2025 Cost Data (January — December) Compiled By: Cost Estimating Services Unit of the Construction Engineering Services Branch February 3, 2026 2025 Cost Data: Construction Table of Contents Number of Pages List of 2025 Bid Projects 8 Bridge Cost per Square Feet 2 Item Unit Costs by Projects 687 Colorado Cost Data Foreword The Colorado Department of Transportation’s Cost Estimating Services Unit of the Construction Engineering Services Branch publishes the Cost Data Book annually. A joint effort has been made between the Department’s sections and the Cost Estimating Services Unit to gather and record cost data for this publication. The following data includes weighted average prices for items on highway construction projects that were bid during the 2025 calendar year. Caution should be used in applying these historical averages to specific projects. Allowances for varying geographic, climatic, social, economic conditions and type of project should be made. Changes and improvements are continually being made to update and increase the usefulness for future issues. Comments and suggestions for improvements for users of this publication are welcome. Bid Letting Contractor/ Project Number Location Dist Terrain Bids Awarded Bid Index 20250109 BRANNAN SAND AND GRAVEL, LLC NHPP2873-206 US287:RESURFACING I-70 TO 92ND 6 U 3 $12,912,912.00 96.97 20250116 STRUCTURES, INC. 2670252-499 I-25:MOBILITY HUB (LONE TREE) 1 R 6 $16,509,889.28 142.33 20250116 Lobato Construction, LLC STRR200-288 CO 9B, US 24A, US 24G, CO 67C, 2 M 7 $1,798,366.30 62.01 20250130 STURGEON ELECTRIC COMPANY, INC STM0132-025 CO13 MM 90.2, US40Z MM 0.65, M 3 U 3 $1,280,705.00 83.07 20250130 KSK, LLC NHPP0702-428 I-70 THROUGH GLENWOOD CANYON I 3 M 5 $6,295,000.00 83.20 20250206 Native Sun Materials Inc BRR100-400 VAR LOCATIONS R1 I25, I225 & I 1 U 4 $2,684,443.68 76.70 20250206 OLDCASTLE SW GROUP, INC. NHPP0403-069 US 40 MP 215.90 - 219.88 IN GR 3 M 2 $5,792,196.70 91.19 20250213 Adiona Transportation Solutions SHE0881-032 LLC FEDERAL BLVD SIGNALS 41st and 1 U 6 $934,434.00 84.95 20250220 ASPHALT SPECIALTIES NHPP0072-033 CO., INC. CO7 28TH ST TO CHERRYVALE RD ( 4 U 4 $8,058,760.55 87.60 20250227 RDZ Build BR0761-249 I-76 4 U 6 $3,259,684.20 101.57 20250228 Myers & Sons STR141A-056 Construction, LLC SH 141 MP 85.5 K-01-B BRIDGE 5 R 4 $2,088,196.75 87.92 20250306 STREAMLINE MARKINGS, LLC MTCER500-233 REGION 5 5 R 6 $1,834,021.50 71.81 20250313 ROADSAFE TRAFFIC SYSTEMS, INC 2 $993,522.30 90.32 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 2 R 20250320 OLDCASTLE SW GROUP, NHPP085A-020 INC. US85:I-76 TO 124TH AVENUE OVER 6 R 3 $7,290,197.96 96.69 20250327 OLDCASTLE SW GROUP, NHPP0403-063 INC. US40 RESURFACING MP 252-258.3 1 M 4 $11,822,056.73 104.62 20250327 TRICON 2, LLC NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 6 P 3 $247,000.00 98.80 20250327 Kilgore Companies, STM141A-057 LLC dba Elam Construc SH141 GATEWAY MP 120 SOUTH 3 M 2 $7,979,767.68 85.17 20250403 BRANNAN SAND STU1191-044 AND GRAVEL, LLC CO119 AND CO 7 FROM US36 (28TH 4 U 1 $4,654,489.73 97.02 20250410 MORTON ELECTRIC, STAM765-015 INC. US50/MAPLE & US287/CEDAR, LAMA 2 U 2 $1,482,502.69 92.66 20250411 KRAEMER NORTH NHPP0703-517 AMERICA, LLC I-70 TOP OF FLOYD HILL TO VETE 1 M 1 $434,861,012.42 101.08 FBR0703-534 I-70 1 M 20250417 MORTON ELECTRIC, C0821-113 INC. CO-82 & Catherine Store Signal 3 M 1 $635,240.00 103.20 20250424 MARTIN MARIETTA STM2873-232 MATERIALS SH287 & LCR 72 AND US287 & OWL 4 R 3 $617,732.65 77.22 20250501 STRUCTURES, STAR500-223 INC. SH50 MM 189.71, US550 MM 98.33 5 R 4 $963,303.00 88.88 20250508 CASTLE ROCK STMM153-003 CONST. CO. OF COLO, LLC CO 17 & SOUTH OF CO 14 4 P 3 $3,502,761.33 71.82 Bid Letting Contractor/ Project Number Location Dist Terrain Bids Awarded Bid Index 20250508 AMERICAN WEST CONSTRUCTION, NHPP0703-536 LLC I-70 DILLON TO EJMT MM 204 TO 3 M 1 $3,373,121.00 76.40 20250508 AMERICAN WEST CONSTRUCTION, STAR500-228 LLC REGION 5 5 R 3 $1,581,538.00 80.65 20250508 STREAMLINE MARKINGS, LLC MTCER300-288 I-70 MM 0-205 REGION WIDE 3 M 2 $1,994,789.44 93.02 20250522 STRUCTURES, INC. NHPP2254-095 I-225 @ 2ND AND 6TH AVES 1 U 3 $2,780,679.42 86.90 20250523 JALISCO INTERNATIONAL, INC. NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 6 U 1 $10,683,069.23 100.00 20250605 Myers & Sons Construction, LLC C0405-042 US 40 IN DEER TRAIL, PINE ST T 1 R 5 $672,753.24 140.16 20250605 INSITUFORM TECHNOLOGIES, LLC NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 1 U 3 $2,422,341.00 89.88 20250605 WORK ZONE TRAFFIC CONTROL, LLC MTCE0361-135 US-36B FROM MP 0.00-33.76 IN B 4 R 4 $928,777.95 106.00 20250612 RIDGWAY VALLEY ENTERPRISES, INC. NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 3 R 4 $4,999,614.34 65.64 20250618 CONNELL RESOURCES, INC. ER060A-028 CO 60 (MP 9-10) 4 U 2 $488,198.00 110.27 20250626 DILLIE AND KUHN, INC. ITSSW03-250 FRONT RANGE 0 P 4 $5,379,255.25 118.96 20250626 ROADSAFE TRAFFIC SYSTEMS, INC MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTNI 2 R 1 $3,546,943.50 110.84 Bid Letting Contractor/ Project Number Location Dist Terrain Bids Awarded Bid Index 20250703 Barricade Holdings LLC MTCE0702-434 I-70 MP 130 TO 168, REGION 3 3 M 3 $656,656.00 131.43 20250703 ROADSAFE TRAFFIC MTCE0402-112 SYSTEMS, INC REGION 3 STENCIL PROJECT ON HI 3 M 2 $448,562.85 89.86 20250711 KRAEMER NORTH STA119A-078 AMERICA, LLC CO 119 (MM 44.237-55.5) 4 U 1 $19,859,813.00 98.67 20250717 LIGHTHOUSE TRANSPORTATION SHE1211-107 GROUP, LLC WADSWORTH BLVD & EVANS AVE 1 U 4 $655,850.00 91.73 20250717 SUBSURFACE, CR400-406 INC REGION-WIDE 4 P 3 $1,864,082.67 107.38 20250724 STRUCTURES, BR0704-265 INC. I-70 EAST 1 R 4 $7,235,022.57 99.21 FBR0704-269 I-70 EAST 1 R 20250724 BRANNAN SAND MTCE0703-541 AND GRAVEL, LLC I-70 EISENHOWER-JOHNSON MEMORI 1 M 1 $2,769,129.65 173.07 20250814 SUBSURFACE, INC C0142-070 SH 14 MP 75.5-85 4 M 3 $196,525.00 71.58 20250814 GOODLAND CONSTRUCTION, CR400-400 INC. VARIOUS LOCATIONS THROUGHOUT R 4 R 4 $2,394,994.00 104.14 20250814 STURGEON ELECTRIC COMPANY, INC SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN,R 1 R 4 $1,459,900.10 48.66 20250815 RALPH L. WADSWORTH CONSTRUCTION FBR0063-066 CO., LLC US 6D IN GARFIELD COUNTY 3 M 1 $10,092,629.21 102.62 20250821 Myers & Sons NHPP0704-260 Construction, LLC I-70 AND PENA BLVD OVERPASS 6 R 5 $818,181.81 90.91 Bid Letting Contractor/ Project Number Location Dist Terrain Bids Awarded Bid Index 20250821 ABCO CONTRACTING, INC. MTCER400-411 SH157 MP3.518 D-16-DG AND I70 4 U 4 $612,588.00 79.12 20250821 WORK ZONE TRAFFIC CONTROL, LLC MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNTI 2 R 2 $1,781,582.00 98.98 20250911 STURGEON ELECTRIC COMPANY, INC FSA052A-053 SH 52 AND WCR 41 SIGNALIZATION 4 P 5 $597,027.50 76.05 20250911 INSITUFORM TECHNOLOGIES, LLC STR050A-042 FREMONT COUNTY IN R2 2 R 5 $1,440,920.00 96.06 20250918 W.W. CLYDE & CO. FBR2851-014 US 50 CONEJOS RIVER BRIDGE STR 5 R 5 $2,866,394.00 78.47 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES 5 R 20250918 Siete, Inc. STR025A-054 I-25C NORTH OUT OF WALSENBURG 2 R 8 $5,987,513.44 89.37 20250926 RLW/SEMA, A Joint Venture 1 $78,893,355.45 101.90 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 25 4 U 20250926 KIEWIT INFRASTRUCTURE SPFS2706-055 CO. I-270 MP 0-3 6 R 1 $1,373,255.58 107.65 20251016 Native Sun Materials NHPP070A-042 Inc I70B EAST OF 3RD STREET 3 U 4 $13,244,314.90 86.05 20251016 STREAMLINE MARKINGS, MTCER400-415 LLC REGION 4 4 R 2 $2,542,335.29 91.38 20251023 OLDCASTLE SW STR012A-054 GROUP, INC. SH12 MP 46.7 to MP 48.1 2 M 5 $3,489,752.57 83.09 20251023 OLDCASTLE SW GROUP, INC. 4 $6,480,440.65 85.53 NHPP0241-070 US 24 MP 192.73 TO 202.30 5 R Bid Letting Contractor/ Project Number Location Dist Terrain Bids Awarded Bid Index 20251023 Myers & Sons Construction, STM318A-002 LLC SH 318 MP 1.25 IN MOFFAT COUNT 3 M 8 $2,095,785.00 110.44 20251023 ABCO CONTRACTING, NHPPR500-227 INC. REGION 5 SECTION 7 5 R 4 $2,065,188.00 84.46 20251023 CC ENTRPRS TRAFFIC MTCER100-428 CONTROL SPECIALISTS I-25 (DENVER TO MONUMENT), I-7 1 U 3 $195,959.50 54.43 20251030 KSK, LLC C0063-067 US 6 PALISADE IMPROVEMENTS MP 3 U 6 $7,160,000.00 84.32 20251106 OLDCASTLE SW GROUP, INC. 2 $7,999,978.41 97.56 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.66 2 M 20251106 EDW. C. LEVY NH0243-097 CO. US 24 - MP 332.02 TO MP 342.65 2 P 2 $11,325,943.09 100.23 20251113 MORTON ELECTRIC, C1601-088 INC. US 160 SIGNALS MILDRED & HARRI 5 U 2 $1,379,406.89 95.90 20251113 C & D ELECTRIC, MTCER200-297 INC. REGION 2 EL PASO COUNTY COLORA 2 U 3 $235,510.00 94.20 20251120 BETTIS ASPHALT STR3501-019 & CONSTRUCTION, INC. MINDEMAN TO EAST OF SH 71 JUNC 2 P 2 $6,675,478.19 84.50 20251120 ASPHALT SPECIALTIES STM052A-062 CO., INC. CO52A RESURFACING I25 TO US85 4 P 5 $8,874,349.77 87.61 20251120 OLDCASTLE SW NH160A-036 GROUP, INC. US160A HUERFANO MP 294.4 TO 30 2 R 2 $9,155,884.13 78.93 20251204 Harper Brothers NHPP0705-083 Construction LLC I-70: SEIBERT EAST PART 2 4 P 5 $30,092,191.10 102.16 Bid Letting Contractor/ Project Number Location Dist Terrain Bids Awarded Bid Index 20251204 OLDCASTLE SW GROUP, INC. 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 5 R 1 $9,174,121.50 105.58 20251204 Kilgore Companies, LLC dba NHPP0701-257 Elam Construc MP 138-148 ON I-70 IN EAGLE CO 3 M 2 $18,121,443.25 98.25 20251204 OLDCASTLE SW STM340A-022 GROUP, INC. CO 340 GRAND AVE TO REDLANDS P 3 R 3 $5,609,674.21 103.93 20251204 ABCO CONTRACTING, NHPP2706-048 INC. I-270 MP 0 - MP 5 6 R 4 $4,834,255.00 80.57 20251204 ACME CONCRETE STA157A-013 PAVING, INC. CO 157 (MM 2.8-4.5) 4 U 3 $4,299,635.45 91.66 20251204 LIGHTHOUSE TRANSPORTATION GROUP, LLC 4 $5,688,636.50 104.13 ITSSW03-417 STATEWIDE 0 M 20251204 Kilgore Companies, NHPP0701-260 LLC dba Elam Construc I-70 MP 80.5 TO MP 88 IN GARFI 3 M 2 $8,192,268.13 81.69 20251204 MORTON ELECTRIC, INC. SHER200-309 REGION 2 WIDE VARIOUS LOCATION 2 U 5 $382,111.03 107.64 20251211 OLDCASTLE SW GROUP, INC. NHPP0501-071 US50 DELTA RESURFACE MP 72 WES 3 U 2 $7,587,320.55 74.11 20251211 OLDCASTLE SW GROUP, INC. 2 $12,017,516.10 84.03 NHPP0402-107 R3 US 40 MILNER EAST AND WEST, 3 M 20251211 ABCO CONTRACTING, INC. 4 $1,791,461.00 70.70 NHPP1602-194 US 160 MP 174.1 5 M 20251218 MARTIN MARIETTA MATERIALS 3 $12,305,350.98 85.45 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 2 P Bid Contractor/ Letting Project Number Location Dist Terrain Bids Awarded Bid Index 20251218 HUDICK EXCAVATING, FBR086A-061 INC. CO 86 (MP 22.75-22.89) 4 P 10 $5,097,021.85 91.20 20251218 Native Sun Materials Inc 3 $8,859,322.69 130.53 STAR500-226 R5 HWYS 550, 491, 285, 184, 17 5 M 20251218 OLDCASTLE SW GROUP, INC. 5 $2,440,781.14 152.07 BR0402-109 US40 MP 108.4 OVER SHELTON DIT 3 M Totals 306 $1,383,729,125.51 98.64 Project Number/ Terr/ Total Total Cost Per Date Let Project Location Bridge ID Length Width Square Ft Cost Square Foot BRIDGE REPAIR 250206 BRR100-400 VAR LOCATIONS R1 I25, I225 & I U 0300 213.0000 39.0000 8307.0 $107,074 $12.89 0301 346.5000 173.0000 59944.5 $695,165 $11.60 0302 543.5000 67.0000 36414.5 $495,348 $13.60 250228 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE R 0300 103.0000 28.0000 2884.0 $82,342 $28.55 250724 BR0704-265 I-70 EAST R F-20-BJ 485.2500 40.5000 19652.6 $1,597,909 $81.31 F-20-BL 488.0000 40.2190 19626.9 $1,544,044 $78.67 250724 FBR0704-269 R F-20-BB 93.5000 42.0000 3927.0 $371,627 $94.63 F-20-BA 93.5000 42.0000 3927.0 $371,627 $94.63 250918 NHPP2851-009 R US 285 CONEJOS RIVER BRIDGES 0300 157.1670 33.5000 5265.1 $134,057 $25.46 251204 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE CO M F-10-AA 1126.0000 42.0000 47292.0 $66,818 $1.41 F-10-AB 1126.0000 42.0000 47292.0 $66,818 $1.41 F-09-AH 88.0000 42.0000 3696.0 $66,818 $18.08 F-09-AI 88.0000 42.0000 3696.0 $66,818 $18.08 F-09-AD 88.0000 42.0000 3696.0 $66,818 $18.08 F-09-AG 449.0000 42.0000 18858.0 $66,818 $3.54 F-09-AE 88.0000 42.0000 3696.0 $66,818 $18.08 F-09-AF 399.0000 42.0000 16758.0 $66,818 $3.99 251204 NHPP2706-048 I-270 MP 0 - MP 5 R E-17-QA 910.0000 71.0000 64610.0 $1,136,115 $17.58 Weighted Average Cost: New Structures 369542.6 $7,069,852 $19.13 Project Number/ Terr/ Total Total Cost Per Date Let Project Location Bridge ID Length Width Square Ft Cost Square Foot CONCRETE SLAB AND GIRDER 251204 NHPP0705-083 I-70: SEIBERT EAST PART 2 P 0300 246.0000 42.0000 10332.0 $418,261 $40.48 0301 246.0000 38.0000 Weighted Average Cost: New Structures 9348.0 19680.0 $418,261 $836,521 $44.74 $42.51 PEDESTRIAN OR BIKEWAY BRIDGE 250116 2670252-499 I-25:MOBILITY HUB (LONE TREE) R 0302 286.0000 14.0000 4004.0 $6,317,408 $1,577.77 Weighted Average Cost: New Structures 4004.0 $6,317,408 $1,577.77 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 201-00000 Clear and Grub Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 20000.00 6317.76 12000.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 10000.00 53833.33 53000.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 25000.00 7271.67 4300.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 10000.00 96000.00 70000.00 BR0761-249 I-76 02/27/25 1.00 10000.00 33955.67 25000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 20000.00 36038.61 17500.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 40636.01 12585.63 5100.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 50000.00 87280.97 32136.36 Weighted Average for the First Quarter 8.00 23204.50 41630.24 27379.55 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 50000.00 34000.00 34000.00 NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET I-70 SH287 & LCR 72 AND US287 & OW 04/11/25 04/24/25 1.00 1.00 548317.95 23768.57 393072.59 4350.00 393072.59 6500.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 34702.43 34702.43 34702.43 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 1.00 7500.00 9185.35 3500.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 15000.00 75804.99 44000.00 Weighted Average for the Second Quarter 6.00 113214.82 54931.45 85962.50 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 12354.63 11244.21 11244.21 CR400-406 REGION-WIDE 07/17/25 1.00 16378.16 60666.67 22000.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 19278.40 4409.25 3955.00 C0142-070 SH 14 MP 75.5-85 08/14/25 1.00 10000.00 9371.67 5000.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 55193.15 41885.12 41885.12 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 19010.55 4403.30 1700.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 1.00 15000.00 15356.00 9055.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 1.00 1.00 65000.00 60000.00 44553.56 74279.82 40000.00 70000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 947755.54 966965.13 966965.13 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 10.00 121997.04 60101.37 117180.45 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 50000.00 69765.25 54560.99 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 36280.93 42694.66 18000.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 41109.54 58959.50 55000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 25000.00 29053.17 18200.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 35770.38 39483.63 33236.65 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 18662.93 27395.98 42500.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 25000.00 20148.33 10000.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 10000.00 18030.00 21060.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 25000.00 33635.00 35000.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 12300.00 102049.38 87484.67 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 25000.00 29200.00 40000.00 Weighted Average for the Fourth Quarter 11.00 27647.62 43786.66 37731.12 Weighted Average for the Year 35.00 68257.69 49201.24 66333.09 201-00001 Clear and Grub Acre STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 9.60 10000.00 3966.67 2400.01 Weighted Average for the Second Quarter 9.60 10000.00 3966.67 2400.01 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 0.10 45000.00 98200.00 50000.00 Weighted Average for the Third Quarter 0.10 45000.00 98200.00 50000.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 0.84 12347.97 13510.00 12020.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.70 7726.09 13586.76 3620.00 Weighted Average for the Fourth Quarter 5.54 8426.88 13584.11 4893.65 Weighted Average for the Year 15.24 9657.80 10574.70 3618.83 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 201-00005 Rem of Debris Lump Sum STR050A-042 FREMONT COUNTY IN R2 09/11/25 1.00 15000.00 15439.00 5020.00 Weighted Average for the Third Quarter 1.00 15000.00 15439.00 5020.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 6000.00 23701.90 28000.00 Weighted Average for the Fourth Quarter 1.00 6000.00 23701.90 28000.00 Weighted Average for the Year 2.00 10500.00 18537.59 16510.00 201-00009 Rem of Debris Cubic Yard NHPP1602-194 US 160 MP 174.1 12/11/25 25.00 500.00 432.56 980.00 Weighted Average for the Fourth Quarter 25.00 500.00 432.56 980.00 Weighted Average for the Year 25.00 500.00 432.56 980.00 202-00000 Rem Str and Obstructions Lump Sum STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 14338.44 14338.44 14338.44 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 30927.17 3533.06 3533.06 Weighted Average for the Third Quarter 2.00 22632.81 8935.75 8935.75 Weighted Average for the Year 2.00 22632.81 8935.75 8935.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00001 Rem Structure Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 3302.51 1600.19 2810.15 Weighted Average for the First Quarter 1.00 3302.51 1600.19 2810.15 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 12998.74 19590.08 19590.08 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 12998.74 19590.08 19590.08 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 30927.17 16175.46 16175.46 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 3677.89 3654.00 3654.00 Weighted Average for the Third Quarter 2.00 17302.53 9914.73 9914.73 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 3000.00 3252.50 3500.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 1000.00 1441.17 1000.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 250.00 6565.38 14636.38 Weighted Average for the Fourth Quarter 3.00 1416.67 3190.54 6378.79 Weighted Average for the Year 7.00 7879.47 4036.62 8766.58 202-00002 Rem of Structure (Spec) Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 1.00 3000.00 5430.01 3800.00 Weighted Average for the Second Quarter 1.00 3000.00 5430.01 3800.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 9077.37 7865.12 7865.12 Weighted Average for the Third Quarter 2.00 9077.37 7865.12 7865.12 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00002 Rem of Structure (Spec) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 9.00 1000.00 676.66 171.64 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 5000.00 916.67 1000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 2000.00 9967.34 16501.10 Weighted Average for the Fourth Quarter 11.00 1454.55 1131.69 1731.44 Weighted Average for the Year 14.00 2653.91 1817.15 2755.44 202-00003 Rem of Structure (Spec) Lump Sum FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 78419.34 73421.77 73421.77 Weighted Average for the Third Quarter 1.00 78419.34 73421.77 73421.77 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 30000.00 17410.31 14291.24 Weighted Average for the Fourth Quarter 1.00 30000.00 17410.31 14291.24 Weighted Average for the Year 2.00 54209.67 28612.60 43856.51 202-00008 Tree Trimming Hour STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 6.00 280.14 650.00 100.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 100.00 527.60 765.49 765.49 FBR0703-534 I-70 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 32.00 205.73 415.00 225.00 Weighted Average for the Second Quarter 138.00 442.20 597.06 611.22 Weighted Average for the Year 138.00 442.20 597.06 611.22 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00010 Rem Tree Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 26.00 702.59 361.67 318.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 6.00 1500.00 2037.50 3300.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 250.00 2121.33 648.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 13.00 695.99 2110.52 642.70 Weighted Average for the First Quarter 46.00 794.89 899.76 805.89 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 8.00 692.00 1441.67 625.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6.00 893.83 893.83 893.83 Weighted Average for the Second Quarter 14.00 778.50 1332.10 740.21 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 1272.55 2593.79 2593.79 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 42.00 607.75 607.74 607.74 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 55.00 546.35 790.17 750.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10.00 1350.76 1366.00 1366.00 Weighted Average for the Third Quarter 111.00 668.22 800.87 818.11 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 17.00 1200.00 1578.75 1815.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 500.00 1471.67 1490.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 52.00 621.91 1217.37 1535.00 Weighted Average for the Fourth Quarter 73.00 749.85 1267.49 1597.74 Weighted Average for the Year 244.00 722.85 1038.31 1044.59 202-00011 Tree Trimming Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 1000.00 1149.88 1149.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 2.00 1000.00 1149.88 1149.50 Weighted Average for the Year 2.00 1000.00 1149.88 1149.50 202-00012 Rem Tree Stump Each FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 5.00 297.05 999.30 205.00 Weighted Average for the Fourth Quarter 5.00 297.05 999.30 205.00 Weighted Average for the Year 5.00 297.05 999.30 205.00 202-00015 Rem Headwall Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6.00 4046.36 5496.38 5496.38 FBR0703-534 I-70 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 3500.00 22190.76 14000.00 Weighted Average for the Second Quarter 7.00 3968.31 12174.13 6711.18 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 2283.24 6285.00 9000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 2100.26 3463.87 2750.20 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 250.00 4235.58 2295.17 Weighted Average for the Fourth Quarter 3.00 1544.50 5105.95 4681.79 Weighted Average for the Year 10.00 3241.17 8640.04 6102.37 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00019 Rem Inlet Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 1581.90 1012.23 625.40 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 1848.22 4148.42 2448.38 Weighted Average for the First Quarter 5.00 1741.70 2580.33 1719.19 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 I-70 DILLON TO EJMT MM 204 TO 05/08/25 15.00 4.00 4046.36 3000.00 2908.97 1900.00 2908.97 1900.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6.00 3107.20 3107.20 3107.20 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 3000.00 6552.95 9000.00 Weighted Average for the Second Quarter 26.00 3628.41 3313.43 3033.76 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 2750.33 2750.33 2750.33 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 45.00 1970.17 1792.99 1792.99 Weighted Average for the Third Quarter 47.00 2003.37 1833.73 1833.73 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 13.00 1500.00 2397.47 2334.89 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6.00 1500.00 1618.83 1300.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 1800.00 4297.57 2900.00 Weighted Average for the Fourth Quarter 20.00 1515.00 2198.22 2052.68 Weighted Average for the Year 98.00 2321.48 2324.54 2190.94 202-00021 Rem Manhole Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 983.06 1021.71 375.24 Weighted Average for the First Quarter 1.00 983.06 1021.71 375.24 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00021 Rem Manhole Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 17.00 7658.44 8103.78 8103.78 FBR0703-534 I-70 Weighted Average for the Second Quarter 17.00 7658.44 8103.78 8103.78 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 3636.35 4872.03 4872.03 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 6182.61 1685.36 1685.36 Weighted Average for the Third Quarter 3.00 5333.86 2747.58 2747.58 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 8.00 2600.00 2726.24 2454.94 Weighted Average for the Fourth Quarter 8.00 2600.00 2726.24 2454.94 Weighted Average for the Year 29.00 5792.35 4127.19 5724.89 202-00023 Rem Emb Prot Ty 3 Each BR0761-249 I-76 02/27/25 2.00 1000.00 1567.00 750.00 Weighted Average for the First Quarter 2.00 1000.00 1567.00 750.00 Weighted Average for the Year 2.00 1000.00 1567.00 750.00 202-00024 Rem Emb Prot Ty 5 Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 15.00 1989.75 2029.19 2029.19 Weighted Average for the Third Quarter 15.00 1989.75 2029.19 2029.19 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 15.00 1989.75 2029.19 2029.19 202-00025 Rem Ditch Lining Lin Foot FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 45.00 47.99 128.67 128.67 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 300.00 18.65 23.79 20.00 Weighted Average for the Third Quarter 345.00 22.47 25.72 34.17 Weighted Average for the Year 345.00 22.47 25.72 34.17 202-00026 Rem S and D Pave Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 59.00 60.07 31.13 31.80 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 359.00 13.88 45.42 15.79 Weighted Average for the First Quarter 418.00 20.40 42.60 18.05 NHPP0703-517 FBR0703-534 NHPP0501-080 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 SH50A MP 89.93 CEADAR CREEK 06/12/25 51.00 82.00 68.14 75.00 23.88 153.70 23.88 68.00 Weighted Average for the Second Quarter 133.00 72.37 136.23 51.08 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 8.00 291.21 292.59 267.00 Weighted Average for the Fourth Quarter 8.00 291.21 292.59 267.00 Weighted Average for the Year 559.00 36.64 62.35 29.47 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00027 Rem Riprap Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 114.00 35.95 43.15 24.38 Weighted Average for the First Quarter 114.00 35.95 43.15 24.38 Weighted Average for the Year 114.00 35.95 43.15 24.38 202-00030 Rem Water Service Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 1500.00 1239.17 2000.00 Weighted Average for the Fourth Quarter 1.00 1500.00 1239.17 2000.00 Weighted Average for the Year 1.00 1500.00 1239.17 2000.00 202-00031 Rem of Fire Hydrant Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 1438.52 1438.52 1438.52 Weighted Average for the Second Quarter 1.00 1438.52 1438.52 1438.52 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4.00 3000.00 3073.38 2168.52 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 2500.00 2747.83 2100.00 Weighted Average for the Fourth Quarter 5.00 2900.00 2984.59 2154.82 Weighted Average for the Year 6.00 2656.42 2917.37 2035.43 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00032 Rem Valve Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 17.00 550.00 917.97 216.86 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 11.00 1200.00 626.17 700.00 Weighted Average for the Fourth Quarter 28.00 805.36 774.24 406.67 Weighted Average for the Year 28.00 805.36 774.24 406.67 202-00033 Rem Pipe Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 1000.00 859.37 800.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 5000.00 3380.00 3500.00 Weighted Average for the Fourth Quarter 2.00 3000.00 2005.11 2150.00 Weighted Average for the Year 2.00 3000.00 2005.11 2150.00 202-00035 Rem Pipe Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 144.00 46.01 54.61 82.68 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 129.00 53.70 38.87 29.99 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 13.00 115.00 164.00 225.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2,152.00 25.10 65.36 51.01 Weighted Average for the First Quarter 2,438.00 28.33 63.33 52.70 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2,429.00 124.11 81.28 81.28 FBR0703-534 I-70 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 190.00 400.00 40.00 40.00 STAR500-228 REGION 5 05/08/25 59.50 60.00 253.33 180.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00035 Rem Pipe Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 128.00 78.26 78.26 78.26 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 8.00 137.64 530.00 530.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 134.00 60.00 84.21 110.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 350.00 38.52 46.35 22.70 Weighted Average for the Second Quarter 3,298.50 125.41 83.76 76.60 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 332.00 421.31 77.68 77.68 CR400-406 REGION-WIDE 07/17/25 48.00 63.08 226.67 330.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 232.00 67.02 36.06 36.06 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 6,697.00 53.71 50.72 50.72 Weighted Average for the Third Quarter 7,309.00 70.89 54.89 53.31 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3,642.00 38.00 32.33 31.32 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 136.00 50.00 191.18 135.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 502.00 50.00 31.69 25.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 63.00 64.15 81.19 82.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 92.00 55.39 105.59 67.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 840.00 95.00 85.28 28.87 Weighted Average for the Fourth Quarter 5,275.00 49.14 48.14 34.24 Weighted Average for the Year 18,320.50 68.78 56.23 51.93 202-00036 Rem of Pipe (Spec) Lin Foot NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 236.00 50.00 137.37 125.00 Weighted Average for the Second Quarter 236.00 50.00 137.37 125.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 15.00 80.29 272.97 272.97 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 15.00 80.29 272.97 272.97 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 240.00 120.00 147.78 36.34 Weighted Average for the Fourth Quarter 240.00 120.00 147.78 36.34 Weighted Average for the Year 491.00 85.14 143.05 86.18 202-00037 Rem of End Section Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 430.36 432.53 250.16 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 650.00 1230.00 2000.00 Weighted Average for the First Quarter 4.00 485.27 512.27 687.62 NHPP0703-517 FBR0703-534 STAR500-228 I-70 TOP OF FLOYD HILL TO VET I-70 REGION 5 04/11/25 05/08/25 5.00 6.00 1652.91 1000.00 1034.97 933.33 1034.97 880.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 49.00 700.00 1181.67 1145.00 Weighted Average for the Second Quarter 60.00 809.41 1151.06 1109.33 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 738.32 738.32 738.32 CR400-406 REGION-WIDE 07/17/25 4.00 458.17 788.33 550.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 22.00 1052.60 405.01 405.01 Weighted Average for the Third Quarter 32.00 919.37 570.00 485.63 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 10.00 481.49 1363.99 615.00 Weighted Average for the Fourth Quarter 10.00 481.49 1363.99 615.00 Weighted Average for the Year 106.00 799.44 1060.45 858.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00039 Rem of Bollard Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 700.00 642.16 1115.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 18.00 150.00 400.07 350.00 Weighted Average for the First Quarter 20.00 205.00 418.69 426.50 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 62.00 67.40 413.25 233.00 Weighted Average for the Third Quarter 62.00 67.40 413.25 233.00 Weighted Average for the Year 82.00 100.96 414.55 280.20 202-00040 Rem Elec Conduit Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 9,325.00 12.37 12.36 12.36 FBR0703-534 I-70 Weighted Average for the Second Quarter 9,325.00 12.37 12.36 12.36 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 200.00 13.26 22.10 22.10 Weighted Average for the Third Quarter 200.00 13.26 22.10 22.10 Weighted Average for the Year 9,525.00 12.39 12.56 12.56 202-00055 Rem of FO Cable Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 125.00 2.17 3.78 5.30 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,280.00 2.17 3.55 3.06 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 1,405.00 2.17 3.58 3.26 NHPP0703-517 FBR0703-534 ITSSW03-250 I-70 TOP OF I-70 FRONT RANGE FLOYD HILL TO VET 04/11/25 06/26/25 38,960.00 415.00 2.25 2.21 2.25 1.82 2.25 2.00 Weighted Average for the Second Quarter 39,375.00 2.25 2.23 2.25 Weighted Average for the Year 40,780.00 2.25 2.40 2.28 202-00060 Rem Trav Time Indicator Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 488.56 845.59 292.56 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 488.56 317.81 280.56 Weighted Average for the First Quarter 2.00 488.56 634.48 286.56 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 584.67 584.66 584.66 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 584.67 584.66 584.66 Weighted Average for the Year 3.00 520.60 629.95 385.93 202-00090 Rem Delineator Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 52.00 40.00 13.89 14.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 82.00 20.00 16.53 17.00 BR0761-249 I-76 02/27/25 22.00 20.00 37.55 100.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 100.00 14.72 20.39 10.20 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 300.00 7.71 12.91 12.36 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00090 Rem Delineator Each STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 298.00 10.00 10.50 5.00 Weighted Average for the First Quarter 854.00 12.79 14.90 12.34 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 25.00 12.00 20.00 20.00 STAR500-228 REGION 5 05/08/25 40.00 12.00 19.33 17.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 18.00 17.06 17.06 17.06 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 124.00 14.08 25.33 25.00 Weighted Average for the Second Quarter 207.00 13.68 23.46 22.16 CR400-406 REGION-WIDE 07/17/25 38.00 15.64 44.00 11.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 40.00 15.03 155.00 46.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 5.00 110.50 11.05 11.05 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 42.00 15.07 10.67 12.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 10.00 19.08 21.17 24.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 10.00 32.53 42.80 20.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 12.00 30.00 20.00 15.37 50.22 24.41 30.00 15.00 Weighted Average for the Third Quarter 187.00 19.24 54.18 21.75 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 317.00 9.34 30.28 20.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 27.00 3.17 56.02 55.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 10.00 20.00 44.36 30.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 30.00 25.00 18.83 20.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 116.00 12.23 14.10 16.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 736.00 5.87 7.13 5.05 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 401.00 7.42 9.97 10.30 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 346.00 6.63 5.25 5.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 500.00 8.05 24.01 26.85 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 239.00 9.88 36.40 54.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 264.00 30.00 3.58 2.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00090 Rem Delineator Each STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 15.00 16.00 23.68 6.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 75.00 76.67 120.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 475.00 10.00 6.30 6.30 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 324.00 7.59 8.00 8.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 70.00 9.40 12.00 12.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 234.00 40.00 12.53 12.75 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 46.00 25.00 53.77 121.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 8.00 20.00 43.20 90.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 832.00 6.11 4.45 4.50 Weighted Average for the Fourth Quarter 4,991.00 10.67 16.19 13.37 Weighted Average for the Year 6,239.00 11.32 17.92 13.77 202-00120 Rem CBC Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 92.00 257.22 390.73 390.73 Weighted Average for the Third Quarter 92.00 257.22 390.73 390.73 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 330.00 353.36 76.24 Weighted Average for the Fourth Quarter 40.00 330.00 353.36 76.24 Weighted Average for the Year 132.00 279.27 369.58 295.43 202-00150 Rem Wall Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4.00 2021.93 1763.23 5000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 4.00 2021.93 1763.23 5000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 6.00 3594.91 5721.80 4290.30 Weighted Average for the Fourth Quarter 6.00 3594.91 5721.80 4290.30 Weighted Average for the Year 10.00 2965.72 2842.84 4574.18 202-00155 Rem Wall Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 361.00 32.50 42.02 27.13 Weighted Average for the First Quarter 361.00 32.50 42.02 27.13 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 120.00 221.73 194.09 194.09 FBR0703-534 I-70 Weighted Average for the Second Quarter 120.00 221.73 194.09 194.09 Weighted Average for the Year 481.00 79.71 50.00 68.78 202-00170 Grinding And Texturing Conc Pvmt Sq Yard STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 73,504.00 7.00 7.47 5.90 NHPP1602-194 US 160 MP 174.1 12/11/25 4,305.00 20.00 25.26 31.00 Weighted Average for the Fourth Quarter 77,809.00 7.72 8.76 7.29 Weighted Average for the Year 77,809.00 7.72 8.76 7.29 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00190 Rem of Conc Median Cover Matl Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 14.00 72.00 38.40 38.85 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 9.00 35.00 60.40 54.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 604.00 25.00 20.28 20.35 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 14.00 64.60 40.58 45.95 Weighted Average for the First Quarter 641.00 27.03 21.76 21.79 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 175.00 18.69 18.69 18.69 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 7.00 50.00 54.50 45.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 462.00 16.52 24.18 11.70 Weighted Average for the Third Quarter 644.00 17.47 24.12 13.96 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 233.00 18.00 20.30 10.68 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6.00 50.00 47.00 36.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 100.00 198.15 71.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 976.00 11.69 26.87 29.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 7.00 45.00 488.97 155.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 49.00 25.00 36.67 45.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 539.00 72.00 17.05 8.50 Weighted Average for the Fourth Quarter 1,811.00 31.12 26.24 21.51 Weighted Average for the Year 3,096.00 27.43 24.89 20.00 202-00195 Rem of Median Cover Sq Yard NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 226.00 25.57 33.00 40.80 Weighted Average for the First Quarter 226.00 25.57 33.00 40.80 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00195 Rem of Median Cover Sq Yard STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 12.00 68.53 99.00 108.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2,647.00 15.37 15.37 15.37 Weighted Average for the Second Quarter 2,659.00 15.61 16.12 15.79 Weighted Average for the Year 2,885.00 16.39 19.54 17.75 202-00200 Rem Sidewalk Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,578.00 25.00 34.91 35.32 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 24.00 34.29 33.46 37.52 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 22.00 50.00 92.75 110.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 128.00 40.00 45.60 54.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 809.00 35.00 20.87 22.70 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 5.00 91.75 35.59 51.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 70.00 38.83 49.24 31.21 Weighted Average for the First Quarter 2,636.00 29.58 31.71 32.92 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 9.50 61.54 112.50 105.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 120.00 1,309.00 30.26 16.95 24.84 16.95 24.84 16.95 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 26.00 60.00 33.72 20.00 Weighted Average for the Second Quarter 1,464.50 19.09 20.08 18.22 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,524.00 11.68 11.68 11.68 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 69.00 51.53 39.00 35.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1,323.00 17.79 29.00 36.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 66.00 47.81 94.57 94.57 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 15.00 53.33 42.84 40.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 2,997.00 16.30 26.58 24.92 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3,265.00 18.00 19.64 9.06 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 538.00 30.00 19.27 17.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 20.00 1000.00 36.80 35.20 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 74.00 44.26 34.80 29.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 255.00 55.00 37.26 30.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 184.00 55.00 33.85 37.00 Weighted Average for the Fourth Quarter 4,336.00 28.21 20.97 12.92 Weighted Average for the Year 11,433.50 24.24 24.83 21.36 202-00201 Rem Curb Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 500.00 12.90 13.96 14.13 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2.00 8.00 116.33 140.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 104.00 25.00 10.73 12.50 Weighted Average for the First Quarter 606.00 14.96 13.58 14.27 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 14.00 25.88 59.50 39.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 30.00 30.00 95.00 95.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1,837.00 9.99 9.99 9.99 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 33.12 26.33 20.00 Weighted Average for the Second Quarter 1,901.00 10.67 12.78 11.65 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 47.00 24.18 14.28 15.10 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 62.00 18.20 29.51 29.51 Weighted Average for the Third Quarter 109.00 20.78 18.05 23.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00201 Rem Curb Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 560.00 9.00 7.36 5.44 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 420.00 20.00 8.66 10.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 789.00 14.09 7.06 3.10 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 240.00 17.95 18.69 20.15 Weighted Average for the Fourth Quarter 2,009.00 14.37 9.53 7.23 Weighted Average for the Year 4,625.00 13.08 10.93 10.35 202-00202 Rem Gutter Lin Foot STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 47.00 15.00 29.90 29.90 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 140.00 120.00 43.00 43.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 110.00 10.09 10.09 10.09 Weighted Average for the Second Quarter 297.00 62.68 28.74 28.74 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 48.00 19.10 38.11 38.11 Weighted Average for the Third Quarter 48.00 19.10 38.11 38.11 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 394.00 9.00 18.10 10.38 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 282.00 13.97 35.73 44.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 55.00 25.84 33.22 40.50 Weighted Average for the Fourth Quarter 731.00 12.18 23.94 25.62 Weighted Average for the Year 1,076.00 26.43 24.70 27.04 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00203 Rem Curb and Gutter Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 3,331.00 16.00 15.13 15.30 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,080.00 11.25 11.98 13.14 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 18.00 25.00 106.42 150.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 125.00 28.45 19.92 22.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 3,552.00 15.00 10.95 10.65 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 465.00 18.77 17.88 13.25 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 451.00 29.44 23.37 15.61 Weighted Average for the First Quarter 9,022.00 16.04 13.61 13.48 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1,416.00 14.00 23.95 23.95 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 32.00 42.09 48.00 50.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 778.00 5,985.00 36.87 11.37 19.82 11.37 19.82 11.37 Weighted Average for the Second Quarter 8,211.00 14.36 14.61 14.49 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 711.00 12.14 12.14 12.14 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 130.00 32.40 16.25 15.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1,620.00 9.88 15.53 15.10 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 95.00 36.04 17.79 15.00 Weighted Average for the Third Quarter 2,556.00 12.63 15.49 14.27 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6,044.00 11.00 10.46 6.08 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,933.00 15.00 10.26 9.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 263.00 18.19 37.74 60.50 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 233.00 15.00 22.35 18.70 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,382.00 13.43 19.09 20.15 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 696.00 19.77 13.20 13.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 260.00 15.00 23.16 25.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 376.00 14.00 23.83 16.50 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0501-071 202-00203 Rem Curb and Gutter US50 DELTA RESURFACE MP 72 WE 12/11/25 Lin Foot 1,410.00 20.00 6.60 5.00 Weighted Average for the Fourth Quarter 12,597.00 13.77 12.40 10.40 Weighted Average for the Year 32,386.00 14.46 13.24 12.60 202-00204 Rem C, G and Sidewalk Lin Foot STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 30.00 50.00 53.80 53.80 Weighted Average for the Second Quarter 30.00 50.00 53.80 53.80 Weighted Average for the Year 30.00 50.00 53.80 53.80 202-00206 Rem Conc Curb Ramp Sq Yard STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 15.00 50.00 97.75 130.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 107.00 35.00 45.69 54.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1,829.00 45.00 20.30 20.45 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 17.00 73.17 33.30 45.90 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 91.00 84.41 56.23 34.33 Weighted Average for the First Quarter 2,059.00 46.49 24.29 23.82 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 13.00 30.00 59.80 59.80 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 7.00 39.52 141.00 132.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 13.00 233.98 14.82 14.82 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 184.00 32.35 32.35 32.35 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 217.00 44.52 39.72 36.16 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 51.00 45.35 45.35 45.35 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 27.00 58.66 40.13 36.