Part 1 Colorado Department of Transporation 14:47 Monday, January 13, 2003 1 2002 Cost Data - Maintenance PROJECTS BID FROM 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/ LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX ------------------------------------------------------------------------------------------------------------------------------------ 02010303 POWER ELECTRIC COMPANY 4 $525,573.34 104.74 MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 3 M 02010304 BEST-WAY PAVING COMPANY 6 $17,910.00 60.02 MTCE 04-013 SH 34 IN LOVELAND 4 P 02011704 G.A. WESTERN CONSTRUCTION CO. 5 $1,031,723.40 128.99 MTCE 03-005 SH 70, 131, 141, AND 340 IN RE 3 M 02012408 K.E.C.I. COLORADO, INC. 1 $39,000.00 102.30 MTCE 03-007 TRAFFIC CONTROL REGION 3 3 R 02013102 GREAT AMERICAN SWEEPING, INC. 2 $378,985.60 96.68 MTCE 06-008 REGION 6 SWEEPING 6 U 02021402 KOLBE STRIPING INC. 4 $32,214.10 42.87 MTCE 02-007 SH 25 AND 50 STRIPING 2 U 02031401 PENHALL COMPANY 6 $313,331.65 71.87 MTCE 06-006 R-6 EXPANSION JOINT REPAIR 6 U 02032804 PAVEOVER INC. 1 $877,282.55 98.87 MTCE 05-009 US 160, EAST OF BAYFIELD 5 R 02040403 BRASIER ASPHALT, INC. CONTRACT REJ - NO REASON GIVEN MTCE 07-001 STATEWIDE RECYCLED PAVEMENT 09 P 02042503 KOLBE STRIPING INC. 3 $63,874.45 64.15 MTCE 02-008 COLO. SPRINGS PAVEMENT MARKING 2 M 02050203 LAFARGE WEST, INC 2 $891,524.00 88.24 MTCE 06-010 SH 285, WADSWORTH TO FEDERAL 6 U 02050901 CONCRETE STABILIZATION TECHNOLOGIES, INC 1 $124,125.00 103.69 MTCE 04-016 BOULDER/GREELEY SLAB JACKING 4 R 02051604 TLM CONSTRUCTORS, INC. 4 $60,199.00 45.04 MTCE 04-017 GREELEY AREA EXPANSION JOINTS 4 R 02052303 BRASIER ASPHALT, INC. 1 $144,930.00 92.90 MTCE 07-001 STATEWIDE RECYCLED PAVEMENT 09 P 02053001 LAWRENCE CONSTRUCTION CO. 1 $14,576.00 112.30 MTCE 05-012 PILE DRIVING ON SH160, MP 70 5 M 02053002 ABCO CONTRACTING, INC. 2 $23,368.80 79.26 MTCE 04-018 BRIDGE DECK WATERPROOFING, SH 4 P 02053004 BALLOU CONSTRUCTION CO., INC. 1 $511,371.25 94.55 MTCE 05-011 SH 160, MACROSURFACING, MP 105 5 M Colorado Department of Transporation 14:47 Monday, January 13, 2003 2 2002 Cost Data - Maintenance PROJECTS BID FROM 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/ LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX ------------------------------------------------------------------------------------------------------------------------------------ 02061305 INTEGRATED ELECTRIC, INC. 3 $86,076.00 69.97 MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 09 M 02062003 AGGREGATE INDUSTRIES - WCR, INC. 5 $406,435.23 101.42 MTCE 01-016 SH 30 & SH 36 OVERLAY, REGION 1 U 02062004 GRASSER CONSTRUCTION INC. 4 $689,875.25 106.51 MTCE 01-017 I-70 OVERLAY, E. OF LIMON 1 P 02062706 LAFARGE WEST, INC 3 $482,221.50 79.30 MTCE 01-014 I70, BAKERVILLE TO SILVERPLUME 1 M 02062707 LAFARGE WEST, INC 3 $582,562.00 80.28 MTCE 01-015 I70, FLOYD HILL TO CHIEF HOSA 1 M 02071804 INTERMOUNTAIN SLURRY SEAL, INC. 3 $389,881.40 107.27 MTCE 05-013 SH 145, SOUTH OF TELLURIDE 5 M 02071806 C & D ELECTRIC 3 $24,875.00 111.15 MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 2 U 02072502 C & D ELECTRIC 3 $322,550.00 70.90 MTCE 02-010 REGION 2, STREET LIGHTING 2 U 02082204 KOLBE STRIPING INC. 4 $700,473.50 97.93 MTCE 05-014 R-5 EAST EPOXY MARKING 5 R 02082205 KOLBE STRIPING INC. 4 $611,932.00 97.38 MTCE 05-015 R-5 WEST EPOXY MARKING 5 R 02082206 UNITED RENTALS HIGHWAY TECHNOLOGIES 8 $473,500.00 104.99 MTCE 05-016 SIGN REPLACEMENT - ALAMOSA AR 5 R 02082207 ALERT TRAFFIC CONTROL, INC. 7 $769,000.00 96.43 MTCE 05-017 SIGN REPLACEMENT - DURANGO ARE 5 R 02082902 MCATEE CONSTRUCTION CO. 2 $325,145.53 84.60 MTCE 04-022 SH 23 STERLING AREA 4 P 02082904 WARNING LITES & EQUIPMENT, INC. 4 $248,550.00 84.61 MTCE 05-018 MTCE SECTION 3 (DURANGO) 5 M 02082905 KOLBE STRIPING INC. 4 $435,465.00 83.87 MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 5 U 02090501 DKS ENTERPRISES INC. 8 $84,470.00 63.98 MTCE 01-018 SH 285 AND RICHMOND HILL RD 1 M 02090502 KIEWIT WESTERN CO 5 $263,050.00 105.02 MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 2 R Colorado Department of Transporation 14:47 Monday, January 13, 2003 3 2002 Cost Data - Maintenance PROJECTS BID FROM 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/ LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX ------------------------------------------------------------------------------------------------------------------------------------ 02091904 BFC, INC. 2 $68,400.00 88.00 MTCE 03-010 I-70 VAIL PASS CRACK SEAL 3 M 02091905 BFC, INC. 5 $273,528.00 96.65 MTCE 04-015 REGION 4 CRACK SEAL 4 M 02092603 COULSON EXCAVATING COMPANY 2 $207,276.00 84.33 MTCE 04-019 I25 RAMPS - LOVELAND, SH 287 - 4 R 02092604 BRANNAN SAND AND GRAVEL COMPANY 5 $184,415.00 94.29 MTCE 04-021 SH 42 NEAR LOUISVILLE 4 R 02092605 AGGREGATE INDUSTRIES - WCR, INC. 4 $212,820.80 89.26 MTCE 04-023 SH 85, N OF NUNN 4 P 02092606 WARNING LITES & EQUIPMENT, INC. 4 $628,679.00 90.04 MTCE 04-029 FY 03 R4 EPOXY WEST 4 M 02092607 UNITED RENTALS HIGHWAY TECHNOLOGIES 5 $555,182.00 85.98 MTCE 04-032 REGION 4 EPOXY EAST 4 M 02092608 MAXWELL ASPHALT, INC. 3 $302,831.10 91.93 MTCE 05-020 ALAMOSA SECTION CRACK SEAL 5 M 02100302 GREAT AMERICAN SWEEPING, INC. 1 $397,882.80 99.72 MTCE 06-012 REGION 6 SWEEPING 6 U 02100303 WATERFORD CORPORATION 6 $109,852.00 72.50 MTCE 06-016 HWYS 72 & 93 FENCING 6 U 02100304 PEGCO CRACK SEALING, INC. 1 $177,925.92 106.60 MTCE 06-020 COLFAX AVE., TOWER RD. WEST 6 U 02100305 INTERFACE COMMUNICATIONS, COMPANY 11 $27,975.00 60.45 MTCE 01-010 SH 83 & MAIN ST. SIGNAL 1 U 02100306 WARNING LITES & EQUIPMENT, INC. 1 $91,440.00 92.83 MTCE 03-009 REGION 3 TRAFFIC CONTROL 3 M 02101001 FRONT RANGE STRIPING 5 $242,646.00 67.33 MTCE 04-030 STENCIL MARKING R4 4 R 02101702 CONNELL RESOURCES, INC. 5 $80,987.40 90.59 MTCE 04-028 BOX CULVERT - LYONS 4 R 02103101 BEST-WAY PAVING COMPANY 6 $24,308.24 55.60 MTCE 04-027 REGION 4 EXPANSION JOINTS 4 P 02103102 DKS ENTERPRISES INC. 5 $127,830.00 87.86 MTCE 01-003 HIGHWAY LIGHTING - REGION 1 1 R Colorado Department of Transporation 14:47 Monday, January 13, 2003 4 2002 Cost Data - Maintenance PROJECTS BID FROM 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/ LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX ------------------------------------------------------------------------------------------------------------------------------------ 02103103 DKS ENTERPRISES INC. 5 $111,680.40 89.57 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 6 P 02103104 WARNING LITES & EQUIPMENT, INC. 8 $124,830.00 48.43 MTCE 06-018 SIGN POST REPLACEMENT - R6 6 P 02103105 GONZALES CONSTRUCTION COMPANY, INC. CONTRACT REJ - NO REASON GIVEN MTCE 03-008 REGION 3 3 M 02110701 DOUBLE D CONSTRUCTION LLC 7 $35,080.40 57.68 MTCE 04-014 FENCING - FT. MORGAN AREA 4 P 02110702 ADARAND CONSTRUCTORS, INC. 3 $293,251.00 90.07 MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 5 R 02111405 IDEAL FENCING CORPORATION 6 $99,998.22 65.02 MTCE 04-025 R-4 GUARDRAIL REPLACEMENT 4 P 02111406 STRUCTURES, INC. 6 $268,897.00 101.10 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 6 U 02120503 AMERICAN CIVIL CONSTRUCTORS, INC. 9 $39,675.00 114.12 MTCE 06-021 R-6 CORBEL & COLUMN REPAIR 6 P 02120504 UNITED RENTALS HIGHWAY TECHNOLOGIES 3 $3,183,538.80 106.21 MTCE 01-020 R-1 EPOXY MARKING 1 R 02121206 IDEAL FENCING CORPORATION 3 $226,375.00 74.71 MTCE 03-008 REGION 3 GUARDRAIL REPAIR 3 M 02121902 MASTEC NORTH AMERICA, INC. 9 $199,472.89 66.50 MTCE 04-031 FY 03 WEST SIGNS R-4 4 R ======= ================ ====== TOTALS 247 $20,242,829.52 92.77 Part 2 Bridge Cost per Square Feet - none bid Part 3 Colorado Department of Transporation 14:47 Monday, January 13, 2003 1 2002 Cost Data - Maintenance INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE ------------------------------------------------------------------------------------------------------------------------------------ 202-00001 Removal of Structure 1 Each 13,000.00 13,000.00 202-00240 Removal of Asphalt Mat (Planing) 193,846 Sq Yard 357,391.00 1.84 202-00246 Removal of Asphalt Mat (Planing) (Special) 3,780 Sq Yard 20,860.00 5.52 202-00250 Removal of Pavement Marking 100,428 Sq Foot 64,625.75 0.64 202-00425 Removal of Bridge Railing 100 Lin Foot 7,500.00 75.00 202-00502 Removal of Portions of Present Structure 100 Cubic Yard 112,293.60 1,122.94 202-00504 Removal of Expansion Device 2,972 Lin Foot 306,446.00 103.11 202-00700 Removal of Light Standard 5 Each 1,300.00 260.00 202-00810 Removal of Ground Sign 5,771 Each 54,836.96 9.50 202-00821 Removal of Sign Panel 5,470 Each 35,315.70 6.46 202-00825 Removal of Flashing Beacon 4 Each 600.00 150.00 202-00831 Removal of Traffic Signal Head 3 Each 123.00 41.00 202-00840 Removal of Traffic Signal Pole 1 Each 734.00 734.00 202-01000 Removal of Fence 101,756 Lin Foot 28,848.20 0.28 202-01130 Removal of Guardrail Type 3 8,441 Lin Foot 15,004.12 1.78 202-01135 Removal of Guardrail Thrie Beam 400 Lin Foot 1,140.00 2.85 202-01300 Removal of End Anchorage 38 Each 3,800.00 100.00 202-04002 Clean Culvert 1 Each 1,200.00 1,200.00 202-05100 Sandblasting Reinforcing Steel 126 Sq Yard 1,260.00 10.00 202-05150 Sandblasting 4,267 Sq Foot 1,493.45 0.35 203-00060 Embankment Material (Complete In Place) 65 Cubic Yard 7,150.00 110.00 206-00065 Structure Backfill (Flow-Fill) 37 Cubic Yard 2,886.00 78.00 210-00015 Reset End Section 1 Each 450.00 450.00 210-00500 Rebuild Portions of Present Structure 5 Each 25,000.00 5,000.00 210-00750 Reset Light Standard 10 Each 5,100.00 510.00 210-00810 Reset Ground Sign 1 Each 160.00 160.00 210-00815 Reset Sign Panel 351 Each 8,881.00 25.30 210-01130 Reset Guardrail Type 3 1,500 Lin Foot 30,000.00 20.00 210-04200 Adjust Guardrail 2,000 Lin Foot 4,000.00 2.00 304-06000 Aggregate Base Course (Class 6) 934 Ton 22,976.40 24.60 304-07009 Aggregate Base Course (Class 7) (Special) 135 Ton 3,408.75 25.25 403-00720 Hot Bituminous Pavement (Patching) (Asphalt) 771 Ton 146,547.00 190.07 403-09500 Furnish Hot Bituminous Pavement 4,422 Ton 198,768.90 44.95 403-33741 Hot Bituminous Pavement (Grading S) (75) (PG 64-22) 22,127 Ton 826,680.18 37.36 403-34721 Hot Bituminous Pavement (Grading SX) (75) (PG 58-28) 3,252 Ton 123,576.00 38.00 403-34741 Hot Bituminous Pavement (Grading SX) (75) (PG 64-22) 9,357 Ton 362,490.18 38.74 403-34841 Hot Bituminous Pavement (Grading SX) (100) (PG 64-22) 15,217 Ton 639,114.00 42.00 403-96600 Hot Bituminous Pavement (Grading Fines) (50) 19,592 Ton 726,491.50 37.08 Colorado Department of Transporation 14:47 Monday, January 13, 2003 2 2002 Cost Data - Maintenance INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE ------------------------------------------------------------------------------------------------------------------------------------ 405-00100 Heating and Remixing Treatment 213,235 Sq Yard 663,160.85 3.11 406-09501 Cold Bituminous Pavement (Recycled) 9,000 Ton 132,930.00 14.77 408-01000 Hot Poured Joint and Crack Sealant 421 Ton 532,759.10 1,265.46 409-02010 Cover Coat Material (Type II) 4,167 Ton 104,175.00 25.00 409-04050 Cover Coat Material (Special) 42,399 Sq Yard 117,445.23 2.77 409-05000 Ultrathin Bonded Wearing Course 150,275 Sq Yard 616,127.50 4.10 409-06000 Macro-Surfacing 289,355 Sq Yard 506,371.25 1.75 411-10216 Emulsified Asphalt (CRS-2P) 2,120 Gallon 3,582.80 1.69 411-10253 Emulsified Asphalt (CSS-1H) 32,224 Gallon 42,203.23 1.31 411-10275 Emulsified Asphalt (HFMS-2P) (High Float) (Polymerize 130,948 Gallon 235,706.40 1.80 411-90010 Asphalt Rejuvenating Agent 12,794 Gallon 15,352.80 1.20 502-00200 Drive Steel Piling 532 Lin Foot 9,576.00 18.00 503-00036 Drilled Caisson (36 Inch) 18 Lin Foot 2,718.00 151.00 515-00120 Waterproofing (Membrane) 3,510 Sq Yard 33,118.80 9.44 518-01002 Bridge Expansion Device (0-2 Inch) 1,321 Lin Foot 89,817.24 67.99 518-01004 Bridge Expansion Device (0-4 Inch) 2,737 Lin Foot 344,411.40 125.84 601-01010 Concrete Class BZ 3 Cubic Yard 675.00 225.00 601-01050 Concrete Class B (Wall) 17 Cubic Yard 51,000.00 3,000.00 601-03020 Concrete Class D (Miscellaneous) 22 Cubic Yard 13,750.00 625.00 601-03041 Concrete Class D (Bridge) (Special) 285 Cubic Yard 210,654.20 739.14 601-06150 Concrete (Patching) 295 Sq Foot 7,375.00 25.00 601-10250 Slab Jacking 14,150 Pound 106,125.00 7.50 601-40301 Structural Concrete Coating 1,776 Sq Foot 7,418.00 4.18 601-40401 Structural Concrete Stain 2,440 Sq Foot 3,050.00 1.25 602-00000 Reinforcing Steel 7,419 Pound 10,386.60 1.40 602-00020 Reinforcing Steel (Epoxy Coated) 6,754 Pound 5,652.40 0.84 603-70804 8x4 Foot Concrete Box Culvert (Precast) 42 Lin Foot 24,360.00 580.00 604-50050 Inlet Grating and Frame Special 1 Each 1,300.00 1,300.00 604-50200 Manhole Ring and Cover 1 Each 350.00 350.00 606-00301 Guardrail Type 3 (6-3 Post Spacing) 16,770 Lin Foot 