpin and Jefferson counties.

Roadsafe Traffic Systems, Inc. Bid Tab
May 24

MTCE R300-244 (22237) ~ In Region 3 various locations, work consists of removal and replacement of highway signs, posts, and bases in Eagle, Garfield, and Mesa Counties. * This does not reflect the technical score that was also considered. 

CC Enterprises *Bid Tab
Mar 29

MTCE R300-245 (22432) ~ Region 3 FY18/19 region wide epoxy striping on SHs 070A and 082A in Mesa, Garfield, Eagle, Summit and Pitkin Counties.

Roadsafe Traffic Systems Inc. Bid Tab
Oct 18

MTCE R400-365 (22577) ~ This work consist of removing and applying modified epoxy pavement markings & high contrast tape at designated points. This project is located in Adams, Morgan, Sedgwick, Washington, and Weld counties from MM25.14 to MM 184.135

Kolbe Stripping, Inc. Bid Tab
Mar 8

MTCE R500-201 (22309) ~ On US 550, US 160 and SH 140 at various locations, work consists of removing and replacing class I & II sign panels, and replace damaged sign posts and bases as needed in La Plata and San Juan counties.

Workzone Traffic Control Bid Tab
Mar 8

MTCE R500-202 (22310) ~ In Region 5 at various locations/highways, work consists of striping 665 miles of highway in La Plata, Montezuma, and Saguache counties.

Pavement Marking Bid Tab
Mar 8

MTCE R500-203 (22477) ~ In Region 5 at various locations/highways, work consists of crack sealing in travel lanes and along the edges of the travel lanes in La Plata, Montezuma, Montrose and Ouray Counties.

A-1 Chipseal Company Bid Tab
May 3

MTCE 0701-246 (22457) ~ On I-70 from MP 37.0 to MP 67.5 in both east and west bound directions, work consists of installing preformed plastic pavement marking Type 1 inlaid on the centerline skips in both directions in Garfield and Mesa Counties.

Innovative Marking Systems Inc. Bid Tab
Sep 27

MTCE 0704-244 (22701)  ~ The project consists of sealing cracks within the concrete pavement on I-70. Incorporated into this entire project is Temporary Traffic Control.  This project is located in Arapahoe, Elbert, Lincoln and Kit Carson counties from M.P. 328.0 to M.P. 427.5 in both westbound and eastbound directions.

Dykhuis Drilling Corp. Bid Tab
Jan 18

MTCE 0712-017 (22177) ~ On CO 71D from MP 123 to MP 138 in both directions of the roadway, work consists of chip seal and fog seal to the full width of the roadway and shoulder, includes cover coat material Type 1, emulsified asphalt and final striping in Lincoln and Washington counties.

A-1 Chipseal Company Bid Tab
May 3

NH 0242-071 (20932) ~ On US 24 and 31st Street and US 24 and Ridge Road, work consists of intersection improvements in El Paso County.

Wildcat Construction Co. Bid Tab
Mar 8

NH 0504-904 (22081) ~ On US 50, work consists of critical culvert repair in Pueblo County.

American West Construction Bid Tab
July 19

NH 0853-106 (21774) ~US 85 and Weld Co. RD. resurfacing in Weld County.

Jalisco International  Bid Tab
Nov 1

NH 2854-139 (20949) ~ US 285, 2.5" Mill and fill from M.P. 171.3 to 174.98, Passing lanes and turn lanes widening from M.P. 174.98 to 178.02 this includes extending 16 existing culvert pipes, 2.5" Mill and fill from M.P. 178.02 to 182.76, 2.5" Mill and fill from M.P. 183.39 to 185.4. 4" Mill and fill from M.P. 185.4 to M.P. 186.1. 2.5" Mill and fill from M.P. 186.1 to M.P. 190.0. This project is located in Park county.

APC Southern   Bid Tab
Apr 4

NHPP 072A-042 (22027) ~ CO 72 / 64th Ave. / Indiana St. traffic signal replacement in Jefferson County.

Interface Communications Company Bid Tab
Jan 4

NHPP C200-009 (20737) ~ On US 550 in Durango at 17th, 22nd and 32nd Streets, work consists of sign replacement, roadway improvements, ADA curb ramp and sidewalk construction in LA Plata County.