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 3,033.00 35.00 33.75 36.00 Weighted Average for the Third Quarter 3,111.00 35.38 33.85 36.15 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 165.00 40.00 31.95 37.40 Weighted Average for the Fourth Quarter 165.00 40.00 31.95 37.40 Weighted Average for the Year 5,552.00 39.99 30.10 31.61 202-00207 Rem of Brick Pavers Sq Yard NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 3.00 48.00 50.94 50.00 Weighted Average for the First Quarter 3.00 48.00 50.94 50.00 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 108.00 75.00 32.30 32.30 Weighted Average for the Second Quarter 108.00 75.00 32.30 32.30 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 6.00 39.57 73.00 36.00 Weighted Average for the Third Quarter 6.00 39.57 73.00 36.00 Weighted Average for the Year 117.00 72.49 40.64 32.94 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00210 Rem Conc Pavement Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 377.00 50.00 38.40 38.85 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,248.00 23.60 45.21 43.25 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 22.00 50.00 59.84 60.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 245.00 53.00 25.22 25.00 BR0761-249 I-76 02/27/25 348.00 42.95 84.32 60.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 6.00 137.64 105.76 52.02 Weighted Average for the First Quarter 2,246.00 34.80 50.08 43.30 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 109.00 35.00 32.30 32.30 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 7.50 78.31 169.00 138.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 5,619.00 49.00 34.50 13.22 25.22 13.22 25.22 13.22 Weighted Average for the Second Quarter 5,784.50 34.39 25.62 25.40 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 6,494.00 193.00 38.83 40.30 34.73 38.73 33.92 45.90 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 192.00 61.83 96.00 59.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 7,864.00 14.73 11.65 11.65 Weighted Average for the Third Quarter 14,743.00 26.29 31.37 22.52 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,183.00 11.00 25.45 18.64 NHPPR500-227 REGION 5 SECTION 7 10/23/25 9.00 150.00 492.50 120.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 150.00 50.00 26.59 19.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 38.00 51.91 87.00 94.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 56.00 45.00 39.50 46.20 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 690.00 33.52 39.47 29.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 22,855.00 20.98 18.92 9.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,805.00 25.00 34.75 30.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00210 Rem Conc Pavement Sq Yard NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 2,042.00 40.60 41.41 45.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1,135.00 31.00 55.33 50.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 186.00 100.00 26.23 21.75 Weighted Average for the Fourth Quarter 31,149.00 23.17 22.60 15.52 Weighted Average for the Year 53,922.50 25.71 25.94 19.65 202-00215 Rem Conc Pvmt (Planing) Sq Yard NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 8,859.00 21.57 47.00 31.00 Weighted Average for the Second Quarter 8,859.00 21.57 47.00 31.00 Weighted Average for the Year 8,859.00 21.57 47.00 31.00 202-00217 Rem Conc Pvmt (Planing) (Spec) Sq Yard NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 914.00 84.63 79.33 70.00 Weighted Average for the Second Quarter 914.00 84.63 79.33 70.00 Weighted Average for the Year 914.00 84.63 79.33 70.00 202-00220 Rem Asphalt Mat Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 202.00 45.00 37.39 35.32 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 281.00 130.00 55.01 35.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00220 Rem Asphalt Mat Sq Yard STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 45.00 80.00 45.38 65.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 475.00 25.00 22.00 30.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 24,598.00 12.00 7.47 7.50 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 4,756.00 6.59 16.90 15.90 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,244.00 30.00 180.96 139.31 Weighted Average for the First Quarter 31,601.00 13.45 16.77 14.80 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 27,980.00 12.00 7.75 7.75 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 127,036.00 14.05 16.34 16.34 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 161.00 50.00 166.75 72.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1,230.00 16.70 11.98 9.94 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 15,225.00 16.28 16.28 16.28 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1,871.00 20.00 28.49 54.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 1,750.00 25.00 15.75 13.50 Weighted Average for the Second Quarter 175,253.00 14.14 15.95 15.34 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5,386.00 12.44 12.44 12.44 CR400-406 REGION-WIDE 07/17/25 49.00 56.68 117.83 27.50 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 104.00 62.70 47.25 50.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 816.00 51.01 29.10 32.40 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2,195.00 14.97 12.14 12.14 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 171.00 60.00 57.68 9.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1,235.00 49.88 23.48 15.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 48,614.00 26.63 28.24 28.24 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 14,899.00 15.08 10.60 10.60 Weighted Average for the Third Quarter 73,469.00 23.71 23.79 22.83 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 14,140.00 11.00 13.63 6.76 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 179.70 44.95 85.48 50.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00220 Rem Asphalt Mat Sq Yard C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 12,138.00 10.00 9.21 3.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 4,737.00 11.66 10.49 11.45 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 754.00 30.44 33.00 35.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2,099.00 42.63 14.46 6.10 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 853.00 28.20 22.16 38.50 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 46.00 115.00 86.99 75.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1,006.00 15.00 23.00 8.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 966.00 58.91 12.50 12.50 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 312.00 50.00 21.98 15.25 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2,332.00 23.00 33.85 25.71 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 742.00 16.74 14.02 4.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 462.20 35.00 21.30 11.00 Weighted Average for the Fourth Quarter 40,766.90 15.99 13.72 8.92 Weighted Average for the Year 321,089.90 16.50 16.64 16.19 202-00222 Removal of Detour Pavement Sq Yard NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 9,416.00 18.86 14.41 14.41 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 36,478.00 18.12 14.38 14.38 Weighted Average for the Third Quarter 45,894.00 18.27 14.39 14.39 Weighted Average for the Year 45,894.00 18.27 14.39 14.39 202-00240 Rem Asphalt Mat (Planing) Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 250,763.00 3.00 3.29 2.42 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 689.00 15.00 22.50 20.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00240 Rem Asphalt Mat (Planing) Sq Yard SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 173.00 12.00 34.93 30.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 83,156.00 3.50 4.74 4.20 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 430.00 50.00 22.84 20.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 168,060.00 2.10 3.58 3.91 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 209,269.00 5.00 6.04 4.90 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 14,624.00 8.00 9.45 10.90 Weighted Average for the First Quarter 727,164.00 3.57 4.59 3.89 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 52,147.00 3.50 3.40 3.40 NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET I-70 SH287 & LCR 72 AND US287 & OW 04/11/25 04/24/25 38,167.00 23,273.00 4.26 3.00 5.51 2.53 5.51 2.55 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 35,716.00 3.50 3.25 2.05 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 13,044.00 3.32 3.32 3.32 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1,937.00 7.00 21.85 54.00 Weighted Average for the Second Quarter 164,284.00 3.63 3.91 4.07 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 39,877.00 3.50 8.75 8.75 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 182.00 6.85 39.89 39.89 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 1,826.00 14,369.00 9.00 9.07 10.86 4.85 7.00 3.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 210,270.00 3.08 3.09 3.09 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 33,705.00 5.92 6.09 6.09 Weighted Average for the Third Quarter 300,229.00 3.78 4.58 4.22 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 399.00 40.00 49.08 36.33 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 778.00 15.08 27.93 23.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 511.00 19.10 29.43 27.95 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1,100.00 8.00 23.83 24.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 59.90 30.00 208.22 100.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00240 Rem Asphalt Mat (Planing) Sq Yard C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3,786.00 6.00 4.98 2.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 285,152.00 3.00 2.65 2.65 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 3,998.00 15.00 16.50 20.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 296,895.00 6.00 3.69 3.25 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 19,686.00 5.11 16.81 3.62 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 260,449.00 3.10 3.42 2.20 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 95,697.00 3.13 4.29 4.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 7,265.90 3.00 9.78 11.30 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 112,292.00 5.00 2.89 3.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 603.00 14.51 36.17 34.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 19,367.00 10.00 6.30 4.35 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1,773.00 10.00 9.78 7.55 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 10,764.00 6.38 6.50 6.50 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 28,085.00 5.00 7.15 5.75 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 338,328.00 4.00 2.00 2.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 444.00 6.00 17.35 18.55 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 14.20 20.00 269.20 116.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 627,008.00 1.39 2.09 1.70 Weighted Average for the Fourth Quarter 2,114,455.00 3.41 3.12 2.57 Weighted Average for the Year 3,306,132.00 3.49 3.60 3.08 202-00246 Rem Asphalt Mat (Planing)(Special) Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,568.00 18.00 17.10 21.40 BR0761-249 I-76 02/27/25 5,778.00 20.61 24.20 19.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 275.00 46.00 30.40 10.00 Weighted Average for the First Quarter 7,621.00 20.99 23.54 19.17 BR0704-265 I-70 EAST 07/24/25 1,172.00 31.01 46.02 46.07 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00246 Rem Asphalt Mat (Planing)(Special) Sq Yard FBR0704-269 FBR2851-014 I-70 EAST US 50 CONEJOS RIVER BRIDGE ST 09/18/25 544.00 21.34 34.79 18.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 1,716.00 27.95 41.90 37.17 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1,202.00 35.00 34.19 49.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2,617.00 25.00 5.82 3.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 167.00 61.19 86.63 74.75 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,422.00 20.56 11.69 14.25 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,382.00 24.54 29.52 18.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 2,490.00 24.29 11.14 8.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 6,507.00 5.00 6.35 6.25 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 10,510.00 20.00 10.85 4.70 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,520.00 17.98 21.84 19.00 Weighted Average for the Fourth Quarter 27,817.00 18.38 12.62 9.46 Weighted Average for the Year 37,154.00 19.36 17.46 12.73 202-00250 Rem Pavement Marking Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,387.00 2.99 6.31 5.30 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2,400.00 2.50 4.24 4.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 44,637.00 1.00 0.74 0.55 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 785.00 2.50 5.60 5.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 44,566.00 1.00 0.79 0.60 BR0761-249 I-76 02/27/25 14,386.00 1.94 2.00 1.20 MTCER500-233 REGION 5 03/06/25 8,397.00 2.75 7.13 3.50 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 5,406.00 2.86 6.38 2.75 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 596.00 3.91 6.94 7.90 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 24,129.00 1.06 1.21 1.29 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00250 Rem Pavement Marking Sq Foot STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 104,218.00 1.00 0.53 0.50 Weighted Average for the First Quarter 250,907.00 1.20 1.56 0.88 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 866.00 1.00 5.60 5.60 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2,454.00 3.36 4.00 4.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 137,610.00 1.13 1.14 1.14 C0821-113 CO-82 & Catherine Store Signa 04/17/25 767.00 2.00 5.00 5.00 MTCER300-288 I-70 MM 0-205 REGION WIDE 05/08/25 481,092.00 0.46 0.74 0.52 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2,094.00 3.39 3.39 3.39 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 2,019.00 5.00 5.14 4.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 3,230.00 5.00 5.02 4.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 580,070.00 0.35 0.40 0.40 Weighted Average for the Second Quarter 1,210,202.00 0.52 0.72 0.57 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 27,454.80 2.00 1.88 1.75 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 26,600.00 2.24 2.24 2.24 CR400-406 REGION-WIDE 07/17/25 2,550.00 3.71 2.33 4.50 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 92.00 7.29 6.63 6.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 9,858.00 3.50 1.55 1.55 BR0704-265 I-70 EAST 07/24/25 16,914.00 1.86 1.55 1.05 FBR0704-269 I-70 EAST CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 326.00 4.90 13.35 7.40 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1,020.00 3.51 6.36 8.25 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 4,600.00 3.05 2.30 1.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 7.00 577.00 25.00 1.73 29.12 3.90 1.00 3.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 62,233.00 1.07 1.10 1.10 Weighted Average for the Third Quarter 152,231.80 1.82 1.86 1.57 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00250 Rem Pavement Marking Sq Foot MTCER400-415 REGION 4 10/16/25 1,897,313.00 0.39 0.34 0.33 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,424.00 2.30 7.79 8.47 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4,800.00 2.30 7.48 7.26 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 88.00 50.00 10.76 5.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3,000.00 3.00 3.80 2.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6,000.00 3.00 3.23 2.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1,976.00 3.00 3.44 3.08 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,000.00 3.16 4.73 4.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 33,409.00 1.37 3.27 1.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 63,162.00 1.00 0.65 0.65 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 2,603.00 3.35 3.81 2.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 3,455.00 1.00 3.92 2.95 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 20,880.00 2.00 1.59 1.53 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 218,262.00 1.00 0.43 0.40 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 84,930.00 0.70 0.40 0.40 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 114,507.00 1.00 0.51 0.42 NHPP1602-194 US 160 MP 174.1 12/11/25 400.00 35.00 4.25 3.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 3,102.00 2.90 2.83 3.65 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1,320.00 4.00 4.60 5.50 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,500.00 3.10 5.39 5.60 Weighted Average for the Fourth Quarter 2,464,131.00 0.56 0.60 0.42 Weighted Average for the Year 4,077,471.80 0.63 0.76 0.54 202-00251 Rem Pvmt Marking (Asph Grooving) Sq Foot NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 66,350.00 0.66 0.61 0.70 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 68,484.00 1.00 0.69 0.80 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 146,540.00 0.67 0.63 0.65 Weighted Average for the Fourth Quarter 281,374.00 0.75 0.64 0.70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 281,374.00 0.75 0.64 0.70 202-00254 Rem of Pvmt Mkg (12 In) Sq Foot SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 658.00 4.07 6.36 8.25 Weighted Average for the Third Quarter 658.00 4.07 6.36 8.25 Weighted Average for the Year 658.00 4.07 6.36 8.25 202-00400 Rem Bridge Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 791657.00 755198.08 755198.08 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 321257.00 365737.50 365737.50 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 829467.54 811316.44 811316.44 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 829468.00 327209.67 327209.67 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 Weighted Average for the Second Quarter 4.00 692962.39 564865.42 564865.42 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 372547.36 311039.96 311039.96 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 1.00 150000.00 116947.68 65000.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3.00 223185.12 217048.13 217048.13 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 60513.98 50612.36 50612.36 Weighted Average for the Third Quarter 6.00 208769.45 159753.51 179632.79 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00400 Rem Bridge Each FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 128900.00 181983.60 62875.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 100000.00 48300.00 50000.00 Weighted Average for the Fourth Quarter 2.00 114450.00 137422.40 56437.50 Weighted Average for the Year 12.00 354447.19 204080.44 287511.12 202-00405 Rem of Pilling Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 668.31 1629.97 1629.97 Weighted Average for the Third Quarter 1.00 668.31 1629.97 1629.97 Weighted Average for the Year 1.00 668.31 1629.97 1629.97 202-00420 Rem Ped Rail Lin Foot FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 48.00 38.45 41.42 41.42 Weighted Average for the Third Quarter 48.00 38.45 41.42 41.42 Weighted Average for the Year 48.00 38.45 41.42 41.42 202-00425 Rem Bridge Railing Lin Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 1,180.00 150.00 115.94 75.00 BR0761-249 I-76 02/27/25 760.00 25.00 55.06 110.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 50.00 81.35 56.20 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 1,950.00 100.77 89.38 88.54 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 877.00 110.00 26.30 24.00 Weighted Average for the Third Quarter 877.00 110.00 26.30 24.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 761.00 50.00 4.10 3.95 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 41.00 127.67 238.41 123.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 57.00 40.00 181.00 78.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 19.00 100.00 1635.00 1640.00 Weighted Average for the Fourth Quarter 878.00 54.06 69.70 49.72 Weighted Average for the Year 3,705.00 91.89 73.11 64.07 202-00450 Rem Port Present Str (1) Sq Yard BR0704-265 I-70 EAST 07/24/25 42.00 367.07 221.18 194.71 FBR0704-269 I-70 EAST Weighted Average for the Third Quarter 42.00 367.07 221.18 194.71 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 167.00 229.61 307.80 350.00 Weighted Average for the Fourth Quarter 167.00 229.61 307.80 350.00 Weighted Average for the Year 209.00 257.24 293.29 318.79 202-00453 Rem Port Present Str (2) Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 78.00 500.00 674.95 670.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00453 Rem Port Present Str (2) Sq Yard BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 324.00 400.00 388.30 393.62 BR0761-249 I-76 02/27/25 308.00 395.65 400.92 350.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 14.00 380.00 638.64 200.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 24.00 350.00 207.00 201.00 Weighted Average for the First Quarter 748.00 406.66 415.79 394.67 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 11.00 773.25 825.67 1462.00 Weighted Average for the Second Quarter 11.00 773.25 825.67 1462.00 BR0704-265 FBR0704-269 FBR2851-014 I-70 EAST I-70 EAST US 50 CONEJOS RIVER BRIDGE ST 07/24/25 09/18/25 102.00 67.00 566.92 524.66 402.75 558.54 461.00 300.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 169.00 550.16 472.99 397.17 NHPPR500-227 REGION 5 SECTION 7 10/23/25 246.00 550.00 450.33 380.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2.00 942.25 2987.50 1975.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 143.00 614.12 493.12 540.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 96.00 507.57 496.82 395.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 167.00 558.48 413.10 450.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 33.00 300.00 967.50 1120.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 163.00 500.00 414.27 300.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 470.00 150.00 383.55 420.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1,023.00 600.00 510.50 511.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 114.00 532.96 499.53 516.00 Weighted Average for the Fourth Quarter 2,457.00 489.81 460.18 469.09 Weighted Average for the Year 3,385.00 475.37 448.48 452.28 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00458 Rem Port Pres Str (Hydrodem)(Fast-Track) Sq Yard BR0704-265 I-70 EAST 07/24/25 4,438.00 265.00 331.26 273.02 FBR0704-269 I-70 EAST Weighted Average for the Third Quarter 4,438.00 265.00 331.26 273.02 Weighted Average for the Year 4,438.00 265.00 331.26 273.02 202-00460 Rem Port Present Str (3) Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 16.00 1200.00 1338.64 1330.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 33.00 1500.00 572.14 515.31 BR0761-249 I-76 02/27/25 66.00 741.96 1087.90 600.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 3.00 2500.00 1858.92 350.00 Weighted Average for the First Quarter 118.00 1060.76 1008.32 668.94 BR0704-265 I-70 EAST 07/24/25 130.00 684.39 626.30 515.21 FBR0704-269 I-70 EAST FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 17.00 1275.28 2061.36 1500.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 147.00 752.73 827.92 629.10 NHPPR500-227 REGION 5 SECTION 7 10/23/25 77.00 1200.00 1957.50 1000.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 29.00 981.27 1465.19 1850.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 36.00 887.81 1123.34 895.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 34.00 1046.32 529.80 550.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 7.00 350.00 2000.00 2870.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 15.00 1092.28 1552.23 480.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 95.00 200.00 1374.50 565.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 208.00 700.00 769.50 769.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid STM0503-096 202-00460 Rem Port Present Str (3) PUEBLO COUNTY LINE TO PURCELL 12/18/25 Sq Yard 23.00 1084.12 1081.38 1200.00 Weighted Average for the Fourth Quarter 524.00 757.18 1210.10 858.94 Weighted Average for the Year 789.00 801.75 1083.01 787.71 202-00495 Rem Port Present Str Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 113659.15 108063.91 108063.91 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 67161.25 68695.68 68695.68 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 59051.30 85196.79 85196.79 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 Weighted Average for the Second Quarter 3.00 79957.23 87318.79 87318.79 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 140379.65 124580.14 124580.14 Weighted Average for the Third Quarter 1.00 140379.65 124580.14 124580.14 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 40000.00 50516.29 20825.00 Weighted Average for the Fourth Quarter 1.00 40000.00 50516.29 20825.00 Weighted Average for the Year 5.00 84050.27 63692.82 81472.30 202-00500 Rem Port Present Str Each STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 9.00 200.00 872.75 341.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 9.00 200.00 872.75 341.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 13072.15 13041.26 13041.26 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 13383.58 13041.26 13041.26 Weighted Average for the Third Quarter 2.00 13227.87 13041.26 13041.26 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 1094.10 9307.60 13750.95 Weighted Average for the Fourth Quarter 1.00 1094.10 9307.60 13750.95 Weighted Average for the Year 12.00 2445.82 1902.92 3575.21 202-00502 Rem Port Present Str Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 7000.00 4012.34 5000.00 Weighted Average for the First Quarter 1.00 7000.00 4012.34 5000.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 59.00 1204.50 830.60 850.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 6.00 1000.00 4205.00 4210.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 0.20 8636.89 52885.00 45000.00 Weighted Average for the Fourth Quarter 65.20 1208.48 1030.06 1294.63 Weighted Average for the Year 66.20 1295.97 1068.37 1350.60 202-00503 Rem Port Present Str Sq Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 144.00 123.00 134.87 134.87 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 144.00 123.00 134.87 134.87 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 4.00 290.80 3319.36 3319.36 Weighted Average for the Third Quarter 4.00 290.80 3319.36 3319.36 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 121.00 300.00 195.50 155.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 10.00 900.00 1315.00 800.00 Weighted Average for the Fourth Quarter 131.00 345.80 239.92 204.24 Weighted Average for the Year 279.00 230.02 235.61 213.10 202-00504 Rem Exp Device Lin Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 856.00 600.00 1185.89 445.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 609.00 500.00 397.89 366.26 BR0761-249 I-76 02/27/25 760.00 238.63 206.26 135.00 Weighted Average for the First Quarter 2,225.00 449.20 619.49 317.56 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 532.00 500.00 574.00 487.00 Weighted Average for the Second Quarter 532.00 500.00 574.00 487.00 BR0704-265 I-70 EAST 07/24/25 76.00 509.21 275.85 333.41 FBR0704-269 I-70 EAST Weighted Average for the Third Quarter 76.00 509.21 275.85 333.41 NHPPR500-227 REGION 5 SECTION 7 10/23/25 101.00 570.00 485.32 295.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 88.00 238.98 94.28 77.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 204.00 385.92 637.22 500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00504 Rem Exp Device Lin Foot STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 75.00 600.00 632.80 250.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 265.00 300.00 785.00 785.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 60.00 420.00 1217.50 1225.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 252.00 237.70 79.80 50.00 Weighted Average for the Fourth Quarter 1,045.00 351.13 494.71 432.01 Weighted Average for the Year 3,878.00 430.91 585.25 371.96 202-00505 Rem Port of Present Structure Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 26.00 700.00 213.28 212.00 BR0761-249 I-76 02/27/25 1,661.00 163.90 135.36 115.00 Weighted Average for the First Quarter 1,687.00 172.16 135.97 116.49 BR0704-265 FBR0704-269 MTCER400-411 I-70 EAST I-70 EAST SH157 MP3.518 D-16-DG AND I70 07/24/25 08/21/25 1,025.00 15.00 94.88 805.84 143.52 393.99 124.09 140.00 Weighted Average for the Third Quarter 1,040.00 105.13 147.14 124.32 NHPPR500-227 REGION 5 SECTION 7 10/23/25 214.00 500.00 347.38 160.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 254.00 286.17 206.98 170.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 237.00 315.20 158.10 154.50 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 316.00 150.00 193.00 175.00 NHPP1602-194 US 160 MP 174.1 12/11/25 79.00 500.00 881.14 490.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 150.00 438.30 242.93 230.00 Weighted Average for the Fourth Quarter 1,250.00 325.63 262.34 194.04 Weighted Average for the Year 3,977.00 202.87 171.41 142.91 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00700 Rem Light Standard Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 9.00 730.83 730.82 730.82 FBR0703-534 I-70 Weighted Average for the Second Quarter 9.00 730.83 730.82 730.82 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 817.70 817.70 817.70 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 1041.13 1604.75 1525.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 16.00 663.43 715.66 525.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 8.00 509.32 519.71 519.71 Weighted Average for the Third Quarter 31.00 665.70 733.48 612.54 Weighted Average for the Year 40.00 680.36 733.32 639.16 202-00705 Rem Light Standard Foundation Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 5.00 718.12 1909.38 906.30 Weighted Average for the First Quarter 5.00 718.12 1909.38 906.30 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 8.00 1293.01 1292.99 1292.99 FBR0703-534 I-70 Weighted Average for the Second Quarter 8.00 1293.01 1292.99 1292.99 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 1149.20 1149.20 1149.20 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 16.00 463.50 1118.15 850.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 8.00 1422.03 1451.05 1451.05 Weighted Average for the Third Quarter 30.00 856.25 1138.22 1070.12 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00705 Rem Light Standard Foundation Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 16.00 1100.00 743.13 302.50 Weighted Average for the Fourth Quarter 16.00 1100.00 743.13 302.50 Weighted Average for the Year 59.00 969.87 1134.48 878.29 202-00710 Rem Power Pole Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 2344.28 2344.26 2344.26 Weighted Average for the Second Quarter 1.00 2344.28 2344.26 2344.26 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 2.00 783.80 751.62 575.00 Weighted Average for the Third Quarter 2.00 783.80 751.62 575.00 Weighted Average for the Year 3.00 1303.96 845.30 1164.75 202-00715 Rem CCTV Pole Each NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 2.00 2642.23 2642.21 2642.21 Weighted Average for the Second Quarter 2.00 2642.23 2642.21 2642.21 ITSSW03-417 STATEWIDE 12/04/25 32.00 943.44 2193.50 1395.00 Weighted Average for the Fourth Quarter 32.00 943.44 2193.50 1395.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 34.00 1043.37 2200.40 1468.37 202-00720 Rem CCTV Camera Each NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 3.00 584.66 584.66 584.66 ITSSW03-250 FRONT RANGE 06/26/25 1.00 315.02 946.00 900.00 Weighted Average for the Second Quarter 4.00 517.25 810.50 663.50 Weighted Average for the Year 4.00 517.25 810.50 663.50 202-00750 Rem Luminaire Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 250.00 317.50 325.00 Weighted Average for the First Quarter 1.00 250.00 317.50 325.00 Weighted Average for the Year 1.00 250.00 317.50 325.00 202-00805 Rem Overhead Sign Str Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 4076.33 11374.83 11374.83 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 4076.33 11374.83 11374.83 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 9904.99 10107.13 10107.13 Weighted Average for the Third Quarter 1.00 9904.99 10107.13 10107.13 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00805 Rem Overhead Sign Str Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 10000.00 6350.00 5445.00 Weighted Average for the Fourth Quarter 1.00 10000.00 6350.00 5445.00 Weighted Average for the Year 3.00 7993.77 7813.66 8975.65 202-00810 Rem Ground Sign Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 96.00 100.00 290.57 295.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 251.91 228.26 126.55 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 12.00 200.00 254.00 250.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 250.00 313.67 577.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 4.00 200.00 257.30 285.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 27.00 147.93 196.73 190.61 Weighted Average for the First Quarter 141.00 122.67 264.28 271.70 NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET I-70 SH287 & LCR 72 AND US287 & OW 04/11/25 04/24/25 157.00 20.00 135.46 136.70 136.09 266.00 136.09 265.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 15.00 121.80 201.67 225.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 21.00 187.68 187.68 187.68 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 665.00 95.00 145.00 40.00 Weighted Average for the Second Quarter 878.00 105.86 148.16 69.00 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 126.00 110.00 126.67 100.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 21.00 336.55 336.55 336.55 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 5.00 221.00 276.25 276.25 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 789.00 120.00 91.33 94.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 6.00 195.70 251.26 295.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 307.00 294.00 150.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00810 Rem Ground Sign Each FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 198.46 172.80 165.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 3.00 250.00 391.60 500.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 16.00 135.64 134.64 100.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 35.00 267.50 272.96 272.96 Weighted Average for the Third Quarter 1,004.00 130.35 105.22 109.68 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 160.00 205.19 90.75 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 2.00 217.19 339.69 157.75 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 11.00 153.50 251.59 178.20 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 33.00 200.00 118.80 200.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 30.00 148.71 190.98 278.45 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 55.00 116.41 191.15 120.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 10.00 350.00 275.67 360.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 38.00 176.31 131.66 155.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 69.00 120.46 123.50 122.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 86.00 112.05 174.94 125.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 84.00 162.88 271.78 507.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 9.00 227.09 270.00 270.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 24.00 145.12 271.91 485.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 81.00 115.58 95.02 97.00 Weighted Average for the Fourth Quarter 539.00 143.65 192.55 218.25 Weighted Average for the Year 2,562.00 124.33 149.88 127.50 202-00815 Rem of Sign (Special) Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 2500.00 2318.83 50.00 Weighted Average for the Fourth Quarter 1.00 2500.00 2318.83 50.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 1.00 2500.00 2318.83 50.00 202-00821 Rem Sign Panel Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 8.00 150.00 173.41 176.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 5.00 100.00 154.84 170.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 8.00 150.01 94.04 155.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 200.00 60.43 133.07 128.79 Weighted Average for the First Quarter 221.00 67.81 133.61 132.38 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 16.00 59.56 165.50 101.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 6.00 10.00 588.96 568.71 591.69 568.71 591.69 568.71 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 70.00 83.00 80.25 45.00 Weighted Average for the Second Quarter 102.00 156.70 112.81 137.29 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 642.00 50.00 96.67 100.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 140.24 140.24 140.24 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 442.00 552.49 552.49 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 646.00 110.00 78.00 84.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4.00 87.01 107.25 75.00 Weighted Average for the Third Quarter 1,295.00 80.49 87.61 92.35 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 70.00 58.59 43.78 15.80 NHPPR500-227 REGION 5 SECTION 7 10/23/25 4.00 45.00 260.06 8.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 49.00 83.96 666.79 700.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 58.00 71.86 140.40 206.05 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 73.00 72.70 117.00 51.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 33.00 60.00 102.86 51.52 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00821 Rem Sign Panel Each NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 35.00 105.90 45.59 31.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 5.00 77.58 75.00 74.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2.00 109.97 102.60 100.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 59.00 147.33 169.40 292.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 82.00 51.01 49.00 49.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 15.00 100.68 60.56 60.00 Weighted Average for the Fourth Quarter 485.00 79.49 168.57 157.97 Weighted Average for the Year 2,103.00 82.62 111.46 113.87 202-00823 Rem Dynamic Message Sign Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 9039.80 9039.73 9039.73 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 9039.80 9039.73 9039.73 Weighted Average for the Year 2.00 9039.80 9039.73 9039.73 202-00825 Rem Flashing Beacon Each STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 318.00 2057.00 936.00 Weighted Average for the Second Quarter 1.00 318.00 2057.00 936.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 5.00 338.08 1084.50 1050.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 1.00 393.65 770.00 1000.00 Weighted Average for the Third Quarter 6.00 347.34 1043.48 1041.67 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 7.00 343.15 1160.42 1026.57 202-00827 Rem of Pull Box Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 8.00 247.62 421.76 292.56 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 10.00 1000.00 447.50 350.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 69.00 250.00 560.63 580.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 250.31 1549.68 1377.27 Weighted Average for the First Quarter 89.00 334.06 554.70 546.24 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 10.00 257.44 450.00 200.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 39.00 3.00 472.23 230.21 472.22 230.21 472.22 230.21 ITSSW03-250 FRONT RANGE 06/26/25 1.00 257.04 710.00 500.00 Weighted Average for the Second Quarter 53.00 413.94 472.50 407.68 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 47.00 325.88 489.00 284.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 2.00 251.73 737.01 720.00 Weighted Average for the Third Quarter 49.00 322.86 508.45 301.80 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 500.00 620.25 590.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 500.00 2088.83 530.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 3.00 300.00 1045.00 1040.00 Weighted Average for the Fourth Quarter 5.00 380.00 1252.45 848.00 Weighted Average for the Year 196.00 354.03 543.42 455.36 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 202-00828 Rem Traf Sig Equipment Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 30000.00 57839.82 45600.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 30000.00 24200.00 29000.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 50000.00 12140.83 10507.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 50000.00 19505.26 17343.43 Weighted Average for the First Quarter 4.00 40000.00 24811.59 25612.61 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 15000.00 37375.00 24750.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 CO-82 & Catherine Store Signa 04/17/25 1.00 1.00 24735.76 10000.00 24735.58 8250.00 24735.58 8250.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 19593.63 19593.63 19593.63 Weighted Average for the Second Quarter 4.00 17332.35 25465.84 19332.30 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 10251.67 10460.89 10460.89 Weighted Average for the Third Quarter 1.00 10251.67 10460.89 10460.89 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 16000.00 65675.00 54450.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 36000.00 19168.55 30200.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 36000.00 18533.35 30200.00 Weighted Average for the Fourth Quarter 3.00 29333.33 42262.98 38283.33 Weighted Average for the Year 12.00 27298.42 29095.98 25424.21 202-00831 Rem Traf Sig Head Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 37.00 120.00 198.27 275.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 37.00 120.00 198.27 275.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 27.00 138.13 138.13 138.13 Weighted Average for the Third Quarter 27.00 138.13 138.13 138.13 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 5.00 112.61 292.20 295.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 17.00 177.29 276.40 239.00 Weighted Average for the Fourth Quarter 22.00 162.59 279.99 251.73 Weighted Average for the Year 86.00 136.59 227.97 226.08 202-00840 Rem Traf Sig Pole Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 3397.88 3397.88 3397.88 Weighted Average for the Third Quarter 4.00 3397.88 3397.88 3397.88 Weighted Average for the Year 4.00 3397.88 3397.88 3397.88 202-00855 Rem Traf Sig Control Cab Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 892.24 3638.85 3213.64 Weighted Average for the First Quarter 1.00 892.24 3638.85 3213.64 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 2248.71 2248.69 2248.69 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 2248.71 2248.69 2248.69 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00855 Rem Traf Sig Control Cab Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 1099.48 1099.48 1099.48 Weighted Average for the Third Quarter 2.00 1099.48 1099.48 1099.48 Weighted Average for the Year 4.00 1334.98 2714.72 1915.32 202-00858 Rem Pedestal Pole Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 3.00 2300.00 1133.66 580.00 Weighted Average for the First Quarter 3.00 2300.00 1133.66 580.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 1657.50 1657.50 1657.50 Weighted Average for the Third Quarter 2.00 1657.50 1657.50 1657.50 Weighted Average for the Year 5.00 2043.00 1208.49 1011.00 202-00860 Rem Ped Push Button Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 13.00 150.00 89.97 110.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 42.00 130.00 241.00 115.00 Weighted Average for the First Quarter 55.00 134.73 212.54 113.82 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 44.00 89.34 315.50 103.00 Weighted Average for the Third Quarter 44.00 89.34 315.50 103.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 10.00 100.00 1027.83 265.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00860 Rem Ped Push Button Each NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 8.00 500.00 168.50 169.00 Weighted Average for the Fourth Quarter 18.00 277.78 728.93 222.33 Weighted Average for the Year 117.00 139.66 310.15 126.44 202-00880 Rem Sig Veh Detector Amp Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 600.00 86.79 76.52 Weighted Average for the First Quarter 3.00 600.00 86.79 76.52 Weighted Average for the Year 3.00 600.00 86.79 76.52 202-00887 Rem Radar Detect Sys Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 330.00 862.26 292.56 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 322.06 635.86 561.11 Weighted Average for the First Quarter 2.00 326.03 771.70 426.84 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 330.00 750.00 1150.00 Weighted Average for the Second Quarter 1.00 330.00 750.00 1150.00 Weighted Average for the Year 3.00 327.35 768.08 667.89 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-00889 Rem of Detect Warning Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 1500.00 1251.83 132.31 Weighted Average for the Fourth Quarter 1.00 1500.00 1251.83 132.31 Weighted Average for the Year 1.00 1500.00 1251.83 132.31 202-00895 Rem of Impact Attenuator Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 1841.87 1841.67 1841.67 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 1841.87 1841.67 1841.67 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 2000.00 2145.00 2500.00 NHPP1602-194 US 160 MP 174.1 12/11/25 2.00 4000.00 1700.61 1500.00 Weighted Average for the Fourth Quarter 3.00 3333.33 1789.49 1833.33 Weighted Average for the Year 4.00 2960.47 1794.23 1835.42 202-00900 Rem Conc Footing Each NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 1703.09 1090.00 550.00 Weighted Average for the Third Quarter 2.00 1703.09 1090.00 550.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2.00 1500.00 6142.50 1545.00 Weighted Average for the Fourth Quarter 2.00 1500.00 6142.50 1545.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 4.00 1601.54 2533.57 1047.50 202-00950 Rem Conc Found/Slab Sq Yard STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 8.00 286.14 180.00 110.00 Weighted Average for the Second Quarter 8.00 286.14 180.00 110.00 Weighted Average for the Year 8.00 286.14 180.00 110.00 202-01000 Rem Fence Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 22.00 25.00 111.20 88.30 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 300.00 50.00 9.96 10.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,725.00 2.37 3.83 2.23 Weighted Average for the First Quarter 2,047.00 9.59 5.42 4.29 NHPP0703-517 FBR0703-534 C0405-042 I-70 TOP OF FLOYD HILL TO VET I-70 US 40 IN DEER TRAIL, PINE ST 04/11/25 06/05/25 954.00 431.00 1.95 7.69 1.96 3.99 1.96 2.00 Weighted Average for the Second Quarter 1,385.00 3.73 3.37 1.97 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 752.00 2.80 2.80 2.80 C0142-070 SH 14 MP 75.5-85 08/14/25 10.00 19.10 125.00 50.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 518.00 38.51 38.51 38.51 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 6,515.00 1.24 2.28 3.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4,648.00 1.34 1.38 1.38 Weighted Average for the Third Quarter 12,443.00 2.94 2.60 3.90 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-01000 Rem Fence Lin Foot STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 500.00 3.62 4.65 2.20 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 195.00 20.00 11.42 10.