177,302.10 10.57 606-00601 Guardrail Type 6 (6-3 Post Spacing) 375 Lin Foot 5,625.00 15.00 606-01340 End Anchorage Type 3D 12 Each 5,712.00 476.00 606-01370 Transition Type 3G 2 Each 1,530.00 765.00 606-02001 End Anchorage (Slotted Rail Terminal) 46 Each 72,330.00 1,572.39 606-02003 End Anchorage (Nonflared) 72 Each 104,040.00 1,445.00 606-02005 End Anchorage (Flared) 12 Each 13,176.00 1,098.00 606-10400 Bridge Rail Type 4 58 Lin Foot 12,736.25 219.59 606-10405 Bridge Rail Type 4 (Special) 100 Lin Foot 12,500.00 125.00 Colorado Department of Transporation 14:47 Monday, January 13, 2003 3 2002 Cost Data - Maintenance INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE ------------------------------------------------------------------------------------------------------------------------------------ 607-00005 End Post 8 Each 680.00 85.00 607-00010 Corner and Line Brace Post 53 Each 4,505.00 85.00 607-01010 Fence Barbed Wire with Metal Posts (Special) 101,756 Lin Foot 110,899.20 1.09 608-00000 Concrete Sidewalk 3 Sq Yard 180.00 60.00 609-21010 Curb and Gutter Type 2 (Section I-B) 4 Lin Foot 119.00 29.75 613-00200 2 Inch Electrical Conduit 200 Lin Foot 800.00 4.00 613-00201 2 Inch Electrical Conduit (Jacked) 706 Lin Foot 20,460.00 28.98 613-00301 3 Inch Electrical Conduit (Jacked) 250 Lin Foot 4,750.00 19.00 613-00700 Inspection Trip 22 Each 19,800.00 900.00 613-01200 2 Inch Electrical Conduit (Plastic) 2,690 Lin Foot 22,520.00 8.37 613-01202 2 Inch Electrical Conduit (Plastic) (Install Only) 100 Lin Foot 800.00 8.00 613-01300 3 Inch Electrical Conduit (Plastic) 250 Lin Foot 3,250.00 13.00 613-01302 3 Inch Electrical Conduit (Plastic) (Install Only) 300 Lin Foot 3,000.00 10.00 613-05000 Direct-Burial Cable 2,000 Lin Foot 13,300.00 6.65 613-07000 Pull Box (Special) 5 Each 2,750.00 550.00 613-07026 Pull Box (16"x24"x12") Deep 14 Each 2,800.00 200.00 613-07199 Pull Box (Install Only) 3 Each 750.00 250.00 613-10000 Wiring 3 Lump Sum 3,520.00 1,173.33 613-20100 Light Standard (Install Only) 10 Each 5,080.00 508.00 613-32300 Light Standard Steel (30 Foot) 10 Each 17,300.00 1,730.00 613-32400 Light Standard Steel (40 Foot) 10 Each 17,700.00 1,770.00 613-34400 Light Standard Metal (40 Foot) 60 Each 51,000.00 850.00 613-40000 Concrete Foundation Pad 4 Each 2,400.00 600.00 613-40010 Light Standard Foundation 10 Each 6,300.00 630.00 613-40030 Transformer Base Aluminum (Install Only) 60 Each 4,200.00 70.00 613-50010 Photoelectric Cell 425 Each 34,600.00 81.41 613-50200 Lighting System 20 Each 7,000.00 350.00 613-60000 Lamps 450 Each 41,950.00 93.22 613-60500 Underground Repair 80 Each 48,000.00 600.00 613-70250 Luminaire High Pressure Sodium (250 Watt) 105 Each 54,840.00 522.29 613-70255 Fuses 200 Each 10,000.00 50.00 613-70260 Fuse Holder 120 Each 6,000.00 50.00 613-70400 Luminaire High Pressure Sodium (400 Watt) 201 Each 94,140.00 468.36 613-80010 Ballast Unit 75 Each 17,250.00 230.00 614-00011 Sign Panel (Class I) 36,442 Sq Foot 349,012.42 9.58 614-00012 Sign Panel (Class II) 20,473 Sq Foot 263,013.89 12.85 614-00013 Sign Panel (Class III) 2,082 Sq Foot 19,133.58 9.19 614-01502 Steel Sign Post (2 Inch Round) 32,733 Lin Foot 213,036.64 6.51 Colorado Department of Transporation 14:47 Monday, January 13, 2003 4 2002 Cost Data - Maintenance INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE ------------------------------------------------------------------------------------------------------------------------------------ 614-01552 Steel Sign Post (2.5 Inch Round) (Slipbase) 17,000 Lin Foot 381,000.00 22.41 614-01554 Steel Sign Post (4 Inch Round) (Slipbase) 116 Lin Foot 4,640.00 40.00 614-01582 Steel Sign Post (2.5 Inch Round)(Slipbase Sch. 80) 6,849 Lin Foot 118,419.79 17.29 614-10128 Blankout Sign (Fiber Optic) 4 Each 52,300.00 13,075.00 614-10150 12 inch LED (Ball) 1,573 Each 210,500.52 133.82 614-10155 12" LED (Arrow) 192 Each 23,266.46 121.18 614-10160 Signal Head Backplates 10 Each 1,842.00 184.20 614-10161 Signal Head B-Plates(Install Only) 12 Each 600.00 50.00 614-70020 Optical Unit Retrofit Kit 420 Each 140,620.20 334.81 614-70118 Pedestrian Signal Face (18) 98 Each 65,990.08 673.37 614-70336 Traffic Signal Face (12-12-12) 3 Each 2,337.00 779.00 614-70560 Traffic Signal Face (12-12-12-12-12) 2 Each 2,474.00 1,237.00 614-72860 Pedestrian Push Button 2 Each 148.00 74.00 614-72875 Loop Detector Wire 4,896 Lin Foot 10,036.80 2.05 614-72892 Power Feed Wire 1,248 Lin Foot 2,059.20 1.65 614-72896 Intersection Detection System (Camera)(Install Only) 2 Each 1,250.00 625.00 614-72897 Signal Cable (Install Only) 6,000 Lin Foot 6,600.00 1.10 614-73010 Piezo Electric Tube, Class 2 (Install Only) 11 Each 5,500.00 500.00 614-75336 Traffic Signal Face (12-12-12) (Install Only) 62 Each 9,795.88 158.00 614-75560 Traffic Signal Face (12-12-12-12-12) (Install Only) 6 Each 1,570.00 261.67 614-75848 Traffic Signal Controller and Cabinet (Install Only) 2 Each 2,000.00 1,000.00 614-75890 Span Wire Cable (Install Only) 1,600 Lin Foot 1,600.00 1.00 614-79336 Traffic Signal Face (12-12-12) (Furnish Only) 46 Each 31,450.20 683.70 614-79560 Traffic Signal Face (12-12-12-12-12) (Furnish Only) 4 Each 5,134.00 1,283.50 614-79867 Fire Preemption Unit and Timer 1 Each 11,000.00 11,000.00 614-80000 Flashing Beacon 12 Each 6,000.00 500.00 614-81150 Traffic Signal-Light Pole Steel (1-50 Foot Mast Arm) 1 Each 17,500.00 17,500.00 614-85001 Impact Attenuator 5 Each 5,000.00 1,000.00 614-85045 Truck with Mounted Attenuator and Flashing Arrow Pane 3 Each 7,860.00 2,620.00 614-86106 Telemetry (Field)(Install Only) 2 Each 800.00 400.00 614-86755 Deicing System 1 Lump Sum 148,000.00 148,000.00 617-00012 12 Inch Culvert Pipe 140 Lin Foot 8,400.00 60.00 622-11100 Storage Building 1 Each 18,000.00 18,000.00 626-00000 Mobilization 34 Lump Sum 297,948.60 8,763.19 626-00005 Mobilization 50 Day 29,375.00 587.50 627-00004 Epoxy Pavement Marking 59,695 Sq Foot 20,779.35 0.35 627-00005 Epoxy Pavement Marking 126,067 Gallon 4,011,634.75 31.82 627-01003 Preformed Plastic Pavement Marking (Type A) (Inlaid) 128,359 Sq Foot 1,108,142.80 8.63 Colorado Department of Transporation 14:47 Monday, January 13, 2003 5 2002 Cost Data - Maintenance INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/02 THROUGH 12/31/02 ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE ------------------------------------------------------------------------------------------------------------------------------------ 627-03003 Preformed Plastic Pavement Marking (Type C) (Inlaid) 120,155 Sq Foot 1,052,940.00 8.76 627-30405 Preformed Thermoplastic Pavement Marking (Word-Symbol 26,017 Sq Foot 218,636.00 8.40 627-30410 Preformed Thermoplastic Pavement Marking (Xwalk-Stop 43,240 Sq Foot 232,010.00 5.37 630-00000 Flagging 5,284 Hour 98,898.40 18.72 630-00001 Pilot Car Operation 80 Hour 3,200.00 40.00 630-00003 Uniformed Traffic Control 620 Hour 63,900.00 103.06 630-00007 Traffic Control Inspection 18 Day 828.00 46.00 630-00009 Traffic Control Vehicle (Truck) 2 Each 4,512.00 2,256.00 630-00012 Traffic Control Management 739 Day 524,952.31 710.35 630-10005 Traffic Control 35 Lump Sum 451,657.21 12,904.49 630-80341 Construction Traffic Sign (Panel Size A) 238 Each 2,149.00 9.03 630-80342 Construction Traffic Sign (Panel Size B) 156 Each 9,117.40 58.44 630-80343 Construction Traffic Sign (Panel Size C) 12 Each 1,753.20 146.10 630-80344 Construction Traffic Sign (Special) 98 Sq Foot 2,450.00 25.00 630-80355 Portable Message Sign Panel 4 Each 11,816.00 2,954.00 630-80357 Advance Warning Flashing or Sequencing Arrow Panel (B 1 Each 150.00 150.00 630-80358 Advance Warning Flashing or Sequencing Arrow Panel (C 14 Each 11,401.40 814.39 630-80359 Portable Message Sign Panel 1 Day 500.00 500.00 630-80360 Drum Channelizing Device 359 Each 2,616.00 7.29 630-80363 Drum Channelizing Device (With Light) (Flashing) 5 Each 165.00 33.00 630-80364 Drum Channelizing Device (With Light) (Steady Burn) 80 Each 240.00 3.00 630-80368 Portable Traffic Speed Monitor 1 Day 500.00 500.00 630-80370 Concrete Barrier (Temporary) 4,600 Lin Foot 45,520.00 9.90 630-80380 Traffic Cone 1,575 Each 11,179.00 7.10 630-80510 Mobile Pavement Marking Zone 2 Lump Sum 7,501.00 3,750.50 630-85040 Impact Attenuator (Truck Mounted Attenuator) (Tempora 1 Each 500.00 500.00 630-86810 Traffic Signal (Temporary) 1 Each 500.00 500.00 637-00100 Roadway Sweeping 15,820 Shoulder M 776,868.40 49.11 Part 4 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 1 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 202-00001 Rem Structure Each =================================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 1.00 10000.00 11061.00 13000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 10000.00 11061.00 13000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 10000.00 11061.00 13000.00 =============== 202-00240 Rem Asphalt Mat (Planing) Sq Yard ================================================ MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 3,588.80 10.00 20.30 22.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,588.80 10.00 20.30 22.50 MTCE 06-010 SH 285, WADSWORTH TO FEDERAL 05/02/02 150,275.00 1.50 1.66 1.56 MTCE 01-014 I70, BAKERVILLE TO SILVERPLUM 06/27/02 39,424.00 1.50 1.06 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 189,699.00 1.50 1.49 1.44 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 558.00 8.00 7.26 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 558.00 8.00 7.26 5.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 193,845.80 1.68 2.29 1.84 =============== 202-00246 Rem Asphalt Mat (Planing)(Special) Sq Yard ================================================ MTCE 04-019 I25 RAMPS - LOVELAND, SH 287 09/26/02 2,870.00 6.50 13.00 6.00 MTCE 04-021 SH 42 NEAR LOUISVILLE 09/26/02 910.00 6.50 4.48 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,780.00 6.50 9.23 5.52 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,780.00 6.50 9.23 5.52 =============== 202-00250 Rem Pavement Marking Sq Foot ================================================ MTCE 02-007 SH 25 AND 50 STRIPING 02/14/02 38,095.00 0.81 0.81 0.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 38,095.00 0.81 0.81 0.45 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 2 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 202-00250 Rem Pavement Marking Sq Foot ================================================ MTCE 02-008 COLO. SPRINGS PAVEMENT MARKIN 04/25/02 17,333.00 1.20 1.00 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 17,333.00 1.20 1.00 1.00 MTCE 05-015 R-5 WEST EPOXY MARKING 08/22/02 2,000.00 0.75 0.96 0.60 MTCE 05-018 MTCE SECTION 3 (DURANGO) 08/29/02 17,000.00 0.75 1.24 0.65 MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 16,000.00 0.75 1.29 0.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 35,000.00 0.75 1.24 0.65 MTCE 01-020 R-1 EPOXY MARKING 12/05/02 10,000.00 0.75 0.92 0.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10,000.00 0.75 0.92 0.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100,428.00 0.85 1.01 0.64 =============== 202-00425 Rem Bridge Railing Lin Foot =============================================== MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 100.00 18.00 108.06 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 18.00 108.06 75.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100.00 18.00 108.06 75.00 =============== 202-00502 Rem Port Present Str Cubic Yard ============================================= MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 42.60 1000.00 1343.20 1036.00 MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 56.80 500.00 1099.17 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 99.40 714.29 1193.03 1129.71 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 99.40 714.29 1193.03 1129.71 =============== 202-00504 Rem Exp Device Lin Foot =============================================== MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 1,649.20 100.00 133.40 135.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 3 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 202-00504 Rem Exp Device Lin Foot =============================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 787.00 200.00 73.00 52.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,436.20 132.30 111.41 108.19 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 536.00 100.00 202.49 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 536.00 100.00 202.49 80.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,972.20 126.48 129.51 103.10 =============== 202-00700 Rem Light Standard Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 5.00 250.00 584.56 260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 250.00 584.56 260.