Rejected N/A
Mar 1

NHPP C200-009 (20737R) ~ On US 550 in Durango at 17th, 22nd and 32nd Streets, work consists of sign replacement, roadway improvements, ADA curb ramp and sidewalk construction in LA Plata County.

Rejected N/A
May 24

NHPP C200-009 (20737S) ~ On US 550 at 17th, 22nd and 32nd intersections, work consists of signal replacement, roadway improvements, ADA curb ramp and sidewalk construction in La Plata County.

Kirkland Construction LLLP Bid Tab
Apr 12

NHPP C470-041 (20805) ~ Douglas County bridge scour repair.

SEMA Construction Inc. Bid Tab
Oct 18

NHPP 006A-064 (21926) ~ This resurfacing project is located on US highway 6 in Mesa county.  The project begins on MP 11.08 and goes to MP 20.05.  The project consists of full width HMA overlay, shouldering, pothole repair, guardrail upgrades, ADA ramp upgrades, and epoxy pavement markings.

Kilgore Companies, LLC Bid Tab
Oct 4

NHPP 006A-066 (22451) ~ US 6: I-25 to Perry St, operational improvement.  This project is located in Denver County.

Jalisco International Inc.  Bid Tab
Jan 18

NHPP 0252-455 (21364) ~ On I-25 northbound from Ridgegate Parkway to University Boulevard and on I-225 from Parker Road to I-25, work consists of installing devices and equipment for ramp metering, modifying existing ramp meter configurations both pavement markings and ramp signal equipment, widening of Dry Creek ramp, installation of new ramp signals on C470, E470 and I-225, installation of fiber optic backbone along northbound I-25 in Arapahoe, Denver and Douglas counties.

Rejected N/A
Apr 19

NHPP 0252-455 (21364R) ~ On I-25 and I-225, work consists of installation of ramp metering devices, modify pavement markings and signal equipment, widening of the Dry Creek ramp, and installation of fiber backbone in Arapahoe, Denver and Douglas Counties.

Rejected N/A
Nov 15

NHPP 0252-455 (21364S) ~ The Smart 25 Project limits are along NB I-25 from Ridgegate to University. There is additional ITS work along 225 between Parker Roadand I-25.  The purpose of the project is to install devices and equipment required to operate a coordinated ramp metering demonstration project along NB I-25. This project will install a new CDOT Fiber backbone in new conduit along portions of NB I-25. Included in the work will be modifying existing pavement markings and ramp signal equipment. New ramp meter signals will be installed on C470, E470 and I-225. The project has been split up into three projects.  A second project, Smart 25 Managed Motorways. The project is located in Arapahoe, Denver, and Douglas counties.

PAONIA, Inc.  Bid Tab
Oct 25

NHPP 0401-023 (21290) ~ This project is located within Moffat County, along US 40, with project limits beginning at MP 31 and continuing East to MP 37. The project's scope includes surface treatment (1.5" overlay), guardrail replacement, pavement marking, and traffic control.

Kilgore Companies, LLC Bid Tab
Nov 15

NHPP 0402-090 (20753) ~ The project located in Moffat and Routt counties.  The project consists of Bridge preventative maintenance project for five structures. B-06-A on US40Z MP 0.02, B-06-S on US40A MP 91.22 in, B-06-V on SH394 MP 1.0, C-06-A on US40A MP 105.50in Routt county, C-08-A on US40A MP 108.38 in Routt county.

Myers & Sons Construction Bid Tab
Jan 4 NHPP 0402-092 (20842) ~ On US 40 from MP 15.1 to MP 152.4, work consists of 2.5” milling and 2" filling surface treatment, guardrail replacement, sign modifications, culvert replacement, sediment control, frost heave repairs, pavement marking, and traffic control in Grand and Routt Counties. Oldcastle SW Group Inc. Bid Tab
Jul 5 NHPP 0501-068 (22414) ~ ADA curb ramps US 50, EBS restricted project, in Delta county. Western Gravel  Bid Tab
Sep 6 NHPP 0501-069 (22415) ~ The project consists of replacing existing ADA curb ramps to bring them into compliance with PROWAG Requirements. This project is located in the City of Delta on US50 MP 70.93 to 72.38 and SH348, MP 0.00 to MP 0.73 in Delta county Western Gravel Constructors, LLC Bid Tab
Sep 20

NHPP 070A-032 (22484) ~ I-70 B&Z in Mesa county.  This project is located in the City of Grand Junction along I-70A between milepost 25.50 and 25.60, I-70B between milepost 4.88 & 7.18, I-70Z between milepost .24 and1.27, and SH340 between milepost 12.84 and 13.28.  The project consists of improvements of existing curb ramps, along with sidewalks and curbs. 