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 5,845.00 1.64 1.44 1.40 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 50.00 5.00 18.83 14.85 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 3,418.00 1.33 1.36 0.90 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1,660.00 2.50 1.70 1.50 Weighted Average for the Fourth Quarter 11,668.00 2.08 1.80 1.50 Weighted Average for the Year 27,543.00 3.11 2.53 2.82 202-01030 Rem of Road Closure Gate Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 2041.00 892.50 1272.00 Weighted Average for the First Quarter 1.00 2041.00 892.50 1272.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 4000.00 5997.10 6891.30 Weighted Average for the Second Quarter 1.00 4000.00 5997.10 6891.30 NHPP1602-194 US 160 MP 174.1 12/11/25 1.00 4000.00 1262.40 620.00 Weighted Average for the Fourth Quarter 1.00 4000.00 1262.40 620.00 Weighted Average for the Year 3.00 3347.00 2184.30 2927.77 202-01035 Rem of Gate Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 267.50 275.77 275.77 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 1.00 267.50 275.77 275.77 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.00 271.42 1466.00 540.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2.00 446.36 262.35 250.00 Weighted Average for the Fourth Quarter 4.00 358.89 1122.10 395.00 Weighted Average for the Year 5.00 340.61 1065.68 371.15 202-01130 Rem Gdrail Ty 3 Lin Foot NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 3,334.00 10.00 5.38 5.75 BR0761-249 I-76 02/27/25 1,430.00 11.00 17.13 20.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,870.00 10.00 4.91 3.61 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 2,525.00 10.00 9.73 6.45 Weighted Average for the First Quarter 9,159.00 10.16 9.67 7.73 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 90.00 7.00 10.50 10.50 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 10,781.00 524.00 3.74 8.46 3.79 8.46 3.79 8.46 Weighted Average for the Second Quarter 11,395.00 3.98 4.06 4.06 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,027.00 3.91 3.91 3.91 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 75.00 23.59 23.59 23.59 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 413.00 9.32 14.17 10.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 401.00 10.38 18.00 28.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 50.00 1,075.00 15.00 7.82 18.16 7.15 13.00 5.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 9,357.00 4.55 4.84 4.84 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 12,398.00 5.28 7.69 5.84 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 15,765.00 4.13 3.44 3.05 NHPPR500-227 REGION 5 SECTION 7 10/23/25 545.00 20.00 7.22 3.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1,291.00 8.10 5.35 5.20 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,475.00 8.87 4.55 6.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,190.10 21.13 3.15 2.75 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,068.75 7.23 5.95 5.20 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,062.00 7.31 5.70 3.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 2,286.00 5.00 2.70 2.65 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 2,083.00 15.00 6.26 2.25 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 7,179.00 7.00 5.25 4.75 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 35,138.00 3.00 2.55 1.95 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 2,837.00 8.35 3.25 3.25 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 25,173.00 5.00 2.75 1.30 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2,095.00 15.00 3.75 3.75 NHPP1602-194 US 160 MP 174.1 12/11/25 50.00 10.00 41.49 34.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2,201.00 5.00 14.87 18.15 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 228.00 9.32 4.81 3.65 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 750.00 10.00 5.24 2.95 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 9,175.00 4.32 3.48 2.20 Weighted Average for the Fourth Quarter 111,591.85 5.20 3.76 2.74 Weighted Average for the Year 144,543.85 5.43 4.51 3.43 202-01135 Rem Gdrail Thrie Beam Lin Foot MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 19.00 20.82 33.43 25.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 25.00 19.76 25.60 25.00 Weighted Average for the Third Quarter 44.00 20.21 28.56 25.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 44.00 20.21 28.56 25.00 202-01140 Rem Gdrail Ty 4 Lin Foot STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 30.00 40.00 102.90 99.80 Weighted Average for the First Quarter 30.00 40.00 102.90 99.80 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2,907.00 30.00 13.90 12.50 Weighted Average for the Fourth Quarter 2,907.00 30.00 13.90 12.50 Weighted Average for the Year 2,937.00 30.10 14.81 13.39 202-01170 Rem Gdrail Ty 7 Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 139.00 75.05 79.27 81.38 Weighted Average for the First Quarter 139.00 75.05 79.27 81.38 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4,091.00 41.22 42.81 42.81 FBR0703-534 I-70 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 85.00 150.00 120.00 120.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1,543.00 62.95 62.95 62.95 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 60.00 50.00 65.85 30.00 Weighted Average for the Second Quarter 5,779.00 48.71 50.05 49.19 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 109.00 98.51 88.20 70.00 Weighted Average for the Third Quarter 109.00 98.51 88.20 70.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-01170 Rem Gdrail Ty 7 Lin Foot NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 408.00 47.54 99.20 85.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 40.00 78.37 62.18 26.00 Weighted Average for the Fourth Quarter 448.00 50.29 91.91 79.73 Weighted Average for the Year 6,475.00 50.23 63.95 52.34 202-01180 Rem Median Barrier Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 258.00 27.00 32.07 31.76 Weighted Average for the Fourth Quarter 258.00 27.00 32.07 31.76 Weighted Average for the Year 258.00 27.00 32.07 31.76 202-01200 Rem High-Tension Cable Barrier Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 8,127.00 11.93 15.02 15.02 Weighted Average for the Third Quarter 8,127.00 11.93 15.02 15.02 Weighted Average for the Year 8,127.00 11.93 15.02 15.02 202-01300 Rem End Anchorage Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 6.00 800.00 489.50 690.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 10.00 417.11 380.51 489.39 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 11.00 200.00 780.50 286.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 27.00 413.75 517.10 451.11 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 525.00 490.00 490.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 9.00 2.00 318.11 507.81 818.33 507.81 818.33 507.81 Weighted Average for the Second Quarter 15.00 398.57 689.37 689.37 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5.00 457.62 457.62 457.62 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 358.02 358.02 358.02 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 1.00 612.60 730.00 295.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 6.00 398.09 561.00 435.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 4.00 2.00 500.00 531.50 607.04 517.34 550.00 500.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 27.00 481.50 512.26 512.26 Weighted Average for the Third Quarter 46.00 471.97 549.96 490.92 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 61.00 486.10 470.45 451.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 7.00 600.00 610.76 625.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 14.00 455.03 213.05 207.75 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 38.00 376.85 335.00 304.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 24.00 495.90 352.02 350.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 14.00 376.62 446.83 505.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 8.00 408.61 349.10 248.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 20.00 400.00 280.50 276.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 19.00 700.00 334.52 240.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 83.00 330.00 458.00 216.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 10.00 523.14 400.00 400.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 50.00 400.00 313.50 205.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 8.00 700.00 308.50 310.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 12.00 400.00 706.19 665.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 394.84 370.95 395.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-01300 Rem End Anchorage Each BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 500.00 377.00 295.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 19.00 393.98 508.41 520.00 Weighted Average for the Fourth Quarter 395.00 431.32 417.13 327.00 Weighted Average for the Year 483.00 433.19 436.98 360.80 202-04001 Plug Culvert Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 4126.30 3723.65 3570.55 Weighted Average for the First Quarter 1.00 4126.30 3723.65 3570.55 Weighted Average for the Year 1.00 4126.30 3723.65 3570.55 202-04002 Clean Culvert Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 8.00 2205.28 3079.38 3526.25 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 6500.00 2542.50 2500.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 27.00 1545.08 4025.50 3381.31 Weighted Average for the First Quarter 37.00 1955.66 3704.58 3365.01 C0821-113 CO-82 & Catherine Store Signa 04/17/25 3.00 3000.00 2500.00 2500.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 6.00 10000.00 12000.00 12000.00 STAR500-228 REGION 5 05/08/25 20.00 4500.00 3945.00 3300.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 7.00 3637.00 3808.33 2925.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 25.00 1111.15 1111.15 1111.15 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 61.00 5000.00 3746.67 1740.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 122.00 4239.65 3723.47 2458.15 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5.00 3315.00 3315.00 3315.00 CR400-406 REGION-WIDE 07/17/25 20.00 2751.63 7633.33 3800.00 C0142-070 SH 14 MP 75.5-85 08/14/25 4.00 6912.79 6598.33 2500.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 3130.27 4400.00 2500.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 34.00 1000.00 3608.00 2725.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 2916.99 6681.00 3500.00 Weighted Average for the Third Quarter 66.00 2158.12 4771.94 3086.74 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 16.00 1532.98 3728.32 350.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 7.00 4000.00 4010.50 10000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 10.00 3449.82 9089.19 8498.10 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 6.00 4895.72 2850.00 1600.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 11.00 4874.87 1750.00 1400.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 6.00 3890.01 4003.78 1600.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 4307.96 13200.00 20800.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 5.00 3557.59 7855.00 2650.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 4000.00 8950.00 7900.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 7.00 5000.00 7479.20 4567.20 Weighted Average for the Fourth Quarter 70.00 3635.14 4903.25 3844.31 Weighted Average for the Year 295.00 3344.04 4301.63 3041.44 202-04003 Clean Culvert (Spec) Each NHPP1602-194 US 160 MP 174.1 12/11/25 17.00 5000.00 8105.17 8500.00 Weighted Average for the Fourth Quarter 17.00 5000.00 8105.17 8500.00 Weighted Average for the Year 17.00 5000.00 8105.17 8500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-04005 Clean Valve Box Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 50.00 100.00 517.13 420.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 5.00 180.00 820.70 577.00 Weighted Average for the First Quarter 55.00 107.27 567.72 434.27 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 12.00 222.23 222.23 222.23 Weighted Average for the Second Quarter 12.00 222.23 222.23 222.23 Weighted Average for the Year 67.00 127.86 546.13 396.29 202-04006 Clean Culvert Hour NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 100.00 511.18 607.23 607.23 FBR0703-534 I-70 Weighted Average for the Second Quarter 100.00 511.18 607.23 607.23 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 150.00 650.70 855.79 855.79 Weighted Average for the Third Quarter 150.00 650.70 855.79 855.79 Weighted Average for the Year 250.00 594.89 756.37 756.37 202-04007 Plug Culvert Cubic Yard STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 115.00 400.00 531.03 594.00 Weighted Average for the Fourth Quarter 115.00 400.00 531.03 594.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 115.00 400.00 531.03 594.00 202-04010 Clean Inlet Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 127.00 300.00 1133.13 1170.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 5.00 1351.08 1606.33 1380.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 10.00 1607.32 1585.37 3575.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 15.00 1438.21 1557.46 1040.40 Weighted Average for the First Quarter 157.00 525.49 1231.89 1317.49 NHPP0703-517 FBR0703-534 NHPP2254-095 I-70 TOP OF FLOYD HILL TO VET I-70 I-225 @ 2ND AND 6TH AVES 04/11/25 05/22/25 15.00 6.00 395.16 1058.03 1731.40 1215.00 1731.40 1095.00 Weighted Average for the Second Quarter 21.00 584.55 1449.73 1549.57 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 773.50 773.50 773.50 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 10.00 1033.71 996.00 300.00 Weighted Average for the Third Quarter 11.00 1010.05 991.64 343.05 NHPPR500-227 REGION 5 SECTION 7 10/23/25 32.00 200.00 588.74 1000.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 4.00 1500.43 1787.50 1575.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 10.00 371.49 755.00 1360.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 2571.50 2975.00 2850.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 8.00 1284.03 1438.15 2100.00 NHPP1602-194 US 160 MP 174.1 12/11/25 10.00 4500.00 2185.43 2120.00 Weighted Average for the Fourth Quarter 65.00 1137.85 1086.14 1426.92 Weighted Average for the Year 254.00 708.06 1183.59 1322.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid NHPP2873-206 202-04050 Clean Exp Joint US287:RESURFACING I-70 TO 92N 01/09/25 Lin Foot 166.00 30.00 112.36 99.00 Weighted Average for the First Quarter 166.00 30.00 112.36 99.00 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 108.00 47.43 25.82 18.28 Weighted Average for the Third Quarter 108.00 47.43 25.82 18.28 Weighted Average for the Year 274.00 36.87 72.16 67.18 202-04100 Abandon Well Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 3000.00 4127.84 2511.34 Weighted Average for the Fourth Quarter 1.00 3000.00 4127.84 2511.34 Weighted Average for the Year 1.00 3000.00 4127.84 2511.34 202-05026 Sawing Asphalt Mat (6 In) Lin Foot FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 309.00 15.00 10.90 6.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 309.00 15.00 10.90 6.00 Weighted Average for the Year 309.00 15.00 10.90 6.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-05030 Sawing Asphalt Mat (10 In) Lin Foot STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 352.00 20.00 14.96 15.00 Weighted Average for the First Quarter 352.00 20.00 14.96 15.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 7,535.00 3.45 3.45 3.45 Weighted Average for the Third Quarter 7,535.00 3.45 3.45 3.45 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 5,886.00 4.63 5.96 5.25 Weighted Average for the Fourth Quarter 5,886.00 4.63 5.96 5.25 Weighted Average for the Year 13,773.00 4.38 6.11 4.51 202-05100 Sandblasting Reinf Steel Sq Yard STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 24.00 25.00 313.00 301.00 Weighted Average for the First Quarter 24.00 25.00 313.00 301.00 Weighted Average for the Year 24.00 25.00 313.00 301.00 202-05150 Sandblasting Sq Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 82,000.00 0.37 0.39 0.39 Weighted Average for the Third Quarter 82,000.00 0.37 0.39 0.39 Weighted Average for the Year 82,000.00 0.37 0.39 0.39 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 202-05300 Rem and Disposal of Paint Lump Sum STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 5000.00 268938.33 185000.00 Weighted Average for the Fourth Quarter 1.00 5000.00 268938.33 185000.00 Weighted Average for the Year 1.00 5000.00 268938.33 185000.00 202-05301 Rem and Disposal of Paint Sq Foot STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 690.00 225.00 104.31 94.00 Weighted Average for the Fourth Quarter 690.00 225.00 104.31 94.00 Weighted Average for the Year 690.00 225.00 104.31 94.00 202-06000 Rem Detour Lump Sum FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 97003.83 106078.83 106078.83 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 1.00 80000.00 72778.83 55000.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 2.00 88501.92 78328.83 80539.42 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 20000.00 117000.00 100000.00 Weighted Average for the Fourth Quarter 1.00 20000.00 117000.00 100000.00 Weighted Average for the Year 3.00 65667.94 95906.64 87026.28 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 203-00000 Uncl Excav Cubic Yard NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 5,318.00 85.00 49.32 49.65 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 20.00 184.17 203.13 105.00 Weighted Average for the First Quarter 5,338.00 85.37 49.75 49.86 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1,229.00 50.00 99.00 99.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 10.40 242.92 312.50 275.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 144.00 100.00 121.50 111.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 555.00 90.00 64.00 43.00 Weighted Average for the Second Quarter 1,938.40 66.20 91.69 84.80 CR400-406 REGION-WIDE 07/17/25 130.00 98.01 175.00 220.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES 185.00 150.00 34.11 28.00 Weighted Average for the Third Quarter 315.00 128.54 75.89 107.24 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,110.00 73.80 57.00 60.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 36.00 50.00 185.80 162.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 3,270.00 30.82 42.36 12.00 NHPP1602-194 US 160 MP 174.1 12/11/25 10.00 125.00 587.85 630.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 29.00 180.00 175.31 295.34 Weighted Average for the Fourth Quarter 4,455.00 42.87 46.42 28.40 Weighted Average for the Year 12,046.40 67.70 51.89 49.05 203-00010 Uncl Excav (CIP) Cubic Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2,320.00 25.00 50.16 74.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-00010 Uncl Excav (CIP) Cubic Yard STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 640.00 80.00 85.86 75.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 10,309.00 18.00 28.87 31.19 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 8,502.00 45.00 49.00 52.00 Weighted Average for the First Quarter 21,771.00 31.11 37.13 45.17 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 214,067.00 8,232.00 59.78 56.12 60.70 56.12 60.70 56.12 Weighted Average for the Second Quarter 222,299.00 59.64 60.53 60.53 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 802.00 62.91 83.13 82.50 Weighted Average for the Third Quarter 802.00 62.91 83.13 82.50 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6,217.00 52.00 62.18 52.72 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,778.00 52.00 48.83 95.32 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 8,191.00 40.00 40.53 45.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 5,499.00 35.00 31.32 33.95 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 5.00 200.00 592.50 275.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 663.00 80.00 77.25 9.50 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 430.00 64.03 84.00 84.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 846.00 50.00 61.40 39.00 Weighted Average for the Fourth Quarter 23,629.00 44.85 47.23 47.79 Weighted Average for the Year 268,501.00 56.04 52.45 58.23 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-00014 Uncl Ex (River Bttm Matl Salv and Repl) Cubic Yard FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1,607.00 205.00 28.01 40.85 Weighted Average for the Fourth Quarter 1,607.00 205.00 28.01 40.85 Weighted Average for the Year 1,607.00 205.00 28.01 40.85 203-00050 Unsuitable Material Cubic Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 109.00 115.00 157.14 190.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 20.00 120.00 160.60 169.60 Weighted Average for the First Quarter 129.00 115.78 158.07 186.84 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,000.00 90.69 101.06 101.06 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 500.00 50.29 50.29 50.29 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 5.00 136.79 201.63 125.00 Weighted Average for the Second Quarter 1,505.00 77.42 86.06 84.27 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,070.00 38.98 38.98 38.98 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 100.00 69.80 155.38 119.50 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 15.00 155.16 155.20 71.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,714.00 39.59 23.22 23.22 Weighted Average for the Third Quarter 2,899.00 41.01 47.65 32.61 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 110.00 100.00 205.60 200.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 750.00 26.75 77.50 78.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 500.00 43.57 53.52 40.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,881.00 50.00 23.00 16.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-00050 Unsuitable Material Cubic Yard NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 13.00 156.37 195.57 215.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 838.00 80.00 81.67 55.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 133.00 75.00 164.00 163.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 50.00 200.00 190.02 295.34 Weighted Average for the Fourth Quarter 4,275.00 55.19 69.26 50.57 Weighted Average for the Year 8,808.00 55.21 68.96 52.41 203-00060 Emb Matl (CIP) Cubic Yard BR0761-249 I-76 02/27/25 1,296.00 50.00 69.38 50.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 56.00 120.00 275.12 204.03 Weighted Average for the First Quarter 1,352.00 52.90 75.14 56.38 STAR500-228 REGION 5 05/08/25 15.00 220.00 195.67 62.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1,447.00 48.00 103.37 71.10 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 81.00 100.00 133.19 35.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 5,834.00 60.00 46.72 26.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 117.00 99.60 155.00 60.00 Weighted Average for the Second Quarter 7,494.00 59.05 57.76 35.41 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 39,220.00 48.24 45.93 45.93 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2,627.00 106.72 118.87 118.87 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 15.00 191.62 204.20 71.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 107.00 120.00 52.13 57.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 32,798.00 25.85 31.89 35.50 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 97,451.00 20.03 20.75 20.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 172,218.00 28.96 31.19 30.82 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 4,152.00 46.85 50.86 48.50 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 239.00 65.00 125.58 100.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 5,432.00 25.00 100.00 95.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 100.00 79.98 78.09 100.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 545.00 68.88 106.68 94.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 300.00 107.50 54.32 32.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 4.00 42.65 231.12 265.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 720.00 200.00 125.46 160.79 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 250.00 80.36 117.47 131.00 Weighted Average for the Fourth Quarter 11,742.00 50.07 76.62 81.91 Weighted Average for the Year 192,806.00 31.59 37.36 34.29 203-00062 Emb Matl (CIP) (Spec) Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4,206.00 35.00 34.53 32.20 Weighted Average for the First Quarter 4,206.00 35.00 34.53 32.20 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 19,579.00 54.00 77.33 77.33 Weighted Average for the Second Quarter 19,579.00 54.00 77.33 77.33 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 206.00 64.83 64.83 64.83 Weighted Average for the Third Quarter 206.00 64.83 64.83 64.83 Weighted Average for the Year 23,991.00 50.76 53.28 69.31 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 203-00066 Emb Matl (CIP) (R40) Cubic Yard STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 100.00 80.00 82.83 43.49 Weighted Average for the Second Quarter 100.00 80.00 82.83 43.49 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 864.00 65.67 65.67 65.67 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 28,478.00 41.39 37.69 37.69 Weighted Average for the Third Quarter 29,342.00 42.10 38.51 38.51 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 30.00 113.26 133.02 67.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,000.00 73.73 63.60 66.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 379.00 92.80 91.67 85.00 Weighted Average for the Fourth Quarter 1,409.00 79.70 70.34 71.49 Weighted Average for the Year 30,851.00 43.94 44.45 40.04 203-00400 Rock Excav Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 36,165.00 77.47 86.30 86.30 FBR0703-534 I-70 Weighted Average for the Second Quarter 36,165.00 77.47 86.30 86.30 Weighted Average for the Year 36,165.00 77.47 86.30 86.30 203-00440 Rock Excav (Spec) Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 9,622.00 81.14 98.96 98.96 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-00440 Rock Excav (Spec) Cubic Yard FBR0703-534 I-70 Weighted Average for the Second Quarter 9,622.00 81.14 98.96 98.96 Weighted Average for the Year 9,622.00 81.14 98.96 98.96 203-01100 Proof Rolling Hour NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 135.00 246.00 115.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 8.00 150.00 199.25 300.00 Weighted Average for the First Quarter 48.00 137.50 232.64 145.83 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 40.00 124.00 170.00 125.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 10.00 144.35 190.44 150.00 Weighted Average for the Second Quarter 50.00 128.07 176.01 130.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 200.00 154.54 169.53 169.53 Weighted Average for the Third Quarter 200.00 154.54 169.53 169.53 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 10.00 145.39 206.14 320.00 Weighted Average for the Fourth Quarter 10.00 145.39 206.14 320.00 Weighted Average for the Year 308.00 147.29 188.33 164.31 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 203-01500 Blading Hour 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 10.00 186.57 185.47 190.80 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 20.00 270.00 231.25 250.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 80.00 200.00 271.59 150.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 80.00 205.47 219.62 252.53 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 20.00 170.00 197.50 195.00 Weighted Average for the First Quarter 210.00 205.25 229.12 204.81 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 150.00 235.00 235.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 40.00 164.00 240.00 150.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 40.00 182.24 182.24 182.24 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 131.72 223.17 175.00 Weighted Average for the Second Quarter 140.00 160.60 226.02 187.07 C0142-070 SH 14 MP 75.5-85 08/14/25 10.00 220.78 160.33 1.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 287.19 211.00 150.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 40.00 247.29 185.56 170.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 200.00 222.40 307.81 307.81 Weighted Average for the Third Quarter 270.00 230.83 225.93 264.34 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 40.00 225.00 234.88 324.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 16.00 186.40 227.07 203.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 20.00 250.00 168.59 165.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 20.00 180.00 242.67 20.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 191.51 161.46 152.45 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 40.00 165.46 212.00 194.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 80.00 156.62 204.52 223.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 40.00 157.27 204.00 185.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 20.00 225.00 203.00 166.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 40.00 200.00 234.90 175.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 90.00 160.00 234.50 226.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-01500 Blading Hour 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 246.29 200.00 200.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 190.00 187.50 200.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 200.00 205.00 240.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 20.00 190.00 211.18 188.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 40.00 200.00 178.00 125.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 40.00 178.31 180.80 200.00 Weighted Average for the Fourth Quarter 626.00 187.17 206.58 196.88 Weighted Average for the Year 1,246.00 196.69 215.99 211.73 203-01510 Backhoe Hour STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 180.00 145.00 170.00 Weighted Average for the First Quarter 10.00 180.00 145.00 170.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 265.00 198.01 263.44 263.44 Weighted Average for the Second Quarter 265.00 198.01 263.44 263.44 CR400-406 REGION-WIDE 07/17/25 15.00 123.46 180.83 192.50 Weighted Average for the Third Quarter 15.00 123.46 180.83 192.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 90.00 150.00 193.50 242.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 200.00 174.50 137.00 Weighted Average for the Fourth Quarter 110.00 159.09 190.05 222.91 Weighted Average for the Year 400.00 184.06 223.02 247.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-01525 Backhoe (Spec) Hour NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 40.00 198.01 263.44 263.44 Weighted Average for the Second Quarter 40.00 198.01 263.44 263.44 Weighted Average for the Year 40.00 198.01 263.44 263.44 203-01550 Dozing Hour 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 10.00 193.63 195.13 190.80 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 80.00 200.00 312.49 150.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 40.00 191.57 274.35 252.53 Weighted Average for the First Quarter 130.00 196.92 277.90 184.69 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 80.00 40.00 193.67 200.00 317.22 285.00 317.22 285.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 227.16 236.17 150.00 Weighted Average for the Second Quarter 140.00 200.26 274.52 284.13 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 40.00 189.02 197.69 170.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 200.00 225.45 319.15 319.15 Weighted Average for the Third Quarter 240.00 219.38 244.40 294.29 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 40.00 160.00 210.88 313.50 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 20.00 180.00 205.50 20.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 194.90 189.96 317.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-01550 Dozing Hour STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 40.00 209.72 219.50 204.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 20.00 180.00 219.00 263.00 Weighted Average for the Fourth Quarter 160.00 186.15 208.16 244.00 Weighted Average for the Year 670.00 203.09 245.63 258.89 203-01565 Hydraulic Excavator Hour STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 15.00 230.00 200.84 200.00 Weighted Average for the First Quarter 15.00 230.00 200.84 200.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 180.00 198.01 263.44 263.44 FBR0703-534 I-70 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 80.00 200.00 300.00 300.00 Weighted Average for the Second Quarter 260.00 198.62 274.69 274.69 Weighted Average for the Year 275.00 200.33 260.84 270.62 203-01580 Truck Hour NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 80.00 200.00 167.56 100.00 Weighted Average for the First Quarter 80.00 200.00 167.56 100.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 150.00 110.00 110.00 Weighted Average for the Second Quarter 40.00 150.00 110.00 110.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 120.00 183.33 156.04 103.33 STM141A-057 203-01582 Truck (Dump) SH141 GATEWAY MP 120 SOUTH 03/27/25 Hour 10.00 150.00 160.00 185.00 Weighted Average for the First Quarter 10.00 150.00 160.00 185.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 48.00 172.88 177.12 177.12 Weighted Average for the Second Quarter 48.00 172.88 177.12 177.12 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 50.00 79.89 156.15 156.15 Weighted Average for the Third Quarter 50.00 79.89 156.15 156.15 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 20.00 200.00 157.20 155.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 20.00 150.00 170.50 176.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 90.00 115.00 183.00 174.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 105.58 135.00 135.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 150.00 163.00 140.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 200.00 162.50 145.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 40.00 170.00 152.00 125.00 Weighted Average for the Fourth Quarter 250.00 141.49 162.47 153.52 Weighted Average for the Year 358.00 137.34 162.89 157.93 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 203-01590 Front End Loader (Rubber) Hour NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 40.00 179.14 192.14 192.14 Weighted Average for the Second Quarter 40.00 179.14 192.14 192.14 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 20.00 131.77 201.25 123.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 50.00 190.00 169.00 184.00 Weighted Average for the Fourth Quarter 70.00 173.36 183.33 166.57 Weighted Average for the Year 110.00 175.46 184.93 175.87 203-01594 Combination Loader Hour 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 20.00 132.87 156.93 169.60 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 40.00 115.00 196.03 20.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 80.00 150.00 415.15 120.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 15.00 230.00 151.87 120.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 80.00 176.86 226.01 176.77 Weighted Average for the First Quarter 235.00 156.84 239.41 126.53 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 30.00 200.00 205.50 267.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 150.00 165.00 165.00 STAR500-228 REGION 5 05/08/25 20.00 210.00 158.33 125.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 40.00 192.00 203.33 150.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 40.00 159.03 159.03 159.03 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 40.00 175.00 172.19 125.00 Weighted Average for the Second Quarter 210.00 177.34 183.47 164.15 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-01594 Combination Loader Hour FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 50.00 100.40 198.94 198.94 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 40.00 159.48 122.70 162.00 FBR2851-014 NHPP2851-009 US US 50 CONEJOS RIVER BRIDGE ST 285 CONEJOS RIVER BRIDGES 09/18/25 40.00 130.00 200.28 127.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 200.00 126.87 167.87 167.87 Weighted Average for the Third Quarter 330.00 127.19 166.33 166.91 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 40.00 135.00 170.63 247.50 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 20.00 250.00 144.51 150.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 143.57 142.63 146.50 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 40.00 140.73 142.00 114.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 20.00 130.00 126.50 108.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 60.00 125.00 166.00 184.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 148.89 120.00 120.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 160.00 116.50 120.00 NHPP1602-194 US 160 MP 174.1 12/11/25 20.00 200.00 170.26 275.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 185.00 244.21 346.50 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 40.00 125.00 140.00 125.00 Weighted Average for the Fourth Quarter 380.00 151.13 159.43 179.16 Weighted Average for the Year 1,155.00 150.22 186.64 162.22 203-01597 Potholing Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 100.00 298.14 448.12 420.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 20.00 327.19 290.70 286.20 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 20.00 400.00 477.83 700.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 10.00 300.00 383.25 575.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 10.00 600.00 407.50 490.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 69.00 250.00 392.50 309.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-01597 Potholing Hour NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 40.00 350.00 381.54 225.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 16.00 350.00 382.58 375.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 80.00 309.73 375.07 360.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 100.00 331.70 432.09 357.07 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 40.00 400.00 326.33 334.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 20.00 250.00 410.50 401.00 Weighted Average for the First Quarter 525.00 322.20 398.35 370.63 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 186.00 281.67 362.50 75.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 200.00 20.00 448.80 300.00 427.47 325.00 427.47 325.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 30.00 330.89 220.00 228.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 30.00 400.00 460.50 492.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 10.00 600.00 280.00 280.00 STAR500-228 REGION 5 05/08/25 40.00 460.00 321.67 260.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 40.00 282.00 297.43 437.29 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 250.00 277.33 277.33 277.33 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 50.00 360.95 333.33 125.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 40.00 313.95 287.14 250.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 30.00 400.00 375.58 275.00 ITSSW03-250 FRONT RANGE 06/26/25 300.00 310.00 302.40 210.00 Weighted Average for the Second Quarter 1,226.00 334.99 322.26 256.99 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 200.00 334.64 334.64 334.64 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 40.00 317.03 410.75 335.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 40.00 275.00 475.00 475.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 5.00 40.00 331.48 320.48 433.72 468.25 544.86 370.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 100.00 305.12 378.50 570.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 80.00 331.68 414.37 414.37 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-01597 Potholing Hour NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 314.51 374.00 275.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 32.00 291.90 355.10 575.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 20.00 450.00 371.80 203.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 40.00 350.31 392.00 250.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 300.00 441.38 577.52 577.52 Weighted Average for the Third Quarter 917.00 363.35 416.61 456.07 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 250.00 310.00 546.48 570.90 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 20.00 367.36 547.75 400.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 10.00 323.83 525.12 500.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 8.00 300.00 686.32 800.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 40.00 450.00 419.20 450.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 100.00 350.00 449.33 350.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 80.00 365.30 274.01 217.75 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 40.00 314.68 540.00 480.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 31.00 323.88 390.00 220.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 40.00 250.00 502.20 443.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 20.00 327.75 376.74 215.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 20.00 400.00 458.00 566.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 16.00 304.18 474.89 620.00 ITSSW03-417 STATEWIDE 12/04/25 400.00 334.08 351.50 345.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 30.00 500.00 456.17 360.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 16.00 80.00 365.00 200.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 30.00 300.00 352.50 305.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 348.39 400.00 400.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 400.00 452.50 430.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 30.00 500.00 222.95 445.00 NHPP1602-194 US 160 MP 174.1 12/11/25 12.00 350.00 558.08 445.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 425.00 649.95 880.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 20.00 300.00 415.00 300.00 Weighted Average for the Fourth Quarter 1,313.00 341.06 433.85 416.96 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 3,981.00 341.84 395.26 370.59 203-01620 Sweeping Hour MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 75.00 129.17 222.50 325.00 Weighted Average for the First Quarter 75.00 129.17 222.50 325.00 Weighted Average for the Year 75.00 129.17 222.50 325.00 203-01622 Sweeping (With Pickup Broom) Hour NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 40.00 200.00 193.61 195.00 Weighted Average for the First Quarter 40.00 200.00 193.61 195.00 CR400-406 REGION-WIDE 07/17/25 54.00 187.18 161.04 158.13 Weighted Average for the Third Quarter 54.00 187.18 161.04 158.13 Weighted Average for the Year 94.00 192.63 177.22 173.82 203-02060 Presplitting Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 16,590.00 12.66 12.66 12.66 FBR0703-534 I-70 Weighted Average for the Second Quarter 16,590.00 12.66 12.66 12.66 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 16,590.00 12.66 12.66 12.66 203-02300 Rock Scaler Hour NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 320.00 280.46 280.46 280.46 FBR0703-534 I-70 Weighted Average for the Second Quarter 320.00 280.46 280.46 280.46 Weighted Average for the Year 320.00 280.46 280.46 280.46 203-02324 Blast Vibration Monitoring Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 143650.00 74766.36 74766.36 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 143650.00 74766.36 74766.36 Weighted Average for the Year 1.00 143650.00 74766.36 74766.36 203-02330 Laborer Hour NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 40.00 85.00 54.94 20.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 80.00 100.00 67.50 40.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 15.00 65.00 59.62 45.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 40.00 67.35 79.17 101.01 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 60.00 48.10 51.20 Weighted Average for the First Quarter 185.00 84.70 64.99 49.88 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 203-02330 Laborer Hour NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 185.00 70.42 80.72 80.72 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 75.00 55.00 55.00 STAR500-228 REGION 5 05/08/25 20.00 60.00 66.67 70.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 40.00 30.00 65.11 45.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 20.00 70.00 73.46 65.00 Weighted Average for the Second Quarter 305.00 65.01 70.85 70.93 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 40.00 71.70 100.00 100.00 C0142-070 SH 14 MP 75.5-85 08/14/25 20.00 70.68 63.33 75.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 50.00 51.69 75.06 75.06 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 40.00 150.00 80.00 63.09 67.80 62.04 50.00 62.04 Weighted Average for the Third Quarter 300.00 65.10 68.84 68.53 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 20.00 56.84 105.03 37.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 20.00 95.00 62.14 45.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 20.00 70.00 55.00 65.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 10.00 60.00 106.33 45.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 55.39 40.00 40.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 65.00 45.15 42.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 60.00 43.40 40.00 NHPP1602-194 US 160 MP 174.1 12/11/25 20.00 95.00 56.90 50.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 20.00 80.00 61.60 40.00 Weighted Average for the Fourth Quarter 190.00 69.75 64.90 44.37 Weighted Average for the Year 980.00 69.67 67.27 61.07 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 206-00000 Str Excav Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,252.00 33.33 38.15 33.92 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 87.00 106.66 134.55 85.61 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2,658.00 35.00 52.26 50.00 Weighted Average for the First Quarter 3,997.00 36.04 48.08 45.74 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 84,027.00 164.00 47.21 55.37 60.62 55.37 60.62 55.37 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 47.00 100.68 65.95 75.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 11,114.00 60.00 29.54 16.00 Weighted Average for the Second Quarter 95,352.00 48.74 49.90 55.42 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,502.00 49.93 49.93 49.93 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 670.00 76.00 95.95 95.95 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 419.00 63.07 63.40 63.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 1,028.00 225.00 65.00 60.67 30.82 60.97 28.00 50.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 11,256.00 38.37 36.68 36.68 Weighted Average for the Third Quarter 15,100.00 44.02 42.43 40.97 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 30.00 137.99 454.40 105.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 154.00 75.00 119.30 75.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,740.00 35.00 53.75 32.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 205.00 63.40 73.39 49.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 92.00 64.63 96.00 100.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 16.00 140.34 311.37 253.50 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 7.00 193.74 200.66 310.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 10.00 500.00 1692.50 415.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 8.00 100.00 184.00 245.