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 250.00 584.56 260.00 =============== 202-00810 Rem Ground Sign Each =================================================== MTCE 05-016 SIGN REPLACEMENT - ALAMOSA A 08/22/02 2,000.00 5.00 13.93 10.00 MTCE 05-017 SIGN REPLACEMENT - DURANGO AR 08/22/02 3,000.00 5.00 16.62 8.00 MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 3.00 80.00 156.71 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,003.00 5.04 15.55 8.85 MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 350.00 35.00 47.25 15.00 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 418.00 16.00 22.30 12.72 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 768.00 24.66 32.95 13.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,771.00 7.66 18.17 9.50 =============== 202-00821 Rem Sign Panel Each =================================================== MTCE 05-016 SIGN REPLACEMENT - ALAMOSA A 08/22/02 2,000.00 10.00 12.45 7.50 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 4 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 202-00821 Rem Sign Panel Each =================================================== MTCE 05-017 SIGN REPLACEMENT - DURANGO AR 08/22/02 3,000.00 10.00 12.42 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,000.00 10.00 12.43 6.00 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 470.00 14.00 18.56 11.31 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 470.00 14.00 18.56 11.31 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,470.00 10.34 13.06 6.46 =============== 202-00825 Rem Flashing Beacon Each =================================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 4.00 225.00 249.38 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 225.00 249.38 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 225.00 249.38 150.00 =============== 202-00831 Rem Traf Sig Head Each =================================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 3.00 250.00 120.60 41.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 250.00 120.60 41.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 250.00 120.60 41.00 =============== 202-00840 Rem Traf Sig Pole Each =================================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 1.00 1100.00 1572.28 734.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1100.00 1572.28 734.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 1100.00 1572.28 734.00 =============== 202-01000 Rem Fence Lin Foot =============================================== MTCE 06-016 HWYS 72 & 93 FENCING 10/03/02 75,760.00 0.50 0.48 0.30 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 5 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 202-01000 Rem Fence Lin Foot =============================================== MTCE 04-014 FENCING - FT. MORGAN AREA 11/07/02 25,996.00 0.80 0.42 0.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 101,756.00 0.58 0.46 0.28 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 101,756.00 0.58 0.46 0.28 =============== 202-01130 Rem Gdrail Ty 3 Lin Foot =============================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 2,930.00 1.50 2.03 2.45 MTCE 04-025 R-4 GUARDRAIL REPLACEMENT 11/14/02 5,511.00 3.00 1.87 1.42 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8,441.00 2.48 1.90 1.78 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,441.00 2.48 1.90 1.78 =============== 202-01135 Rem Gdrail Thrie Beam Lin Foot =============================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 400.00 4.00 2.90 2.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 400.00 4.00 2.90 2.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 400.00 4.00 2.90 2.85 =============== 202-01300 Rem End Anchorage Each =================================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 38.00 100.00 111.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 38.00 100.00 111.00 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 38.00 100.00 111.00 100.00 =============== 202-04002 Clean Culvert Each =================================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 1.00 2400.00 1388.20 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 2400.00 1388.20 1200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 2400.00 1388.20 1200.00 =============== 202-05100 Sandblasting Reinf Steel Sq Yard ================================================ MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 126.00 25.00 24.87 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 126.00 25.00 24.87 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 126.00 25.00 24.87 10.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 6 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 202-05150 Sandblasting Sq Foot ================================================ MTCE 02-008 COLO. SPRINGS PAVEMENT MARKIN 04/25/02 4,267.00 0.60 0.78 0.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,267.00 0.60 0.78 0.35 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,267.00 0.60 0.78 0.35 =============== 203-00060 Emb Matl (CIP) Cubic Yard ============================================= MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 09/05/02 65.00 15.00 104.61 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 65.00 15.00 104.61 110.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 65.00 15.00 104.61 110.00 =============== 206-00065 Str Bkfl (Flow-Fill) Cubic Yard ============================================= MTCE 04-028 BOX CULVERT - LYONS 10/17/02 37.00 102.00 108.90 78.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 37.00 102.00 108.90 78.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 37.00 102.00 108.90 78.00 =============== 210-00015 Res End Section Each =================================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 1.00 400.00 445.67 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 400.00 445.67 450.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 400.00 445.67 450.00 =============== 210-00500 Reb Port Present Str Each =================================================== MTCE 06-021 R-6 CORBEL & COLUMN REPAIR 12/05/02 5.00 3000.00 9276.67 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 3000.00 9276.67 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 3000.00 9276.67 5000.00 =============== 210-00750 Res Light Standard Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 10.00 1000.00 613.66 510.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 1000.00 613.66 510.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 1000.00 613.66 510.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 7 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 210-00810 Res Ground Sign Each =================================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 1.00 175.00 503.63 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 175.00 503.63 160.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 175.00 503.63 160.00 =============== 210-00815 Res Sign Panel Each =================================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 1.00 175.00 171.65 131.00 MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 350.00 120.00 70.27 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 351.00 120.16 70.66 25.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 351.00 120.16 70.66 25.30 =============== 210-01130 Res Gdrail Ty 3 Lin Foot =============================================== MTCE 03-008 REGION 3 GUARDRAIL REPAIR 12/12/02 1,500.00 20.00 23.44 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,500.00 20.00 23.44 20.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,500.00 20.00 23.44 20.00 =============== 210-04200 Adj Gdrail Lin Foot =============================================== MTCE 03-008 REGION 3 GUARDRAIL REPAIR 12/12/02 2,000.00 3.50 5.17 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,000.00 3.50 5.17 2.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,000.00 3.50 5.17 2.00 =============== 304-06000 ABC (CL 6) Ton ==================================================== MTCE 04-023 SH 85, N OF NUNN 09/26/02 934.00 20.00 17.03 24.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 934.00 20.00 17.03 24.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 934.00 20.00 17.03 24.60 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 8 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 304-07009 ABC (CL 7) (Spec) Ton ==================================================== MTCE 04-022 SH 23 STERLING AREA 08/29/02 135.00 20.00 22.63 25.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 135.00 20.00 22.63 25.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 135.00 20.00 22.63 25.25 =============== 403-00720 HBP (Patching) (Asph) Ton ==================================================== MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 771.30 92.00 149.40 190.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 771.30 92.00 149.40 190.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 771.30 92.00 149.40 190.00 =============== 403-09500 Furnish HBP Ton ==================================================== MTCE 05-009 US 160, EAST OF BAYFIELD 03/28/02 4,422.00 37.00 44.95 44.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,422.00 37.00 44.95 44.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,422.00 37.00 44.95 44.95 =============== 403-33741 HBP (Gr S) (75) (PG 64-22) Ton ==================================================== MTCE 04-022 SH 23 STERLING AREA 08/29/02 6,866.00 55.00 46.79 43.83 MTCE 04-019 I25 RAMPS - LOVELAND, SH 287 09/26/02 4,821.00 44.00 37.50 36.00 MTCE 04-021 SH 42 NEAR LOUISVILLE 09/26/02 4,950.00 36.50 38.98 34.50 MTCE 04-023 SH 85, N OF NUNN 09/26/02 5,394.00 40.00 41.49 32.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22,031.00 44.76 41.09 37.27 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 96.00 65.00 80.70 58.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 96.00 65.00 80.70 58.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22,127.00 44.85 41.36 37.36 =============== 403-34721 HBP (Gr SX) (75) (PG 58-28) Ton ==================================================== MTCE 01-014 I70, BAKERVILLE TO SILVERPLUM 06/27/02 3,252.00 55.00 44.49 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,252.00 55.00 44.49 38.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,252.00 55.00 44.49 38.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 9 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 403-34741 HBP (Gr SX) (75) (PG 64-22) Ton ==================================================== MTCE 01-016 SH 30 & SH 36 OVERLAY, REGION 06/20/02 9,357.00 40.00 45.86 38.74 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9,357.00 40.00 45.86 38.74 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,357.00 40.00 45.86 38.74 =============== 403-34841 HBP (Gr SX) (100) (PG 64-22) Ton ==================================================== MTCE 01-017 I-70 OVERLAY, E. OF LIMON 06/20/02 15,217.00 40.00 47.74 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 15,217.00 40.00 47.74 42.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15,217.00 40.00 47.74 42.00 =============== 403-96600 HBP (Gr Fines) (50) Ton ==================================================== MTCE 01-014 I70, BAKERVILLE TO SILVERPLUM 06/27/02 6,350.00 55.00 42.98 37.25 MTCE 01-015 I70, FLOYD HILL TO CHIEF HOSA 06/27/02 13,242.00 50.00 46.37 37.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 19,592.00 51.62 45.27 37.08 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 19,592.00 51.62 45.27 37.08 =============== 405-00100 Heating and Remixing Treatment Sq Yard ================================================ MTCE 05-009 US 160, EAST OF BAYFIELD 03/28/02 213,235.00 3.28 3.11 3.11 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 213,235.00 3.28 3.11 3.11 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 213,235.00 3.28 3.11 3.11 =============== 406-09501 Cold Bitum Pvmt (Recycled) Ton ==================================================== MTCE 07-001 STATEWIDE RECYCLED PAVEMENT 05/23/02 9,000.00 16.00 14.77 14.77 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9,000.00 16.00 14.77 14.77 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,000.00 16.00 14.77 14.77 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 10 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 408-01000 Hot Joint-Crack Sealant Ton ==================================================== MTCE 03-010 I-70 VAIL PASS CRACK SEAL 09/19/02 35.60 1762.00 1650.00 1500.00 MTCE 04-015 REGION 4 CRACK SEAL 09/19/02 149.60 1825.00 2162.93 1180.00 MTCE 05-020 ALAMOSA SECTION CRACK SEAL 09/26/02 235.30 1400.00 1603.67 1287.