KSK, LLC Bid Tab
Apr 19

NHPP 0701-239 (21201) ~ On I-70 from MP 68 to MP 75, work consists of resurfacing travel lanes, including variable depth overlay, guard and bridge rail replacement, and sliplinning of two culverts in Garfield County. Ol

Oldcastle SW Group Inc. Bid Tab
Jun 14 NHPP 0702-342 (19875R) ~ On I-70 in Glenwood Canyon, installation of variable speed limit signs, closed caption TVs, RWIS, removal and replacement of traffic signs, installation of conduit, pull boxes, manholes for fiber and electric cable, boring and attachment to structures, installation of electric wiring and services to devices, and installation of netwrok equipment in Eagle & Garfield counties. Casper Electric Bid Tab
Nov 27 NHPP 0702-344 (19944) ~ I-70 Edwards Interchange Upgrade Phase 2 CMGC in Region 3 Kraemer North America LLC Bid Tab
Nov 8 NHPP 0702-366 (21245) ~ This project is located on I-70 from MP 166.0 to 174.5, with work and mainline resurfacing between MP 167 and 173.52 in Eagle County.  The construction will consist of a 2" mill and HMA overlay, guardrail work, rumble strips, striping, bridge rail, bridge joint repair, erosion control, and traffic control management. Oldcastle SW Group Inc.  Bid Tab
Jan 11 NHPP 0702-373 (21696) ~ On I-70 from MP 116 to MP 133, work consists of roadway resurfacing, asphalt and waterproofing membrane removal and replacement, pavement marking and traffic control in Eagle and Garfield Counties. Oldcastle SW Group Inc. Bid Tab
Jun 28 NHPP 0703-436 (21224) ~ Waterproofing membrane repair for EJMT in Clear Creek and Summit Counties. ABCO Contracting Bid Tab
Aug 2 NHPP 0703-448 (22231) ~ Median guardrail barrier construction at three sites locations with concrete paving at one of the sites in Denver and Jefferson counties.  Cruz Construction Inc.  Bid Tab
Mar 29 NHPP 0703-449 (22250) ~ I-70 bridge deck and expansion joint repairs with HMA overlay in Clear Creek and Jefferson Counties.  Structures Inc. Bid Tab
Nov 15 NHPP 0705-082 (21878) ~ This project is located on I-70 in Kit Carson and Lincoln county beginning at MP 380.0 extending 15.1 miles. The project consists of concrete overlay with concrete paving, removal of hot mix asphalt and full depth reclamation and stripping. Castle Rock Construction Co.  Bid Tab
Jun 14 NHPP 0761-230 (22227) ~ On I-76, repairs to damaged retaining walls in Morgan county.  TLM Constructors Bid Tab
Mar 29 NHPP 0852-112 (20473) ~ US 85, Hampden to Lipan, widen SB lanes, replace broken slabs and ADA ramps in Arapahoe and Denver Counties.   Jalisco International Inc. Bid Tab
Feb 15

NHPP 1602-153 (20705) ~ On SH 160 from MP 144.29 to MP 158.56, work consists of 2.5” HMA surface treatment, planning, striping, replacing mailboxes and delineators, upgrading guardrails, bridge repairs, patching, mill and fill work, widening, geohazard/culver/ditch improvements in Archuleta and Mineral Counties.

A and S Construction Co. Bid Tab
Mar 8

NHPP 1602-164 (21744) ~ On US 160 at Wolf Creek Pass, work consists of sign structures, signs, striping and barrier construction in Mineral County.

Structures, Inc. Bid Tab
Mar 8

NHPP 1602-166 (22010) ~ On US 160 from MP 91.8 to MP 102.3, work consists of deep patch, HMA leveling course, followed by HMA overlay with shouldering, guardrail replacement, striping, delineation, and mailbox replacement in La Plata County.