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-00000 Str Excav Cubic Yard STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1,943.00 40.00 85.25 57.30 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 917.00 29.47 29.16 15.30 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 130.00 90.00 73.00 52.00 Weighted Average for the Fourth Quarter 5,252.00 42.15 60.72 44.59 Weighted Average for the Year 119,701.00 47.43 50.44 52.80 206-00010 Str Excav (Spec) Cubic Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 118.00 231.69 240.39 240.39 Weighted Average for the Third Quarter 118.00 231.69 240.39 240.39 Weighted Average for the Year 118.00 231.69 240.39 240.39 206-00050 Str Bkfl (Spec) Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 2,560.00 124.98 142.29 142.29 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 86.00 300.00 1500.00 1500.00 Weighted Average for the Second Quarter 2,646.00 130.67 186.42 186.42 Weighted Average for the Year 2,646.00 130.67 186.42 186.42 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-00060 Str Bkfl (Spec) (Flow-Fill) Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 15.00 434.49 526.00 526.00 FBR0703-534 I-70 Weighted Average for the Second Quarter 15.00 434.49 526.00 526.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 3.00 629.08 1394.71 1433.00 Weighted Average for the Fourth Quarter 3.00 629.08 1394.71 1433.00 Weighted Average for the Year 18.00 466.92 960.35 677.17 206-00065 Str Bkfl (Flow-Fill) Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 22.00 680.00 1364.36 750.00 Weighted Average for the First Quarter 22.00 680.00 1364.36 750.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 123.00 110.00 252.50 205.00 Weighted Average for the Second Quarter 123.00 110.00 252.50 205.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 154.00 1877.68 371.61 371.61 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 21.00 429.98 481.51 300.00 Weighted Average for the Third Quarter 175.00 1703.96 428.95 363.02 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 57.00 400.00 284.21 289.85 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 120.00 650.00 285.00 255.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 698.07 2375.00 3000.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 661.56 2734.32 1900.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 22.00 500.00 1760.00 1500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-00065 Str Bkfl (Flow-Fill) Cubic Yard STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 539.00 300.00 447.36 555.50 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 22.00 350.00 1397.99 1500.00 Weighted Average for the Fourth Quarter 762.00 370.81 440.53 547.82 Weighted Average for the Year 1,082.00 563.07 449.91 483.07 206-00066 Str Bkfl (FF Ash) Cubic Yard NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 61.00 160.05 333.21 333.21 Weighted Average for the Third Quarter 61.00 160.05 333.21 333.21 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 32.00 750.00 896.19 600.00 Weighted Average for the Fourth Quarter 32.00 750.00 896.19 600.00 Weighted Average for the Year 93.00 363.04 787.86 425.01 206-00100 Str Bkfl (CL 1) Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 281.00 76.51 61.26 58.30 Weighted Average for the First Quarter 281.00 76.51 61.26 58.30 NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO VET I-70 CO 17 & SOUTH OF CO 14 04/11/25 05/08/25 128,952.00 1.00 52.15 205.00 62.23 450.00 62.23 1000.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 55.00 165.06 148.50 75.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 560.00 90.00 82.26 64.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid ER060A-028 206-00100 Str Bkfl (CL 1) CO 60 (MP 9-10) 06/18/25 Cubic Yard 123.00 94.26 96.00 67.00 Weighted Average for the Second Quarter 129,691.00 52.41 62.82 62.25 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,346.00 75.29 75.29 75.29 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 505.00 144.96 149.28 149.28 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 361.00 104.41 81.20 92.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 710.00 119.00 120.00 90.98 78.31 128.54 47.00 70.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3,898.00 98.27 95.88 95.88 Weighted Average for the Third Quarter 6,939.00 99.63 91.03 90.13 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 30.00 128.93 298.56 195.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 169.00 125.00 252.76 299.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 959.00 55.00 98.00 56.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 4.00 199.17 251.15 300.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 349.00 90.00 306.76 85.18 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 464.00 141.44 73.98 67.70 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 180.00 90.00 189.00 85.00 Weighted Average for the Fourth Quarter 2,155.00 88.99 129.08 87.11 Weighted Average for the Year 139,066.00 55.38 70.70 64.02 206-00200 Str Bkfl (CL 2) Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 826.00 22.60 40.31 14.84 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 274.00 33.21 256.97 78.84 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 597.00 100.00 45.48 35.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 1,697.00 51.54 69.90 32.27 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL I-70 VASQUEZ BLVD - I270 TO TO VET 04/11/25 64TH - 05/23/25 18,122.00 3.00 42.09 176.67 41.58 176.67 41.58 176.67 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 25.00 99.57 94.46 50.00 Weighted Average for the Second Quarter 18,150.00 42.19 41.96 41.61 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 36.00 109.34 163.04 163.04 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 241.00 624.00 75.00 39.16 43.45 61.61 21.00 61.61 Weighted Average for the Third Quarter 901.00 51.55 51.83 54.80 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 295.00 53.46 68.08 84.65 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2.00 176.26 882.53 740.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 248.00 35.36 36.26 29.00 Weighted Average for the Fourth Quarter 545.00 45.67 45.10 61.73 Weighted Average for the Year 21,293.00 43.42 50.31 41.94 206-00300 Str Bkfl (CL 3) Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 201.00 50.00 110.04 110.04 Weighted Average for the Second Quarter 201.00 50.00 110.04 110.04 Weighted Average for the Year 201.00 50.00 110.04 110.04 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-00360 Mechanical Reinforcement of Soil Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 71,410.00 3.97 3.69 3.69 Weighted Average for the Second Quarter 71,410.00 3.97 3.69 3.69 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 596.00 16.51 13.37 13.37 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 362.00 16.87 47.38 47.38 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2,908.00 13.61 15.72 15.72 Weighted Average for the Third Quarter 3,866.00 14.36 18.32 18.32 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 61.00 70.00 189.35 30.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 428.00 18.25 43.78 48.00 Weighted Average for the Fourth Quarter 489.00 24.71 58.68 45.75 Weighted Average for the Year 75,765.00 4.64 7.67 4.71 206-00505 Filter Matl (Spec) Cubic Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 116.00 158.56 124.35 124.35 Weighted Average for the Third Quarter 116.00 158.56 124.35 124.35 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,399.00 120.00 124.50 112.00 Weighted Average for the Fourth Quarter 1,399.00 120.00 124.50 112.00 Weighted Average for the Year 1,515.00 122.95 124.50 112.95 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-00510 Filter Matl (CL A) Cubic Yard NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 949.88 949.88 949.88 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 635.00 150.00 90.85 56.00 Weighted Average for the Second Quarter 638.00 153.76 91.86 60.20 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 56.00 160.17 160.17 160.17 Weighted Average for the Third Quarter 56.00 160.17 160.17 160.17 Weighted Average for the Year 694.00 154.28 93.33 68.27 206-00520 Filter Matl (CL B) Cubic Yard NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 6.00 100.00 1858.33 175.00 Weighted Average for the First Quarter 6.00 100.00 1858.33 175.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 26.00 1636.69 270.13 270.13 FBR0703-534 I-70 Weighted Average for the Second Quarter 26.00 1636.69 270.13 270.13 Weighted Average for the Year 32.00 1348.56 919.85 252.29 206-00530 Filter Matl (CL C) Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 10.00 1636.36 701.44 701.44 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 10.00 1636.36 701.44 701.44 Weighted Average for the Year 10.00 1636.36 701.44 701.44 206-01750 Shoring Lump Sum STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 25000.00 73500.00 140000.00 Weighted Average for the Fourth Quarter 1.00 25000.00 73500.00 140000.00 Weighted Average for the Year 1.00 25000.00 73500.00 140000.00 206-01781 Shoring (A 1) Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 95842.25 100932.09 100932.09 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 35798.00 36624.39 36624.39 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 85474.00 85992.43 85992.43 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 261744.00 267614.56 267614.56 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 1428129.00 1408984.03 1408984.03 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 72370.00 105948.81 105948.81 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 128487.00 142421.22 142421.22 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 61140.00 33030.87 33030.87 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 549400.00 561843.46 561843.46 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 126255.00 131007.20 131007.20 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 33950.00 36463.22 36463.22 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 69487.00 70486.46 70486.46 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 65789.00 60973.94 60973.94 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 90525.48 26294.06 26294.06 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 24288.67 329866.78 329866.78 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 325019.30 113006.96 113006.96 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 103866.88 22344.36 22344.36 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 90525.49 29364.02 29364.02 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-01781 Shoring (A 1) Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 20850.39 328502.72 328502.72 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 17440.86 14022.78 14022.78 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 90245.94 246901.07 246901.07 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 310842.59 146759.09 146759.09 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 19495.60 389909.03 389909.03 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 41900.57 87927.05 87927.05 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 228621.75 23467.93 23467.93 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 60780.00 97724.16 97724.16 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 36726.00 50302.24 50302.24 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 24395.00 65318.14 65318.14 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 124457.32 39356.69 39356.69 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 407374.20 26556.35 26556.35 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-01781 Shoring (A 1) Lump Sum FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 I-70 I-70 I-70 I-70 I-70 I-70 I-70 I-70 Weighted Average for the Second Quarter 30.00 167707.38 169331.54 169331.54 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 15172.57 153668.11 150000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 34000.00 48082.54 41800.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 19483.99 5957.56 Weighted Average for the Fourth Quarter 3.00 23724.19 106458.61 65919.19 Weighted Average for the Year 33.00 154618.00 150323.44 159930.41 206-01782 Shoring (A 2) Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 121790.00 128629.37 128629.37 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 111697.00 20598.32 20598.32 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 17192.00 20598.32 20598.32 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 17459.00 21501.84 21501.84 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 1053450.00 1087426.84 1087426.84 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 74767.00 44960.72 44960.72 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 74754.72 80040.96 80040.96 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 17191.91 1.00 1.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 39686.60 131810.54 131810.54 FBR0703-534 I-70 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-01782 Shoring (A 2) Lump Sum FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 I-70 I-70 I-70 I-70 I-70 I-70 I-70 Weighted Average for the Second Quarter 9.00 169776.47 170618.66 170618.66 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 15172.56 101862.49 45000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 25000.00 39817.14 36302.45 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 29702.94 26377.76 Weighted Average for the Fourth Quarter 3.00 20724.19 75664.85 35893.40 Weighted Average for the Year 12.00 132513.40 114509.59 136937.34 206-01783 Shoring (A 3) Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 477841.77 264545.85 264545.85 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 30489.64 35534.31 35534.31 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 278051.72 250958.47 250958.47 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 238831.00 307721.88 307721.88 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 Weighted Average for the Second Quarter 4.00 256303.53 214690.13 214690.13 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 32343.27 32343.27 32343.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 1.00 32343.27 32343.27 32343.27 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 20000.00 46214.22 46439.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 28770.72 10094.30 Weighted Average for the Fourth Quarter 2.00 21000.00 35748.12 28266.65 Weighted Average for the Year 7.00 157079.63 106984.44 135376.73 206-01784 Shoring (A 4) Lump Sum STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 23689.38 23689.98 23689.98 Weighted Average for the Third Quarter 1.00 23689.38 23689.98 23689.98 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 26322.92 9750.91 Weighted Average for the Fourth Quarter 1.00 22000.00 26322.92 9750.91 Weighted Average for the Year 2.00 22844.69 25664.69 16720.45 206-01785 Shoring (A 5) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 29052.64 15940.06 Weighted Average for the Fourth Quarter 1.00 22000.00 29052.64 15940.06 Weighted Average for the Year 1.00 22000.00 29052.64 15940.06 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-01786 Shoring (A 6) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 28303.37 18415.72 Weighted Average for the Fourth Quarter 1.00 22000.00 28303.37 18415.72 Weighted Average for the Year 1.00 22000.00 28303.37 18415.72 206-01787 Shoring (A 7) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 21211.62 11140.47 Weighted Average for the Fourth Quarter 1.00 22000.00 21211.62 11140.47 Weighted Average for the Year 1.00 22000.00 21211.62 11140.47 206-01788 Shoring (A 8) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 20423.67 8776.61 Weighted Average for the Fourth Quarter 1.00 22000.00 20423.67 8776.61 Weighted Average for the Year 1.00 22000.00 20423.67 8776.61 206-01789 Shoring (A 9) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 20961.40 10389.79 Weighted Average for the Fourth Quarter 1.00 22000.00 20961.40 10389.79 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 1.00 22000.00 20961.40 10389.79 206-01790 Shoring (A 10) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 21436.64 9815.52 Weighted Average for the Fourth Quarter 1.00 22000.00 21436.64 9815.52 Weighted Average for the Year 1.00 22000.00 21436.64 9815.52 206-01791 Shoring (A 11) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 20951.91 8361.34 Weighted Average for the Fourth Quarter 1.00 22000.00 20951.91 8361.34 Weighted Average for the Year 1.00 22000.00 20951.91 8361.34 206-01792 Shoring (A 12) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 28813.05 26944.76 Weighted Average for the Fourth Quarter 1.00 22000.00 28813.05 26944.76 Weighted Average for the Year 1.00 22000.00 28813.05 26944.76 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 206-01793 Shoring (A 13) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 22658.58 11619.63 Weighted Average for the Fourth Quarter 1.00 22000.00 22658.58 11619.63 Weighted Average for the Year 1.00 22000.00 22658.58 11619.63 206-01794 Shoring (A 14) Lump Sum STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 22000.00 32131.15 43899.04 Weighted Average for the Fourth Quarter 1.00 22000.00 32131.15 43899.04 Weighted Average for the Year 1.00 22000.00 32131.15 43899.04 207-00205 Topsoil Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2,200.00 50.00 37.30 31.80 Weighted Average for the First Quarter 2,200.00 50.00 37.30 31.80 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 36.00 100.00 58.33 31.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 36.00 100.00 58.33 31.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 270.00 41.37 150.00 150.00 Weighted Average for the Fourth Quarter 270.00 41.37 150.00 150.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2,506.00 49.79 39.81 44.52 207-00210 Stockpile Topsoil Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 161.00 30.00 15.80 15.00 Weighted Average for the First Quarter 161.00 30.00 15.80 15.00 NHPP0703-517 FBR0703-534 C0405-042 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 US 40 IN DEER TRAIL, PINE ST 06/05/25 7,945.00 18.00 30.04 57.95 30.73 41.27 30.73 10.00 Weighted Average for the Second Quarter 7,963.00 30.10 30.85 30.68 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 16,000.00 5.73 5.73 5.73 Weighted Average for the Third Quarter 16,000.00 5.73 5.73 5.73 Weighted Average for the Year 24,124.00 13.94 14.17 14.03 207-00305 Wetland Topsoil Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 25.00 50.00 53.82 42.40 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 7.00 152.56 1053.91 1019.76 Weighted Average for the First Quarter 32.00 72.44 211.13 256.20 Weighted Average for the Year 32.00 72.44 211.13 256.20 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 207-00310 Stockpile Wetland Topsoil Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 8.00 30.00 87.01 50.00 Weighted Average for the First Quarter 8.00 30.00 87.01 50.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,016.40 44.23 44.23 44.23 Weighted Average for the Third Quarter 1,016.40 44.23 44.23 44.23 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 99.00 36.74 73.50 66.75 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 130.00 35.08 47.50 61.00 Weighted Average for the Fourth Quarter 229.00 35.80 58.74 63.49 Weighted Average for the Year 1,253.40 42.60 49.55 47.78 207-00405 Topsoil (Spec) Cubic Yard FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 269.00 50.00 61.93 55.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 269.00 50.00 61.93 55.00 Weighted Average for the Year 269.00 50.00 61.93 55.00 207-00700 Topsoil (Onsite) Cubic Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 850.00 20.00 30.85 64.75 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 34.00 120.00 89.75 120.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 3,692.00 30.00 25.00 21.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 207-00700 Topsoil (Onsite) Cubic Yard BR0761-249 I-76 02/27/25 1,372.00 25.04 20.34 42.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 161.00 50.00 20.86 15.00 Weighted Average for the First Quarter 6,109.00 28.52 23.97 32.20 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 162.00 20.00 80.00 80.00 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 19,574.00 650.00 64.06 30.00 67.87 40.25 67.87 34.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 5,243.00 11.30 12.37 5.60 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1,500.00 32.60 32.60 32.60 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 18.00 85.00 44.27 12.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 575.00 30.00 38.72 80.00 Weighted Average for the Second Quarter 27,722.00 50.63 42.49 53.68 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 16,000.00 11.59 11.59 11.59 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 500.00 31.11 57.75 47.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 250.00 55.91 113.12 113.12 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 484.00 72.48 25.60 20.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 40.00 53.10 77.40 55.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 10,252.00 16.66 12.30 5.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 65,836.00 17.26 16.54 16.54 Weighted Average for the Third Quarter 93,362.00 16.70 14.84 14.88 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2,017.00 75.00 21.26 14.50 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 141.00 116.61 71.77 20.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2,067.00 29.96 26.18 25.45 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 493.00 67.75 64.25 26.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 39,688.00 8.50 7.45 5.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 121.00 100.00 120.50 196.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 33.00 165.00 91.30 12.60 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2,258.00 16.19 20.14 26.60 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 207-00700 Topsoil (Onsite) Cubic Yard BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 399.00 35.00 50.40 50.00 Weighted Average for the Fourth Quarter 47,217.00 14.16 10.58 8.48 Weighted Average for the Year 174,410.00 21.82 15.50 19.92 207-00702 Topsoil (Offsite) Cubic Yard NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2,700.00 120.00 87.98 35.42 Weighted Average for the First Quarter 2,700.00 120.00 87.98 35.42 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 112.22 312.50 275.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2,030.00 57.67 57.67 57.67 Weighted Average for the Second Quarter 2,032.00 57.72 58.17 57.88 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 110.00 83.73 123.14 123.14 Weighted Average for the Third Quarter 110.00 83.73 123.14 123.14 Weighted Average for the Year 4,842.00 93.04 83.60 46.84 207-00703 Topsoil (Wetlnd) Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 8.00 500.00 90.62 50.00 Weighted Average for the First Quarter 8.00 500.00 90.62 50.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 22.50 175.00 132.00 43.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 22.50 175.00 132.00 43.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,016.40 27.01 27.01 27.01 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 307.00 50.00 68.06 70.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 1,323.40 32.34 51.71 36.98 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 130.00 95.00 55.13 59.25 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 807.00 28.61 33.92 38.00 Weighted Average for the Fourth Quarter 937.00 37.82 34.58 40.95 Weighted Average for the Year 2,290.90 37.62 39.51 38.71 207-00704 Sub Soil Prep Sq Yard STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 145.00 11.15 58.00 110.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 111,320.00 8,960.00 1.76 2.05 2.51 2.05 2.51 2.05 Weighted Average for the Second Quarter 120,425.00 1.79 2.61 2.61 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 61,178.00 1.30 1.30 1.30 BR0704-265 FBR0704-269 NHPP0704-260 I-70 EAST I-70 EAST I-70 AND PENA BLVD OVERPASS 07/24/25 08/21/25 7,500.00 1,090.00 2.26 4.86 6.90 9.20 8.09 9.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 7,260.00 11,000.00 2.00 1.94 2.24 1.87 2.50 1.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 395,020.00 0.63 0.48 0.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 483,048.00 0.80 1.25 0.76 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 12,100.00 1.68 5.90 3.75 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 17,900.00 3.24 2.95 1.95 Weighted Average for the Fourth Quarter 30,000.00 2.61 4.80 2.68 Weighted Average for the Year 633,473.00 1.07 1.86 1.20 208-00002 Erosion Log Type 1 (12 In) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 575.00 7.35 7.28 8.20 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 600.00 5.97 6.34 8.44 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2,000.00 10.00 5.91 5.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 44.00 8.00 21.01 24.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 570.00 10.00 11.17 6.50 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 200.00 8.32 12.00 10.70 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 820.00 6.77 6.41 5.20 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 200.00 6.00 8.92 8.75 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 2,000.00 8.00 6.60 6.20 Weighted Average for the First Quarter 7,009.00 8.31 7.37 6.43 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 24.00 11.80 33.50 46.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 4,000.00 60.00 5.95 12.00 6.80 7.00 6.80 7.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 1,300.00 7.00 10.02 10.50 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 500.00 10.00 7.00 7.00 STAR500-228 REGION 5 05/08/25 1,690.00 7.00 8.30 9.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 7,500.00 6.49 6.49 6.49 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 1,160.00 7.09 9.83 8.50 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 200.00 9.01 8.48 6.25 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 790.00 15.00 9.68 14.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00002 Erosion Log Type 1 (12 In) Lin Foot ITSSW03-250 FRONT RANGE 06/26/25 760.00 7.27 5.86 8.00 Weighted Average for the Second Quarter 17,984.00 7.05 8.02 7.67 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4,005.00 5.22 5.22 5.22 CR400-406 REGION-WIDE 07/17/25 1,950.00 7.21 11.00 11.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 500.00 7.29 7.06 3.50 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1,400.00 7.25 7.25 7.25 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 160.00 7.91 11.00 10.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 750.00 8.23 8.00 9.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 140.00 8.38 6.40 6.70 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 2,100.00 1,000.00 10.00 6.76 9.12 7.05 8.00 9.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 55,000.00 5.23 5.32 5.32 SPFS2706-055 I-270 MP 0-3 09/26/25 100.00 15.31 16.92 16.92 Weighted Average for the Third Quarter 67,105.00 5.58 6.49 5.72 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 320.00 6.57 8.65 6.20 NHPPR500-227 REGION 5 SECTION 7 10/23/25 401.00 10.00 9.31 8.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 500.00 10.00 9.97 6.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,010.00 8.00 7.68 8.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 462.00 7.07 6.69 6.65 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 22,053.00 4.92 5.08 4.95 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 10.00 10.03 83.00 180.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 100.00 7.75 6.87 6.25 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 200.00 10.00 6.55 5.60 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 100.00 9.28 11.00 10.00 ITSSW03-417 STATEWIDE 12/04/25 1,000.00 7.28 7.89 7.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 500.00 7.00 9.45 5.90 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 800.00 7.21 5.00 5.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 800.00 15.00 5.93 5.25 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 100.00 7.00 5.90 5.65 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00002 Erosion Log Type 1 (12 In) Lin Foot NHPP1602-194 US 160 MP 174.1 12/11/25 700.00 9.00 11.66 7.50 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 4,360.00 9.00 7.63 6.66 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 830.00 6.00 6.15 5.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 200.00 7.57 6.32 7.60 Weighted Average for the Fourth Quarter 34,446.00 6.28 6.55 5.57 Weighted Average for the Year 126,544.00 6.13 6.81 5.99 208-00008 Erosion Log Type 2 (12 In) Lin Foot STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 2,300.00 10.00 7.30 7.30 Weighted Average for the Second Quarter 2,300.00 10.00 7.30 7.30 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2,500.00 5.50 7.98 8.20 Weighted Average for the Fourth Quarter 2,500.00 5.50 7.98 8.20 Weighted Average for the Year 4,800.00 7.66 7.92 7.77 208-00009 Erosion Log Type 2 (18 In) Lin Foot STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 3,000.00 13.43 14.05 13.00 Weighted Average for the First Quarter 3,000.00 13.43 14.05 13.00 Weighted Average for the Year 3,000.00 13.43 14.05 13.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00011 Erosion Bales (Weed Free) Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 20.00 26.02 46.58 40.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 650.00 30.76 31.30 31.30 Weighted Average for the Third Quarter 670.00 30.62 34.32 31.56 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 52.00 17.82 42.47 22.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 117.00 21.85 22.13 21.95 Weighted Average for the Fourth Quarter 169.00 20.61 32.83 21.97 Weighted Average for the Year 839.00 28.60 33.76 29.63 208-00012 Erosion Log Type 1 (9 In) Lin Foot STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 200.00 5.95 4.14 4.13 Weighted Average for the Fourth Quarter 200.00 5.95 4.14 4.13 Weighted Average for the Year 200.00 5.95 4.14 4.13 208-00013 Erosion Log Type 1 (20 In) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4,300.00 8.00 9.29 11.19 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 250.00 20.00 8.50 7.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 370.00 11.15 10.32 8.32 Weighted Average for the First Quarter 4,920.00 8.85 9.33 10.79 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 13,000.00 13.25 9.27 9.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00013 Erosion Log Type 1 (20 In) Lin Foot FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 50.00 11.78 11.78 11.78 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 100.00 10.86 9.68 8.33 Weighted Average for the Second Quarter 13,150.00 13.23 9.29 9.27 BR0704-265 I-70 EAST 07/24/25 2,444.00 13.95 9.84 9.36 FBR0704-269 I-70 EAST NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,000.00 8.30 8.44 8.44 Weighted Average for the Third Quarter 3,444.00 12.31 9.71 9.09 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 70.00 9.00 18.03 9.05 Weighted Average for the Fourth Quarter 70.00 9.00 18.03 9.05 Weighted Average for the Year 21,584.00 12.07 9.42 9.59 208-00019 Silt Fence (Reinforced)(Special) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2,150.00 7.86 7.43 7.43 FBR0703-534 I-70 Weighted Average for the Second Quarter 2,150.00 7.86 7.43 7.43 Weighted Average for the Year 2,150.00 7.86 7.43 7.43 208-00020 Silt Fence Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,260.00 1.96 3.06 3.35 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 2670252-499 208-00020 Silt Fence I-25:MOBILITY HUB (LONE TREE) 01/16/25 Lin Foot 400.00 1.99 3.22 3.11 Weighted Average for the First Quarter 1,660.00 1.96 3.12 3.29 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 400.00 3.50 5.27 4.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1,100.00 3.00 2.00 1.76 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 500.00 2.84 2.84 2.84 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 200.00 8.00 4.62 2.58 Weighted Average for the Second Quarter 2,200.00 3.51 3.29 2.49 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 7,000.00 1.39 1.39 1.39 BR0704-265 FBR0704-269 STR025A-054 I-70 EAST I-70 EAST I-25C NORTH OUT OF WALSENBURG 07/24/25 09/18/25 6,658.00 7,500.00 2.11 3.53 3.18 2.50 5.70 3.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 45,000.00 1.55 1.58 1.58 Weighted Average for the Third Quarter 66,158.00 1.81 2.27 2.14 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 200.00 2.43 3.67 2.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 7,600.00 1.57 1.47 1.45 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 500.00 2.63 2.38 2.35 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 800.00 4.53 2.49 2.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 100.00 6.05 5.00 5.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 500.00 3.00 2.45 2.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 200.00 2.50 2.18 1.35 Weighted Average for the Fourth Quarter 9,900.00 2.02 1.81 1.64 Weighted Average for the Year 79,918.00 1.89 2.28 2.11 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 208-00021 Silt Fence (Reinf) Lin Foot STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 205.00 5.00 10.09 6.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,100.00 7.60 5.86 5.72 Weighted Average for the First Quarter 1,305.00 7.19 6.52 5.84 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 26,000.00 2.78 2.82 2.82 Weighted Average for the Second Quarter 26,000.00 2.78 2.82 2.82 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 100.00 3.59 6.10 6.10 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 360.00 3,000.00 78.00 4.01 8.46 4.08 4.00 4.08 Weighted Average for the Third Quarter 3,460.00 11.70 5.73 4.13 Weighted Average for the Year 30,765.00 3.97 3.75 3.10 208-00023 Erosion Log Type 3 (12 In) Lin Foot BR0761-249 I-76 02/27/25 1,800.00 8.11 8.10 6.00 Weighted Average for the First Quarter 1,800.00 8.11 8.10 6.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1,700.00 7.10 7.48 8.19 Weighted Average for the Second Quarter 1,700.00 7.10 7.48 8.19 C0142-070 SH 14 MP 75.5-85 08/14/25 200.00 10.46 13.67 10.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 500.00 6.21 6.31 6.31 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 700.00 7.42 10.32 7.36 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 950.00 7.37 7.99 7.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 8,780.00 7.18 6.16 5.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 300.00 8.99 9.16 9.70 Weighted Average for the Fourth Quarter 10,030.00 7.25 6.50 5.77 Weighted Average for the Year 14,230.00 7.35 6.89 6.17 208-00033 Sediment Trap Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 4985.74 2833.42 895.49 Weighted Average for the First Quarter 1.00 4985.74 2833.42 895.49 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6.00 5996.77 5525.00 5525.00 FBR0703-534 I-70 Weighted Average for the Second Quarter 6.00 5996.77 5525.00 5525.00 Weighted Average for the Year 7.00 5852.33 4179.21 4863.64 208-00035 Aggregate Bag Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 84.00 14.13 11.81 12.50 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,750.00 9.20 9.83 12.97 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 200.00 15.00 18.06 20.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 160.00 25.00 12.41 9.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 50.00 15.26 20.29 25.30 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 102.00 10.00 15.66 22.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00035 Aggregate Bag Lin Foot BR0761-249 I-76 02/27/25 2,000.00 10.69 10.38 15.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 300.00 12.25 13.95 12.40 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 252.00 13.95 10.60 9.36 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 300.00 11.00 12.83 12.50 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 200.00 10.00 12.03 9.05 Weighted Average for the First Quarter 5,398.00 11.11 10.90 13.77 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 900.00 12.00 8.00 8.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 11,500.00 60.00 8.82 40.00 9.46 15.00 9.46 15.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 300.00 12.02 10.92 12.75 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 30.00 11.00 18.95 19.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 500.00 15.00 11.00 11.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 500.00 15.00 8.09 8.78 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 50.00 15.88 26.67 39.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 252.00 16.15 16.15 16.15 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 40.00 16.72 12.22 8.39 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 160.00 9.00 12.38 15.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 100.00 20.00 13.51 20.00 ITSSW03-250 FRONT RANGE 06/26/25 1,400.00 10.86 7.11 8.50 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 175.00 12.16 15.00 15.00 Weighted Average for the Second Quarter 15,967.00 10.02 9.17 9.80 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 150.00 12.53 9.12 9.12 CR400-406 REGION-WIDE 07/17/25 1,525.00 10.60 13.67 11.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 476.00 13.10 2.00 2.00 C0142-070 SH 14 MP 75.5-85 08/14/25 200.00 13.07 14.33 15.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 50.00 14.58 10.07 10.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 600.00 15.25 15.25 15.25 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 125.00 15.69 17.34 17.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 200.00 13.87 14.80 12.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00035 Aggregate Bag Lin Foot STR050A-042 FREMONT COUNTY IN R2 09/11/25 40.00 14.93 17.60 17.00 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 200.00 5,000.00 15.00 7.65 15.56 7.78 15.00 7.78 SPFS2706-055 I-270 MP 0-3 09/26/25 100.00 10.75 11.88 11.88 Weighted Average for the Third Quarter 8,666.00 9.74 11.61 9.24 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 860.00 16.00 15.98 16.68 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 200.00 15.08 17.08 13.50 NHPPR500-227 REGION 5 SECTION 7 10/23/25 119.00 15.00 13.85 15.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 300.00 15.00 13.16 9.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 480.00 12.00 12.63 5.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 80.00 9.67 7.01 6.95 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 546.00 10.57 10.68 7.25 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 600.00 9.94 8.87 8.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 800.00 9.73 7.81 9.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 100.00 10.00 13.70 12.40 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 50.00 15.55 16.89 12.00 ITSSW03-417 STATEWIDE 12/04/25 200.00 14.18 20.27 12.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 200.00 12.00 14.58 16.75 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 720.00 12.00 9.00 7.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 130.00 16.00 16.00 13.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 250.00 13.00 16.75 24.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 500.00 12.00 10.48 11.75 NHPP1602-194 US 160 MP 174.1 12/11/25 100.00 20.00 26.33 23.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 800.00 10.00 14.92 14.52 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 500.00 10.52 6.98 5.50 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 100.00 15.00 11.85 15.00 Weighted Average for the Fourth Quarter 7,635.00 12.16 11.61 11.15 Weighted Average for the Year 37,666.00 10.54 10.81 10.51 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00041 Rock Check Dam Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 70.00 1689.96 2100.55 2100.55 FBR0703-534 I-70 Weighted Average for the Second Quarter 70.00 1689.96 2100.55 2100.55 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 25.00 823.90 1173.76 1173.76 Weighted Average for the Third Quarter 25.00 823.90 1173.76 1173.76 Weighted Average for the Year 95.00 1462.05 1856.66 1856.66 208-00045 Conc Washout Str Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 6000.00 3027.40 780.30 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 1.00 1800.00 3333.33 7500.00 Weighted Average for the First Quarter 2.00 3900.00 3158.51 4140.15 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 5.00 89395.08 81929.10 81929.10 FBR0703-534 I-70 Weighted Average for the Second Quarter 5.00 89395.08 81929.10 81929.10 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 9009.47 9009.47 9009.47 CR400-406 REGION-WIDE 07/17/25 12.00 1529.90 2100.00 3000.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 2202.98 3425.00 1700.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 1.00 2500.00 1573.33 1120.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 2568.00 2797.96 2797.96 Weighted Average for the Third Quarter 17.00 2567.58 2496.45 3508.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00045 Conc Washout Str Each STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 5.00 2967.58 1796.50 2950.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 2726.92 3543.05 3600.00 Weighted Average for the Fourth Quarter 6.00 2927.47 2199.55 3058.33 Weighted Average for the Year 30.00 17199.63 8101.21 16530.42 208-00046 Pre-fab Conc Washout Str (Type 1) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 1805.77 2597.85 2095.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 5000.00 4153.89 4102.86 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 1.00 6000.00 13456.06 7500.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 5000.00 2835.08 3000.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 3.00 2500.00 3588.73 2875.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 4000.00 6630.50 6100.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 1500.00 2908.08 3058.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 2.00 3000.00 5994.07 1700.00 BR0761-249 I-76 02/27/25 6.00 995.89 2283.85 3000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 2.00 2299.14 2921.64 2570.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 2000.00 6505.00 3010.00 Weighted Average for the First Quarter 25.00 2451.87 3715.82 3099.07 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 3250.35 5337.50 6475.00 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 6.00 1.00 12334.15 2000.00 6605.29 4500.00 6605.29 4500.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 10.00 1040.00 2634.00 702.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 2.00 1886.86 4921.33 4664.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 4251.32 4251.32 4251.32 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 1.00 2281.31 1960.10 1000.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 1.00 2763.00 1873.00 1200.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 208-00046 Pre-fab Conc Washout Str (Type 1) Each NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 2.00 3000.00 4755.55 1400.00 ITSSW03-250 FRONT RANGE 06/26/25 4.00 1367.92 1945.60 1100.00 Weighted Average for the Second Quarter 31.00 3958.03 3180.68 2874.47 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 2806.51 2806.51 2806.51 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 6.00 2.00 1501.42 961.35 3497.03 961.34 2988.10 961.34 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 2.00 1378.44 2436.54 600.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 2834.43 2683.00 1700.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 1623.61 2594.90 3150.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 2.00 6000.00 4381.20 2230.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 3362.41 5093.25 5000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 12.00 5243.00 3818.57 3818.57 Weighted Average for the Third Quarter 31.00 3472.60 3504.36 2980.97 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4.00 4500.00 6830.40 8421.60 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 1859.89 4725.50 2755.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 3.00 2500.00 3480.30 5000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2.00 5000.00 5119.67 2500.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 2475.49 3843.12 3630.25 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 1.00 5000.00 4773.33 8500.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 3961.08 4081.21 3700.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4.00 1447.99 5996.10 2480.50 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 2.00 2201.94 7320.38 4600.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 5000.00 5171.83 5000.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 8.00 4500.00 2716.67 1650.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 3000.00 1573.00 521.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 3000.00 4055.00 6000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 3800.00 2305.00 520.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 10000.00 7995.43 10285.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00046 Pre-fab Conc Washout Str (Type 1) Each FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 921.47 4615.30 1600.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 4500.00 6460.00 5000.00 Weighted Average for the Fourth Quarter 38.00 3446.79 4726.61 3653.70 Weighted Average for the Year 125.00 3381.00 3972.31 3182.69 208-00051 Storm Drain Inlet Protection (Type I) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 500.00 10.75 43.79 184.60 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 86.00 13.30 17.23 10.40 Weighted Average for the First Quarter 586.00 11.13 41.06 159.03 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 68.00 17.57 19.50 17.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 24.00 28.82 93.67 230.00 ITSSW03-250 FRONT RANGE 06/26/25 100.00 16.52 15.96 8.50 Weighted Average for the Second Quarter 192.00 18.43 24.54 39.20 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 200.00 12.53 9.12 9.12 BR0704-265 FBR0704-269 NHPP0253-302 I-70 EAST 07/24/25 I-70 EAST I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 150.00 39.94 7.65 116.10 9.96 334.40 9.96 Weighted Average for the Third Quarter 351.00 10.52 10.68 10.41 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 80.00 20.00 33.05 16.69 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 119.00 20.00 19.18 15.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 8.00 30.98 103.27 20.00 NHPP1602-194 US 160 MP 174.1 12/11/25 12.00 50.00 132.66 250.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 219.00 22.04 30.47 28.68 Weighted Average for the Year 1,348.00 13.78 34.85 82.09 208-00052 Storm Drain Inlet Protection (Type II) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 100.00 45.57 41.58 41.58 Weighted Average for the Third Quarter 100.00 45.57 41.58 41.58 Weighted Average for the Year 100.00 45.57 41.58 41.58 208-00053 Storm Drain Inlet Protect (Ty I)(84 In) Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 300.00 367.35 500.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 5.00 207.41 343.67 305.00 Weighted Average for the First Quarter 6.00 222.84 347.62 337.50 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 6.00 300.00 165.00 165.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 7.00 397.60 397.60 397.60 Weighted Average for the Second Quarter 13.00 352.55 290.25 290.25 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 4.00 152.83 220.20 170.