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 420.50 1581.85 1880.12 1266.97 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 420.50 1581.85 1880.12 1266.97 =============== 409-02010 CC Matl (Ty II) Ton ==================================================== MTCE 05-013 SH 145, SOUTH OF TELLURIDE 07/18/02 4,167.00 40.00 40.00 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,167.00 40.00 40.00 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,167.00 40.00 40.00 25.00 =============== 409-04050 CC Matl (Spec) Sq Yard ================================================ MTCE 06-020 COLFAX AVE., TOWER RD. WEST 10/03/02 42,399.00 3.50 2.77 2.77 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 42,399.00 3.50 2.77 2.77 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 42,399.00 3.50 2.77 2.77 =============== 409-05000 Ultrath Bond Wearing Course Sq Yard ================================================ MTCE 06-010 SH 285, WADSWORTH TO FEDERAL 05/02/02 150,275.00 5.00 4.23 4.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 150,275.00 5.00 4.23 4.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 150,275.00 5.00 4.23 4.10 =============== 409-06000 Macro-Surfacing Sq Yard ================================================ MTCE 05-011 SH 160, MACROSURFACING, MP 10 05/30/02 289,355.00 1.80 1.75 1.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 289,355.00 1.80 1.75 1.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 289,355.00 1.80 1.75 1.75 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 11 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 411-10216 Emul Asph (CRS-2P) Gallon ================================================= MTCE 06-020 COLFAX AVE., TOWER RD. WEST 10/03/02 2,120.00 1.70 1.69 1.69 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,120.00 1.70 1.69 1.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,120.00 1.70 1.69 1.69 =============== 411-10253 Emul Asph (CSS-1H) Gallon ================================================= MTCE 01-016 SH 30 & SH 36 OVERLAY, REGION 06/20/02 4,253.00 1.00 2.03 0.85 MTCE 01-017 I-70 OVERLAY, E. OF LIMON 06/20/02 6,917.00 1.00 1.41 2.50 MTCE 01-014 I70, BAKERVILLE TO SILVERPLUM 06/27/02 7,744.00 1.00 1.71 1.00 MTCE 01-015 I70, FLOYD HILL TO CHIEF HOSA 06/27/02 12,038.00 1.00 1.40 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 30,952.00 1.00 1.59 1.31 MTCE 06-020 COLFAX AVE., TOWER RD. WEST 10/03/02 1,272.00 1.50 1.19 1.19 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,272.00 1.50 1.19 1.19 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 32,224.00 1.02 1.59 1.31 =============== 411-10275 Emul Asph (HFMS-2P) Gallon ================================================= MTCE 05-013 SH 145, SOUTH OF TELLURIDE 07/18/02 130,948.00 1.35 1.47 1.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 130,948.00 1.35 1.47 1.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 130,948.00 1.35 1.47 1.80 =============== 411-90010 Asph Rejuvenating Agent Gallon ================================================= MTCE 05-009 US 160, EAST OF BAYFIELD 03/28/02 12,794.00 1.90 1.20 1.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12,794.00 1.90 1.20 1.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12,794.00 1.90 1.20 1.20 =============== 502-00200 Drive Steel Piling Lin Foot =============================================== MTCE 05-012 PILE DRIVING ON SH160, MP 70 05/30/02 532.00 15.00 18.00 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 532.00 15.00 18.00 18.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 532.00 15.00 18.00 18.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 12 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 503-00036 Drilled Caisson (36 In) Lin Foot =============================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 18.00 600.00 246.93 151.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 18.00 600.00 246.93 151.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 600.00 246.93 151.00 =============== 515-00120 Waterproofing (Membrane) Sq Yard ================================================ MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 780.00 11.00 20.10 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 780.00 11.00 20.10 12.50 MTCE 04-018 BRIDGE DECK WATERPROOFING, SH 05/30/02 2,730.00 10.80 9.36 8.56 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,730.00 10.80 9.36 8.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,510.00 10.84 13.83 9.44 =============== 518-01002 Br Expan Device (0-2 In) Lin Foot =============================================== MTCE 04-013 SH 34 IN LOVELAND 01/03/02 124.00 160.00 247.25 127.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 124.00 160.00 247.25 127.50 MTCE 04-017 GREELEY AREA EXPANSION JOINTS 05/16/02 955.00 130.00 69.45 57.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 955.00 130.00 69.45 57.80 MTCE 04-027 REGION 4 EXPANSION JOINTS 10/31/02 242.00 160.00 122.19 77.72 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 242.00 160.00 122.19 77.72 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,321.00 138.31 104.17 67.99 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 13 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 518-01004 Br Expan Device (0-4 In) Lin Foot =============================================== MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 1,414.40 130.00 160.30 128.50 MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 787.00 150.00 166.17 127.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,201.40 137.15 162.65 127.96 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 536.00 150.00 168.75 117.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 536.00 150.00 168.75 117.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,737.40 139.67 163.96 125.82 =============== 601-01010 Conc CL BZ Cubic Yard ============================================= MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 3.00 260.00 244.57 225.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 260.00 244.57 225.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 260.00 244.57 225.00 =============== 601-01050 Conc CL B (Wall) Cubic Yard ============================================= MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 09/05/02 17.00 500.00 1126.36 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 17.00 500.00 1126.36 3000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17.00 500.00 1126.36 3000.00 =============== 601-03020 Conc CL D (Misc) Cubic Yard ============================================= MTCE 04-028 BOX CULVERT - LYONS 10/17/02 22.00 550.00 590.05 625.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 22.00 550.00 590.05 625.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22.00 550.00 590.05 625.00 =============== 601-03041 Conc CL D (Bridge) (Spec) Cubic Yard ============================================= MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 172.70 600.00 688.80 654.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 14 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 601-03041 Conc CL D (Bridge) (Spec) Cubic Yard ============================================= MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 56.80 600.00 1560.50 413.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 229.50 600.00 935.48 594.35 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 55.00 600.00 1498.97 1350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 55.00 600.00 1498.97 1350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 284.50 600.00 1056.68 740.44 =============== 601-06150 Conc (Patching) Sq Foot ================================================ MTCE 06-021 R-6 CORBEL & COLUMN REPAIR 12/05/02 295.00 35.00 118.33 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 295.00 35.00 118.33 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 295.00 35.00 118.33 25.00 =============== 601-10250 Slab Jacking Pound ================================================== MTCE 04-016 BOULDER/GREELEY SLAB JACKING 05/09/02 14,150.00 7.40 7.50 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14,150.00 7.40 7.50 7.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,150.00 7.40 7.50 7.50 =============== 601-40301 Struct Conc Coating Sq Foot ================================================ MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 96.00 5.00 17.50 43.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 96.00 5.00 17.50 43.00 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 680.00 0.75 4.96 3.00 MTCE 06-021 R-6 CORBEL & COLUMN REPAIR 12/05/02 1,000.00 1.00 5.59 1.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,680.00 0.90 5.40 1.96 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,776.00 1.12 5.91 4.18 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 15 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 601-40401 Struct Conc Stain Sq Foot ================================================ MTCE 06-021 R-6 CORBEL & COLUMN REPAIR 12/05/02 2,440.00 1.00 3.93 1.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,440.00 1.00 3.93 1.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,440.00 1.00 3.93 1.25 =============== 602-00000 Reinf Steel Pound ================================================== MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 7,419.00 1.00 2.08 1.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7,419.00 1.00 2.08 1.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,419.00 1.00 2.08 1.40 =============== 602-00020 Reinf Steel (Epoxy) Pound ================================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 4,754.00 0.75 0.76 0.60 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 2,000.00 0.75 2.10 1.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6,754.00 0.75 1.21 0.84 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,754.00 0.75 1.21 0.84 =============== 603-70804 8x4 Ft CBC (Precast) Lin Foot =============================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 42.00 520.00 686.80 580.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 42.00 520.00 686.80 580.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 42.00 520.00 686.80 580.00 =============== 604-50050 IG and F Spec Each =================================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 1.00 3500.00 2268.00 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 3500.00 2268.00 1300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 3500.00 2268.00 1300.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 16 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 604-50200 MH R and C Each =================================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 1.00 3000.00 752.40 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 3000.00 752.40 350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 3000.00 752.40 350.00 =============== 606-00301 Gdrail Ty 3 (6-3) Lin Foot =============================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 9,950.00 13.00 10.62 9.65 MTCE 04-025 R-4 GUARDRAIL REPLACEMENT 11/14/02 5,820.00 13.00 12.98 10.53 MTCE 03-008 REGION 3 GUARDRAIL REPAIR 12/12/02 1,000.00 36.00 26.50 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 16,770.00 14.37 12.54 10.57 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16,770.00 14.37 12.54 10.57 =============== 606-00601 Gdrail Ty 6 (6-3) Lin Foot =============================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 375.00 25.00 14.42 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 375.00 25.00 14.42 15.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 375.00 25.00 14.42 15.00 =============== 606-01340 End Anchor Ty 3D Each =================================================== MTCE 04-025 R-4 GUARDRAIL REPLACEMENT 11/14/02 12.00 400.00 471.00 476.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 400.00 471.00 476.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 400.00 471.00 476.00 =============== 606-01370 Transition Ty 3G Each =================================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 2.00 1000.00 806.67 765.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 1000.00 806.67 765.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1000.00 806.67 765.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 17 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 606-02001 End Anchor (SRT) Each =================================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 6.00 1600.00 1131.67 1055.00 MTCE 03-008 REGION 3 GUARDRAIL REPAIR 12/12/02 40.00 3000.00 1950.00 1650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 46.00 2817.39 1843.26 1572.39 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 46.00 2817.39 1843.26 1572.39 =============== 606-02003 End Anchor (Nonflared) Each =================================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 72.00 1500.00 1558.33 1445.