PS&E Package to FHWA
2015-7. Revised on October 9, 2015. In order to not delay going to ad, the PS&E (Plans, Specifications and Estimate) Package for projects of Division Interest (PoDI) must be sent to FHWA two weeks before beginning the Form 1180 process. FHWA now requires that the PS&E package be delivered in paper format.