Oldcastle SW Group Inc. Bid Tab
Nov 29

NHPP 2854-138 (20852) ~ The project installs water-proofing membrane over 4 existing bridge structures (F-15-DJ, F-15-DI, F-15-DG, & F-16-UA)through the Conifer area of US 285 in Jefferson County. The membrane will be installed directly over the pre-cast concrete box girders in the median areas and over milled concrete pavement areas of the PCC driving lanes and shoulders. Also,drainage improvements are included in the work at each of the bridges.

ABCO Contracting, Inc.  Bid Tab
Nov 15

NHPP 4912-007 (20684) ~ This project consists of minor widening at junction with Montezuma county road S located on US 491 north of Cortez in Montezuma county from MP 33.48 to MP 34.01.   The project consists of HMA leveling course and SMA overlay located on US 491 from MP 36.15 to MP 53.74 and SMA overlay located on CO 184 from MP 0.00 to MP 3.78.   It also consists of installation of an advanced warning sign system located on and around JCT US 491 with Montezuma County Road BB. The project is located in Montezuma and Dolores counties.

Oldcastle SW Group, Inc.  Bid Tab
Jan 25

NHPP 5502-088 (20799) ~ At the US 550 Red Mountain Pass snow shed tunnel MP 88.15, work consists of replacing existing lighting and replacing with new LED lighting system in Ouray County.

Main Electric LTD Bid Tab
July 12 NHPP 5502-090 (20894) ~ Lighted chain stations in San Juan, Ouray, Chaffee, Saquache and Mineral counties.  Interface Communications Company  Bid Tab
Mar 1

NHPP 5502-096 (21743R) ~ On US 550 and CO 62 at various locations, work consists of chip sealing, installation of pavement markings, and centerline rumble strips in Ouray County.

Kilgore d/b/a Elam Construction Bid Tab
Dec 6

NHPP R100-241 (20869) ~ This project is located in Adams, Clear Creek, Denver, and Jefferson counties of 9 bridges.  This project consists of repairing bride bearings for 3 bridges; abutment and bridge rail repair on a 4th bridge, sandblasting, painting, and crack sealing on a 5th bridge.  The project will include slope paving repair and debris removal on a 6th bridge. On the 7th bridge anchor bolt and spall repair.  This includes providing temporary support for various portions of these structures, new bearing devices, traffic control during the raising/lowering and public information. 

Hamilton Construction Co. Bid Tab
Oct 18

NHPP R100-280 (21792) ~ Work consists of upgrading traffic signal controllers and cabinets to improve coordination and operations.  This project is located in Adams county.

Interface Communications Co. Bid Tab
Sep 6

NHPP R100-287 (22022R) ~ Up-grade ADA Curb Ramp at various locations in Adams, Denver, and Douglas counties. 

Villalobos Concrete, Inc. Bid Tab
Aug 2

NHPP R100-243 (20873) ~ Culvert repairs, utilize spray lining methods including replacement of failed wing walls with C.I.P. and soil nails walls in Adams, Arapahoe, Broomfield, Clear Creek, Denver, Douglas and Jefferson counties.  

American West Construction Bid Tab 
July 19

NHPP R100-287 (22022) ~ Region 1 Up-grade ADA curb ramp at various locations in Adams, Denver, and Douglas counties.

TBD low bid withdrawn N/A
Apr 19

SHE 025A-042 (21571) ~ On I-25 from MP 121.0-122.3 and from MP 122.9-125.2, work consists of installing TL-4 median cable barrier in the southbound lane, earthwork to flatten slopes, installation of a weed barrier and update median crossovers in El Paso and Pueblo Counties.

Kirkland Construction LLLC Bid Tab
Jan 4

SHE 0212-010 (22314) ~ At CO 21 and Omaha Blvd. intersection improvements to remove left turn movements to and from Powers Blvd at Omaha Blvd. creating a right in – right out intersection, and extending the left turn lanes northbound Powers at Palmer Park Blvd., work consists of removal of existing turn islands, embankment, aggregate base course, HMA paving, curb and gutter, lighting, signing, and pavement marking in El Paso County.