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 72.00 1500.00 1558.33 1445.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 72.00 1500.00 1558.33 1445.00 =============== 606-02005 End Anchor (Flared) Each =================================================== MTCE 04-025 R-4 GUARDRAIL REPLACEMENT 11/14/02 12.00 1400.00 1299.67 1098.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 1400.00 1299.67 1098.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 1400.00 1299.67 1098.00 =============== 606-10400 Brdg Rail Ty 4 Lin Foot =============================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 57.50 300.00 244.42 221.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 57.50 300.00 244.42 221.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 57.50 300.00 244.42 221.50 =============== 606-10405 Brdg Rail Ty 4 (Spec) Lin Foot =============================================== MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 100.00 150.00 189.07 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 150.00 189.07 125.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100.00 150.00 189.07 125.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 18 ITE2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 607-00005 End Post Each =================================================== MTCE 04-014 FENCING - FT. MORGAN AREA 11/07/02 8.00 110.00 147.86 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 110.00 147.86 85.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 110.00 147.86 85.00 =============== 607-00010 Corner and Line Br Post Each =================================================== MTCE 04-014 FENCING - FT. MORGAN AREA 11/07/02 53.00 150.00 182.00 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 53.00 150.00 182.00 85.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 53.00 150.00 182.00 85.00 =============== 607-01010 Fence BW MP (Spec) Lin Foot =============================================== MTCE 06-016 HWYS 72 & 93 FENCING 10/03/02 75,760.00 1.50 1.44 1.16 MTCE 04-014 FENCING - FT. MORGAN AREA 11/07/02 25,996.00 1.20 1.30 0.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 101,756.00 1.42 1.40 1.09 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 101,756.00 1.42 1.40 1.09 =============== 608-00000 Conc Sidewalk Sq Yard ================================================ MTCE 04-028 BOX CULVERT - LYONS 10/17/02 3.00 37.00 100.00 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 37.00 100.00 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 37.00 100.00 60.00 =============== 609-21010 C and G Ty 2 I-B Lin Foot =============================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 3.50 13.00 66.20 34.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.50 13.00 66.20 34.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.50 13.00 66.20 34.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 19 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 613-00200 2 In Elec Cond Lin Foot =============================================== MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 200.00 10.00 11.62 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 200.00 10.00 11.62 4.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 200.00 10.00 11.62 4.00 =============== 613-00201 2 In Elec Cond (Jacked) Lin Foot =============================================== MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 456.00 60.00 39.50 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 456.00 60.00 39.50 35.00 MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 250.00 20.00 28.54 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 250.00 20.00 28.54 18.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 706.00 45.84 34.27 28.98 =============== 613-00301 3 In Elec Cond (Jacked) Lin Foot =============================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 250.00 22.00 31.01 19.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 250.00 22.00 31.01 19.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 250.00 22.00 31.01 19.00 =============== 613-00700 Insp Trip Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 22.00 1250.00 1722.33 900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 1250.00 1722.33 900.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22.00 1250.00 1722.33 900.00 =============== 613-01200 2 In Elec Cond (P) Lin Foot =============================================== MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 440.00 12.00 12.25 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 440.00 12.00 12.25 8.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 20 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 613-01200 2 In Elec Cond (P) Lin Foot =============================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 2,000.00 10.00 15.03 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,000.00 10.00 15.03 8.00 MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 250.00 10.00 17.95 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 250.00 10.00 17.95 12.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,690.00 10.33 15.03 8.37 =============== 613-01202 Inst 2 In Elec Cond (P) Lin Foot =============================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 100.00 5.00 14.48 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 100.00 5.00 14.48 8.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100.00 5.00 14.48 8.00 =============== 613-01300 3 In Elec Cond (P) Lin Foot =============================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 250.00 14.00 19.50 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 250.00 14.00 19.50 13.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 250.00 14.00 19.50 13.00 =============== 613-01302 Inst 3 In Elec Cond (P) Lin Foot =============================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 300.00 5.00 15.81 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 300.00 5.00 15.81 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 300.00 5.00 15.81 10.00 =============== 613-05000 Dir Burial Cable Lin Foot =============================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 1,000.00 15.00 8.58 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,000.00 15.00 8.58 7.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 21 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 613-05000 Dir Burial Cable Lin Foot =============================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 1,000.00 13.00 10.77 6.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,000.00 13.00 10.77 6.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,000.00 14.00 9.42 6.65 =============== 613-07000 Pull Box (Spec) Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 5.00 250.00 828.60 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 250.00 828.60 550.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 250.00 828.60 550.00 =============== 613-07026 Pull Box (16"x24"x12") Deep Each =================================================== MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 14.00 325.00 295.00 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14.00 325.00 295.00 200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 325.00 295.00 200.00 =============== 613-07199 Inst Pull Box Each =================================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 3.00 200.00 209.53 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 200.00 209.53 250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 200.00 209.53 250.00 =============== 613-10000 Wiring LUMP SUM =============================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 1.00 2750.00 5177.00 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 2750.00 5177.00 2500.00 MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 1.00 3500.00 3168.98 540.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 22 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 613-10000 Wiring LUMP SUM =============================================== MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 1.00 10000.00 20344.97 480.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 6750.00 8536.47 510.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 5416.67 7416.65 1173.33 =============== 613-20100 Inst Light Std Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 10.00 450.00 771.54 508.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 450.00 771.54 508.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 450.00 771.54 508.00 =============== 613-32300 Light Std Steel (30 Ft) Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 10.00 1500.00 2246.40 1730.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 1500.00 2246.40 1730.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 1500.00 2246.40 1730.00 =============== 613-32400 Light Std Steel (40 Ft) Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 10.00 2200.00 2746.85 1770.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 2200.00 2746.85 1770.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 2200.00 2746.85 1770.00 =============== 613-34400 Light Std Metal (40 Ft) Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 60.00 2000.00 1331.00 850.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 60.00 2000.00 1331.00 850.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 60.00 2000.00 1331.00 850.00 =============== 613-40000 Conc Foundation Pad Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 4.00 800.00 1790.00 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 800.00 1790.00 600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 800.00 1790.00 600.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 23 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 613-40010 Light Std Foundation Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 10.00 600.00 1141.98 630.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 600.00 1141.98 630.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 600.00 1141.98 630.00 =============== 613-40030 Inst Transformer Base Alum Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 60.00 250.00 739.33 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 60.00 250.00 739.33 70.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 60.00 250.00 739.33 70.00 =============== 613-50010 Photoel Cell Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 300.00 100.00 128.33 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 300.00 100.00 128.33 85.00 MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 50.00 120.00 208.97 110.00 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 75.00 100.00 79.15 48.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 125.00 108.00 131.08 72.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 425.00 102.35 129.46 81.41 =============== 613-50200 Lighting System Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 20.00 500.00 302.00 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 500.00 302.00 350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 500.00 302.00 350.00 =============== 613-60000 Lmps Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 350.00 125.00 141.75 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 350.00 125.00 141.75 100.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 24 2002 COST DATA Book (Maintenance) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 613-60000 Lmps Each =================================================== MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 100.00 150.00 109.86 69.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 150.00 109.86 69.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 450.00 130.56 131.46 93.22 =============== 613-60500 Underground Rep Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 80.00 900.00 989.33 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 80.00 900.00 989.33 600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 900.00 989.33 600.00 =============== 613-70250 Lumin HPS (250 W) Each =================================================== MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 50.00 400.00 561.27 450.00 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 55.00 525.00 919.65 588.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 105.00 465.48 748.99 522.29 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 105.00 465.48 748.99 522.29 =============== 613-70255 Fus Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 200.00 50.00 75.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 200.00 50.00 75.00 50.