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 2.00 241.84 664.67 2756.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 5.00 200.00 101.60 126.50 Weighted Average for the Fourth Quarter 11.00 190.46 301.67 620.41 Weighted Average for the Year 30.00 267.18 311.23 420.76 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00054 Storm Drain Inlet Protection (Type II) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 32.00 243.56 288.27 335.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2.00 310.00 331.59 450.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 5.00 273.84 346.65 316.25 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 5.00 277.35 460.60 405.00 Weighted Average for the First Quarter 44.00 253.86 317.56 346.05 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 36.00 300.00 230.00 230.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 21.00 472.46 472.46 472.46 Weighted Average for the Second Quarter 57.00 363.54 319.33 319.33 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 3.00 288.06 300.25 200.00 Weighted Average for the Third Quarter 3.00 288.06 300.25 200.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 57.00 340.00 323.55 289.19 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 300.00 418.45 264.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 5.00 245.00 272.00 240.00 Weighted Average for the Fourth Quarter 63.00 331.83 322.19 284.89 Weighted Average for the Year 167.00 321.32 319.81 311.23 208-00055 Rigid Inlet Prot Device Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 22.00 420.48 327.02 305.00 Weighted Average for the First Quarter 22.00 420.48 327.02 305.00 CR400-406 REGION-WIDE 07/17/25 2.00 408.52 2983.33 1650.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00055 Rigid Inlet Prot Device Each MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 110.00 408.52 450.00 450.00 Weighted Average for the Third Quarter 112.00 408.52 581.03 471.43 Weighted Average for the Year 134.00 410.49 488.92 444.10 208-00056 Storm Drain Inlet Protection (Type III) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 12.00 265.04 196.11 294.68 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 320.00 446.27 600.00 Weighted Average for the First Quarter 13.00 269.27 206.12 318.17 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 120.00 109.65 155.63 155.63 FBR0703-534 I-70 Weighted Average for the Second Quarter 120.00 109.65 155.63 155.63 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 422.04 626.00 390.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 40.00 197.95 201.37 201.37 Weighted Average for the Third Quarter 41.00 203.42 248.55 205.97 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 600.00 347.30 289.19 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 3.00 290.00 331.95 264.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 355.70 265.08 210.00 Weighted Average for the Fourth Quarter 6.00 404.28 320.81 263.40 Weighted Average for the Year 180.00 152.36 198.51 182.43 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00057 Storm Drain Inlet Protect (Ty I)(144 In) Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 450.00 250.00 250.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 7.00 374.29 374.29 374.29 Weighted Average for the Second Quarter 11.00 401.82 329.09 329.09 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 5.00 292.72 247.26 210.00 Weighted Average for the Fourth Quarter 5.00 292.72 247.26 210.00 Weighted Average for the Year 16.00 367.73 272.27 291.88 208-00058 Storm Drain Inlet Protect (Ty I)(204 In) Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 300.00 320.00 320.00 Weighted Average for the Second Quarter 1.00 300.00 320.00 320.00 Weighted Average for the Year 1.00 300.00 320.00 320.00 208-00070 Vehicle Tracking Pad Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 2500.00 3906.50 5000.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 3000.00 3974.96 599.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 3297.25 3524.79 2496.97 Weighted Average for the First Quarter 6.00 2932.42 3813.49 2698.66 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4.00 16025.63 36163.51 36163.51 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 4.00 16025.63 36163.51 36163.51 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 5.00 4047.02 3909.56 3909.56 Weighted Average for the Third Quarter 5.00 4047.02 3909.56 3909.56 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 3591.80 2500.00 2500.00 Weighted Average for the Fourth Quarter 1.00 3591.80 2500.00 2500.00 Weighted Average for the Year 16.00 6595.25 7594.87 11430.86 208-00071 Maint Aggregate (Veh Track Pad) Cubic Yard NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 500.00 89.17 89.42 89.42 Weighted Average for the Third Quarter 500.00 89.17 89.42 89.42 Weighted Average for the Year 500.00 89.17 89.42 89.42 208-00075 Pre-fab Vehicle Track Pad Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 3678.07 3852.62 4800.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 42.00 1000.00 1078.86 1500.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 5000.00 8918.41 4855.45 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 4000.00 13154.23 800.00 BR0761-249 I-76 02/27/25 2.00 3983.52 6854.29 4500.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 5000.00 10843.22 25000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 2.00 3727.79 4806.14 4375.00 Weighted Average for the First Quarter 53.00 1675.07 2025.53 2466.35 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00075 Pre-fab Vehicle Track Pad Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 8000.00 5000.00 5000.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 5165.59 7500.00 1000.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 6.00 1.00 16025.50 6000.00 18413.28 5000.00 18413.28 5000.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 1.00 10000.00 4487.00 3850.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 1.00 5000.00 13216.00 8864.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 2.00 2325.00 4633.33 1200.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 14636.59 14636.59 14636.59 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 3.00 3200.00 4726.94 1500.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 2.00 5000.00 13064.54 24000.00 ITSSW03-250 FRONT RANGE 06/26/25 2.00 4642.52 6760.80 5000.00 Weighted Average for the Second Quarter 26.00 8549.71 8442.96 9398.73 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 7.00 14293.39 12682.58 12682.58 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 4.00 2.00 4752.74 20627.04 5562.31 20626.81 5949.24 20626.81 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 4222.17 5380.00 2100.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 3827.63 5425.30 1500.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 3.00 6.00 14000.00 3102.56 9748.40 7631.88 3270.00 5000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 15.00 8190.06 7285.83 7285.83 Weighted Average for the Third Quarter 40.00 8901.42 7811.85 7715.65 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4.00 4000.00 10235.00 16940.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.00 2890.30 9350.50 8000.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 2.00 4500.00 11263.13 1300.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 2.00 10000.00 8881.79 15000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2.00 6000.00 9876.67 5000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 4.00 3787.99 6103.94 4510.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00075 Pre-fab Vehicle Track Pad Each STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 5.00 2871.53 2419.75 4500.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 7000.00 6505.20 1000.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2.00 3321.74 10250.59 6400.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 2.00 4496.96 5792.00 4400.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 4.00 2639.81 5193.28 5300.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 6.00 1884.91 6168.60 5843.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 2.00 8000.00 5525.00 6575.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 7000.00 11095.00 19690.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 6000.00 7530.00 4500.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 4.00 4000.00 7769.25 11495.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 4890.00 5502.31 3375.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 2.00 5000.00 4940.00 1500.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 2.00 3867.52 7302.98 13400.00 Weighted Average for the Fourth Quarter 53.00 4265.87 7028.47 7397.53 Weighted Average for the Year 172.00 5193.14 4966.03 6254.53 208-00082 Construction Mat Sq Foot STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 4,000.00 25.00 20.42 30.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 800.00 25.00 13.00 22.00 Weighted Average for the First Quarter 4,800.00 25.00 20.02 28.67 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 9,150.00 64.00 14.64 50.00 15.86 110.25 15.86 86.00 STAR500-228 REGION 5 05/08/25 50.00 70.00 96.00 78.00 Weighted Average for the Second Quarter 9,264.00 15.18 19.65 16.68 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00082 Construction Mat Sq Foot BR0704-265 FBR0704-269 STR050A-042 I-70 EAST I-70 EAST FREMONT COUNTY IN R2 07/24/25 09/11/25 29,957.00 100.00 9.41 45.41 11.15 74.40 2.09 25.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES 1,000.00 20.00 45.09 14.00 Weighted Average for the Third Quarter 31,057.00 9.86 12.75 2.55 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1,000.00 20.00 16.05 14.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 2,500.00 30.00 19.42 15.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4,855.00 10.00 13.40 17.00 Weighted Average for the Fourth Quarter 8,355.00 17.18 16.11 16.04 Weighted Average for the Year 53,476.00 13.29 14.84 9.45 208-00090 Erosion Control (Curb Ramp) Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 95.00 600.00 899.22 2100.00 Weighted Average for the First Quarter 95.00 600.00 899.22 2100.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 150.00 421.34 551.50 184.00 Weighted Average for the Third Quarter 150.00 421.34 551.50 184.00 Weighted Average for the Year 245.00 490.62 686.33 926.94 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00103 Removal and Disposal of Sediment (Labor) Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 40.00 78.84 83.52 82.40 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 60.00 60.58 72.98 100.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 100.00 65.99 67.32 49.71 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 100.00 75.00 55.89 5.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 8.00 80.00 269.50 350.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 50.00 72.61 85.38 189.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 75.00 132.00 53.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 24.00 70.00 101.50 145.00 BR0761-249 I-76 02/27/25 80.00 69.65 67.57 115.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 20.00 150.00 88.30 45.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 80.00 77.73 84.65 75.25 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 120.00 84.22 106.40 72.83 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 20.00 70.00 59.10 51.20 Weighted Average for the First Quarter 742.00 75.65 79.51 78.89 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 40.00 85.00 115.00 115.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 700.00 10.00 70.42 50.00 80.72 150.00 80.72 150.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 20.00 79.79 67.08 105.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 15.00 70.00 75.00 60.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 100.00 55.00 55.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 20.00 75.00 114.50 58.50 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 45.00 77.40 93.33 59.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 80.00 48.27 48.27 48.27 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 40.00 80.11 81.67 120.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 83.92 57.51 45.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 20.00 85.00 86.76 115.00 ITSSW03-250 FRONT RANGE 06/26/25 40.00 78.73 114.16 1.00 Weighted Average for the Second Quarter 1,090.00 71.94 84.26 76.63 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00103 Removal and Disposal of Sediment (Labor) Hour SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 8.00 86.31 132.50 85.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 20.00 67.00 100.00 100.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 10.00 84.82 101.00 105.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 50.00 60.65 151.31 151.31 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 2.00 87.40 123.22 100.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 79.87 95.50 150.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 4.00 72.76 144.20 235.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 20.00 40.00 100.00 65.12 105.60 80.59 51.00 40.00 Weighted Average for the Third Quarter 156.00 71.42 98.37 98.43 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 40.00 70.00 73.44 90.75 NHPPR500-227 REGION 5 SECTION 7 10/23/25 30.00 80.00 135.63 75.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 60.00 95.00 73.51 45.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 110.00 60.00 58.45 20.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 73.94 135.40 144.95 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 10.00 60.00 112.15 107.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 20.00 72.62 92.26 45.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 120.00 73.24 94.90 80.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 120.00 66.83 83.20 81.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 50.00 60.00 55.00 65.00 ITSSW03-417 STATEWIDE 12/04/25 40.00 76.90 96.63 85.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 20.00 75.00 110.53 45.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 30.00 85.00 103.33 110.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 20.00 50.00 48.10 48.20 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 79.45 40.00 40.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 70.00 57.40 40.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 50.00 62.03 77.25 NHPP1602-194 US 160 MP 174.1 12/11/25 10.00 300.00 159.58 160.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 85.00 157.87 220.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 80.00 66.39 73.51 53.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 80.00 60.00 61.60 40.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 1,000.00 72.53 80.91 71.47 Weighted Average for the Year 2,988.00 73.03 82.00 76.60 208-00105 Removal and Disposal of Sediment (Equip) Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 40.00 154.81 149.71 163.30 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 60.00 151.37 144.45 175.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 25.00 134.51 128.02 105.14 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 80.00 100.00 118.52 5.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 50.00 146.10 137.45 189.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 150.00 311.00 120.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 16.00 150.00 140.00 73.00 BR0761-249 I-76 02/27/25 24.00 148.61 137.69 150.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 20.00 150.00 135.16 100.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 40.00 155.86 182.65 163.90 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 40.00 177.41 241.17 119.65 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 20.00 150.00 161.50 170.00 Weighted Average for the First Quarter 455.00 143.39 153.56 122.76 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 8.00 175.00 250.00 250.00 NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 SH287 & LCR 72 AND US287 & OW 04/24/25 150.00 8.00 132.23 172.96 192.91 100.00 192.91 80.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 15.00 150.00 168.25 143.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 150.00 145.00 145.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 60.00 147.00 195.17 175.50 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 60.00 114.64 114.64 114.64 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 40.00 169.39 153.33 175.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 165.68 133.18 85.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 20.00 120.00 165.62 220.00 ITSSW03-250 FRONT RANGE 06/26/25 40.00 143.13 223.55 1.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 461.00 140.52 177.02 152.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 8.00 165.73 191.75 145.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 20.00 130.00 200.00 200.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 10.00 144.60 134.50 150.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 50.00 131.64 128.54 128.54 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 152.13 146.50 290.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 20.00 40.00 110.00 143.95 153.20 164.31 100.00 110.00 Weighted Average for the Third Quarter 150.00 134.77 159.63 133.78 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 40.00 180.00 163.93 205.70 NHPPR500-227 REGION 5 SECTION 7 10/23/25 30.00 200.00 171.25 100.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 60.00 200.00 153.47 100.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 110.00 150.00 129.83 20.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 158.22 223.64 220.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 10.00 115.00 188.25 220.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 20.00 158.12 306.68 375.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 32.00 157.28 191.34 175.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 40.00 140.41 166.90 114.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 35.00 100.00 104.00 108.00 ITSSW03-417 STATEWIDE 12/04/25 40.00 171.01 141.75 150.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 20.00 200.00 173.93 125.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 20.00 110.00 156.00 162.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 159.94 100.00 100.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 250.00 139.50 125.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 155.00 229.33 220.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 24.00 139.36 129.57 114.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 45.00 170.00 159.00 125.00 Weighted Average for the Fourth Quarter 666.00 162.35 155.97 131.06 Weighted Average for the Year 1,732.00 149.17 158.85 134.69 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00106 Sweeping (Sediment Removal) Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 40.00 148.41 239.35 187.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 100.00 147.33 192.02 114.09 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 80.00 115.00 226.27 20.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 10.00 250.00 247.92 300.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 40.00 148.41 211.97 189.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 200.00 193.00 120.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 16.00 150.00 205.33 216.00 BR0761-249 I-76 02/27/25 104.00 147.42 191.05 105.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 100.00 205.92 234.87 209.20 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 50.00 146.88 231.91 140.45 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 20.00 150.00 147.50 145.00 Weighted Average for the First Quarter 600.00 158.29 208.64 135.16 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 96.00 175.00 220.00 220.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 21.00 171.58 162.00 94.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 700.00 10.00 190.03 200.00 195.94 75.00 195.94 75.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 20.00 223.02 166.00 170.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 15.00 150.00 194.75 154.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 200.00 165.00 165.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 40.00 148.00 179.00 117.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 25.00 201.58 306.67 160.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 120.00 215.08 215.08 215.08 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 40.00 149.40 203.11 200.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 20.00 250.00 142.99 125.00 ITSSW03-250 FRONT RANGE 06/26/25 20.00 149.41 181.70 1.00 Weighted Average for the Second Quarter 1,167.00 189.26 196.48 187.08 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 8.00 149.43 209.25 170.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00106 Sweeping (Sediment Removal) Hour MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 20.00 160.00 400.00 400.00 BR0704-265 I-70 EAST 07/24/25 240.00 198.20 173.68 114.70 FBR0704-269 I-70 EAST C0142-070 SH 14 MP 75.5-85 08/14/25 16.00 188.82 168.33 125.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 10.00 188.87 149.50 120.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 10.00 194.17 386.75 386.75 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 4.00 212.70 272.41 175.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 183.44 170.40 150.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 9.00 165.01 130.60 120.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 4.00 201.29 228.60 410.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 10.00 160.00 182.92 130.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 40.00 168.15 243.03 110.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 208.00 177.19 244.89 244.89 SPFS2706-055 I-270 MP 0-3 09/26/25 40.00 215.00 237.58 237.58 Weighted Average for the Third Quarter 639.00 186.86 198.30 182.34 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 40.00 210.00 258.38 423.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 40.00 161.89 224.00 375.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 30.00 160.00 213.75 200.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 60.00 250.00 148.66 200.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 15.00 149.51 71.33 10.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 70.00 150.00 184.00 35.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 196.62 188.59 189.90 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 60.00 208.49 150.50 144.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 20.00 150.00 217.05 32.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 40.00 147.68 289.24 375.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 240.00 149.49 197.45 195.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 304.00 182.72 190.50 82.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 50.00 100.00 164.00 228.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 40.00 190.02 266.78 230.00 ITSSW03-417 STATEWIDE 12/04/25 50.00 219.27 179.45 225.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 20.00 200.00 257.23 125.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00106 Sweeping (Sediment Removal) Hour STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 64.00 175.00 155.00 140.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 20.00 190.00 151.50 153.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 40.00 206.79 100.00 100.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 180.00 134.00 125.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 150.00 209.25 185.50 NHPP1602-194 US 160 MP 174.1 12/11/25 10.00 200.00 214.61 300.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 250.00 234.46 330.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 240.00 181.38 182.21 213.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 80.00 170.00 154.00 125.00 Weighted Average for the Fourth Quarter 1,653.00 178.28 187.38 175.56 Weighted Average for the Year 4,059.00 179.83 193.75 173.97 208-00107 Rem Trash Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 20.00 144.11 128.63 94.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 50.00 99.92 93.00 65.99 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 5.00 200.00 74.03 40.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 4.00 90.00 149.83 200.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 20.00 123.27 98.48 189.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 100.00 87.00 53.00 BR0761-249 I-76 02/27/25 10.00 107.99 83.82 110.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 10.00 146.09 109.89 97.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 20.00 134.32 138.07 78.03 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 40.00 160.00 132.92 143.75 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 20.00 120.00 92.00 124.00 Weighted Average for the First Quarter 239.00 124.40 104.97 100.23 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 260.00 172.15 87.10 87.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00107 Rem Trash Hour C0821-113 CO-82 & Catherine Store Signa 04/17/25 10.00 110.00 75.00 75.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 150.00 55.00 55.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 40.00 125.00 144.50 58.50 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 18.00 116.77 118.67 116.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 20.00 224.22 224.22 224.22 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 40.00 119.30 81.71 55.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 20.00 100.00 129.37 65.00 ITSSW03-250 FRONT RANGE 06/26/25 20.00 127.67 125.60 1.00 Weighted Average for the Second Quarter 468.00 155.49 105.29 81.26 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 10.00 92.00 100.00 100.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 10.00 116.91 106.25 120.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 5.00 144.20 75.06 75.06 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 1.00 142.45 159.25 75.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 125.65 86.00 100.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 3.00 112.61 90.50 150.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 20.00 97.51 127.72 70.00 Weighted Average for the Third Quarter 69.00 112.37 109.74 94.21 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 40.00 60.00 92.88 71.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 20.00 108.55 154.30 49.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 20.00 120.00 95.09 45.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 15.00 117.07 58.00 10.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 70.00 150.00 90.00 15.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 112.09 141.95 92.85 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 60.00 93.43 73.80 72.60 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 10.00 95.00 172.05 65.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 20.00 113.87 126.24 49.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 40.00 118.98 138.85 140.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 20.00 88.31 157.40 249.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 20.00 100.00 68.35 91.70 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 40.00 117.99 101.65 60.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00107 Rem Trash Hour ITSSW03-417 STATEWIDE 12/04/25 20.00 111.21 128.50 80.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 20.00 150.00 126.13 45.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 20.00 129.61 110.00 110.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 30.00 75.00 90.50 133.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 10.00 126.69 40.00 40.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 10.00 125.00 121.00 40.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 150.00 122.80 152.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 200.00 189.43 220.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 20.00 86.57 89.93 53.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 30.00 100.00 87.60 40.00 Weighted Average for the Fourth Quarter 635.00 116.70 109.85 85.12 Weighted Average for the Year 1,411.00 130.66 108.01 86.84 208-00146 Pre-fab Conc Washout Str (Type 2) Each STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2.00 100.00 3025.34 5000.00 Weighted Average for the First Quarter 2.00 100.00 3025.34 5000.00 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 6.00 1750.00 2080.00 2080.00 C0821-113 CO-82 & Catherine Store Signa 04/17/25 1.00 3000.00 500.00 500.00 Weighted Average for the Second Quarter 7.00 1928.57 1854.29 1854.29 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 1846.14 2832.75 2600.00 Weighted Average for the Third Quarter 1.00 1846.14 2832.75 2600.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 2.00 3000.00 5305.63 2500.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 2000.00 1392.95 2200.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00146 Pre-fab Conc Washout Str (Type 2) Each STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 14.00 1846.14 1420.50 670.00 ITSSW03-417 STATEWIDE 12/04/25 66.00 2350.00 576.46 800.00 NHPP1602-194 US 160 MP 174.1 12/11/25 1.00 5000.00 2272.47 2500.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 19.00 4300.00 1751.31 4235.00 Weighted Average for the Fourth Quarter 103.00 2676.17 1001.89 1479.08 Weighted Average for the Year 113.00 2576.92 1071.41 1574.56 208-00200 Erosion Control Management Lump Sum STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 168282.03 168282.03 168282.03 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 10000.00 4081.40 920.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 1220177.65 1319000.43 1319000.43 Weighted Average for the Third Quarter 3.00 466153.23 215384.21 496067.49 Weighted Average for the Year 3.00 466153.23 215384.21 496067.49 208-00207 Erosion Control Management Day NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 200.00 330.59 385.31 388.50 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 60.00 350.04 258.61 150.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 210.00 304.76 145.73 316.49 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 50.00 400.00 840.00 150.00 BR0761-249 I-76 02/27/25 26.00 400.00 419.30 385.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 40.00 454.05 485.88 450.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 50.00 404.34 609.47 312.12 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 10.00 350.00 553.33 750.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 646.00 345.82 301.33 327.86 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 12.00 750.00 600.00 600.00 NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO VET I-70 CO 17 & SOUTH OF CO 14 04/11/25 05/08/25 1,195.00 10.00 2015.91 390.00 2302.71 630.83 2302.71 292.50 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 303.00 279.33 279.33 279.33 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 12.00 485.93 473.07 100.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 208.00 600.00 317.68 700.00 ITSSW03-250 FRONT RANGE 06/26/25 100.00 536.62 529.47 1100.00 Weighted Average for the Second Quarter 1,840.00 1462.42 1166.42 1686.58 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 8.00 620.98 635.25 540.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 10.00 500.00 950.00 950.00 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 120.00 60.00 299.90 1083.23 335.85 331.50 233.38 331.50 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 32.00 383.47 526.00 150.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 28.00 150.00 500.00 442.64 673.88 305.51 263.00 250.00 Weighted Average for the Third Quarter 408.00 499.06 363.13 272.99 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 198.00 50.00 570.99 413.97 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 50.00 389.38 399.85 70.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 90.00 650.00 512.83 200.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 100.00 427.96 340.38 358.65 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 30.00 347.14 262.50 375.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 81.00 703.40 730.00 850.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 10.00 543.41 566.67 775.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 60.00 484.65 380.95 122.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 25.00 200.00 680.00 800.00 Weighted Average for the Fourth Quarter 644.00 368.90 512.71 395.19 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 3,538.00 948.40 604.00 1040.41 208-00300 Temporary Berms Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 800.00 11.35 7.71 7.71 Weighted Average for the Second Quarter 800.00 11.35 7.71 7.71 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2,000.00 10.80 9.96 9.96 Weighted Average for the Third Quarter 2,000.00 10.80 9.96 9.96 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 100.00 14.74 20.66 11.75 Weighted Average for the Fourth Quarter 100.00 14.74 20.66 11.75 Weighted Average for the Year 2,900.00 11.09 10.07 9.40 208-00303 Temporary Diversion (Special) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 400.00 22.70 9.51 9.51 Weighted Average for the Second Quarter 400.00 22.70 9.51 9.51 Weighted Average for the Year 400.00 22.70 9.51 9.51 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 208-00400 Water Control Lump Sum STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 1.00 50000.00 76301.59 45000.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 50000.00 40003.68 11022.08 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 75000.00 152471.24 98000.00 Weighted Average for the First Quarter 3.00 58333.33 81412.83 51340.69 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47970.00 18416.31 18416.31 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47970.00 31262.27 31262.27 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47970.00 24982.02 24982.02 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47970.00 21513.87 21513.87 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47969.52 18086.60 18086.60 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47969.52 18086.60 18086.60 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47969.52 17720.80 17720.80 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47969.52 17720.80 17720.80 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47969.52 30264.46 30264.46 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47969.52 29743.70 29743.70 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 580161.69 636111.17 636111.17 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 237325.63 204705.74 204705.74 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47970.00 37222.75 37222.75 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 76218.65 71997.05 71997.05 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47970.00 17917.80 17917.80 NHPP0703-517 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 I-70 I-70 I-70 I-70 I-70 I-70 I-70 I-70 I-70 I-70 I-70 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 47969.52 46364.33 46364.33 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 208-00400 Water Control Lump Sum FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 FBR0703-534 STAR500-223 I-70 I-70 I-70 I-70 I-70 SH50 MM 189.71, US550 MM 98.3 05/01/25 1.00 150000.00 65289.44 22602.00 STAR500-228 REGION 5 05/08/25 1.00 50000.00 44870.00 59000.00 Weighted Average for the Second Quarter 18.00 95406.26 71212.35 73539.90 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 280337.66 123494.03 123494.03 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 1.00 1.00 40000.00 163531.98 87552.00 176961.16 60000.00 176961.16 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 1001470.51 872579.86 872579.86 Weighted Average for the Third Quarter 4.00 371335.04 201349.38 308258.76 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 50000.00 137503.70 50000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 37000.00 83055.85 55003.75 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 10000.00 33193.61 35600.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 31271.47 30250.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 22351.65 18150.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 16034.76 10285.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 30876.69 42350.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 27243.35 30250.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 73783.16 78650.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 33288.14 36300.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 29650.90 30250.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 23249.24 18150.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 32000.00 26896.99 30250.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 35000.00 164500.00 210000.00 Weighted Average for the Fourth Quarter 14.00 32285.71 63970.97 48249.20 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 39.00 98196.22 79910.67 86827.29 208-00511 Environmental Solid Wall (Temporary) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 400.00 216.69 202.69 202.69 Weighted Average for the Second Quarter 400.00 216.69 202.69 202.69 Weighted Average for the Year 400.00 216.69 202.69 202.69 209-00000 Water M Gallon NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 10.00 175.83 103.14 103.14 FBR0703-534 I-70 Weighted Average for the Second Quarter 10.00 175.83 103.14 103.14 Weighted Average for the Year 10.00 175.83 103.14 103.14 209-00600 Dust Palliative (Mg Cl) Gallon STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 200.00 2.00 24.74 5.00 Weighted Average for the Fourth Quarter 200.00 2.00 24.74 5.00 Weighted Average for the Year 200.00 2.00 24.74 5.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 209-00800 Air Quality Construction Plan Lump Sum NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 625872.97 618438.65 618438.65 Weighted Average for the Third Quarter 1.00 625872.97 618438.65 618438.65 Weighted Average for the Year 1.00 625872.97 618438.65 618438.65 210-00001 Res Structure Each CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1.00 4730.78 3760.75 6253.00 Weighted Average for the Third Quarter 1.00 4730.78 3760.75 6253.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 5000.00 1945.40 1020.00 Weighted Average for the Fourth Quarter 1.00 5000.00 1945.40 1020.00 Weighted Average for the Year 2.00 4865.39 3155.63 3636.50 210-00007 Res Wheel Stop Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 10.00 50.00 174.38 227.53 Weighted Average for the Fourth Quarter 10.00 50.00 174.38 227.53 Weighted Average for the Year 10.00 50.00 174.38 227.53 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00009 Res Communications Cabinet Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 9557.00 9556.92 9556.92 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 9557.00 9556.92 9556.92 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 10647.57 10864.87 10864.87 Weighted Average for the Third Quarter 1.00 10647.57 10864.87 10864.87 Weighted Average for the Year 2.00 10102.29 10210.90 10210.90 210-00010 Res Mailbox Str Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3.00 500.00 882.17 600.00 Weighted Average for the Fourth Quarter 3.00 500.00 882.17 600.00 Weighted Average for the Year 3.00 500.00 882.17 600.00 210-00011 Res Mailbox Str (Ty 1) Each 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 45.00 371.17 282.00 282.00 Weighted Average for the Fourth Quarter 45.00 371.17 282.00 282.00 Weighted Average for the Year 45.00 371.17 282.00 282.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 210-00012 Res Mailbox Str (Ty 2) Each 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 8.00 496.34 298.00 298.00 Weighted Average for the Fourth Quarter 8.00 496.34 298.00 298.00 Weighted Average for the Year 8.00 496.34 298.00 298.00 210-00013 Res Mailbox Str (Ty 3) Each 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 2.00 379.98 455.00 455.00 Weighted Average for the Fourth Quarter 2.00 379.98 455.00 455.00 Weighted Average for the Year 2.00 379.98 455.00 455.00 210-00015 Res End Section Each NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 50.00 1800.00 783.33 450.00 Weighted Average for the Second Quarter 50.00 1800.00 783.33 450.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 802.50 2724.73 2724.73 Weighted Average for the Third Quarter 2.00 802.50 2724.73 2724.73 Weighted Average for the Year 52.00 1761.63 808.88 537.49 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP070A-042 210-00035 Res Water Meter I70B EAST OF 3RD STREET 10/16/25 Each 14.00 3000.00 1994.63 223.50 Weighted Average for the Fourth Quarter 14.00 3000.00 1994.63 223.50 Weighted Average for the Year 14.00 3000.00 1994.63 223.50 210-00050 Res Fire Hydrant Each FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 3536.03 4023.51 4023.51 Weighted Average for the Third Quarter 1.00 3536.03 4023.51 4023.51 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 5000.00 14790.10 13000.00 Weighted Average for the Fourth Quarter 1.00 5000.00 14790.10 13000.00 Weighted Average for the Year 2.00 4268.02 11201.24 8511.76 210-00065 Res Monument (Ty 3A) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 21.00 700.00 1010.33 465.00 Weighted Average for the First Quarter 21.00 700.00 1010.33 465.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 900.00 866.33 450.00 Weighted Average for the Fourth Quarter 1.00 900.00 866.33 450.00 Weighted Average for the Year 22.00 709.09 997.81 464.32 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00075 Reset Pre-Fab Veh Tracking Pad Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 3.00 500.00 543.04 500.00 Weighted Average for the Second Quarter 3.00 500.00 543.04 500.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 1965.57 1965.57 1965.57 Weighted Average for the Third Quarter 4.00 1965.57 1965.57 1965.57 Weighted Average for the Year 7.00 1337.47 842.52 1337.47 210-00090 Res Delineator Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 5.00 50.00 50.00 50.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 124.00 36.02 75.33 50.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 25.00 30.00 80.49 75.00 Weighted Average for the Second Quarter 154.00 35.50 76.15 54.06 Weighted Average for the Year 154.00 35.50 76.15 54.06 210-00460 Replace Structure Sign Each STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 3.00 1000.00 250.00 250.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 1000.00 168.28 173.00 Weighted Average for the Fourth Quarter 4.00 1000.00 222.76 230.75 Weighted Average for the Year 4.00 1000.00 222.76 230.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00473 Res TV Cameras Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 1911.40 1911.38 1911.38 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 1911.40 1911.38 1911.38 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 1808.30 1845.20 1845.20 Weighted Average for the Third Quarter 1.00 1808.30 1845.20 1845.20 Weighted Average for the Year 3.00 1877.03 1889.32 1889.32 210-00474 Res Traf Contr Signal Head Each SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 28.00 100.00 772.41 864.03 Weighted Average for the Fourth Quarter 28.00 100.00 772.41 864.03 Weighted Average for the Year 28.00 100.00 772.41 864.03 210-00475 Res CCTV Pole Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 3597.93 3597.90 3597.90 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 3597.93 3597.90 3597.90 Weighted Average for the Year 2.00 3597.93 3597.90 3597.90 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00476 Reset MVRD Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 1911.40 1911.38 1911.38 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 1911.40 1911.38 1911.38 Weighted Average for the Year 2.00 1911.40 1911.38 1911.38 210-00479 Res Radio Com Antenna Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 900.00 1063.88 1250.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 2000.00 1494.17 1900.00 Weighted Average for the First Quarter 2.00 1450.00 1279.02 1575.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 1551.65 1551.65 1551.65 Weighted Average for the Second Quarter 1.00 1551.65 1551.65 1551.65 Weighted Average for the Year 3.00 1483.88 1317.97 1567.22 210-00481 Reset DSRC (Roadside Unit) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3.00 1911.40 1911.38 1911.38 FBR0703-534 I-70 ITSSW03-250 FRONT RANGE 06/26/25 1.00 2162.19 1714.80 1600.00 Weighted Average for the Second Quarter 4.00 1974.10 1788.52 1833.54 Weighted Average for the Year 4.00 1974.10 1788.52 1833.54 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00520 Reb Port Present Str Sq Yard FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 4.00 4972.50 3420.25 3420.25 Weighted Average for the Third Quarter 4.00 4972.50 3420.25 3420.25 Weighted Average for the Year 4.00 4972.50 3420.25 3420.25 210-00530 Rebuild Port of Present Str Sq Foot NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 237.00 236.55 200.30 198.50 Weighted Average for the Fourth Quarter 237.00 236.55 200.30 198.50 Weighted Average for the Year 237.00 236.55 200.30 198.50 210-00650 Reb Timber Deck Lump Sum NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 8500.00 7887.15 15151.52 Weighted Average for the First Quarter 1.00 8500.00 7887.15 15151.52 Weighted Average for the Year 1.00 8500.00 7887.15 15151.52 210-00750 Res Light Standard Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 4.00 2122.65 2122.65 2122.65 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 4.00 2122.65 2122.65 2122.65 Weighted Average for the Year 4.00 2122.65 2122.65 2122.65 210-00760 Res Luminaire Each NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 800.00 2120.00 2140.00 Weighted Average for the Fourth Quarter 2.00 800.00 2120.00 2140.00 Weighted Average for the Year 2.00 800.00 2120.00 2140.00 210-00766 Res Light Ctrl Cntr Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 5621.76 5621.72 5621.72 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 5621.76 5621.72 5621.72 Weighted Average for the Year 1.00 5621.76 5621.72 5621.72 210-00805 Res Overhead Sign Str Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 44043.34 44942.18 44942.18 Weighted Average for the Third Quarter 2.00 44043.34 44942.18 44942.18 Weighted Average for the Year 2.00 44043.34 44942.18 44942.18 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 210-00810 Res Ground Sign Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 7.00 423.51 744.79 873.76 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 12.00 500.00 647.50 675.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 500.00 576.67 1031.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 17.00 700.00 467.87 505.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 4.00 300.00 438.00 376.00 Weighted Average for the First Quarter 42.00 549.16 578.31 627.79 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 46.00 1.00 765.65 550.00 769.20 190.00 769.20 190.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 9.00 625.58 625.58 625.58 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 10.00 350.00 208.92 525.00 Weighted Average for the Second Quarter 66.00 680.30 516.25 703.84 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 1.00 350.00 655.00 490.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 12.00 224.37 224.37 224.37 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 27.00 409.37 438.25 398.