Kiewit Infrastructure Co. Bid Tab
Jul 19

SHE 0701-227 (20288) ~ Wildlife fence on I-70 in Garfield and Mesa counties 

Ideal Fencing  Bid Tab
Jul 12

SHE 0701-245 (22410) ~ Removal and replacement of guardrail in Mesa county.

Cruz Construction Inc. Bid Tab
Oct 18

SHE 2254-092 (22449) ~ SB I-225 off-ramp to 17th Place, install: 2 new blankout LED signs, new conduit on the bridge exterior to connect the signs to the cabinet, mumble strips in the travel lanes, and relocate 2 existing signs and plaques. This project is located in Adams county. 

Morton Electric Inc.  Pending
Dec 13 SHE R100-302 (22366) ~ This Project will consist of installation and reset of ramp metering at various locations in Region 1 along C470 and I76.  This project is located in Adams, Douglas, and Jefferson counties. 

W.L. Contractors, Inc. Bid Tab
Oct 18

SHE R200-243 (21978) ~ In southern Colorado at various work locations consisting of highway pavement marking installations on various roadway surface types, highway sign placement and removal along I-25 and Hwy 24 (MLK Bypass) in El Paso, Huerfano, Las Animas, and Pueblo Counties.

Workzone Traffic Control, Inc. Bid Tab
Apr 19

STA 001A-002 (21847) ~ On CO 1 and I-25 southbound ramp in Wellington, work consists of installing a traffic signal that includes conduit, signal poles, cabinet, controller, pull boxes in Larimer County.

Sturgeon Electric Company Inc. Bid Tab
Aug 23

STA 052A-040 (20715) ~ CO 52 MP 62.241 Replace existing undersized culverts in Morgan county.

AB Underground Bid Tab
Dec 13

STA 052A-045 (21852) ~ This project consists of full depth reclamation of the existing asphalt, regrading, wetting and compacting in place. The roadway will then be overlayed with two lifts of HMA for a total compacted thickness of five inches. Shouldering material will be placed along the edges of the HMA and the roadway will have new pavement markings, delineation, and sign panels put in place. This project is located in Morgan and Weld county.

Simon Contractors Bid Tab
Dec 6

STA 050A-028 (20751) ~ This project is located in Pueblo, CO along US 50C from 4th St. to Baxter Rd. The project consists of HMA Mill and Fill, Installing new ADA ramps and upgrading existing ADA ramps, new RCP Storm Sewer in the areas of Aspen St. - Carson St., 20th Lane - south of US 50C, anda short run of new storm sewer in an existing parking lot east of 20th Lane. Bridge work includes joint and crack sealant, polyurethane slab jacking, concrete pavement joint repair.

Tony J. Beltramo & Sons Inc. Bid Tab
Oct 4 STA 141A-043(20989R) ~ CO 141 Colorado River Bridge work elements include removal and replacement of bridge deck overhang, deck repairs, asphalt milling and overlay, new bridge curb,and type 10 bridge rail, approach guardrail, utility relocation, water line replacement, drainage improvements, and temporary bike way detour. This project is in Mesa county.   Rejected N/A 
Nov 29 STA 086A-051 (18611) ~ Located in Elbert county on CO 86 beginning at M.P. 33.1 and extending approximately 26.1 miles easterly ending at M.P. 59.2 with a no work section beginning at M.P. 38.1 and ending to M.P. 50.5.  Consisting of roadway resurfacing, which includes: H.M.A. Overlay, Bridge repair, and striping. Kiewit Infrastructures  Bid Tab
Jan 4 STA 141A-043 (20989) ~ On SH 141B at MP 159.93 over the Colorado River, work consists of removal and replacement of bridge railing and a portion of the deck, utility relocation, deck repairs, waterproofing membrane, culver replacement, embankment, asphalt removal and replacement, pavement marking removal and replacement, guardrail removal and replacement, polyester end dams, excavation, and traffic control in Mesa County. Rejected N/A
Aug 9 STA 141A-045 (21193) ~ Clifton traffic signal pole replacement on SH 141 MM 160 to 160.3 & I-70 MM 11.67 in Mesa county.  Sturgeon Electric Co.  Bid Tab 
May 10

STA 177A-011 (20511) ~ On CO 177 from Easter Avenue to Hampden Avenue and on US 85 from north of County Line Road to Bowles Avenue, work consists of roadway resurfacing 2.5” mill/fill with HMA, curb ramps, signal replacements, culvert repair, median reconfiguration, signing and striping in Arapahoe County.