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 200.00 50.00 75.00 50.00 =============== 613-70260 Fus Holder Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 120.00 50.00 123.67 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 120.00 50.00 123.67 50.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 120.00 50.00 123.67 50.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 25 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 613-70400 Lumin HPS (400 W) Each =================================================== MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 150.00 450.00 541.00 475.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 150.00 450.00 541.00 475.00 MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 1.00 1100.00 489.40 390.00 MTCE 01-003 HIGHWAY LIGHTING - REGION 1 10/31/02 50.00 600.00 590.72 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 51.00 609.80 586.45 448.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 201.00 490.55 557.68 468.36 =============== 613-80010 Ballast Un Each =================================================== MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 75.00 250.00 390.24 230.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 75.00 250.00 390.24 230.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 75.00 250.00 390.24 230.00 =============== 614-00011 Sign Panel (CL I) Sq Foot ================================================ MTCE 05-016 SIGN REPLACEMENT - ALAMOSA A 08/22/02 12,000.00 10.00 9.75 9.00 MTCE 05-017 SIGN REPLACEMENT - DURANGO AR 08/22/02 21,000.00 10.00 10.01 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 33,000.00 10.00 9.91 9.64 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 3,442.00 12.00 10.25 9.01 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,442.00 12.00 10.25 9.01 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 36,442.00 10.19 9.95 9.58 =============== 614-00012 Sign Panel (CL II) Sq Foot ================================================ MTCE 05-016 SIGN REPLACEMENT - ALAMOSA A 08/22/02 6,000.00 13.50 13.63 13.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 26 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 614-00012 Sign Panel (CL II) Sq Foot ================================================ MTCE 05-017 SIGN REPLACEMENT - DURANGO AR 08/22/02 11,000.00 13.50 14.59 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 17,000.00 13.50 14.22 13.65 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 3,473.00 15.00 13.60 8.93 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,473.00 15.00 13.60 8.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20,473.00 13.75 14.10 12.85 =============== 614-00013 Sign Panel (CL III) Sq Foot ================================================ MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 2,082.00 20.00 16.66 9.19 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,082.00 20.00 16.66 9.19 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,082.00 20.00 16.66 9.19 =============== 614-01502 Steel Sign Post (2 In Rd) Lin Foot =============================================== MTCE 05-016 SIGN REPLACEMENT - ALAMOSA A 08/22/02 11,000.00 6.00 7.45 7.50 MTCE 05-017 SIGN REPLACEMENT - DURANGO AR 08/22/02 20,000.00 6.00 7.23 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 31,000.00 6.00 7.31 6.53 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 1,733.00 8.25 8.18 6.08 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,733.00 8.25 8.18 6.08 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 32,733.00 6.12 7.37 6.51 =============== 614-01552 Steel Sign Post (2.5 In Rd) (Slip) Lin Foot =============================================== MTCE 05-016 SIGN REPLACEMENT - ALAMOSA A 08/22/02 6,000.00 24.00 24.88 25.00 MTCE 05-017 SIGN REPLACEMENT - DURANGO AR 08/22/02 11,000.00 24.00 24.72 21.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 17,000.00 24.00 24.78 22.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17,000.00 24.00 24.78 22.41 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 27 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 614-01554 Steel Sign Post (4 In Rd) (Slip) Lin Foot =============================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 116.00 60.00 61.62 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 116.00 60.00 61.62 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 116.00 60.00 61.62 40.00 =============== 614-01582 Steel Sign Post (2.5 In Rd)(Slip Sch 80) Lin Foot =============================================== MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 3,500.00 45.00 28.75 25.50 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 3,349.00 23.00 21.61 8.71 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6,849.00 34.24 25.05 17.29 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,849.00 34.24 25.05 17.29 =============== 614-10128 Blankout Sign (Fib Opt) Each =================================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 4.00 15000.00 13832.84 13075.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 15000.00 13832.84 13075.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 15000.00 13832.84 13075.00 =============== 614-10150 12 in LED (Ball) Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 1,573.00 158.83 169.47 133.82 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,573.00 158.83 169.47 133.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,573.00 158.83 169.47 133.82 =============== 614-10155 12" LED (Arr) Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 192.00 118.80 143.36 121.18 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 192.00 118.80 143.36 121.18 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 192.00 118.80 143.36 121.18 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 28 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 614-10160 Sig Head B-Plates Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 10.00 175.00 142.16 184.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 175.00 142.16 184.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 175.00 142.16 184.20 =============== 614-10161 Signal Head B-Plates(Install Only) Each =================================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 12.00 20.00 147.62 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12.00 20.00 147.62 50.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 20.00 147.62 50.00 =============== 614-70020 Opt Unit Retrofit Kit Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 420.00 250.00 318.04 334.81 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 420.00 250.00 318.04 334.81 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 420.00 250.00 318.04 334.81 =============== 614-70118 Ped Sig Face (18) Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 96.00 500.00 722.34 678.23 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 96.00 500.00 722.34 678.23 MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 2.00 800.00 672.00 440.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 800.00 672.00 440.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 98.00 506.12 719.61 673.37 =============== 614-70336 Traf Sig Face (12-12-12) Each =================================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 3.00 1300.00 1026.64 779.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 1300.00 1026.64 779.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 1300.00 1026.64 779.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 29 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 614-70560 Traf Sig Face (12-12-12-12-12) Each =================================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 2.00 1500.00 1559.24 1237.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 1500.00 1559.24 1237.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1500.00 1559.24 1237.00 =============== 614-72860 Ped Push Button Each =================================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 2.00 175.00 216.51 74.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 175.00 216.51 74.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 175.00 216.51 74.00 =============== 614-72875 Loop Detect Wire Lin Foot =============================================== MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 4,896.00 3.00 2.92 2.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,896.00 3.00 2.92 2.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,896.00 3.00 2.92 2.05 =============== 614-72892 Power Feed Wire Lin Foot =============================================== MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 1,248.00 5.00 11.17 1.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,248.00 5.00 11.17 1.65 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,248.00 5.00 11.17 1.65 =============== 614-72896 Intersect Detect Sys (Camera)(Inst Only) Each =================================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 2.00 400.00 855.64 625.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 400.00 855.64 625.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 400.00 855.64 625.00 =============== 614-72897 Signal Cable (Install Only) Lin Foot =============================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 6,000.00 1.00 1.25 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6,000.00 1.00 1.25 1.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,000.00 1.00 1.25 1.10 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 30 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 614-73010 Inst Piezo Elec Tube, CL 2 Each =================================================== MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 11.00 400.00 491.67 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 11.00 400.00 491.67 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 400.00 491.67 500.00 =============== 614-75336 Inst Traf Sig Face (12-12-12) Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 46.00 300.00 302.42 160.78 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 46.00 300.00 302.42 160.78 MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 16.00 135.00 214.20 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 16.00 135.00 214.20 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 62.00 257.42 284.17 158.00 =============== 614-75560 Inst Traf Sig Face (12-12-12-12-12) Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 4.00 400.00 531.65 292.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 400.00 531.65 292.50 MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 2.00 200.00 307.24 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 200.00 307.24 200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 333.33 470.45 261.67 =============== 614-75848 Inst Traf Sig Ctrler + Cab Each =================================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 2.00 800.00 1364.22 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 800.00 1364.22 1000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 800.00 1364.22 1000.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 31 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 614-75890 Inst Span Wire Cable Lin Foot =============================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 1,600.00 1.00 4.55 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,600.00 1.00 4.55 1.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,600.00 1.00 4.55 1.00 =============== 614-79336 Furn Traf Sig Face (12-12-12) Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 46.00 500.00 656.34 683.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 46.00 500.00 656.34 683.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 46.00 500.00 656.34 683.70 =============== 614-79560 Furn Traf Sig Face (12-12-12-12-12) Each =================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 4.00 1000.00 1107.57 1283.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 1000.00 1107.57 1283.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 1000.00 1107.57 1283.50 =============== 614-79867 Fire Preempt Unit + Timer Each =================================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 1.00 22000.00 10683.88 11000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 22000.00 10683.88 11000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 22000.00 10683.88 11000.00 =============== 614-80000 Flash Beacon Each =================================================== MTCE 01-018 SH 285 AND RICHMOND HILL RD 09/05/02 12.00 2000.00 656.99 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12.00 2000.00 656.99 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 2000.00 656.99 500.00 =============== 614-81150 Sig-Light Pole Steel (1-50 Ft) Each =================================================== MTCE 01-010 SH 83 & MAIN ST. SIGNAL 10/03/02 1.00 20000.00 20204.77 17500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 20000.00 20204.77 17500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 20000.00 20204.77 17500.