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 554.54 566.75 160.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 4.00 386.75 552.49 552.49 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 8.00 500.00 471.67 315.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 16.00 856.00 873.47 873.47 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 12.00 1177.00 1201.02 1201.02 Weighted Average for the Third Quarter 81.00 592.80 525.54 582.79 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 15.00 450.00 434.88 544.50 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 2.00 556.15 580.88 656.50 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 16.00 550.00 465.83 750.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 78.00 346.09 410.20 345.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 6.00 521.72 590.49 788.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 521.86 781.67 1095.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00810 Res Ground Sign Each NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 600.00 624.50 635.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 3.00 500.00 590.00 525.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 610.72 438.63 431.00 Weighted Average for the Fourth Quarter 123.00 406.67 439.72 462.26 Weighted Average for the Year 312.00 532.06 482.41 566.94 210-00815 Res Sign Panel Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 20.00 130.00 306.04 210.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 4.00 250.00 212.41 225.00 Weighted Average for the First Quarter 24.00 150.00 286.33 212.50 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 400.00 212.75 146.25 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 14.00 284.35 284.35 284.35 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 17.00 257.00 179.25 215.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 6.00 350.00 107.79 145.00 Weighted Average for the Second Quarter 38.00 285.52 177.94 227.69 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 8.00 186170.66 188.50 130.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 9.00 160.00 190.00 145.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4.00 408.85 163.75 75.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 8.00 267.50 272.96 272.96 Weighted Average for the Third Quarter 29.00 51537.26 187.73 166.51 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4.00 60.00 156.63 60.50 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6.00 150.00 72.92 100.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 209.31 182.80 250.60 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00815 Res Sign Panel Each NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 34.00 208.22 71.13 52.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 3.00 253.72 192.10 230.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 400.00 756.50 758.00 Weighted Average for the Fourth Quarter 51.00 199.98 116.13 104.26 Weighted Average for the Year 142.00 10698.80 178.80 168.30 210-00816 Res Sign Panel (Spec) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3.00 1578.25 1610.46 1610.46 Weighted Average for the Third Quarter 3.00 1578.25 1610.46 1610.46 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 3.00 1158.21 2612.80 5450.00 Weighted Average for the Fourth Quarter 3.00 1158.21 2612.80 5450.00 Weighted Average for the Year 6.00 1368.23 2445.74 3530.23 210-00820 Res Var Mesg Sign Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 10899.02 11121.45 11121.45 Weighted Average for the Third Quarter 1.00 10899.02 11121.45 11121.45 Weighted Average for the Year 1.00 10899.02 11121.45 11121.45 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 210-00825 Res Flashing Beacon Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 1581.20 5150.60 5407.07 Weighted Average for the First Quarter 2.00 1581.20 5150.60 5407.07 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 3071.78 1016.20 1015.00 Weighted Average for the Fourth Quarter 1.00 3071.78 1016.20 1015.00 Weighted Average for the Year 3.00 2078.06 3560.44 3943.05 210-00827 Res Pull Box Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 20.00 1095.19 1078.26 1750.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 1539.76 1494.10 1229.60 Weighted Average for the First Quarter 21.00 1116.36 1116.06 1725.22 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 922.34 941.16 941.16 Weighted Average for the Third Quarter 2.00 922.34 941.16 941.16 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 2000.00 1014.46 1312.85 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 4.00 825.00 1405.55 720.00 Weighted Average for the Fourth Quarter 6.00 1216.67 1210.01 917.62 Weighted Average for the Year 29.00 1123.74 1129.79 1504.06 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 210-00831 Res Traf Sig Head Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8.00 1353.63 1353.63 1353.63 Weighted Average for the Third Quarter 8.00 1353.63 1353.63 1353.63 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2.00 1400.00 1095.20 1070.00 Weighted Average for the Fourth Quarter 2.00 1400.00 1095.20 1070.00 Weighted Average for the Year 10.00 1362.90 1210.06 1296.90 210-00848 Res Traf Sig Control+Cab Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 2546.16 11197.27 9073.60 Weighted Average for the First Quarter 1.00 2546.16 11197.27 9073.60 Weighted Average for the Year 1.00 2546.16 11197.27 9073.60 210-00855 Res Traf Sig Control Cab Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 9779.25 9779.25 9779.25 Weighted Average for the Third Quarter 2.00 9779.25 9779.25 9779.25 Weighted Average for the Year 2.00 9779.25 9779.25 9779.25 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00858 Res Pedestal Pole Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 1196.44 2220.72 1754.30 Weighted Average for the First Quarter 1.00 1196.44 2220.72 1754.30 Weighted Average for the Year 1.00 1196.44 2220.72 1754.30 210-00859 Mod Ped Push Button Each STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 550.00 1189.60 900.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 700.00 2017.50 2025.00 Weighted Average for the Fourth Quarter 5.00 580.00 1307.87 1125.00 Weighted Average for the Year 5.00 580.00 1307.87 1125.00 210-00860 Res Ped Push Button Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1.00 600.00 455.61 375.00 Weighted Average for the First Quarter 1.00 600.00 455.61 375.00 C0821-113 CO-82 & Catherine Store Signa 04/17/25 4.00 500.00 260.00 260.00 Weighted Average for the Second Quarter 4.00 500.00 260.00 260.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 3.00 213.67 468.25 387.00 Weighted Average for the Third Quarter 3.00 213.67 468.25 387.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid C1601-088 210-00860 Res Ped Push Button US 160 SIGNALS MILDRED & HARR 11/13/25 Each 10.00 525.00 348.85 300.00 Weighted Average for the Fourth Quarter 10.00 525.00 348.85 300.00 Weighted Average for the Year 18.00 471.72 386.46 309.78 210-00866 Res Fire Preempt Unit+Timer Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 6.00 600.00 1251.42 1470.00 Weighted Average for the First Quarter 6.00 600.00 1251.42 1470.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 835.06 835.06 835.06 Weighted Average for the Second Quarter 2.00 835.06 835.06 835.06 Weighted Average for the Year 8.00 658.77 1209.79 1311.27 210-00867 Res Fire Preempt Unit Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 9.00 1200.00 1142.63 1270.50 Weighted Average for the Fourth Quarter 9.00 1200.00 1142.63 1270.50 Weighted Average for the Year 9.00 1200.00 1142.63 1270.50 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP070A-042 210-00870 Res Coordination I70B EAST OF 3RD Unit STREET 10/16/25 Each 5.00 2500.00 1032.21 828.85 Weighted Average for the Fourth Quarter 5.00 2500.00 1032.21 828.85 Weighted Average for the Year 5.00 2500.00 1032.21 828.85 210-00882 Res Detector Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 4.00 2000.00 955.50 763.00 Weighted Average for the First Quarter 4.00 2000.00 955.50 763.00 Weighted Average for the Year 4.00 2000.00 955.50 763.00 210-00890 Res Int Detect Sys (Camera) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 1685.13 1685.13 1685.13 Weighted Average for the Third Quarter 4.00 1685.13 1685.13 1685.13 Weighted Average for the Year 4.00 1685.13 1685.13 1685.13 210-00892 Port Pan-Tilt-Zoom Cam (Reset) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 1500.00 1251.42 1470.00 Weighted Average for the First Quarter 4.00 1500.00 1251.42 1470.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-00892 Port Pan-Tilt-Zoom Cam (Reset) Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 1417.31 1725.00 1250.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 311.45 311.45 311.45 Weighted Average for the Second Quarter 2.00 864.38 1253.82 780.73 Weighted Average for the Year 6.00 1288.13 1251.90 1240.24 210-01000 Res Fence Lin Foot STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 300.00 50.00 26.62 30.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 100.00 50.00 31.99 35.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 19.00 65.92 293.82 505.05 Weighted Average for the First Quarter 419.00 50.72 35.34 52.73 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 150.00 5.00 18.13 14.50 STAR500-228 REGION 5 05/08/25 100.00 50.00 17.67 16.00 Weighted Average for the Second Quarter 250.00 23.00 17.97 15.10 CR400-406 REGION-WIDE 07/17/25 140.00 26.50 40.50 82.50 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 20.00 21.30 21.97 21.97 Weighted Average for the Third Quarter 160.00 25.85 39.66 74.93 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 62.00 50.00 51.41 78.65 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 4,500.00 4.22 7.60 4.40 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 150.00 50.00 48.65 25.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 214.00 46.00 46.50 50.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1,790.00 15.00 33.93 18.15 Weighted Average for the Fourth Quarter 6,716.00 9.87 15.82 10.66 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 7,545.00 12.91 17.63 14.51 210-01011 Res Gate Each FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 738.37 1104.99 1104.99 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 647.35 667.37 667.37 Weighted Average for the Third Quarter 2.00 692.86 886.18 886.18 Weighted Average for the Year 2.00 692.86 886.18 886.18 210-01130 Res Gdrail Ty 3 Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 500.00 13.70 62.88 25.76 Weighted Average for the First Quarter 500.00 13.70 62.88 25.76 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 225.00 150.00 340.00 340.00 Weighted Average for the Second Quarter 225.00 150.00 340.00 340.00 NHPP1602-194 US 160 MP 174.1 12/11/25 50.00 60.00 104.45 40.00 Weighted Average for the Fourth Quarter 50.00 60.00 104.45 40.00 Weighted Average for the Year 775.00 56.26 92.02 117.91 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-01170 Res Gdrail Ty 7 Lin Foot NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 20.00 300.00 640.00 640.00 Weighted Average for the Second Quarter 20.00 300.00 640.00 640.00 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 400.00 25.20 30.16 7.45 Weighted Average for the Fourth Quarter 400.00 25.20 30.16 7.45 Weighted Average for the Year 420.00 38.28 37.69 37.57 210-01180 Reset Guardrail (Special) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2,017.00 5.35 5.69 5.69 Weighted Average for the Third Quarter 2,017.00 5.35 5.69 5.69 Weighted Average for the Year 2,017.00 5.35 5.69 5.69 210-02510 Relay Sprinkler System Lump Sum C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 5000.00 1372.15 1375.00 Weighted Average for the Fourth Quarter 1.00 5000.00 1372.15 1375.00 Weighted Average for the Year 1.00 5000.00 1372.15 1375.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-02806 Grinding: Slope Correction Sq Foot CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 63.00 120.00 99.93 13.70 Weighted Average for the Third Quarter 63.00 120.00 99.93 13.70 Weighted Average for the Year 63.00 120.00 99.93 13.70 210-02900 Relay Riprap Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 385.00 100.00 114.48 200.00 Weighted Average for the First Quarter 385.00 100.00 114.48 200.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 310.00 160.94 160.94 160.94 Weighted Average for the Third Quarter 310.00 160.94 160.94 160.94 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 106.00 50.00 281.82 275.00 Weighted Average for the Fourth Quarter 106.00 50.00 281.82 275.00 Weighted Average for the Year 801.00 116.97 145.66 194.81 210-04010 Adj Manhole Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 72.00 1200.00 1013.82 695.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 4.00 1200.00 1598.47 900.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 4.00 1300.00 2112.50 1060.00 Weighted Average for the First Quarter 80.00 1205.00 1089.42 723.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-04010 Adj Manhole Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 34.00 1250.00 1475.00 1475.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 2.00 1088.56 2480.67 642.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 658.01 658.01 658.01 Weighted Average for the Second Quarter 39.00 1196.18 1558.33 1369.44 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 6439.48 6439.48 6439.48 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 70.00 1000.00 1275.00 1275.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 4.00 1081.28 2311.00 1005.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 1200.00 2280.80 1800.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 1659.52 1621.40 1621.40 Weighted Average for the Third Quarter 77.00 1086.03 1588.89 1339.36 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 2600.00 2663.34 5553.34 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 7.00 1500.00 1618.00 950.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 5.00 1336.10 762.82 608.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 9.00 1068.91 1280.14 1600.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 23.00 1800.00 1940.00 1650.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 7.00 1000.00 1627.50 1045.00 Weighted Average for the Fourth Quarter 53.00 1516.99 1717.88 1518.14 Weighted Average for the Year 249.00 1233.24 1402.93 1184.26 210-04011 Adj Manhole (Spec) Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 8.00 1673.02 1673.02 1673.02 Weighted Average for the Second Quarter 8.00 1673.02 1673.02 1673.02 Weighted Average for the Year 8.00 1673.02 1673.02 1673.02 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 210-04015 Modify Manhole Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 5610.23 5610.23 5610.23 Weighted Average for the Second Quarter 2.00 5610.23 5610.23 5610.23 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 6380.13 2365.22 2365.22 Weighted Average for the Third Quarter 2.00 6380.13 2365.22 2365.22 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3.00 4200.00 3517.33 2600.00 Weighted Average for the Fourth Quarter 3.00 4200.00 3517.33 2600.00 Weighted Average for the Year 7.00 5225.82 3602.86 3392.99 210-04020 Modify Inlet Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 4650.24 5271.32 6572.93 Weighted Average for the First Quarter 2.00 4650.24 5271.32 6572.93 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 8.00 12898.19 8010.54 8010.54 FBR0703-534 I-70 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 16.00 12000.00 11000.00 11000.00 Weighted Average for the Second Quarter 24.00 12299.40 10003.51 10003.51 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 5097.58 8480.00 6000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 2763.80 5215.70 5215.70 Weighted Average for the Third Quarter 2.00 3930.69 7935.95 5607.85 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 210-04020 Modify Inlet Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2.00 7000.00 3618.67 3200.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 4146.41 16458.34 9000.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 1.00 4940.22 8049.51 7000.00 Weighted Average for the Fourth Quarter 4.00 5771.66 7519.70 5600.00 Weighted Average for the Year 32.00 10482.31 8077.30 8963.93 210-04025 Modify Structure Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4.00 46970.83 10282.39 10282.39 FBR0703-534 I-70 Weighted Average for the Second Quarter 4.00 46970.83 10282.39 10282.39 Weighted Average for the Year 4.00 46970.83 10282.39 10282.39 210-04027 Modify Str (Spec) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 59039.61 64198.10 64198.10 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 46972.32 77159.45 77159.45 FBR0703-534 I-70 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 53005.97 70678.78 70678.78 Weighted Average for the Year 2.00 53005.97 70678.78 70678.78 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 210-04050 Adj Valve Box Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 100.00 550.00 484.30 375.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 500.00 1235.50 1774.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 2.00 600.00 1070.12 475.00 Weighted Average for the First Quarter 103.00 550.49 513.58 390.52 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 97.00 675.00 935.00 935.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 12.00 274.16 274.16 274.16 Weighted Average for the Second Quarter 109.00 630.87 862.25 862.25 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 10.00 459.50 747.50 938.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4.00 600.00 619.82 500.00 Weighted Average for the Third Quarter 14.00 499.64 690.75 812.86 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 900.00 823.88 465.51 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 17.00 800.00 779.00 550.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 655.11 727.07 536.50 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 500.00 1705.80 1520.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 18.00 590.78 635.14 310.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 11.00 1000.00 653.00 950.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2.00 600.00 564.00 375.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 22.00 500.00 353.75 303.50 Weighted Average for the Fourth Quarter 74.00 680.94 662.99 483.71 Weighted Average for the Year 300.00 609.50 631.04 604.61 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 210-04060 Adj Water Meter Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 1000.00 1475.00 1475.00 Weighted Average for the Second Quarter 1.00 1000.00 1475.00 1475.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6.00 2000.00 1652.68 1455.73 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3.00 1000.00 1528.33 1500.00 Weighted Average for the Fourth Quarter 9.00 1666.67 1599.39 1470.49 Weighted Average for the Year 10.00 1600.00 1596.50 1470.94 210-04200 Adj Gdrail Lin Foot STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2,612.50 15.62 22.05 20.00 Weighted Average for the Fourth Quarter 2,612.50 15.62 22.05 20.00 Weighted Average for the Year 2,612.50 15.62 22.05 20.00 210-04500 Relocate Building Lump Sum NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 121430.07 137890.86 137890.86 Weighted Average for the Second Quarter 1.00 121430.07 137890.86 137890.86 Weighted Average for the Year 1.00 121430.07 137890.86 137890.86 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 211-00136 4 In Drilled Hole Lin Foot BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 69.00 200.00 113.85 109.25 Weighted Average for the First Quarter 69.00 200.00 113.85 109.25 Weighted Average for the Year 69.00 200.00 113.85 109.25 211-00150 Patch Exist Drill Hole Each BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 69.00 200.00 102.86 109.25 Weighted Average for the First Quarter 69.00 200.00 102.86 109.25 Weighted Average for the Year 69.00 200.00 102.86 109.25 211-01111 Rock Reinf (Dowels) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,410.00 162.66 162.67 162.67 FBR0703-534 I-70 Weighted Average for the Second Quarter 1,410.00 162.66 162.67 162.67 Weighted Average for the Year 1,410.00 162.66 162.67 162.67 211-01115 Rock Reinf (No.10) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 700.00 173.86 173.88 173.88 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 700.00 173.86 173.88 173.88 Weighted Average for the Year 700.00 173.86 173.88 173.88 211-01150 Rock Reinf Tests Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 28.00 1121.83 1121.83 1121.83 FBR0703-534 I-70 Weighted Average for the Second Quarter 28.00 1121.83 1121.83 1121.83 Weighted Average for the Year 28.00 1121.83 1121.83 1121.83 211-02277 Cement Grout (Voids) Cubic Yard STAR500-228 REGION 5 05/08/25 53.00 4000.00 1738.33 2100.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 61.00 3500.00 1916.67 850.00 Weighted Average for the Second Quarter 114.00 3732.46 1833.76 1431.14 CR400-406 REGION-WIDE 07/17/25 20.00 692.96 2316.67 1600.00 Weighted Average for the Third Quarter 20.00 692.96 2316.67 1600.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 34.00 2500.00 1859.80 759.00 Weighted Average for the Fourth Quarter 34.00 2500.00 1859.80 759.00 Weighted Average for the Year 168.00 3121.19 1896.52 1315.21 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 211-03005 Dewatering Lump Sum NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 16378.09 16378.09 16378.09 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 25000.00 418855.23 175000.00 Weighted Average for the Second Quarter 2.00 20689.05 338359.80 95689.05 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 0.46 141183.94 160207.65 160207.65 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 0.42 141183.94 160207.65 160207.65 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 0.12 141183.94 160207.65 160207.65 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 13000.00 16834.10 6000.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES 1.00 40000.00 96552.00 50000.00 Weighted Average for the Third Quarter 3.00 64727.98 66103.47 72069.22 Weighted Average for the Year 5.00 47112.41 151183.57 81517.15 212-00006 Seeding (Native) Acre NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 0.01 120000.00 118583.33 93750.00 Weighted Average for the First Quarter 0.01 120000.00 118583.33 93750.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 9.10 2124.76 2232.67 2232.67 Weighted Average for the Second Quarter 9.10 2124.76 2232.67 2232.67 Weighted Average for the Year 9.11 2254.15 2614.98 2333.13 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 212-00009 Seeding (Temporary) Acre NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 4.50 1698.22 1840.01 1840.01 Weighted Average for the Second Quarter 4.50 1698.22 1840.01 1840.01 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 347.75 353.76 353.76 Weighted Average for the Third Quarter 2.00 347.75 353.76 353.76 Weighted Average for the Year 6.50 1282.69 1382.70 1382.70 212-00011 Seeding (Lawn) Acre FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 0.10 16575.00 3646.46 3646.46 Weighted Average for the Third Quarter 0.10 16575.00 3646.46 3646.46 Weighted Average for the Year 0.10 16575.00 3646.46 3646.46 212-00022 Seeding (Riparian) Acre NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.36 2830.92 2974.90 2974.90 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.36 2830.92 2974.90 2974.90 Weighted Average for the Year 1.36 2830.92 2974.90 2974.90 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00028 Seeding (Wetlands) Acre STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 0.03 2000.00 24000.00 48500.00 Weighted Average for the Second Quarter 0.03 2000.00 24000.00 48500.00 Weighted Average for the Year 0.03 2000.00 24000.00 48500.00 212-00032 Soil Conditioning Acre NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 0.01 140000.00 128916.67 93750.00 Weighted Average for the First Quarter 0.01 140000.00 128916.67 93750.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 0.85 8539.61 5714.25 5347.22 Weighted Average for the Second Quarter 0.85 8539.61 5714.25 5347.22 Weighted Average for the Year 0.86 10068.22 6577.82 6375.16 212-00050 Sod Sq Foot STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 825.00 3.00 13.52 18.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 170.00 5.50 16.17 14.00 Weighted Average for the First Quarter 995.00 3.43 14.29 17.32 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 600.00 3.00 2.80 2.80 Weighted Average for the Second Quarter 600.00 3.00 2.80 2.80 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid FBR0063-066 212-00050 Sod US 6D IN GARFIELD COUNTY 08/15/25 Sq Foot 4,800.00 5.53 5.52 5.52 Weighted Average for the Third Quarter 4,800.00 5.53 5.52 5.52 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6,708.00 3.00 2.29 2.24 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4,760.00 3.50 2.67 2.00 Weighted Average for the Fourth Quarter 11,468.00 3.21 2.48 2.14 Weighted Average for the Year 17,863.00 3.84 3.35 3.92 212-00100 Tree Retention and Protection Lump Sum SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 5000.00 4625.50 2233.00 Weighted Average for the First Quarter 1.00 5000.00 4625.50 2233.00 Weighted Average for the Year 1.00 5000.00 4625.50 2233.00 212-00700 Organic Fertilizer Pound NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 200.00 1.43 3.14 3.70 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 435.00 2.03 1.09 0.59 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 12.00 8.00 59.23 80.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1,420.00 2.00 1.05 1.00 BR0761-249 I-76 02/27/25 660.00 2.29 1.51 3.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 150.00 0.40 2.68 2.35 Weighted Average for the First Quarter 2,877.00 1.97 1.61 1.98 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00700 Organic Fertilizer Pound STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 210.00 2.00 1.85 1.85 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 9.00 7.71 40.50 43.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 235.00 2.00 3.61 3.20 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1,920.00 1.40 0.95 0.41 ITSSW03-250 FRONT RANGE 06/26/25 147.00 4.04 3.54 7.00 Weighted Average for the Second Quarter 2,521.00 1.68 1.65 1.33 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5,056.00 0.91 0.91 0.91 CR400-406 REGION-WIDE 07/17/25 219.00 3.04 4.83 2.48 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 761.00 22.00 2.12 1.19 7.64 1.19 1.57 1.19 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 33.00 7.33 10.33 6.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 180.00 2.60 3.80 4.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 15.00 12.00 25.03 32.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 3,360.00 1.75 1.49 0.35 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 22,230.00 0.73 0.74 0.74 Weighted Average for the Third Quarter 31,876.00 0.94 1.59 0.80 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 5.00 25.10 88.67 180.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 225.00 4.42 0.49 0.47 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 180.00 2.37 3.16 1.55 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 18,600.00 0.47 0.67 0.55 ITSSW03-417 STATEWIDE 12/04/25 297.00 4.10 17.71 4.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 400.00 20.00 3.00 3.65 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 150.00 3.88 3.00 3.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 960.00 3.19 1.02 1.20 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 150.00 3.30 1.78 2.30 Weighted Average for the Fourth Quarter 20,967.00 1.13 0.96 0.78 Weighted Average for the Year 58,241.00 1.09 1.22 0.87 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 212-00701 Compost (Mech App) Cubic Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 131.00 56.74 78.93 89.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 283.00 51.00 64.13 64.77 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 7.00 211.00 151.37 86.68 Weighted Average for the First Quarter 421.00 55.45 68.03 72.67 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 70.00 150.00 150.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 379.81 820.00 440.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2,925.00 68.86 72.24 72.24 FBR0703-534 STMM153-003 I-70 CO 17 & SOUTH OF CO 14 05/08/25 624.00 38.00 52.57 42.71 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 100.00 97.43 97.43 97.43 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 56.00 121.65 94.20 70.63 ITSSW03-250 FRONT RANGE 06/26/25 32.00 111.90 78.25 85.00 Weighted Average for the Second Quarter 3,743.00 65.81 67.77 68.35 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 306.00 91.13 91.13 91.13 CR400-406 REGION-WIDE 07/17/25 50.00 103.93 167.67 165.00 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 175.00 52.83 125.23 68.91 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 30.50 155.81 155.80 155.80 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 8.00 220.05 741.67 125.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 39.00 122.58 102.80 60.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 3.00 122.13 152.80 125.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4,817.00 45.53 46.32 46.32 Weighted Average for the Third Quarter 5,428.50 50.35 65.52 51.54 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 2.00 200.00 594.15 484.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 48.75 127.49 58.25 58.25 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4,030.00 68.02 52.22 61.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00701 Compost (Mech App) Cubic Yard NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 6.50 98.63 165.91 140.00 ITSSW03-417 STATEWIDE 12/04/25 24.00 137.30 317.04 165.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 33.00 105.98 40.00 40.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 208.00 67.83 65.51 84.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 49.50 100.00 145.40 88.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 32.50 131.74 123.13 128.50 Weighted Average for the Fourth Quarter 4,434.25 70.25 56.09 64.01 Weighted Average for the Year 14,026.75 60.92 60.10 60.60 212-00702 Bio Soil Amd (Hyd App) Pound 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 15,225.00 2.00 1.07 1.05 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 140.00 4.00 21.24 7.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 310.00 3.00 3.27 3.80 BR0761-249 I-76 02/27/25 7,700.00 1.45 1.53 2.15 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1,050.00 10.00 2.43 2.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 6,548.00 1.52 1.28 1.07 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1,750.00 1.00 2.75 2.50 Weighted Average for the First Quarter 32,723.00 2.00 1.35 1.47 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 700.00 2.00 2.00 2.00 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 36,750.00 2,737.00 1.42 2.50 1.49 2.04 1.49 2.65 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 33.00 20.00 2.00 2.00 STAR500-228 REGION 5 05/08/25 6,504.00 1.40 1.98 2.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 3,745.00 2.00 2.28 1.75 Weighted Average for the Second Quarter 50,469.00 1.54 1.83 1.65 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00702 Bio Soil Amd (Hyd App) Pound STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8,504.00 1.20 1.37 1.37 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 2,450.00 1.71 3.32 7.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 3,850.00 0.98 0.98 0.98 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 4,550.00 2.00 2.05 1.20 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 32,893.00 1.12 1.14 1.14 Weighted Average for the Third Quarter 52,247.00 1.23 1.70 1.45 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 8,750.00 1.09 2.24 1.50 NHPPR500-227 REGION 5 SECTION 7 10/23/25 644.00 2.00 2.70 2.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 2,240.00 2.00 3.06 3.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 17,815.00 1.58 2.01 2.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2,444.00 2.31 1.38 1.75 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2,625.00 2.26 1.40 1.15 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2,100.00 1.77 2.14 1.55 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 525.00 2.00 2.83 1.65 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1,750.00 2.00 1.98 1.80 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 875.00 2.00 2.48 1.80 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 3,500.00 3.00 2.18 1.70 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 14,070.00 3.00 2.42 2.42 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1,106.00 3.00 2.75 1.70 Weighted Average for the Fourth Quarter 58,444.00 2.07 2.28 1.96 Weighted Average for the Year 193,883.00 1.69 1.81 1.66 212-00703 Humate Pound NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 151.00 2.35 2.71 2.70 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 870.00 1.91 1.44 0.59 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 6.00 15.00 68.66 95.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00703 Humate Pound NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 125.00 2.34 3.55 6.12 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 100.00 0.50 2.73 2.45 Weighted Average for the First Quarter 1,252.00 1.96 1.92 2.00 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 30.00 2.00 4.50 4.50 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 14,247.00 1.06 1.12 1.12 Weighted Average for the Second Quarter 14,277.00 1.06 1.13 1.13 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1,680.00 2.40 1.76 0.45 Weighted Average for the Third Quarter 1,680.00 2.40 1.76 0.45 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 764.00 2.32 4.14 4.10 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 46.00 7.67 2.53 4.50 Weighted Average for the Fourth Quarter 810.00 2.62 4.04 4.12 Weighted Average for the Year 18,019.00 1.32 1.64 1.26 212-00704 Mycorrhizae Pound NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 11.00 17.80 30.82 30.50 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 39.00 14.24 12.61 12.88 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.60 50.00 346.39 500.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 950.00 10.00 19.00 22.50 BR0761-249 I-76 02/27/25 44.00 38.73 21.06 18.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 18.00 10.00 59.54 45.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 32.00 27.36 13.34 12.24 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 1,095.60 11.95 20.22 22.82 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 18.00 57.00 57.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 70.33 132.50 165.00 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 801.00 47.00 11.21 25.00 11.79 23.50 11.79 11.00 STAR500-228 REGION 5 05/08/25 112.00 18.00 30.13 35.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 192.00 14.00 12.91 10.24 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 250.00 23.69 23.69 23.69 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 7.00 23.86 48.55 43.11 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 214.00 15.00 14.38 18.00 ITSSW03-250 FRONT RANGE 06/26/25 29.00 26.51 30.76 70.00 Weighted Average for the Second Quarter 1,658.00 15.16 17.71 17.20 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 252.80 11.39 24.49 24.49 CR400-406 REGION-WIDE 07/17/25 49.00 16.88 24.92 13.75 BR0704-265 FBR0704-269 SHER100-414 I-70 EAST I-70 EAST SH 74/KERRGULCH;SH83/GILLIAN, 07/24/25 08/14/25 23.00 42.00 24.05 16.87 29.19 35.47 24.76 46.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 22.00 25.80 25.80 25.80 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 7.00 34.85 26.50 27.50 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 24.00 19.02 28.00 35.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 3.00 67.50 98.33 130.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 78.00 89.60 20.00 29.61 21.56 14.75 10.00 10.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3,474.00 10.25 10.43 10.43 Weighted Average for the Third Quarter 4,064.40 11.38 14.70 12.12 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 50.00 30.18 25.46 37.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 11.00 45.00 54.83 27.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 41.00 30.50 12.30 12.20 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 13.00 43.21 21.05 25.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00704 Mycorrhizae Pound NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 45.00 44.80 17.29 17.80 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 6.00 63.95 9.95 9.95 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 12.00 30.31 17.50 18.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,240.00 6.11 10.65 8.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 0.80 38.39 432.26 550.00 ITSSW03-417 STATEWIDE 12/04/25 297.00 14.36 34.79 30.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 30.00 25.96 21.00 21.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 241.00 21.00 26.50 26.62 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 172.00 11.12 24.94 36.50 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 18.40 10.00 16.74 19.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 5.00 44.85 38.77 44.00 Weighted Average for the Fourth Quarter 2,182.20 12.19 17.71 17.06 Weighted Average for the Year 9,000.20 12.34 17.27 15.56 212-00705 Elemental Sulfur Pound NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3,487.00 4.28 4.49 4.49 FBR0703-534 I-70 Weighted Average for the Second Quarter 3,487.00 4.28 4.49 4.49 Weighted Average for the Year 3,487.00 4.28 4.49 4.49 212-00706 Seed (Native) Drill Acre NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 0.75 2508.99 2687.33 3375.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 1576.12 599.53 498.20 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 4.75 1723.42 778.49 952.43 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 34.50 996.79 1047.51 1047.51 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 9.20 1040.00 1147.48 1152.45 ITSSW03-250 FRONT RANGE 06/26/25 0.49 2886.39 3784.98 2000.00 Weighted Average for the Second Quarter 44.19 1026.74 1194.16 1079.92 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10.20 592.37 535.42 535.42 BR0704-265 FBR0704-269 NHPP0704-260 I-70 EAST I-70 EAST I-70 AND PENA BLVD OVERPASS 07/24/25 08/21/25 0.61 0.60 3038.73 2779.16 1989.58 4302.00 2458.32 3500.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 11.20 1461.11 1538.86 1300.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 74.00 668.75 781.44 781.44 Weighted Average for the Third Quarter 96.61 780.62 1221.44 843.05 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 61.00 822.48 815.68 837.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 3.00 1442.31 857.00 819.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 0.76 3000.00 1523.69 170.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 0.75 4003.66 1770.99 1901.00 Weighted Average for the Fourth Quarter 65.51 912.61 833.52 840.60 Weighted Average for the Year 211.06 894.34 983.03 894.35 212-00707 Seed (Native) Hyd) Acre 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 0.10 5000.00 5483.92 5803.50 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 4.72 3000.00 1082.50 1500.00 BR0761-249 I-76 02/27/25 2.20 2000.00 2598.38 3500.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 0.30 2500.00 5614.23 5000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.46 1609.70 1232.26 1376.68 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 212-00707 Seed (Native) Hyd) Acre STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 0.50 1000.00 2590.00 2330.00 Weighted Average for the First Quarter 9.28 2442.28 2057.15 2159.40 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 0.20 3000.00 7900.00 7900.00 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 10.50 0.78 2358.09 3000.00 2478.10 2423.00 2478.10 1692.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 0.50 1000.00 4500.00 4500.00 STAR500-228 REGION 5 05/08/25 1.86 2000.00 3336.33 2500.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.85 1327.34 1327.34 1327.34 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 0.85 2743.89 2769.66 2188.66 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.40 4000.00 1411.36 1300.00 Weighted Average for the Second Quarter 17.94 2358.37 2473.30 2338.60 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.40 1258.79 1258.79 1258.79 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 3874.97 4012.50 5000.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.10 1271.86 1271.84 1271.84 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 1.30 7.60 2000.00 1016.50 3014.80 1170.14 1960.00 1170.14 Weighted Average for the Third Quarter 13.40 1389.59 2266.64 1556.80 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.50 1575.82 2517.26 1740.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 0.18 4500.00 4736.25 1400.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 0.64 4000.00 3293.73 1725.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 5.09 4000.00 2094.48 2077.80 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 0.61 2884.50 3732.00 2950.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 0.75 1476.64 1786.36 1431.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 0.75 3124.38 1120.00 1120.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 0.60 2838.89 4000.00 2690.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 0.15 2500.00 2860.00 2770.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00707 Seed (Native) Hyd) Acre STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 0.50 12000.00 3969.01 3350.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 0.25 3500.00 2077.50 2450.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 3500.00 1455.00 1300.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 4.02 2000.00 2654.34 4235.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 0.32 4000.00 4731.39 2150.00 Weighted Average for the Fourth Quarter 17.36 3148.03 2686.68 2495.73 Weighted Average for the Year 57.97 2384.28 2429.74 2176.26 212-00708 Seed (Native) Brdcst Acre NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 0.25 4698.23 4650.44 4330.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 10.50 3000.00 2778.18 2200.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 0.25 5000.00 1636.90 943.40 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 0.02 15000.00 48005.32 73000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 0.10 3275.00 4297.38 4079.05 Weighted Average for the First Quarter 11.12 3107.20 2817.72 2363.87 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 0.03 17401.05 51666.50 73333.00 NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO VET I-70 CO 17 & SOUTH OF CO 14 04/11/25 05/08/25 10.50 0.40 1851.18 3668.00 1945.36 2520.50 1945.36 3451.50 Weighted Average for the Second Quarter 10.93 1960.35 2257.73 2196.42 CR400-406 REGION-WIDE 07/17/25 0.73 2542.00 8620.83 3162.50 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 0.10 7438.35 8784.00 5480.00 BR0704-265 FBR0704-269 MTCER200-301 I-70 EAST I-70 EAST R2 VARIOUS HIGHWAYS AND COUNT 07/24/25 08/21/25 0.89 0.11 2822.86 1400.00 2166.43 3716.67 2465.73 7250.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 212-00708 Seed (Native) Brdcst Acre FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 0.05 50000.00 40503.60 21500.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 0.10 5917.14 13023.00 3715.00 Weighted Average for the Third Quarter 1.98 4220.98 6634.80 3684.41 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 0.05 10568.84 30203.33 26000.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1.00 2948.07 1661.91 1653.50 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 0.10 5200.78 13076.90 14500.00 ITSSW03-417 STATEWIDE 12/04/25 0.99 1740.10 6609.94 3100.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 0.50 3214.04 835.00 835.00 NHPP1602-194 US 160 MP 174.1 12/11/25 0.01 50000.00 377446.00 14000.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 0.20 1882.72 2357.33 3033.00 Weighted Average for the Fourth Quarter 2.85 2878.19 5350.72 3030.39 Weighted Average for the Year 26.88 2698.63 3298.23 2463.72 212-00709 Seeding (Wetland) Drill Acre FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 2580.13 1395.87 1455.00 Weighted Average for the Fourth Quarter 1.00 2580.13 1395.87 1455.00 Weighted Average for the Year 1.00 2580.13 1395.87 1455.00 212-00710 Seeding (Wetland) Hydraulic Acre STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 0.02 2500.00 19514.20 9000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 0.10 4200.00 9012.58 6628.46 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 0.12 3978.26 10382.35 6937.79 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 0.03 2000.00 24860.00 51940.00 STAR500-228 REGION 5 05/08/25 0.55 3500.00 5231.67 2600.00 Weighted Average for the Second Quarter 0.58 3427.34 6479.32 4990.17 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 0.19 1.40 5000.00 1992.34 6058.20 2026.79 5300.00 2026.79 Weighted Average for the Third Quarter 1.59 2351.75 3656.51 2417.93 NHPPR500-227 REGION 5 SECTION 7 10/23/25 0.02 5000.00 38731.25 5800.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 0.32 4700.00 7669.50 18755.00 Weighted Average for the Fourth Quarter 0.34 4717.65 10058.87 17992.94 Weighted Average for the Year 2.62 2966.75 6280.55 5201.78 212-00711 Seeding (Wetland) Broadcast Acre STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 0.60 2141.66 2141.66 2141.66 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 0.14 6036.97 7684.22 4836.86 Weighted Average for the Third Quarter 0.74 2878.61 4817.38 2651.56 Weighted Average for the Year 0.74 2878.61 4817.38 2651.56 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 212-00900 Compost Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 1,490.00 70.32 73.92 73.92 Weighted Average for the Second Quarter 1,490.00 70.32 73.92 73.92 Weighted Average for the Year 1,490.00 70.32 73.92 73.92 212-01200 Landscape Restoration Lump Sum NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 58182.22 10688.50 8950.00 Weighted Average for the First Quarter 1.00 58182.22 10688.50 8950.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 5000.00 8492.50 6950.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1.00 35000.00 71567.25 15909.00 Weighted Average for the Third Quarter 2.00 20000.00 40029.88 11429.50 Weighted Average for the Year 3.00 32727.41 32027.68 10603.00 213-00002 Mulching (Weed Free Hay) Acre 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 1468.28 1324.18 1203.10 Weighted Average for the First Quarter 3.00 1468.28 1324.18 1203.10 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 0.11 1300.00 3083.33 5500.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 0.10 4164.24 12301.00 3905.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 0.21 2663.93 8636.14 4740.48 Weighted Average for the Year 3.21 1546.50 1646.48 1434.52 213-00003 Mulching (Weed Free) Acre NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 0.75 2387.26 2951.29 3765.