APC Construction Co. Bid Tab
Jan 11

STA 0142-065 (20945) ~ On CO 14 in Ft. Collins between Lemay Street and I-25, work consists of 3-4” mill and overlay, full depth turn lane widening, full depth road reconstruction on eastbound SH 14 from Timberline to Summitview, detour paving, ADA curb ramp replacements, cable rail section in median, reset pull box’s, culvert extension, signal work, signing and striping in Larimer County.

Connell Resources Inc. Bid Tab
Jun 7

STA 0661-016 (22406) ~ On CO 66 and US 85 in Platteville, sidewalk replacement with asphalt patching, installation of reinforced concrete piping and traffic control in Weld county.

Mountain Constructors, Inc. Bid Tab
Mar 8

STA 1381-008 (20768) ~ On CO 138, work consists of bridge replacement, HMA paving, pavement marking, ADA curb ramps, channel grading and rip rap placement in Sedgwick County.

McAtee Construction Co. Bid Tab
Nov 8

STA 3851-017 (20855) ~ US 385 at Cheyenne Wells 90 degree curve.  This project shall reconstruct the two 90 degree curves on US 385 in Cheyenne Wells between MP 150.33 and MP 150.73, as well as install sidewalk from W. 3rd Street S. to E. 4th Street S. and will include storm sewer and drainage improvements. 

Jalisco International, Inc.  Bid Tab
Feb 8

STA M086-076 (20927) ~ At the intersections of SH 45 & Hollywood Drive, CO 45 & LeHigh Avenue, CO 96 & Acero – Belmont Avenue, and US 50 & Bonforte Boulevard, work consists of removal and replacement of traffic signals in Pueblo County.

Arrow Electric Services Inc. Bid Tab
Dec 13 STA R100-279 (21789R) ~ This project consists of asphalt chip seal in four locations.  This project is located in Adams, Clear Creek, Douglas, and Jefferson counties. SH-79 from north of 48th Avenue (Bennett) to 112th Avenue (MP 4.1 to 11.8). SH-74 from Shady Lane (Idledale) to SH-8 (MP 14.6 to 18.1). SH-103 from Tower Road to Squaw Pass Summit (MP 17.8 to 22.5). SH-105 from Wolfensberger Road (Castle Rock) to SH-67 (MP 28.2 to 32.6).

Intermountain Slurry Seal, Inc.  Bid Tab
Sep 20

STA R400-345 (20942) ~ This project consists of traffic signal pole replacement including removals, poles, conduit, heads,cameras, signing, striping, curb and gutter, and pavement patching. This project will take place at US 85 bus @ 26th St and US 85 @ CR 14.5.  Project located in Weld county.

PAONIA, Inc. Bid Tab
Apr 12

STA R400-347 (20940) ~ FY18 R4 controller and cabinet replacement project in Adams, Arapahoe, Broomfield, Denver, Douglas, El Paso, Huerfano, Kit Carson, Larimer, Las Animas, Lincoln, Mrogan, Phillips, Pueblo and Weld Counties.

Paonia Inc. Bid Tab
Apr 12

STM 0242-081 (21450) ~ US 24 rockfall mitigation in El Paso County.

Drill Tech Drilling & Shoring Inc. Bid Tab
Sep 6

TM 0252-469 (22383) ~ Replacing and or modifying curb ramps along the I-25 and the CO 21 Powers Corridor in Colorado Springs located in El Paso county.   

Avery Asphalt Inc. Bid Tab
Sep 20 

STM R200-246 (22058) ~ This project will repair 2 culverts in El Paso County and 1 culvert in Fremont County.

American West Construction, LLC Pending
Dec 6

STR 112A-001 (21317) ~ On SH 112, from US 285 to SH 17, work consists of HMA leveling course, followed by HMA overlay, shouldering, concrete ramp, sidewalk, signing and pavement markings in Rio Grande, Alamosa, and Saguache counties.