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 32 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 614-85001 Impact Atten Each =================================================== MTCE 03-008 REGION 3 GUARDRAIL REPAIR 12/12/02 5.00 5000.00 2366.67 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 5000.00 2366.67 1000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 5000.00 2366.67 1000.00 =============== 614-85045 Truck w/Mtd Atten & Flash Arrow Panel Each =================================================== MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 2.00 10000.00 7077.96 3180.00 MTCE 06-021 R-6 CORBEL & COLUMN REPAIR 12/05/02 1.00 1000.00 8640.00 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 7000.00 7747.41 2620.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 7000.00 7747.41 2620.00 =============== 614-86106 Telemetry (Field)(Install Only) Each =================================================== MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 2.00 600.00 808.04 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 600.00 808.04 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 600.00 808.04 400.00 =============== 614-86755 Deicing System LUMP SUM =============================================== MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 09/05/02 1.00 170000.00 184127.17 148000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 170000.00 184127.17 148000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 170000.00 184127.17 148000.00 =============== 617-00012 12 In Culvert Pipe Lin Foot =============================================== MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 09/05/02 140.00 25.00 43.79 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 140.00 25.00 43.79 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 140.00 25.00 43.79 60.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 33 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 622-11100 Storage Bldg Each =================================================== MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 09/05/02 1.00 50000.00 64143.00 18000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 50000.00 64143.00 18000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 50000.00 64143.00 18000.00 =============== 626-00000 Mobilization LUMP SUM =============================================== MTCE 07-001 STATEWIDE RECYCLED PAVEMENT 05/23/02 1.00 6000.00 6000.00 6000.00 MTCE 05-012 PILE DRIVING ON SH160, MP 70 05/30/02 1.00 5000.00 5000.00 5000.00 MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 1.00 2500.00 2411.67 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 3178.57 2682.92 3178.57 MTCE 05-014 R-5 EAST EPOXY MARKING 08/22/02 1.00 10000.00 3125.25 1.00 MTCE 05-015 R-5 WEST EPOXY MARKING 08/22/02 1.00 10000.00 3125.25 1.00 MTCE 05-016 SIGN REPLACEMENT - ALAMOSA A 08/22/02 1.00 10000.00 31651.99 20000.00 MTCE 05-017 SIGN REPLACEMENT - DURANGO AR 08/22/02 1.00 10000.00 39821.71 15000.00 MTCE 05-018 MTCE SECTION 3 (DURANGO) 08/29/02 1.00 1000.00 6375.25 5000.00 MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 1.00 1000.00 20250.00 5500.00 MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 09/05/02 1.00 10000.00 22438.00 25000.00 MTCE 04-015 REGION 4 CRACK SEAL 09/19/02 1.00 10000.00 75466.00 97000.00 MTCE 04-029 FY 03 R4 EPOXY WEST 09/26/02 1.00 25000.00 2500.75 1.00 MTCE 04-032 REGION 4 EPOXY EAST 09/26/02 1.00 25000.00 2000.80 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10.00 11200.00 23459.96 16750.40 MTCE 06-020 COLFAX AVE., TOWER RD. WEST 10/03/02 1.00 10000.00 47400.00 47400.00 MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 1.00 1000.00 1000.00 1000.00 MTCE 04-030 STENCIL MARKING R4 10/10/02 1.00 25000.00 3000.60 5000.00 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 1.00 4000.00 8722.40 2500.00 MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 1.00 10000.00 21770.00 22810.00 MTCE 01-020 R-1 EPOXY MARKING 12/05/02 1.00 10000.00 4334.00 1.00 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 1.00 15000.00 7224.84 4233.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7.00 7800.00 8445.02 8594.46 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 6897.06 13128.74 8763.19 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 34 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 626-00005 Mobilization Day ==================================================== MTCE 03-008 REGION 3 GUARDRAIL REPAIR 12/12/02 50.00 500.00 662.50 587.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 50.00 500.00 662.50 587.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50.00 500.00 662.50 587.50 =============== 627-00004 Epoxy Pvmt Mkg Sq Foot ================================================ MTCE 02-007 SH 25 AND 50 STRIPING 02/14/02 38,095.00 0.90 0.57 0.33 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 38,095.00 0.90 0.57 0.33 MTCE 02-008 COLO. SPRINGS PAVEMENT MARKIN 04/25/02 21,600.00 1.00 0.66 0.38 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 21,600.00 1.00 0.66 0.38 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 59,695.00 0.94 0.60 0.35 =============== 627-00005 Epoxy Pvmt Mkg Gallon ================================================= MTCE 01-016 SH 30 & SH 36 OVERLAY, REGION 06/20/02 144.00 50.00 127.20 130.00 MTCE 01-017 I-70 OVERLAY, E. OF LIMON 06/20/02 169.00 60.00 111.06 89.25 MTCE 01-014 I70, BAKERVILLE TO SILVERPLUM 06/27/02 35.00 60.00 213.43 205.00 MTCE 01-015 I70, FLOYD HILL TO CHIEF HOSA 06/27/02 510.00 50.00 71.67 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 858.00 52.38 98.56 83.42 MTCE 05-014 R-5 EAST EPOXY MARKING 08/22/02 22,750.00 31.00 32.01 30.79 MTCE 05-015 R-5 WEST EPOXY MARKING 08/22/02 19,900.00 31.00 31.98 30.69 MTCE 04-029 FY 03 R4 EPOXY WEST 09/26/02 20,038.00 33.00 35.00 31.00 MTCE 04-032 REGION 4 EPOXY EAST 09/26/02 18,506.00 33.00 31.90 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 81,194.00 31.95 32.67 30.64 MTCE 01-020 R-1 EPOXY MARKING 12/05/02 44,015.00 33.50 34.67 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 44,015.00 33.50 34.67 33.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 126,067.00 32.63 33.64 31.82 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 35 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 627-01003 Preform Plastic Pvmt Mkg (Ty A) (Inlaid) Sq Foot ================================================ MTCE 02-008 COLO. SPRINGS PAVEMENT MARKIN 04/25/02 1,717.00 12.00 13.08 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,717.00 12.00 13.08 10.00 MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 45,300.00 10.36 11.94 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 45,300.00 10.36 11.94 9.00 MTCE 01-020 R-1 EPOXY MARKING 12/05/02 81,342.00 7.40 8.63 8.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 81,342.00 7.40 8.63 8.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 128,359.00 8.50 10.08 8.63 =============== 627-03003 Preform Plastic Pvmt Mkg (Ty C) (Inlaid) Sq Foot ================================================ MTCE 02-008 COLO. SPRINGS PAVEMENT MARKIN 04/25/02 1,267.00 15.00 14.33 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,267.00 15.00 14.33 10.00 MTCE 01-020 R-1 EPOXY MARKING 12/05/02 118,888.00 7.60 8.92 8.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 118,888.00 7.60 8.92 8.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 120,155.00 7.68 8.97 8.76 =============== 627-30405 Preform Thermoplastic Pvmt Mkg (WS) Sq Foot ================================================ MTCE 05-018 MTCE SECTION 3 (DURANGO) 08/29/02 14,000.00 10.00 10.44 8.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 14,000.00 10.00 10.44 8.75 MTCE 04-030 STENCIL MARKING R4 10/10/02 12,017.00 10.50 8.84 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12,017.00 10.50 8.84 8.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 26,017.00 10.23 9.61 8.40 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 36 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 627-30410 Preform Thermoplastic Pvmt Mkg (XS) Sq Foot ================================================ MTCE 05-018 MTCE SECTION 3 (DURANGO) 08/29/02 20,000.00 7.00 7.75 5.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20,000.00 7.00 7.75 5.50 MTCE 04-030 STENCIL MARKING R4 10/10/02 23,240.00 7.00 6.18 5.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 23,240.00 7.00 6.18 5.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 43,240.00 7.00 6.82 5.37 =============== 630-00000 Flagging Hour =================================================== MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 500.00 25.00 21.25 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 500.00 25.00 21.25 15.00 MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 400.00 25.00 23.00 23.00 MTCE 04-030 STENCIL MARKING R4 10/10/02 1,500.00 22.00 6.80 10.00 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 24.00 23.00 22.50 22.00 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 480.00 32.00 19.55 20.33 MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 480.00 35.00 18.58 5.00 MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 1,500.00 30.00 28.98 28.60 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 400.00 18.50 18.17 29.03 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,784.00 26.78 16.86 19.11 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,284.00 26.61 17.22 18.72 =============== 630-00001 Pilot Car Operation Hour =================================================== MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 80.00 30.00 40.00 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 80.00 30.00 40.00 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 30.00 40.00 40.00 =============== 630-00003 Uniformed Traf Ctrl Hour =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 250.00 50.00 88.42 106.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 250.00 50.00 88.42 106.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 37 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-00003 Uniformed Traf Ctrl Hour =================================================== MTCE 06-010 SH 285, WADSWORTH TO FEDERAL 05/02/02 70.00 50.00 62.50 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 70.00 50.00 62.50 80.00 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 300.00 90.00 86.85 106.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 300.00 90.00 86.85 106.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 620.00 69.35 86.54 103.06 =============== 630-00007 Traf Ctrl Inspection Day ==================================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 18.00 120.00 67.60 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 18.00 120.00 67.60 46.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 120.00 67.60 46.00 =============== 630-00009 Traf Ctrl Vehicle (Truck) Each =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 2.00 15000.00 7459.33 2256.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 15000.00 7459.33 2256.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 15000.00 7459.33 2256.00 =============== 630-00012 Traf Ctrl Mgmt Day ==================================================== MTCE 03-001 VARIOUS LOCATIONS IN REGION 3 01/03/02 80.00 400.00 581.89 488.55 MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 120.00 600.00 1478.60 1525.00 MTCE 03-007 TRAFFIC CONTROL REGION 3 01/24/02 25.00 1525.00 1560.00 1560.00 MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 25.00 400.00 569.00 666.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 250.00 608.50 1093.80 1110.94 MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 200.00 350.00 350.00 350.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 38 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-00012 Traf Ctrl Mgmt Day ==================================================== MTCE 04-028 BOX CULVERT - LYONS 10/17/02 3.00 400.00 418.20 350.00 MTCE 04-027 REGION 4 EXPANSION JOINTS 10/31/02 5.00 1000.00 1348.33 1100.00 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 60.00 350.00 464.50 642.00 MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 60.00 350.00 302.40 300.00 MTCE 03-008 REGION 3 GUARDRAIL REPAIR 12/12/02 60.00 1000.00 1100.00 1200.00 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 101.00 300.00 247.48 417.31 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 489.00 426.38 389.87 505.