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 0.32 500.00 5697.23 4150.00 Weighted Average for the First Quarter 1.07 1829.06 3937.01 3878.87 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 0.78 3500.00 4014.00 2756.00 STAR500-228 REGION 5 05/08/25 2.40 3000.00 4063.33 3700.00 Weighted Average for the Second Quarter 3.18 3122.88 4048.39 3468.01 BR0704-265 FBR0704-269 FBR2851-014 I-70 EAST I-70 EAST US 50 CONEJOS RIVER BRIDGE ST 07/24/25 09/18/25 1.64 1.50 2200.58 4000.00 3175.17 3294.20 2500.67 1400.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 3.14 3060.18 3238.66 1974.87 NHPPR500-227 REGION 5 SECTION 7 10/23/25 0.20 4000.00 5671.00 4500.00 ITSSW03-417 STATEWIDE 12/04/25 0.99 3161.09 6821.22 3700.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 0.50 3669.73 2400.00 2400.00 NHPP1602-194 US 160 MP 174.1 12/11/25 0.01 50000.00 295047.75 10700.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 3.02 4300.00 3552.24 3388.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 0.76 3000.00 2298.48 1500.00 Weighted Average for the Fourth Quarter 5.48 3928.56 4705.08 3145.71 Weighted Average for the Year 12.87 3343.71 4051.78 3000.39 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 213-00004 Mulching (Weed Free Straw) Acre NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO I-70 CO 17 & SOUTH OF CO 14 VET 04/11/25 05/08/25 12.00 6.90 1150.58 945.00 1209.11 995.50 1209.11 1111.50 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 0.85 2013.77 1876.87 1256.44 Weighted Average for the Second Quarter 19.75 1115.91 1166.25 1177.05 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10.20 1150.57 1150.57 1150.57 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 0.60 2250.73 4786.00 2200.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 11.20 622.98 1560.54 1150.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 33.20 957.65 974.21 974.21 Weighted Average for the Third Quarter 55.20 939.45 1457.81 1055.79 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 61.15 606.93 951.63 956.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2.20 2171.97 747.71 698.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 0.75 2079.81 1563.62 1440.00 Weighted Average for the Fourth Quarter 64.10 677.88 942.21 952.81 Weighted Average for the Year 139.05 843.93 1098.09 1025.54 213-00005 Mulching (Decorative) Cubic Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4,323.00 6.03 10.34 10.81 Weighted Average for the First Quarter 4,323.00 6.03 10.34 10.81 Weighted Average for the Year 4,323.00 6.03 10.34 10.81 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 213-00007 Mulching (Wood Strand) Acre NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 9.00 9882.33 10385.23 10385.23 Weighted Average for the Second Quarter 9.00 9882.33 10385.23 10385.23 Weighted Average for the Year 9.00 9882.33 10385.23 10385.23 213-00008 Mulching (Wood Chip) Cubic Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 243.00 3.51 6.87 5.51 Weighted Average for the First Quarter 243.00 3.51 6.87 5.51 Weighted Average for the Year 243.00 3.51 6.87 5.51 213-00011 Mulching (Hydraulic) Acre NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.46 2792.41 2780.46 3059.29 Weighted Average for the First Quarter 1.46 2792.41 2780.46 3059.29 Weighted Average for the Year 1.46 2792.41 2780.46 3059.29 213-00012 Spray-on Mulch Blanket Acre 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 0.10 10000.00 6134.25 5856.50 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 0.02 15000.00 510183.11 700000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 213-00012 Spray-on Mulch Blanket Acre NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 4.72 4700.00 6790.00 5580.00 BR0761-249 I-76 02/27/25 3.20 6331.43 4558.79 3800.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 0.50 4000.00 6392.50 5770.00 Weighted Average for the First Quarter 8.54 5356.51 6346.88 6553.66 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 0.40 4800.00 7300.00 7300.00 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 15.00 0.50 4135.21 20000.00 4345.63 6300.00 4345.63 6300.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.85 5623.35 5623.35 5623.35 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.30 5000.00 6546.23 8250.00 Weighted Average for the Second Quarter 19.05 4769.10 5041.31 4849.48 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.40 3987.12 3987.12 3987.12 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 6232.14 5890.00 9700.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.20 5513.95 5513.89 5513.89 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 0.05 50000.00 54578.40 24000.00 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 1.50 15.00 6000.00 3664.75 7079.00 3728.13 4000.00 3728.13 Weighted Average for the Third Quarter 21.15 4202.80 5351.06 4208.40 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 0.44 9000.00 9146.92 6000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.64 4782.19 7338.81 7280.35 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 0.75 5876.51 4845.00 4845.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 0.15 5000.00 9245.00 11530.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 14000.00 5138.26 5550.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 0.25 5500.00 6057.50 6190.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 0.80 7500.00 5315.00 5400.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 6500.00 9539.81 9317.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 7.03 7057.12 7299.98 6822.24 Weighted Average for the Year 55.77 4932.58 5932.46 5115.90 213-00061 Mulch Tackifier Pound NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 150.00 6.70 5.34 5.10 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3,280.00 5.00 3.05 2.81 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 63.00 3.00 19.92 15.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 219.00 4.39 2.53 3.06 Weighted Average for the First Quarter 3,712.00 5.00 3.28 3.12 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 12,000.00 79.00 2.93 5.50 3.12 13.55 3.12 3.20 STAR500-228 REGION 5 05/08/25 240.00 5.00 17.13 19.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1,380.00 3.00 3.59 2.93 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 370.00 6.15 6.15 6.15 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 85.00 5.00 8.51 7.70 Weighted Average for the Second Quarter 14,154.00 3.09 4.16 3.48 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2,040.00 3.91 3.91 3.91 BR0704-265 FBR0704-269 MTCER200-301 I-70 EAST I-70 EAST R2 VARIOUS HIGHWAYS AND COUNT 07/24/25 08/21/25 163.50 16.00 7.19 10.34 8.31 14.00 3.23 12.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 120.00 7.48 9.40 12.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 10.00 15.00 56.62 62.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 19,500.00 2.12 2.99 2.75 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 15,200.00 3.48 3.54 3.54 Weighted Average for the Third Quarter 37,049.50 2.82 3.11 3.19 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 213-00061 Mulch Tackifier Pound NHPPR500-227 REGION 5 SECTION 7 10/23/25 41.00 8.00 11.41 5.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 264.00 5.86 12.35 12.25 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 12,230.00 2.74 3.19 3.50 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 4.00 16.10 69.55 100.00 ITSSW03-417 STATEWIDE 12/04/25 158.00 6.78 31.53 10.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 150.00 6.08 5.00 5.00 NHPP1602-194 US 160 MP 174.1 12/11/25 2.00 100.00 216.03 48.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 182.00 6.00 6.43 6.05 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 440.00 4.08 2.89 2.75 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 152.00 10.00 4.60 6.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 100.00 8.21 7.82 8.10 Weighted Average for the Fourth Quarter 13,723.00 3.12 3.63 3.87 Weighted Average for the Year 68,638.50 3.05 3.32 3.38 213-00065 Inorg Mulch Cubic Yard C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 70.00 100.00 109.62 50.00 Weighted Average for the Fourth Quarter 70.00 100.00 109.62 50.00 Weighted Average for the Year 70.00 100.00 109.62 50.00 213-00067 Rock Mulch (Weed Free) Sq Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 885.00 7.52 4.45 5.10 Weighted Average for the First Quarter 885.00 7.52 4.45 5.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 213-00067 Rock Mulch (Weed Free) Sq Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2,364.00 5.40 5.40 5.40 Weighted Average for the Third Quarter 2,364.00 5.40 5.40 5.40 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 12,131.00 3.00 3.62 2.79 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 15,566.00 3.00 3.62 2.79 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 61,936.00 2.00 3.83 5.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 800.00 5.00 2.37 2.04 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 224.00 6.00 20.86 26.00 Weighted Average for the Fourth Quarter 90,657.00 2.34 3.80 4.35 Weighted Average for the Year 93,906.00 2.47 3.82 4.38 213-00150 Bonded Fiber Matrix Acre 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 0.10 7394.61 6305.08 5856.50 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 4600.00 6400.00 4800.00 Weighted Average for the First Quarter 2.10 4733.08 6387.62 4850.31 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 35.00 4135.21 4345.63 4345.63 FBR0703-534 I-70 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 7.00 3643.00 4251.67 4095.00 Weighted Average for the Second Quarter 42.00 4053.17 4310.39 4303.86 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5.00 3987.12 3987.12 3987.12 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 0.30 8287.50 9361.46 9361.46 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 6726.48 5490.18 3800.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 35.00 3664.75 3728.13 3728.13 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 41.30 3811.49 4081.78 3802.14 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.50 3850.93 6990.19 7320.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 0.61 7216.79 4993.00 5350.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 0.75 7447.17 5271.60 5297.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 70.00 2896.51 3908.04 4226.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.20 4349.49 4031.33 4550.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 0.18 6000.00 6391.71 7100.00 Weighted Average for the Fourth Quarter 78.24 3089.49 4028.89 4367.93 Weighted Average for the Year 163.64 3540.14 4085.31 4214.88 213-00300 Conc Landscape Border Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 273.00 19.00 19.93 18.46 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3,413.00 20.00 24.08 15.00 Weighted Average for the Fourth Quarter 3,686.00 19.93 23.87 15.26 Weighted Average for the Year 3,686.00 19.93 23.87 15.26 213-00462 Landscape Border (3/16x5-1/2 In) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 600.00 7.34 11.32 13.25 Weighted Average for the First Quarter 600.00 7.34 11.32 13.25 Weighted Average for the Year 600.00 7.34 11.32 13.25 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 213-00610 Landscape Log Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 24.00 3417.52 3326.86 3326.86 Weighted Average for the Second Quarter 24.00 3417.52 3326.86 3326.86 Weighted Average for the Year 24.00 3417.52 3326.86 3326.86 213-00700 Landscape Boulder Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 154.00 389.89 336.47 336.47 FBR0703-534 I-70 Weighted Average for the Second Quarter 154.00 389.89 336.47 336.47 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 33.00 985.38 985.38 985.38 Weighted Average for the Third Quarter 33.00 985.38 985.38 985.38 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 8.00 300.00 343.83 500.00 Weighted Average for the Fourth Quarter 8.00 300.00 343.83 500.00 Weighted Average for the Year 195.00 486.98 429.10 452.99 213-00800 Brush Fill Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3,219.00 101.88 68.54 68.54 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 3,219.00 101.88 68.54 68.54 Weighted Average for the Year 3,219.00 101.88 68.54 68.54 214-00000 Landscape Maintenance Lump Sum 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 10000.00 27586.10 27729.60 Weighted Average for the First Quarter 1.00 10000.00 27586.10 27729.60 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 7500.00 31922.50 4840.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 20000.00 2209.00 2200.00 Weighted Average for the Fourth Quarter 2.00 13750.00 22018.00 3520.00 Weighted Average for the Year 3.00 12500.00 24802.05 11589.87 214-00005 Landscape Maintenance (24 Month) Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 538953.86 566890.08 566890.08 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 538953.86 566890.08 566890.08 Weighted Average for the Year 1.00 538953.86 566890.08 566890.08 214-00008 Extended Landscape Preservation Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 17000.00 57585.70 89000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 32500.00 37919.99 4079.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 2.00 24750.00 46348.15 46539.53 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 1153525.70 1059135.69 1059135.69 Weighted Average for the Third Quarter 1.00 1153525.70 1059135.69 1059135.69 Weighted Average for the Year 3.00 401008.57 172946.59 384071.58 214-00205 Deciduous Tree (#5 Container) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 8.00 69.21 225.41 96.88 Weighted Average for the First Quarter 8.00 69.21 225.41 96.88 Weighted Average for the Year 8.00 69.21 225.41 96.88 214-00220 Deciduous Tree (2 In C) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 23.00 790.02 862.98 810.90 Weighted Average for the First Quarter 23.00 790.02 862.98 810.90 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 3.00 1105.00 1104.99 1104.99 Weighted Average for the Third Quarter 3.00 1105.00 1104.99 1104.99 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 750.00 801.94 718.74 Weighted Average for the Fourth Quarter 7.00 750.00 801.94 718.74 Weighted Average for the Year 33.00 810.17 857.16 818.09 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 214-00225 Deciduous Tree (2.5 In C) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 11.00 800.00 878.14 792.55 Weighted Average for the Fourth Quarter 11.00 800.00 878.14 792.55 Weighted Average for the Year 11.00 800.00 878.14 792.55 214-00227 Furn Deciduous Tree (2.5 In C) Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6.00 1017.28 1017.28 1017.28 Weighted Average for the Second Quarter 6.00 1017.28 1017.28 1017.28 Weighted Average for the Year 6.00 1017.28 1017.28 1017.28 214-00280 Deciduous Tree (8 Ft) Each FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES 13.00 400.00 1131.60 1010.00 Weighted Average for the Third Quarter 13.00 400.00 1131.60 1010.00 Weighted Average for the Year 13.00 400.00 1131.60 1010.00 214-00310 Deciduous Shrub (#1 Container) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 10.00 36.64 68.96 50.99 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 10.00 36.64 68.96 50.99 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 6.00 30.00 80.65 55.00 Weighted Average for the Fourth Quarter 6.00 30.00 80.65 55.00 Weighted Average for the Year 16.00 34.15 71.66 52.49 214-00350 Deciduous Shrub (#5 Container) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 392.00 80.14 84.22 84.22 Weighted Average for the Second Quarter 392.00 80.14 84.22 84.22 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 329.00 90.00 101.97 92.87 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 9.00 60.00 128.70 104.50 Weighted Average for the Fourth Quarter 338.00 89.20 102.33 93.18 Weighted Average for the Year 730.00 84.34 98.22 88.37 214-00450 Evergreen Tree (#5 Container) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 67.35 262.30 96.88 Weighted Average for the First Quarter 2.00 67.35 262.30 96.88 Weighted Average for the Year 2.00 67.35 262.30 96.88 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 214-00504 Evergreen Tree (4 Ft)(B-B) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 329.00 483.01 507.59 507.59 Weighted Average for the Second Quarter 329.00 483.01 507.59 507.59 Weighted Average for the Year 329.00 483.01 507.59 507.59 214-00506 Evergreen Tree (6 Ft)(B-B) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 774.94 841.17 795.00 Weighted Average for the First Quarter 3.00 774.94 841.17 795.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 329.00 522.88 549.49 549.49 FBR0703-534 I-70 Weighted Average for the Second Quarter 329.00 522.88 549.49 549.49 Weighted Average for the Year 332.00 525.16 564.62 551.71 214-00901 Perennials (Tubeling) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 530.00 5.18 5.45 5.45 FBR0703-534 I-70 Weighted Average for the Second Quarter 530.00 5.18 5.45 5.45 Weighted Average for the Year 530.00 5.18 5.45 5.45 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 214-00910 Perennials (#1 Container) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 86.00 27.00 34.50 32.98 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 32.00 35.00 55.18 46.75 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 18.00 35.00 58.33 46.75 Weighted Average for the Fourth Quarter 136.00 29.94 39.41 38.04 Weighted Average for the Year 136.00 29.94 39.41 38.04 STAR500-228 214-01010 Brush Layer REGION 5 Cutting 05/08/25 Each 1,240.00 10.00 26.07 28.00 Weighted Average for the Second Quarter 1,240.00 10.00 26.07 28.00 Weighted Average for the Year 1,240.00 10.00 26.07 28.00 214-01012 Live Brush Fascine Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO I-70 VET 04/11/25 2,313.00 90.96 95.59 95.59 Weighted Average for the Second Quarter 2,313.00 90.96 95.59 95.59 Weighted Average for the Year 2,313.00 90.96 95.59 95.59 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 214-01013 Live Willow Stakes Each STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 73.00 25.00 30.32 22.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 105.00 6.94 11.40 10.20 Weighted Average for the First Quarter 178.00 14.35 19.16 15.04 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 306.00 8.54 8.98 8.98 Weighted Average for the Second Quarter 306.00 8.54 8.98 8.98 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 US 285 CONEJOS RIVER BRIDGES 1,600.00 15.00 18.37 10.00 Weighted Average for the Third Quarter 1,600.00 15.00 18.37 10.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 784.00 8.50 29.35 26.62 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 50.00 20.00 15.01 14.55 Weighted Average for the Fourth Quarter 834.00 9.19 26.83 25.90 Weighted Average for the Year 2,918.00 12.62 20.21 14.74 214-01025 Dormant Log Cutting Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 15.00 88.74 37.99 25.49 Weighted Average for the First Quarter 15.00 88.74 37.99 25.49 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 59.00 27.06 28.43 28.43 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 59.00 27.06 28.43 28.43 Weighted Average for the Year 74.00 39.56 33.25 27.83 214-01227 Rootwad Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 50.00 628.82 916.31 916.31 FBR0703-534 I-70 Weighted Average for the Second Quarter 50.00 628.82 916.31 916.31 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 6.00 400.00 1023.60 1050.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 6.00 400.00 1023.60 1050.00 Weighted Average for the Year 56.00 604.30 956.54 930.63 214-01228 Riprap Planting Pocket Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 47.00 628.82 952.45 952.45 FBR0703-534 I-70 Weighted Average for the Second Quarter 47.00 628.82 952.45 952.45 Weighted Average for the Year 47.00 628.82 952.45 952.45 214-01404 DRC #180 Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 240.00 29.50 31.01 31.01 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 214-01404 DRC #180 Each FBR0703-534 I-70 Weighted Average for the Second Quarter 240.00 29.50 31.01 31.01 Weighted Average for the Year 240.00 29.50 31.01 31.01 214-01422 #10 Container Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 56.00 268.85 282.53 282.53 FBR0703-534 I-70 Weighted Average for the Second Quarter 56.00 268.85 282.53 282.53 Weighted Average for the Year 56.00 268.85 282.53 282.53 216-00101 Soil Reten Blanket (S-C)(PhotoD Cl 1) Sq Yard ITSSW03-250 FRONT RANGE 06/26/25 5,000.00 3.01 4.45 3.20 Weighted Average for the Second Quarter 5,000.00 3.01 4.45 3.20 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 200.00 5.65 7.72 6.00 Weighted Average for the Fourth Quarter 200.00 5.65 7.72 6.00 Weighted Average for the Year 5,200.00 3.12 4.55 3.31 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 216-00201 Soil Reten Blanket (S-C)(BioD Cl 1) Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,210.00 5.09 4.52 5.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 5,400.00 3.75 3.08 2.54 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 970.00 5.00 4.18 4.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 50.00 6.00 36.06 35.69 Weighted Average for the First Quarter 7,630.00 4.14 3.45 3.33 NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO VET I-70 CO 17 & SOUTH OF CO 14 04/11/25 05/08/25 54,000.00 13,058.00 2.34 3.50 2.45 3.06 2.45 2.93 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1,076.00 4.00 3.82 4.90 Weighted Average for the Second Quarter 68,134.00 2.59 2.76 2.58 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6,776.00 2.41 2.41 2.41 CR400-406 REGION-WIDE 07/17/25 3,305.00 4.42 5.63 6.88 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 8,200.00 2.95 3.00 2.75 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 259,877.00 3.09 3.15 3.15 Weighted Average for the Third Quarter 278,158.00 3.09 3.18 3.16 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 980.00 5.71 4.12 2.05 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2,910.00 3.00 3.43 3.45 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4,116.00 3.87 3.22 3.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 200.00 5.00 3.40 4.30 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 968.00 3.50 2.83 3.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 5,158.00 3.28 2.71 2.75 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1,530.00 4.00 2.98 3.25 Weighted Average for the Fourth Quarter 15,862.00 3.64 3.04 3.01 Weighted Average for the Year 369,784.00 3.04 3.10 3.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 216-00202 Soil Reten Blanket (S-C)(BioD Cl 2) Sq Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,767.00 2.41 2.96 2.96 Weighted Average for the Third Quarter 1,767.00 2.41 2.96 2.96 Weighted Average for the Year 1,767.00 2.41 2.96 2.96 216-00211 Soil Reten Blanket (Exc)(BioD Cl 1) Sq Yard C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 450.00 8.29 4.96 3.95 Weighted Average for the Second Quarter 450.00 8.29 4.96 3.95 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 12,012.00 2.50 2.83 2.80 Weighted Average for the Fourth Quarter 12,012.00 2.50 2.83 2.80 Weighted Average for the Year 12,462.00 2.71 3.01 2.84 216-00222 Soil Reten Blanket (C)(BioD Cl 2) Sq Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,500.00 2.34 2.45 2.45 FBR0703-534 I-70 Weighted Average for the Second Quarter 1,500.00 2.34 2.45 2.45 Weighted Average for the Year 1,500.00 2.34 2.45 2.45 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 216-00301 Turf Reinf Mat (Cl 1) Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 146.00 9.05 8.50 7.74 Weighted Average for the First Quarter 146.00 9.05 8.50 7.74 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3,472.00 4.84 5.08 5.08 FBR0703-534 I-70 Weighted Average for the Second Quarter 3,472.00 4.84 5.08 5.08 Weighted Average for the Year 3,618.00 5.01 5.77 5.19 216-00302 Turf Reinf Mat (Cl 2) Sq Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 458.00 5.41 7.72 7.72 Weighted Average for the Third Quarter 458.00 5.41 7.72 7.72 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 7,293.00 6.27 10.89 10.80 Weighted Average for the Fourth Quarter 7,293.00 6.27 10.89 10.80 Weighted Average for the Year 7,751.00 6.22 10.79 10.62 216-00303 Turf Reinf Mat (Cl 3) Sq Yard NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1,191.00 7.42 11.65 11.55 Weighted Average for the Fourth Quarter 1,191.00 7.42 11.65 11.55 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 1,191.00 7.42 11.65 11.55 216-00306 Coir Mat Sq Yard NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 262.00 8.83 8.98 8.98 Weighted Average for the Third Quarter 262.00 8.83 8.98 8.98 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4,840.00 10.00 5.86 5.75 Weighted Average for the Fourth Quarter 4,840.00 10.00 5.86 5.75 Weighted Average for the Year 5,102.00 9.94 5.88 5.92 217-00000 Herbicide Treatment Sq Yard STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 28,700.00 1.50 0.30 0.30 Weighted Average for the Second Quarter 28,700.00 1.50 0.30 0.30 Weighted Average for the Year 28,700.00 1.50 0.30 0.30 217-00020 Herbicide Treatment Hour 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 16.00 206.98 339.75 344.50 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 8.00 300.00 185.34 200.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 10.00 216.60 352.51 255.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 40.00 188.87 277.58 127.47 Weighted Average for the First Quarter 74.00 208.55 296.94 199.47 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 217-00020 Herbicide Treatment Hour NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 100.00 358.84 377.10 377.10 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 20.00 230.00 345.52 251.55 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 193.58 237.42 165.00 Weighted Average for the Second Quarter 140.00 316.83 316.09 328.86 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 40.00 143.51 143.51 143.51 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 5.00 171.51 356.20 400.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 500.00 321.00 326.55 326.55 Weighted Average for the Third Quarter 545.00 306.60 314.90 313.79 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 20.00 216.59 321.00 395.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 80.00 222.96 299.40 334.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 20.00 244.96 285.63 285.00 Weighted Average for the Fourth Quarter 120.00 225.56 298.55 336.00 Weighted Average for the Year 879.00 288.91 305.80 309.60 218-00000 Noxious Weed Management Lump Sum STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 47115.14 29105.82 29105.82 Weighted Average for the Third Quarter 1.00 47115.14 29105.82 29105.82 Weighted Average for the Year 1.00 47115.14 29105.82 29105.82 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 240-00000 Wildlife Biologist Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 40.00 143.90 206.41 215.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 8.00 160.72 174.98 174.90 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 20.00 200.00 233.59 120.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 40.00 140.83 224.08 189.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 200.00 142.00 150.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 20.00 250.00 302.16 273.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 120.00 117.61 177.74 155.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 40.00 171.03 251.51 115.61 Weighted Average for the First Quarter 328.00 154.36 209.51 166.69 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 200.00 40.00 187.96 200.00 187.96 236.25 187.96 265.00 STAR500-228 REGION 5 05/08/25 40.00 250.00 275.00 350.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 40.00 162.27 221.33 182.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 40.00 195.64 195.64 195.64 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 40.00 159.15 183.33 125.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 8.00 421.67 221.64 230.00 Weighted Average for the Second Quarter 408.00 195.21 217.05 206.22 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 16.00 149.25 149.25 149.25 BR0704-265 FBR0704-269 SHER100-414 I-70 EAST I-70 EAST SH 74/KERRGULCH;SH83/GILLIAN, 07/24/25 08/14/25 120.00 16.00 165.66 429.70 166.80 207.00 167.20 200.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 8.00 243.10 243.10 243.10 STR050A-042 FREMONT COUNTY IN R2 09/11/25 8.00 135.09 248.80 140.00 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 20.00 60.00 400.00 197.95 282.24 204.07 210.00 204.07 SPFS2706-055 I-270 MP 0-3 09/26/25 80.00 160.00 176.80 176.80 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 328.00 197.70 191.28 180.81 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 15.00 140.00 324.42 395.67 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 15.00 137.21 293.00 240.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 20.00 172.94 362.55 295.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 20.00 280.00 292.48 265.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 40.00 250.00 341.96 337.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 40.00 180.00 225.00 100.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 10.00 135.00 277.60 242.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 30.00 174.97 349.50 349.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 10.00 180.00 275.50 276.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 40.00 117.61 260.41 300.00 ITSSW03-417 STATEWIDE 12/04/25 20.00 182.68 347.00 225.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 20.00 150.00 190.90 100.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 10.00 220.00 266.00 272.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 25.00 131.63 200.00 200.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 10.00 278.44 272.50 175.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 10.00 150.00 209.00 305.00 NHPP1602-194 US 160 MP 174.1 12/11/25 15.00 250.00 420.99 465.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 325.00 384.99 363.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 80.00 146.45 201.64 195.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 40.00 220.00 244.00 125.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 40.00 203.17 278.18 285.00 Weighted Average for the Fourth Quarter 550.00 191.53 267.65 251.63 NHPP0501-080 240-00001 Weighted Average for the Year Wildlife Biologist SH50A MP 89.93 CEADAR CREEK 06/12/25 1,614.00 Day 4.00 186.16 1000.00 236.24 2072.53 208.50 2100.00 Weighted Average for the Second Quarter 4.00 1000.00 2072.53 2100.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 4.00 1000.00 2072.53 2100.00 240-00010 Rem of Nests Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 40.00 156.28 268.95 215.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 200.00 172.66 123.12 185.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 20.00 200.00 254.28 120.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 40.00 174.29 218.08 189.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 200.00 117.00 100.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 10.00 250.00 295.33 273.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 80.00 77.79 175.71 155.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 40.00 171.00 238.37 115.61 Weighted Average for the First Quarter 470.00 160.25 159.33 168.82 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 200.00 176.57 176.57 176.57 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 20.00 220.00 151.00 58.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 40.00 184.57 260.00 370.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 40.00 184.13 184.13 184.13 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 10.00 180.00 286.90 325.00 Weighted Average for the Second Quarter 310.00 181.49 202.99 199.64 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 40.00 143.51 143.51 143.51 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 120.00 50.00 181.52 187.85 198.26 187.85 248.03 187.85 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 4.00 189.74 415.60 450.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 20.00 197.95 204.07 204.07 SPFS2706-055 I-270 MP 0-3 09/26/25 80.00 120.00 132.60 132.60 Weighted Average for the Third Quarter 314.00 163.16 191.89 195.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 240-00010 Rem of Nests Hour NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 15.00 115.00 319.42 395.67 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 12.00 208.86 412.55 295.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 10.00 280.00 351.23 500.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 10.00 220.00 331.55 200.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 10.00 200.00 225.00 100.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 182.64 221.62 216.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 10.00 213.88 279.45 260.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 40.00 75.53 338.96 315.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 20.00 161.74 219.00 219.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 10.00 231.94 318.00 165.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 5.00 350.00 275.50 276.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 40.00 80.77 257.58 265.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 40.00 300.00 190.90 100.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 5.00 300.00 372.80 440.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 10.00 327.45 272.50 175.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 10.00 215.00 209.00 305.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 40.00 140.00 188.28 170.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 5.00 250.00 318.00 245.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 100.00 186.07 273.52 286.00 Weighted Average for the Fourth Quarter 432.00 181.98 257.11 247.63 Weighted Average for the Year 1,526.00 171.32 199.33 202.88 240-00020 Netting Sq Yard NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 500.00 10.00 14.00 15.00 Weighted Average for the First Quarter 500.00 10.00 14.00 15.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 200.00 33.04 33.04 33.04 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 200.00 33.04 33.04 33.04 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 275.00 33.15 33.15 33.15 Weighted Average for the Third Quarter 275.00 33.15 33.15 33.15 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 20.00 35.00 71.91 35.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1,110.00 10.41 14.57 14.25 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 260.00 19.80 14.65 13.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 800.00 15.63 20.19 19.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 50.00 27.46 12.90 12.90 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 20.00 30.00 79.00 175.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,500.00 9.58 13.82 14.00 Weighted Average for the Fourth Quarter 3,760.00 12.30 16.86 16.06 Weighted Average for the Year 4,735.00 14.14 17.32 17.66 240-00100 Prairie Dog Mgmt Lump Sum NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 17722.57 17722.57 17722.57 Weighted Average for the Second Quarter 1.00 17722.57 17722.57 17722.57 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 68034.20 29717.30 29717.30 Weighted Average for the Third Quarter 1.00 68034.20 29717.30 29717.30 Weighted Average for the Year 2.00 42878.39 23719.94 23719.94 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 250-00010 Envir Health/Safety Mngmt Lump Sum 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 10000.00 5395.83 2544.00 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 1.00 2000.00 4666.67 2200.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 5000.00 7515.00 10030.00 Weighted Average for the First Quarter 3.00 5666.67 5582.27 4924.67 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 15000.00 8692.50 11385.00 Weighted Average for the Second Quarter 1.00 15000.00 8692.50 11385.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 11050.00 5524.94 5524.94 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 1.00 10000.00 18974.00 5670.00 Weighted Average for the Third Quarter 2.00 10525.00 16732.49 5597.47 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 15000.00 23306.25 66550.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 15000.00 21358.33 25000.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 8000.00 11921.17 7500.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 10000.00 5287.50 2575.00 Weighted Average for the Fourth Quarter 4.00 12000.00 17847.57 25406.25 Weighted Average for the Year 10.00 10105.00 13144.07 13897.89 250-00050 Monitoring Technician Hour NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 8.00 150.00 150.67 139.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 100.00 400.50 401.00 Weighted Average for the First Quarter 18.00 122.22 264.23 284.56 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 250-00050 Monitoring Technician Hour STAR500-228 REGION 5 05/08/25 8.00 160.00 276.67 530.00 Weighted Average for the Second Quarter 8.00 160.00 276.67 530.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 40.00 200.00 294.80 190.00 Weighted Average for the Third Quarter 40.00 200.00 294.80 190.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 50.00 360.00 316.03 254.10 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 40.00 195.00 203.67 200.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 40.00 180.00 331.85 200.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 225.00 223.75 97.50 Weighted Average for the Fourth Quarter 150.00 250.00 268.10 204.37 Weighted Average for the Year 216.00 226.76 274.29 220.45 250-00110 Health and Safety Officer Hour NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 3.00 200.00 195.67 184.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 100.00 413.00 401.00 Weighted Average for the First Quarter 13.00 123.08 345.55 350.92 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 24.00 252.78 221.00 221.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 40.00 200.00 293.88 190.00 Weighted Average for the Third Quarter 64.00 219.79 286.07 201.63 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 20.00 450.00 367.15 193.60 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 250-00110 Health and Safety Officer Hour C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 20.00 200.00 198.50 50.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 20.00 170.00 231.93 200.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 400.00 179.13 108.25 Weighted Average for the Fourth Quarter 80.00 305.00 247.58 137.96 Weighted Average for the Year 157.00 255.20 268.31 181.55 250-00120 Material Sampling and Delivery Each STAR500-228 REGION 5 05/08/25 2.00 215.00 1155.00 300.00 Weighted Average for the Second Quarter 2.00 215.00 1155.00 300.00 Weighted Average for the Year 2.00 215.00 1155.00 300.00 250-00204 Materials Management Plan Lump Sum 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 2000.00 4152.67 1855.00 Weighted Average for the First Quarter 1.00 2000.00 4152.67 1855.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 3210.00 3210.00 3210.00 Weighted Average for the Third Quarter 1.00 3210.00 3210.00 3210.00 Weighted Average for the Year 2.00 2605.00 4018.00 2532.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 250-00210 Solid Waste Disposal Cubic Yard NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 70.00 200.00 175.15 75.59 Weighted Average for the Fourth Quarter 70.00 200.00 175.15 75.59 Weighted Average for the Year 70.00 200.00 175.15 75.59 250-00224 Hazardous Waster Disposal (Radioactive) Cubic Yard NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 249.00 45.00 92.05 91.21 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 100.00 140.00 123.17 20.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 10.00 60.00 787.94 98.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 30.00 170.00 336.50 161.00 Weighted Average for the Fourth Quarter 389.00 79.45 124.21 78.46 Weighted Average for the Year 389.00 79.45 124.21 78.46 304-01000 ABC (CL 1) Ton NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1,063.03 35.00 42.84 34.00 Weighted Average for the Second Quarter 1,063.03 35.00 42.84 34.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1,177.79 67.44 61.05 61.05 Weighted Average for the Third Quarter 1,177.79 67.44 61.05 61.05 Weighted Average for the Year 2,240.82 52.05 46.79 48.22 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 304-01005 ABC (CL 1) Cubic Yard NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 3,866.00 90.00 65.00 52.00 Weighted Average for the First Quarter 3,866.00 90.00 65.00 52.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 37.50 200.00 318.34 350.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 735.00 90.00 83.33 82.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,622.00 75.00 66.50 49.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 287.00 150.00 94.80 90.60 Weighted Average for the Fourth Quarter 2,681.50 88.89 85.97 66.71 Weighted Average for the Year 6,547.50 89.54 76.00 58.02 304-02000 ABC (CL 2) Ton STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 96.00 90.00 129.50 103.00 Weighted Average for the Second Quarter 96.00 90.00 129.50 103.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 157.00 80.00 59.80 36.00 Weighted Average for the Third Quarter 157.00 80.00 59.80 36.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 578.00 65.49 28.50 28.50 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 879.00 70.00 75.66 66.71 Weighted Average for the Fourth Quarter 1,457.00 68.21 67.18 51.55 Weighted Average for the Year 1,710.00 70.52 71.32 53.01 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 304-03005 ABC (CL 3) Cubic Yard NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 39.00 140.00 176.75 220.00 Weighted Average for the First Quarter 39.00 140.00 176.75 220.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,778.00 75.00 84.06 58.22 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 525.00 90.00 76.00 82.00 Weighted Average for the Fourth Quarter 2,303.00 78.42 81.58 63.64 Weighted Average for the Year 2,342.00 79.44 82.30 66.24 304-05000 ABC (CL 5) Ton NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2,750.00 35.00 71.55 63.74 Weighted Average for the First Quarter 2,750.00 35.00 71.55 63.74 Weighted Average for the Year 2,750.00 35.00 71.55 63.74 304-06000 ABC (CL 6) Ton NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 807.00 65.00 93.14 115.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 44.00 75.00 111.69 65.00 Weighted Average for the First Quarter 851.00 65.52 94.96 112.41 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 10.20 107.53 307.00 314.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 48.00 170.00 164.50 113.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 720.03 65.00 52.26 36.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 778.23 72.03 60.90 44.39 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1,662.00 60.00 69.38 69.50 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 841.27 67.44 90.38 90.38 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 143.00 80.00 66.54 53.00 Weighted Average for the Third Quarter 2,646.27 63.45 71.28 75.25 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 447.00 75.00 103.50 107.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 6,936.50 65.00 44.00 46.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 290.00 69.30 31.50 31.50 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 6,780.00 60.00 55.80 53.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 678.00 80.00 151.44 60.66 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 389.20 80.00 104.00 90.00 Weighted Average for the Fourth Quarter 15,520.70 64.22 60.72 52.29 Weighted Average for the Year 19,796.20 64.48 64.56 57.63 304-06004 ABC (CL 6) Sq Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 728.00 18.11 21.79 21.79 Weighted Average for the Second Quarter 728.00 18.11 21.79 21.79 Weighted Average for the Year 728.00 18.11 21.79 21.79 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 304-06007 ABC (CL 6) Cubic Yard STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 233.00 170.00 189.14 135.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,081.00 80.00 80.13 66.78 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2,963.00 120.00 85.50 87.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 4,615.00 90.00 79.69 101.50 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 771.00 80.93 116.46 71.45 Weighted Average for the First Quarter 9,663.00 99.29 88.33 91.58 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 775.00 100.00 114.00 114.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 19,625.00 4.00 91.47 300.00 94.49 335.00 94.49 335.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 23.00 250.00 340.00 340.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 501.00 100.00 116.00 88.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 7,415.00 70.73 70.73 70.73 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 4.00 191.62 1716.67 1650.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 292.00 99.54 94.25 78.50 Weighted Average for the Second Quarter 28,639.00 86.73 91.06 89.04 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4,344.00 105.42 105.42 105.42 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 3,205.00 63.93 69.29 38.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 17,141.00 67.61 67.93 67.93 Weighted Average for the Third Quarter 24,690.00 73.78 72.12 70.64 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3,920.00 150.00 101.28 65.12 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1,782.00 100.00 95.64 92.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 28.90 175.00 370.23 275.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2,271.00 90.00 94.33 79.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2,086.00 65.00 83.76 97.60 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 614.00 98.17 97.36 95.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 8,030.00 93.50 73.74 50.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 304-06007 ABC (CL 6) Cubic Yard NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 747.00 100.00 69.50 49.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 360.00 101.83 133.51 160.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 52.00 150.00 256.95 425.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 459.00 90.00 131.67 135.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 190.00 80.00 126.50 110.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 88.00 150.00 148.35 245.50 NHPP1602-194 US 160 MP 174.1 12/11/25 3.00 1000.00 1216.03 940.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 150.00 108.22 85.89 75.90 Weighted Average for the Fourth Quarter 20,780.90 102.52 88.29 72.42 Weighted Average for the Year 83,772.90 88.28 84.97 79.79 304-06008 ABC (CL 6) (Spec) Cubic Yard NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET I-70 SH287 & LCR 72 AND US287 & OW 04/11/25 04/24/25 4,446.00 45.00 68.35 166.10 43.80 167.67 43.80 185.00 Weighted Average for the Second Quarter 4,491.00 69.33 47.45 45.21 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 293.00 132.06 132.06 132.06 Weighted Average for the Third Quarter 293.00 132.06 132.06 132.06 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 326.00 74.51 106.96 48.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 51.00 100.00 127.83 90.