APC Southern Construction Co. Bid Tab
Jan 18

STR 133A-045 (20915R) ~ On CO 133 from MP 42 to MP 51, work consists of heating and remixing treatment, chip seal, guardrail upgrades, pavement markings, and traffic control with pilot car operations in Pitkin County.

Oldcastle SW Group Inc. Bid Tab
Jul 12

STR 151A-010 (21091) ~ Replacement of two 84" corrugated metal pipes with one 12"x 8" precast concrete box culvert. Detour pavement, guardrail and asphalt paving in Archuleta county. 

Tricon 2, LLC Bid Tab
Dec 13 STR 1591-001 (21559) ~ This project is located in Costilla county.  SH 159 San Luis to Fort Garland surface treatment.  Work consists of HMA leveling course, HMA overlay, shouldering, signing and pavement markings.   A&S Construction Co. Bid Tab
Jan 4

STR 069A-032 (20950) ~ On SH 69 from MP 25.7 to MP 50.1, work consists of 1.5” HMA overlay, 1” HMA leveling course at select locations, roto milling, placing shouldering material, seeding, mulching, replacing guardrail, installation of delineators, signing, rumble strips, and striping in Custer and Huerfano Counties.

A&S Construction Co. Bid Tab
Jan 4

STR 133A-046 (21262) ~ On CO 133 from MP 11.43 to MP 23.8, work consists of full width cold bituminous pavement recycled, 2” overlay, shouldering, guardrail upgrades, epoxy pavement markings, mill and fill bridge work and end block modification on structures I-06-O, I-06-V, and I-07-S, fence replacement on structures I-06-O, replacement of joint gland on structure I-07-S, and mill and fill on structures I-07-P and I-07-Q in Delta and Gunnison Counties.

Oldcastle SW Group Inc. Bid Tab
Aug 23

STR 167A-002 (20754) ~ CO 167 near Flower between MP0 and 4.86 1.5" mill and overlay in Crowley and Otero counties.  

A&S Construction Co.  Bid Tab
Nov 29

STR M331-007 (20790) ~ This project consist of either replacing or installing new ADA curb ramp, sidewalks, minor culvert bridge improvements, and install permanent traffic control devices in City of Walsenburg within Huerfano County. The project includes, but is not limited to, the following elements: will modify the existing box culvert on Walsen Ave (I-25 C) between Pine St and Grand Ave to accommodate a multi-use shared path; provide sidewalk and ADA improvements along Walsen Ave between Spruce St and Grand Ave; provide a mid block crossing (Rapid Rectangular Flashing Beacon - RRFB) between Spruce and Elm St to access the Library across Walsen Ave; provide sidewalk and ADA improvements along 7th St (US 160) between Ysidrio Ave and Olive Ave for the City Water Park, along with a Rapid Rectangular Flashing Beacon (RRFB) for the pedestrian crossing at Ysidrio Ave.

The Walsenberg Sand & Gravel Co. Bid Tab
Jan 18

STR R200-238 (21787) ~ On CO 101 and CO 109, work consists of culvert replacement/rehabilitation in Bent and Otero Counties.

American West Construction LLC Bid Tab
Jan 4 STR 0091-043 (20759) ~ On CO 9 Summit Boulevard from MP 96.1 to MP 97.2, work consists of HMA resurfacing, ADA curb ramp upgrades, and signal cameras in Summit County. A&S Construction Co. Bid Tab
Nov 29 STU 1211-085 (20322) ~ This project is located on CO 121 (S. Wadsworth Blvd) beginning at Bear Creek MP 8.5 and extending north approximately 3.7 miles to W. 4th Ave. MP 12.28. The project consists of 2.5 inch H.M.A. Resurfacing, curb ramp upgrades, adjusting manhole and valve boxes, cleaning inlets, constructing a pipe edge drain, and placing final signing and stripping.  This project is in Denver and Jefferson counties. Martin Marietta Materials Bid Tab
Aug 9 PWQ ID/IQ maintenance project in various counties in Region 2 DBI Services Inc.  Pending
Swipe table to see more content

Filed under:
Contact Us
  • RB Simmons
    Construction Contracts Manager
    303-757-9416

Colorado: The Official State Web Portal