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 739.00 487.99 630.07 710.35 =============== 630-10005 Traf Ctrl LUMP SUM =============================================== MTCE 04-013 SH 34 IN LOVELAND 01/03/02 1.00 10000.00 22550.00 2100.00 MTCE 02-007 SH 25 AND 50 STRIPING 02/14/02 1.00 10000.00 2875.25 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 10000.00 14680.10 2300.00 MTCE 02-008 COLO. SPRINGS PAVEMENT MARKIN 04/25/02 1.00 15000.00 7333.33 7000.00 MTCE 06-010 SH 285, WADSWORTH TO FEDERAL 05/02/02 1.00 30000.00 30683.75 35367.50 MTCE 04-016 BOULDER/GREELEY SLAB JACKING 05/09/02 1.00 15000.00 18000.00 18000.00 MTCE 04-017 GREELEY AREA EXPANSION JOINTS 05/16/02 1.00 9500.00 8949.50 5000.00 MTCE 05-011 SH 160, MACROSURFACING, MP 10 05/30/02 1.00 20000.00 5000.00 5000.00 MTCE 07-002 STATEWIDE TRAFFIC LOOP REPAIR 06/13/02 1.00 3000.00 1903.33 1700.00 MTCE 01-016 SH 30 & SH 36 OVERLAY, REGION 06/20/02 1.00 15000.00 21851.00 21610.00 MTCE 01-017 I-70 OVERLAY, E. OF LIMON 06/20/02 1.00 22000.00 32593.88 18385.50 MTCE 01-014 I70, BAKERVILLE TO SILVERPLUM 06/27/02 1.00 11000.00 49860.88 67765.00 MTCE 01-015 I70, FLOYD HILL TO CHIEF HOSA 06/27/02 1.00 26000.00 48656.67 49970.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 9825.00 12545.06 12339.90 MTCE 05-013 SH 145, SOUTH OF TELLURIDE 07/18/02 1.00 20000.00 39346.33 50000.00 MTCE 02-011 HWY 24 G & MARKSHEFFEL RD. 07/18/02 1.00 5000.00 11069.63 4000.00 MTCE 02-010 REGION 2, STREET LIGHTING 07/25/02 1.00 30000.00 29300.00 26400.00 MTCE 04-022 SH 23 STERLING AREA 08/29/02 1.00 4000.00 18270.00 20800.00 MTCE 02-009 SH 67 NEAR CRIPPLE CREEK 09/05/02 1.00 7500.00 10227.20 5500.00 MTCE 03-010 I-70 VAIL PASS CRACK SEAL 09/19/02 1.00 15000.00 10000.00 15000.00 MTCE 04-019 I25 RAMPS - LOVELAND, SH 287 09/26/02 1.00 15000.00 49750.00 16500.00 MTCE 04-021 SH 42 NEAR LOUISVILLE 09/26/02 1.00 9000.00 16298.67 10000.00 MTCE 04-023 SH 85, N OF NUNN 09/26/02 1.00 4000.00 18412.50 14000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 12166.67 20740.25 18022.22 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 39 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-10005 Traf Ctrl LUMP SUM =============================================== MTCE 06-020 COLFAX AVE., TOWER RD. WEST 10/03/02 1.00 3000.00 7984.21 7984.21 MTCE 04-025 R-4 GUARDRAIL REPLACEMENT 11/14/02 1.00 40000.00 12975.00 12000.00 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 1.00 21000.00 23739.98 16575.00 MTCE 06-021 R-6 CORBEL & COLUMN REPAIR 12/05/02 1.00 5000.00 18512.11 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 17250.00 17949.23 9514.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25.00 11285.71 15694.25 12904.49 =============== 630-80341 Const Traf Sign (A) Each =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 2.00 100.00 83.75 94.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 100.00 83.75 94.50 MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 20.00 50.00 87.50 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 50.00 87.50 20.00 MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 200.00 15.00 5.00 5.00 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 16.00 70.00 34.60 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 216.00 19.07 13.46 7.22 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 238.00 22.35 31.65 9.03 =============== 630-80342 Const Traf Sign (B) Each =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 15.00 130.00 109.50 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 130.00 109.50 120.00 MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 12.00 70.00 138.75 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12.00 70.00 138.75 20.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 40 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-80342 Const Traf Sign (B) Each =================================================== MTCE 04-030 STENCIL MARKING R4 10/10/02 60.00 120.00 13.20 25.00 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 8.00 150.00 130.92 53.50 MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 8.00 150.00 69.74 10.00 MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 13.00 70.00 52.83 55.00 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 40.00 78.00 58.98 108.86 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 129.00 105.66 46.02 54.86 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 156.00 105.26 56.82 58.44 =============== 630-80343 Const Traf Sign (C) Each =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 4.00 180.00 129.33 148.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 180.00 129.33 148.00 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 8.00 139.00 76.57 145.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 139.00 76.57 145.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 152.67 89.76 146.10 =============== 630-80344 Const Traf Sign (Spec) Sq Foot ================================================ MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 98.00 20.00 29.83 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 98.00 20.00 29.83 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 98.00 20.00 29.83 25.00 =============== 630-80355 Port Mesg Panel Each =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 1.00 15000.00 6892.31 5076.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 15000.00 6892.31 5076.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 41 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-80355 Port Mesg Panel Each =================================================== MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 2.00 10000.00 6422.50 1250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 10000.00 6422.50 1250.00 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 1.00 5000.00 5556.27 4240.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 5000.00 5556.27 4240.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 10000.00 6303.57 2954.00 =============== 630-80357 Flash Arrow Panel (B Ty) Each =================================================== MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 1.00 500.00 150.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 500.00 150.00 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 500.00 150.00 150.00 =============== 630-80358 Flash Arrow Panel (C Ty) Each =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 2.00 3000.00 1156.00 2256.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 3000.00 1156.00 2256.00 MTCE 04-030 STENCIL MARKING R4 10/10/02 3.00 1250.00 72.20 250.00 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 1.00 1252.00 418.20 350.00 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 2.00 2000.00 1314.30 535.00 MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 2.00 2000.00 641.00 50.00 MTCE 06-015 R-6 EXPANSION JOINT REPAIR 11/14/02 2.00 1000.00 1329.63 1590.00 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 2.00 646.00 665.36 719.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 1357.83 717.17 574.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 1592.43 777.01 814.39 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 42 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-80359 Port Mesg Panel Day ==================================================== MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 1.00 200.00 500.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 200.00 500.00 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 200.00 500.00 500.00 =============== 630-80360 Drum Channel Dev Each =================================================== MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 25.00 50.00 88.50 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 25.00 50.00 88.50 25.00 MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 300.00 10.00 3.00 3.00 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 24.00 72.00 30.60 34.00 MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 10.00 35.00 28.45 27.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 334.00 15.20 12.06 5.96 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 359.00 17.63 25.96 7.29 =============== 630-80363 Drum Channel Dev (Light) (F) Each =================================================== MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 5.00 40.00 36.17 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 40.00 36.17 33.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 40.00 36.17 33.00 =============== 630-80364 Drum Channel Dev (Light) (SB) Each =================================================== MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 80.00 15.00 3.00 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 80.00 15.00 3.00 3.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 15.00 3.00 3.00 =============== 630-80368 Port Traf Speed Monitor Day ==================================================== MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 1.00 200.00 500.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 200.00 500.00 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 200.00 500.00 500.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 43 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-80370 Conc Barrier (Temp) Lin Foot =============================================== MTCE 03-005 SH 70, 131, 141, AND 340 IN R 01/17/02 4,400.00 25.00 17.01 9.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,400.00 25.00 17.01 9.05 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 200.00 30.00 22.82 28.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 200.00 30.00 22.82 28.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,600.00 25.22 17.26 9.90 =============== 630-80380 Traffic Cone Each =================================================== MTCE 06-006 R-6 EXPANSION JOINT REPAIR 03/14/02 100.00 20.00 15.08 16.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 100.00 20.00 15.08 16.95 MTCE 05-019 MTCE SECTION 3 (DURANGO AREA) 08/29/02 100.00 15.00 37.00 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 100.00 15.00 37.00 6.00 MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 500.00 5.00 1.50 1.50 MTCE 04-030 STENCIL MARKING R4 10/10/02 150.00 17.00 11.20 15.00 MTCE 04-028 BOX CULVERT - LYONS 10/17/02 25.00 14.00 8.40 12.00 MTCE 06-019 OVERHEAD SIGN LIGHTING - R6 10/31/02 200.00 15.00 12.99 6.42 MTCE 06-018 SIGN POST REPLACEMENT - R6 10/31/02 200.00 15.00 8.62 5.00 MTCE 05-021 REGION 5 - GUARDRAIL UPGRADE 11/07/02 50.00 12.00 5.70 5.50 MTCE 04-031 FY 03 WEST SIGNS R-4 12/19/02 250.00 8.50 10.09 12.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,375.00 10.27 9.50 6.46 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,575.00 11.19 11.44 7.10 =============== 630-80510 Mobile Pvmt Mkg Zone LUMP SUM =============================================== MTCE 04-029 FY 03 R4 EPOXY WEST 09/26/02 1.00 12000.00 2125.50 7500.00 COLORADO DEPARTMENT OF TRANSPORTATION 11:44 Friday, January 17, 2003 44 2002 COST DATA BOOK (MAINTENANCE) -- ITEM UNIT COSTS BY PROJECTS -- ------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/ PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID ------------------------------------------------------------------------------------------------------------------------------------ =============== 630-80510 Mobile Pvmt Mkg Zone LUMP SUM =============================================== MTCE 04-032 REGION 4 EPOXY EAST 09/26/02 1.00 10000.00 200.80 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 11000.00 1056.22 3750.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 11000.00 1056.22 3750.50 =============== 630-85040 Impact Atten (T-M-A) (Temp) Each =================================================== MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 1.00 1000.00 500.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1000.00 500.00 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 1000.00 500.00 500.00 =============== 630-86810 Traffic Signal (Temp) Each =================================================== MTCE 03-009 REGION 3 TRAFFIC CONTROL 10/03/02 1.00 500.00 500.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 500.00 500.00 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 500.00 500.00 500.00 =============== 637-00100 Roadway Sweep Shoulder Mile ========================================== MTCE 06-008 REGION 6 SWEEPING 01/31/02 7,840.00 50.00 61.17 48.34 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7,840.00 50.00 61.17 48.34 MTCE 06-012 REGION 6 SWEEPING 10/03/02 7,980.00 50.00 49.86 49.86 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7,980.00 50.00 49.86 49.86 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15,820.00 50.00 57.36 49.11