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 578.00 98.09 117.38 99.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 30,280.00 65.84 70.84 30.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 640.00 90.00 86.35 79.80 Weighted Average for the Fourth Quarter 31,875.00 67.06 72.75 32.53 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 304-06009 Weighted Average ABC (CL 6) (Spec) for the Year 36,659.00 Ton 67.86 72.16 34.88 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 27.00 110.75 163.00 168.00 Weighted Average for the Fourth Quarter 27.00 110.75 163.00 168.00 Weighted Average for the Year 27.00 110.75 163.00 168.00 304-07000 ABC (CL 7) Ton NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 269.89 75.00 59.85 36.00 Weighted Average for the Second Quarter 269.89 75.00 59.85 36.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 53.67 36.33 194.34 194.34 Weighted Average for the Third Quarter 53.67 36.33 194.34 194.34 Weighted Average for the Year 323.56 68.59 66.21 62.26 304-07005 ABC (CL 7) Cubic Yard STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 4,040.00 150.00 53.50 57.00 Weighted Average for the First Quarter 4,040.00 150.00 53.50 57.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 158.00 70.00 98.33 80.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 304-07005 ABC (CL 7) Cubic Yard STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 258.00 100.00 138.97 185.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 5,780.00 55.00 71.80 77.60 Weighted Average for the Fourth Quarter 6,196.00 57.26 77.61 82.13 Weighted Average for the Year 10,236.00 93.86 68.49 72.21 304-07010 ABC (CL 7) (Spec) Cubic Yard STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 788.00 80.00 87.50 67.50 Weighted Average for the Second Quarter 788.00 80.00 87.50 67.50 Weighted Average for the Year 788.00 80.00 87.50 67.50 304-08000 ABC (Shoulder Material) Ton STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 3,978.00 45.00 59.73 57.45 Weighted Average for the Fourth Quarter 3,978.00 45.00 59.73 57.45 Weighted Average for the Year 3,978.00 45.00 59.73 57.45 304-08002 ABC (Shoulder Material) Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 370.00 167.95 229.51 229.51 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 370.00 167.95 229.51 229.51 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 736.00 254.53 287.65 287.65 Weighted Average for the Third Quarter 736.00 254.53 287.65 287.65 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 257.00 66.70 122.45 90.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1,135.00 87.98 84.46 89.40 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2,465.00 37.14 124.50 118.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,336.00 65.00 75.35 99.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 2,529.00 268.00 52.45 25.00 Weighted Average for the Fourth Quarter 7,722.00 126.03 83.34 79.12 Weighted Average for the Year 8,828.00 138.50 93.64 102.81 304-09000 ABC (Spec) Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 4.00 250.00 575.83 50.00 Weighted Average for the First Quarter 4.00 250.00 575.83 50.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 190.00 100.00 104.00 90.00 Weighted Average for the Fourth Quarter 190.00 100.00 104.00 90.00 Weighted Average for the Year 194.00 103.09 110.53 89.18 304-09014 ABC (Spec) Ton NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1,408.00 39.94 64.79 45.75 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 7,409.00 35.61 44.00 44.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 8,817.00 36.30 52.98 44.28 Weighted Average for the Year 8,817.00 36.30 52.98 44.28 304-09102 ABC (RAP) Cubic Yard STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 84.00 8.00 48.00 43.99 Weighted Average for the Second Quarter 84.00 8.00 48.00 43.99 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 730.00 36.80 47.33 47.33 Weighted Average for the Third Quarter 730.00 36.80 47.33 47.33 Weighted Average for the Year 814.00 33.83 47.50 46.99 306-01000 Reconditioning Sq Yard NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 24,256.00 3.00 3.14 4.50 Weighted Average for the First Quarter 24,256.00 3.00 3.14 4.50 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 27,400.00 4.00 2.80 2.80 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 26,880.00 9.02 9.02 9.02 Weighted Average for the Second Quarter 54,280.00 6.49 5.88 5.88 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 277.00 11.39 20.00 20.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 148.00 40.39 39.00 30.00 Weighted Average for the Third Quarter 425.00 21.48 27.61 23.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 306-01000 Reconditioning Sq Yard NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 2,144.00 8.69 12.00 10.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 4,233.00 4.00 11.67 16.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 898.00 5.58 5.73 4.00 Weighted Average for the Fourth Quarter 7,275.00 5.58 10.00 12.75 Weighted Average for the Year 86,236.00 5.50 5.33 6.16 310-00608 Full Depth Reclam. of HMA Pvmt (0-8 in.) Sq Yard NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 7,492.00 6.00 7.13 7.25 Weighted Average for the First Quarter 7,492.00 6.00 7.13 7.25 Weighted Average for the Year 7,492.00 6.00 7.13 7.25 310-00610 Full Depth Reclam. of HMA Pvmt (8-12 in) Sq Yard STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 8,267.00 4.00 11.99 20.00 Weighted Average for the Fourth Quarter 8,267.00 4.00 11.99 20.00 Weighted Average for the Year 8,267.00 4.00 11.99 20.00 403-00720 HMA (Patching) (Asph) Ton NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 400.00 300.00 274.36 190.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 153.64 400.00 630.11 300.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 403-00720 HMA (Patching) (Asph) Ton STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 9.00 800.00 808.62 900.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 72.00 300.00 311.17 270.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 157.00 400.00 442.41 320.00 BR0761-249 I-76 02/27/25 253.00 300.00 318.85 315.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 88.00 400.00 616.85 537.50 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 100.00 314.72 342.60 375.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 138.60 400.00 273.00 221.00 Weighted Average for the First Quarter 1,371.24 343.53 399.44 288.06 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 500.00 275.00 276.50 276.50 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 809.00 344.69 342.16 342.16 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 53.00 500.00 1048.75 894.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 199.00 285.00 446.71 220.14 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 595.00 107.91 107.91 107.91 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 4.00 508.35 3116.67 650.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 423.84 350.00 248.32 260.00 Weighted Average for the Second Quarter 2,583.84 276.39 322.75 264.43 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 421.00 357.58 357.58 357.58 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 44.00 380.00 650.00 650.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 448.00 247.49 305.50 282.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 31.50 508.30 508.29 508.29 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 45.00 435.97 571.00 600.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 657.00 121.00 454.80 300.59 293.40 233.13 289.00 200.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,985.00 263.00 237.54 237.54 Weighted Average for the Third Quarter 3,752.50 312.06 289.33 275.57 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 21.39 360.08 503.66 275.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 403-00720 HMA (Patching) (Asph) Ton NHPPR500-227 REGION 5 SECTION 7 10/23/25 575.00 400.00 450.72 255.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 58.60 300.00 865.46 800.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 141.00 500.00 378.83 370.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 595.00 238.07 232.48 227.05 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 500.00 300.00 217.50 175.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 90.46 300.00 220.04 250.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 250.00 287.87 238.50 272.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 540.00 223.78 272.04 235.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,744.00 220.75 283.16 190.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 100.00 250.00 314.00 268.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 100.00 300.00 263.50 277.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 320.00 311.52 265.00 265.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 405.00 275.00 233.00 240.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 115.82 400.00 277.75 211.50 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 530.00 250.00 556.55 616.74 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 10.00 700.00 407.00 340.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 468.75 280.35 204.75 250.00 Weighted Average for the Fourth Quarter 6,565.02 275.05 320.77 263.74 Weighted Average for the Year 14,272.60 291.60 325.33 269.31 403-00721 HMA (Patching) (Asph) Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 12.00 297.97 448.50 371.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 828.00 160.00 53.50 40.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,082.00 300.00 438.52 299.80 Weighted Average for the First Quarter 1,922.00 239.68 333.35 188.32 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 29.00 150.00 880.00 880.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 3.00 150.26 640.00 950.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 32.00 150.02 798.18 886.56 CR400-406 REGION-WIDE 07/17/25 49.00 253.26 357.83 423.50 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 54.00 235.00 270.00 215.00 Weighted Average for the Third Quarter 103.00 243.69 305.57 314.19 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 108.00 200.00 155.05 145.20 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 100.00 98.30 200.99 210.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 863.00 200.00 399.91 330.52 Weighted Average for the Fourth Quarter 1,071.00 190.50 345.73 300.58 Weighted Average for the Year 3,128.00 222.05 338.69 238.05 403-00800 Emerg Pothole Rep Ton NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 100.00 656.29 537.62 530.75 Weighted Average for the First Quarter 100.00 656.29 537.62 530.75 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 3.00 1385.96 6160.36 1741.44 Weighted Average for the Third Quarter 3.00 1385.96 6160.36 1741.44 Weighted Average for the Year 103.00 677.54 701.39 566.01 403-09221 SMA (Fibers)(Asph) Ton NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 28,926.00 150.13 138.92 134.90 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 28,926.00 150.13 138.92 134.90 NHPP0703-517 FBR0703-534 NHPP2254-095 I-70 TOP OF I-70 I-225 @ 2ND FLOYD HILL TO VET 04/11/25 AND 6TH AVES 05/22/25 35,363.00 1,361.46 205.37 185.00 205.30 223.00 205.30 221.00 Weighted Average for the Second Quarter 36,724.46 204.62 207.13 205.88 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 5,379.00 150.00 212.00 212.00 Weighted Average for the Third Quarter 5,379.00 150.00 212.00 212.00 Weighted Average for the Year 71,029.46 178.29 162.35 177.44 403-09551 Place HMA Hour STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 50.00 200.00 1056.25 451.50 Weighted Average for the Fourth Quarter 50.00 200.00 1056.25 451.50 Weighted Average for the Year 50.00 200.00 1056.25 451.50 403-33841 HMA (Gr S) (100) (PG 64-22) Ton NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1,869.00 134.40 219.49 244.50 Weighted Average for the First Quarter 1,869.00 134.40 219.49 244.50 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 36,480.00 144.59 144.11 144.11 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 5,510.00 101.08 101.08 101.08 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 41,990.00 138.88 138.46 138.46 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4,657.00 118.31 126.40 126.40 Weighted Average for the Third Quarter 4,657.00 118.31 126.40 126.40 Weighted Average for the Year 48,516.00 136.73 146.08 141.39 403-33851 HMA (Gr S) (100) (PG 64-28) Ton NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 959.00 163.52 166.89 166.89 FBR0703-534 I-70 Weighted Average for the Second Quarter 959.00 163.52 166.89 166.89 Weighted Average for the Year 959.00 163.52 166.89 166.89 403-34601 HMA (Gr SX) (50) Ton NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 14,332.30 90.00 94.35 83.70 Weighted Average for the Fourth Quarter 14,332.30 90.00 94.35 83.70 Weighted Average for the Year 14,332.30 90.00 94.35 83.70 403-34701 HMA (Gr SX) (75) Ton NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 11,568.00 130.00 126.00 135.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 27,069.62 85.00 94.75 94.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 38,637.62 98.47 104.11 106.63 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 674.78 287.30 287.30 287.30 Weighted Average for the Third Quarter 674.78 287.30 287.30 287.30 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 32,193.00 100.00 102.00 96.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 227.60 200.00 376.00 240.00 Weighted Average for the Fourth Quarter 32,420.60 100.70 106.76 97.01 Weighted Average for the Year 71,733.00 101.26 106.18 103.98 403-34721 HMA (Gr SX) (75) (PG 58-28) Ton NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 30,062.00 105.00 137.32 127.57 Weighted Average for the First Quarter 30,062.00 105.00 137.32 127.57 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 7,887.98 150.00 140.78 125.00 Weighted Average for the Third Quarter 7,887.98 150.00 140.78 125.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 8,925.83 180.00 207.18 149.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2,534.70 135.00 100.13 101.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 16,882.00 150.08 143.50 127.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 25,980.38 130.00 115.82 110.63 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 293.00 120.00 188.66 140.00 Weighted Average for the Fourth Quarter 54,615.91 144.56 152.48 121.70 Weighted Average for the Year 92,565.89 132.17 144.46 123.89 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 403-34731 HMA (Gr SX) (75) (PG 58-34) Ton NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 19,209.00 131.43 180.26 133.05 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 24,047.00 156.30 170.00 170.00 Weighted Average for the Fourth Quarter 43,256.00 145.26 177.82 153.59 Weighted Average for the Year 43,256.00 145.26 177.82 153.59 403-34741 HMA (Gr SX) (75) (PG 64-22) Ton NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 11,326.00 118.29 115.87 115.87 Weighted Average for the Third Quarter 11,326.00 118.29 115.87 115.87 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 17,736.00 115.00 158.30 170.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 172.00 241.02 213.59 225.60 Weighted Average for the Fourth Quarter 17,908.00 116.21 159.35 170.53 Weighted Average for the Year 29,234.00 117.02 154.51 149.36 403-34751 HMA (Gr SX) (75) (PG 64-28) Ton STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 15,698.00 135.00 130.50 130.50 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 229.00 285.00 256.03 260.09 Weighted Average for the Second Quarter 15,927.00 137.16 135.76 132.36 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,176.00 235.83 232.82 232.82 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 1,176.00 235.83 232.82 232.82 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 44,302.00 110.00 102.70 102.85 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 7,469.00 130.00 181.24 175.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 480.00 213.02 209.65 204.30 Weighted Average for the Fourth Quarter 52,251.00 113.81 129.06 114.10 Weighted Average for the Year 69,354.00 121.24 130.62 120.30 403-34771 HMA (Gr SX) (75) (PG 76-28) Ton ER060A-028 CO 60 (MP 9-10) 06/18/25 784.00 190.00 222.50 170.00 Weighted Average for the Second Quarter 784.00 190.00 222.50 170.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 3,622.37 180.00 152.78 137.00 Weighted Average for the Third Quarter 3,622.37 180.00 152.78 137.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 42,250.13 135.00 116.82 116.50 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 72,727.49 115.00 96.17 91.25 Weighted Average for the Fourth Quarter 114,977.62 122.35 101.93 100.53 Weighted Average for the Year 119,383.99 124.54 106.92 102.09 403-34801 HMA (Gr SX) (100) Ton NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1,322.98 175.00 176.48 190.00 Weighted Average for the Second Quarter 1,322.98 175.00 176.48 190.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 403-34801 HMA (Gr SX) (100) Ton NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,097.30 110.00 275.70 217.80 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,335.00 100.00 218.67 200.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 14,704.20 85.00 91.35 84.70 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 13,570.67 85.00 104.37 108.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 60,020.00 80.00 107.00 104.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 40,861.30 85.00 81.03 82.75 Weighted Average for the Fourth Quarter 131,588.47 83.08 103.29 97.58 Weighted Average for the Year 132,911.45 84.00 104.63 98.50 403-34841 HMA (Gr SX) (100) (PG 64-22) Ton NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 538.66 160.00 137.00 136.00 Weighted Average for the Second Quarter 538.66 160.00 137.00 136.00 Weighted Average for the Year 538.66 160.00 137.00 136.00 403-34851 HMA (Gr SX) (100) (PG 64-28) Ton NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 6,462.00 140.00 120.66 121.50 BR0761-249 I-76 02/27/25 1,162.00 221.08 181.31 120.00 Weighted Average for the First Quarter 7,624.00 152.36 133.54 121.27 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 2,889.00 125.00 107.33 111.00 Weighted Average for the Second Quarter 2,889.00 125.00 107.33 111.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 403-34851 HMA (Gr SX) (100) (PG 64-28) Ton STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,514.00 155.14 159.89 159.89 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 454.00 175.96 173.27 173.27 Weighted Average for the Third Quarter 1,968.00 159.94 162.98 162.98 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 39,961.00 119.94 115.29 96.50 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 449.00 250.00 1.14 2.42 Weighted Average for the Fourth Quarter 40,410.00 121.39 114.52 95.45 Weighted Average for the Year 52,891.00 127.49 117.21 102.54 403-34871 HMA (Gr SX) (100) (PG 76-28) Ton NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 38,248.00 120.00 106.55 84.60 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 15,416.00 130.00 123.99 127.00 Weighted Average for the First Quarter 53,664.00 122.87 112.64 96.78 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3,394.00 136.21 136.21 136.21 Weighted Average for the Second Quarter 3,394.00 136.21 136.21 136.21 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 50.00 262.28 446.67 385.00 Weighted Average for the Fourth Quarter 50.00 262.28 446.67 385.00 Weighted Average for the Year 57,108.00 123.79 113.37 99.38 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 403-36621 HMA (Gr ST)(50)(PG 58-28) Ton STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 10,976.00 160.00 144.50 134.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 14,583.24 130.00 125.75 116.49 Weighted Average for the Fourth Quarter 25,559.24 142.88 133.80 124.01 Weighted Average for the Year 25,559.24 142.88 133.80 124.01 403-36701 HMA (Gr ST)(75) Ton STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 14,549.07 125.00 94.95 94.90 Weighted Average for the First Quarter 14,549.07 125.00 94.95 94.90 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 14,717.10 100.00 87.15 80.30 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 217.21 180.00 290.56 210.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 5,569.00 100.00 110.00 113.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 293.00 100.00 167.00 169.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 22,082.00 80.00 101.00 94.00 Weighted Average for the Fourth Quarter 42,878.31 90.11 99.31 92.87 Weighted Average for the Year 57,427.38 98.95 98.21 93.38 403-36721 HMA (Gr ST)(75)(PG 58-28) Ton NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 13,753.00 164.21 175.25 122.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 13,591.00 153.09 145.00 145.00 Weighted Average for the Fourth Quarter 27,344.00 158.69 169.26 133.43 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 27,344.00 158.69 169.26 133.43 408-01000 Hot Joint-Crack Sealant Ton STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 4.00 8000.00 6721.67 7665.00 Weighted Average for the Fourth Quarter 4.00 8000.00 6721.67 7665.00 Weighted Average for the Year 4.00 8000.00 6721.67 7665.00 408-01100 Joint Sealant Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 514.00 25.00 43.09 53.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 340.00 14.43 25.35 15.90 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 160.00 36.00 25.65 28.30 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 96.00 50.00 75.38 100.00 Weighted Average for the First Quarter 1,110.00 25.51 35.50 42.14 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,048.00 19.90 37.95 37.95 FBR0703-534 I-70 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 532.00 25.90 30.67 35.00 Weighted Average for the Second Quarter 1,580.00 21.92 33.55 36.96 CR400-406 REGION-WIDE 07/17/25 684.00 18.58 30.00 35.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 150.00 27.65 53.02 10.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 378.00 49.87 45.25 45.25 Weighted Average for the Third Quarter 1,212.00 29.46 37.24 35.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 408-01100 Joint Sealant Lin Foot NHPPR500-227 REGION 5 SECTION 7 10/23/25 418.00 40.00 35.74 25.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 934.00 32.00 31.04 12.10 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 80.00 57.80 33.52 30.30 Weighted Average for the Fourth Quarter 1,432.00 35.78 32.90 16.88 Weighted Average for the Year 5,334.00 28.10 34.65 32.22 411-03342 Asph Cem (PG 64-28) Ton NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 79.38 1500.00 664.95 690.00 Weighted Average for the Second Quarter 79.38 1500.00 664.95 690.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 40.49 928.20 928.19 928.19 Weighted Average for the Third Quarter 40.49 928.20 928.19 928.19 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,030.20 650.00 496.00 592.00 Weighted Average for the Fourth Quarter 1,030.20 650.00 496.00 592.00 Weighted Average for the Year 1,150.07 718.46 525.42 610.60 411-03345 Asph Cem (PG 76-28) Ton NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 21.82 700.00 821.97 949.87 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 61.00 800.00 830.00 690.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 809.20 650.00 553.50 657.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 831.73 760.00 597.86 450.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 411-03345 Asph Cem (PG 76-28) Ton NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 3,640.00 800.00 499.50 574.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2,533.00 800.00 547.00 500.00 Weighted Average for the Fourth Quarter 7,896.75 780.14 542.22 547.64 Weighted Average for the Year 7,896.75 780.14 542.22 547.64 411-03346 Asph Cem (PG 76-34) Ton NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 932.20 850.00 696.00 692.00 Weighted Average for the Fourth Quarter 932.20 850.00 696.00 692.00 Weighted Average for the Year 932.20 850.00 696.00 692.00 411-03352 Asph Cem (PG 58-28) Ton NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 650.00 650.00 435.00 400.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 989.34 600.00 500.00 550.00 Weighted Average for the First Quarter 1,639.34 619.83 474.23 490.52 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 352.00 600.00 418.00 436.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1,502.00 700.00 376.50 325.00 Weighted Average for the Fourth Quarter 1,854.00 681.01 384.38 346.07 Weighted Average for the Year 3,493.34 652.30 426.54 413.86 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 411-03354 Asph Cem (PG 64-22) Ton STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1,625.94 650.00 495.00 540.00 Weighted Average for the First Quarter 1,625.94 650.00 495.00 540.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 44.02 600.00 584.94 695.77 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 25.00 650.00 646.67 500.00 Weighted Average for the Fourth Quarter 69.02 618.11 613.34 624.86 Weighted Average for the Year 1,694.96 648.70 505.78 543.46 411-03355 Asph Cem (PG 58-34) Ton NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1,938.00 750.00 454.00 375.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 13.60 2500.00 1008.00 750.00 Weighted Average for the Fourth Quarter 1,951.60 762.20 463.55 377.61 Weighted Average for the Year 1,951.60 762.20 463.55 377.61 411-10255 Emul Asph (SS) Gallon NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 12,546.00 4.00 4.55 5.30 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 7,313.00 5.00 4.30 5.50 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 1,092.00 9.45 8.75 16.50 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 7,710.00 6.05 4.80 4.10 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 26,784.00 5.00 4.25 3.00 Weighted Average for the First Quarter 55,445.00 5.01 4.51 4.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 411-10255 Emul Asph (SS) Gallon NHPP0703-517 FBR0703-534 STAR500-223 I-70 I-70 SH50 TOP OF FLOYD HILL TO VET MM 189.71, US550 MM 98.3 04/11/25 05/01/25 5,846.00 24.00 6.14 5.00 6.34 117.88 6.34 8.50 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3,821.00 6.05 6.05 6.05 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 460.00 13.00 3.95 3.00 Weighted Average for the Second Quarter 10,151.00 6.41 6.79 6.08 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 4,202.00 7.30 4.50 4.50 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 117.00 6.63 6.63 6.63 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 7,645.00 6.26 5.63 4.25 Weighted Average for the Third Quarter 11,964.00 6.63 5.56 4.36 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 599.00 2.75 3.50 3.63 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 21,962.00 5.69 5.12 5.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2,329.00 10.00 6.67 5.50 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 527.00 6.00 4.54 3.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 15,083.00 7.00 6.52 9.15 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 17,028.00 5.03 5.25 5.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 14,917.00 5.00 4.21 5.50 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 28,369.00 5.09 4.22 2.93 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 13,717.00 3.54 4.62 5.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 13,694.00 5.77 4.59 6.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 24,873.10 5.00 4.25 3.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 6,006.00 5.00 4.25 5.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 33,881.00 4.50 4.33 3.15 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 21,883.00 6.27 5.50 5.50 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 39,617.00 4.00 2.95 2.75 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 18,608.00 4.00 3.53 4.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 186.00 11.06 6.98 5.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 83.90 25.00 6.40 5.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 31,350.00 4.60 5.56 3.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 304,713.00 4.98 4.62 4.34 Weighted Average for the Year 382,273.00 5.07 4.70 4.37 412-00000 Furn Conc Pvmt Cubic Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 35.00 231.51 453.95 453.95 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 17.00 152.05 152.30 152.30 Weighted Average for the Third Quarter 52.00 205.53 355.33 355.33 Weighted Average for the Year 52.00 205.53 355.33 355.33 412-00190 Conc Pvmt (Patching) Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 317.00 350.00 87.27 88.30 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 224.00 283.18 173.58 114.48 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 211.00 250.00 101.69 115.00 Weighted Average for the First Quarter 752.00 302.04 128.10 103.59 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 207.00 144.42 230.50 250.00 Weighted Average for the Third Quarter 207.00 144.42 230.50 250.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 160.00 160.00 223.17 294.50 Weighted Average for the Fourth Quarter 160.00 160.00 223.17 294.50 Weighted Average for the Year 1,119.00 252.57 161.84 157.97 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 412-00600 Conc Pvmt (6 In) Sq Yard STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 109.00 150.00 131.50 131.50 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 57.00 137.45 142.10 142.10 Weighted Average for the Second Quarter 166.00 145.69 135.14 135.14 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 783.00 80.00 102.43 95.72 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 144.00 150.00 114.67 92.00 Weighted Average for the Fourth Quarter 927.00 90.87 105.08 95.14 Weighted Average for the Year 1,093.00 99.20 106.27 101.22 412-00605 Conc Pvmt (6 In) (Fast Track) Sq Yard NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 186.00 250.00 143.50 134.00 Weighted Average for the Fourth Quarter 186.00 250.00 143.50 134.00 STMM153-003 412-00700 Weighted Average for the Year Conc Pvmt (7 In) CO 17 & SOUTH OF CO 14 05/08/25 186.00 Sq Yard 35,373.00 250.00 87.00 143.50 71.82 134.00 56.46 Weighted Average for the Second Quarter 35,373.00 87.00 71.82 56.46 Weighted Average for the Year 35,373.00 87.00 71.82 56.46 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 412-00800 Conc Pvmt (8 In) Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 57.00 130.07 115.15 86.92 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 22.00 200.00 140.60 117.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 21.00 37.00 390.77 112.36 Weighted Average for the First Quarter 100.00 125.91 162.66 98.88 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 142.00 131.48 131.48 131.48 Weighted Average for the Second Quarter 142.00 131.48 131.48 131.48 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 195,580.00 53.00 63.67 56.84 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1,135.00 107.06 177.67 175.00 Weighted Average for the Fourth Quarter 196,715.00 53.31 64.07 57.52 Weighted Average for the Year 196,957.00 53.41 64.14 57.60 412-00801 Conc Pvmt (8 In) (Spec) Sq Yard STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 108.00 200.00 143.50 143.50 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 856.00 209.17 216.25 216.25 Weighted Average for the Second Quarter 964.00 208.14 208.10 208.10 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,038.00 177.03 177.33 177.33 Weighted Average for the Third Quarter 1,038.00 177.03 177.33 177.33 Weighted Average for the Year 2,002.00 192.01 192.15 192.15 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 412-00805 Conc Pvmt (8 In) (Fast Track) Sq Yard NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 78.00 150.00 126.16 135.00 Weighted Average for the First Quarter 78.00 150.00 126.16 135.00 Weighted Average for the Year 78.00 150.00 126.16 135.00 412-00850 Conc Pvmt (8-1/2 In) Sq Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 117.00 203.19 228.60 228.60 FBR0703-534 I-70 Weighted Average for the Second Quarter 117.00 203.19 228.60 228.60 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10,269.00 109.64 108.79 108.79 Weighted Average for the Third Quarter 10,269.00 109.64 108.79 108.79 Weighted Average for the Year 10,386.00 110.69 110.14 110.14 412-00900 Conc Pvmt (9 In) Sq Yard C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6,216.00 170.00 147.67 158.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,373.00 199.62 146.74 125.00 Weighted Average for the Fourth Quarter 7,589.00 175.36 147.52 152.03 Weighted Average for the Year 7,589.00 175.36 147.52 152.03 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 412-00950 Conc Pvmt (9-1/2 In) Sq Yard NHPP1602-194 US 160 MP 174.1 12/11/25 26.00 150.00 1262.14 1300.00 Weighted Average for the Fourth Quarter 26.00 150.00 1262.14 1300.00 Weighted Average for the Year 26.00 150.00 1262.14 1300.00 412-01000 Conc Pvmt (10 In) Sq Yard SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 57.00 172.66 174.00 235.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 148.00 180.00 244.00 235.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 213,213.00 66.30 66.03 66.03 Weighted Average for the Third Quarter 213,418.00 66.41 66.76 66.19 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,531.00 200.00 146.66 128.63 Weighted Average for the Fourth Quarter 1,531.00 200.00 146.66 128.63 Weighted Average for the Year 214,949.00 67.36 68.98 66.64 412-01001 Conc Pvmt (10 In) (Spec) Sq Yard C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 399.00 260.00 215.17 215.00 Weighted Average for the Fourth Quarter 399.00 260.00 215.17 215.00 Weighted Average for the Year 399.00 260.00 215.17 215.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 412-01020 Conc Pvmt (10 In) (Fast Track) Sq Yard C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 56.00 120.00 155.15 140.00 Weighted Average for the Fourth Quarter 56.00 120.00 155.15 140.00 Weighted Average for the Year 56.00 120.00 155.15 140.00 412-01050 Conc Pvmt (10-1/2 In) Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3,961.00 120.00 143.47 137.80 Weighted Average for the First Quarter 3,961.00 120.00 143.47 137.80 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,493.00 136.10 136.10 136.10 Weighted Average for the Third Quarter 1,493.00 136.10 136.10 136.10 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 10,224.00 210.00 149.11 113.42 Weighted Average for the Fourth Quarter 10,224.00 210.00 149.11 113.42 Weighted Average for the Year 15,678.00 180.22 146.79 121.74 412-01060 Conc Pvmt (10-1/2 In) (Fast Track) Sq Yard NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,720.00 100.00 195.84 133.37 Weighted Average for the Fourth Quarter 1,720.00 100.00 195.84 133.37 Weighted Average for the Year 1,720.00 100.00 195.84 133.37 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 412-01100 Conc Pvmt (11 In) Sq Yard BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 7,500.00 105.04 128.94 112.75 Weighted Average for the Third Quarter 7,500.00 105.04 128.94 112.75 Weighted Average for the Year 7,500.00 105.04 128.94 112.75 412-01200 Conc Pvmt (12 In) Sq Yard NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 22,855.00 55.00 85.86 80.50 Weighted Average for the Fourth Quarter 22,855.00 55.00 85.86 80.50 Weighted Average for the Year 22,855.00 55.00 85.86 80.50 412-01250 Conc Pvmt (12-1/2 In) Sq Yard NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 1,913.00 300.00 218.44 151.00 Weighted Average for the Fourth Quarter 1,913.00 300.00 218.44 151.00 NHPP0253-302 412-01300 Weighted Average for the Year Conc Pvmt (13 In) I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,913.00 Sq Yard 13,668.00 300.00 93.29 218.44 92.47 151.00 92.47 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 13,668.00 93.29 92.47 92.47 Weighted Average for the Year 13,668.00 93.29 92.47 92.47 412-02000 Conc SafetyEdge Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 53,395.00 4.34 4.35 4.35 Weighted Average for the Third Quarter 53,395.00 4.34 4.35 4.35 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 100,726.00 3.02 3.00 2.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 707.00 10.33 29.50 49.50 Weighted Average for the Fourth Quarter 101,433.00 3.07 3.11 2.33 Weighted Average for the Year 154,828.00 3.51 3.23 3.03 412-04998 Replace Conc Pvmt (PRS) Sq Yard NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 155.00 850.00 1587.00 1161.00 Weighted Average for the Second Quarter 155.00 850.00 1587.00 1161.00 Weighted Average for the Year 155.00 850.00 1587.00 1161.00 412-04999 Replace Conc Pvmt Sq Yard STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 7.50 300.00 534.00 418.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 7.50 300.00 534.00 418.00 Weighted Average for the Year 7.50 300.00 534.00 418.00 412-05000 Partial Depth Repair of Conc Pvmt Sq Foot NHPP1602-194 US 160 MP 174.1 12/11/25 58.00 50.00 777.44 260.00 Weighted Average for the Fourth Quarter 58.00 50.00 777.44 260.00 Weighted Average for the Year 58.00 50.00 777.44 260.00 412-05002 Full Depth Repair of Conc Pavement Sq Foot STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 38,096.00 20.00 29.95 25.85 Weighted Average for the Fourth Quarter 38,096.00 20.00 29.95 25.85 Weighted Average for the Year 38,096.00 20.00 29.95 25.85 412-05100 Poly Slab Jacking Pound BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 1,000.00 20.00 19.89 18.09 Weighted Average for the First Quarter 1,000.00 20.00 19.89 18.09 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1,270.00 100.00 12.45 12.40 Weighted Average for the Fourth Quarter 1,270.00 100.00 12.45 12.40 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2,270.00 64.76 17.00 14.91 412-14000 Sawing and Sealing Joints Lin Foot STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 134,799.00 2.65 1.97 1.95 NHPP1602-194 US 160 MP 174.1 12/11/25 10,701.00 5.00 11.30 5.00 Weighted Average for the Fourth Quarter 145,500.00 2.82 2.86 2.17 Weighted Average for the Year 145,500.00 2.82 2.86 2.17 412-15000 Routing and Sealing Cracks Lin Foot NHPP1602-194 US 160 MP 174.1 12/11/25 178.00 65.00 46.24 81.00 Weighted Average for the Fourth Quarter 178.00 65.00 46.24 81.00 Weighted Average for the Year 178.00 65.00 46.24 81.00 420-00000 Geomembrane Sq Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 26,415.00 15.73 9.97 9.97 FBR0703-534 I-70 Weighted Average for the Second Quarter 26,415.00 15.73 9.97 9.97 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 303.00 14.62 23.75 23.75 Weighted Average for the Third Quarter 303.00 14.62 23.75 23.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 26,718.00 15.72 10.13 10.13 420-00102 Geotextile (Er Cont) (CL 1) Sq Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1,125.00 5.00 12.53 15.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 397.00 10.80 22.61 5.10 Weighted Average for the First Quarter 1,522.00 6.51 15.16 12.42 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 79.00 22.84 25.95 25.95 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1,023.00 23.32 24.76 24.76 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 47.00 3,493.00 15.00 11.33 24.28 11.58 11.00 11.58 Weighted Average for the Third Quarter 4,642.00 14.21 15.22 14.72 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 56.00 15.06 85.10 35.25 Weighted Average for the Fourth Quarter 56.00 15.06 85.10 35.25 Weighted Average for the Year 6,220.00 12.33 16.93 14.34 420-00112 Geotextile (Drain) (CL 1) Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 66.00 13.25 11.16 10.60 Weighted Average for the First Quarter 66.00 13.25 11.16 10.60 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 19,039.00 11.87 10.23 10.23 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 19,039.00 11.87 10.23 10.23 CR400-406 REGION-WIDE 07/17/25 29.00 17.51 32.67 55.00 Weighted Average for the Third Quarter 29.00 17.51 32.67 55.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2,175.00 35.00 11.50 10.25 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 378.00 16.19 5.01 4.65 Weighted Average for the Fourth Quarter 2,553.00 32.21 8.48 9.42 Weighted Average for the Year 21,687.00 14.28 9.80 10.20 420-00113 Geotextile (Drain) (CL 2) Sq Yard NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 852.00 4.00 10.29 15.00 Weighted Average for the Second Quarter 852.00 4.00 10.29 15.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 2,350.00 2.90 4.47 3.00 Weighted Average for the Third Quarter 2,350.00 2.90 4.47 3.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,100.00 6.00 4.71 3.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 507.00 6.00 22.57 42.35 Weighted Average for the Fourth Quarter 1,607.00 6.00 8.05 15.41 Weighted Average for the Year 4,809.00 4.13 6.08 9.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 420-00114 Geotextile (Drain) (CL 3) Sq Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 47.00 11.92 36.14 36.14 FBR0703-534 I-70 Weighted Average for the Second Quarter 47.00 11.92 36.14 36.14 Weighted Average for the Year 47.00 11.92 36.14 36.14 420-00132 Geotextile (Separator) (CL 1) Sq Yard NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 926.00 3.50 11.77 15.00 Weighted Average for the Second Quarter 926.00 3.50 11.77 15.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 500.00 26.79 18.93 18.93 Weighted Average for the Third Quarter 500.00 26.79 18.93 18.93 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,181.00 6.21 4.28 3.75 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,805.00 2.00 4.85 8.00 Weighted Average for the Fourth Quarter 2,986.00 3.67 4.62 6.32 Weighted Average for the Year 4,412.00 6.25 7.93 9.57 420-00133 Geotextile (Separator) (CL 2) Sq Yard STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,841.00 5.00 7.98 8.50 Weighted Average for the Fourth Quarter 1,841.00 5.00 7.98 8.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 1,841.00 5.00 7.98 8.50 420-00300 Geotextile (Reinforcement) Sq Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2,200.00 11.87 6.95 6.95 FBR0703-534 I-70 Weighted Average for the Second Quarter 2,200.00 11.87 6.95 6.95 Weighted Average for the Year 2,200.00 11.87 6.95 6.95 420-00520 Geogrid Pvmt Reinf Sq Yard STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 161.00 45.00 12.88 9.50 Weighted Average for the Second Quarter 161.00 45.00 12.88 9.50 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 603.00 12.00 9.82 4.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 56,574.00 3.34 2.93 2.93 Weighted Average for the Third Quarter 57,177.00 3.43 3.28 2.94 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1,934.00 9.38 6.50 6.50 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1,469.00 15.00 5.13 5.72 Weighted Average for the Fourth Quarter 3,403.00 11.81 5.55 6.16 Weighted Average for the Year 60,741.00 4.01 3.59 3.14 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0701-260 420-00526 Cellular Geogrid I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 Sq Yard 1,805.00 4.00 6.85 8.00 Weighted Average for the Fourth Quarter 1,805.00 4.00 6.85 8.00 Weighted Average for the Year 1,805.00 4.00 6.85 8.00 501-00000 Steel Sheet Pile (Ty I) Sq Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 594.00 80.00 112.43 114.95 Weighted Average for the Fourth Quarter 594.00 80.00 112.43 114.95 Weighted Average for the Year 594.00 80.00 112.43 114.95 501-00210 Steel Sheet Piling Cap Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 22.00 120.00 1274.18 423.50 Weighted Average for the Fourth Quarter 22.00 120.00 1274.18 423.50 Weighted Average for the Year 22.00 120.00 1274.18 423.50 502-00460 Pile Tip Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 4.00 254.10 742.55 776.00 Weighted Average for the Second Quarter 4.00 254.10 742.55 776.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 502-00460 Pile Tip Each FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 18.00 1611.53 664.35 664.35 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 194.00 136.90 136.90 136.90 Weighted Average for the Third Quarter 212.00 262.10 181.68 181.68 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 14.00 261.71 357.24 207.25 Weighted Average for the Fourth Quarter 14.00 261.71 357.24 207.25 Weighted Average for the Year 230.00 261.94 277.91 193.58 502-00500 CJP Splice Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 4.00 1004.36 2056.69 1695.00 Weighted Average for the Second Quarter 4.00 1004.36 2056.69 1695.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 14.00 775.60 1782.38 1782.38 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 17.00 1042.94 1329.62 1329.62 Weighted Average for the Third Quarter 31.00 922.21 1534.09 1534.09 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 1198.59 3478.75 3835.00 Weighted Average for the Fourth Quarter 1.00 1198.59 3478.75 3835.00 Weighted Average for the Year 36.00 939.01 2024.23 1615.89 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 502-01120 Restriking Pile Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 1133.34 920.46 920.46 Weighted Average for the Third Quarter 4.00 1133.34 920.46 920.46 Weighted Average for the Year 4.00 1133.34 920.46 920.46 502-02010 Dynamic Pile Test Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 2.00 3870.81 4547.90 5000.00 Weighted Average for the Second Quarter 2.00 3870.81 4547.90 5000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10.00 3745.00 3745.00 3745.00 Weighted Average for the Third Quarter 10.00 3745.00 3745.00 3745.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2.00 4500.00 4173.04 4430.00 Weighted Average for the Fourth Quarter 2.00 4500.00 4173.04 4430.00 Weighted Average for the Year 14.00 3870.83 4159.74 4022.14 502-11274 Steel Pile (HP 12x74) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3,238.00 136.03 129.41 129.41 Weighted Average for the Third Quarter 3,238.00 136.03 129.41 129.41 Weighted Average for the Year 3,238.00 136.03 129.41 129.41 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid C0405-042 502-11489 Steel Pile (HP 14x89) US 40 IN DEER TRAIL, PINE ST 06/05/25 Lin Foot 181.00 80.00 206.30 204.87 Weighted Average for the Second Quarter 181.00 80.00 206.30 204.87 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 848.00 289.26 243.74 243.74 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4,226.00 144.96 143.90 143.90 Weighted Average for the Third Quarter 5,074.00 169.08 160.59 160.59 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 797.00 168.23 158.15 150.00 Weighted Average for the Fourth Quarter 797.00 168.23 158.15 150.00 Weighted Average for the Year 6,052.00 166.30 162.16 160.52 502-14117 Steel Pile (HP 14x117) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 971.00 155.33 175.38 175.38 Weighted Average for the Third Quarter 971.00 155.33 175.38 175.38 Weighted Average for the Year 971.00 155.33 175.38 175.38 503-00000 Ground Improvement Sq Foot NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 15,806.00 185.00 127.00 124.00 Weighted Average for the Fourth Quarter 15,806.00 185.00 127.00 124.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 15,806.00 185.00 127.00 124.00 503-00018 Drilled Shaft (18 In) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 35.00 350.00 430.94 264.90 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 128.00 309.10 178.22 121.30 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 45.00 500.00 491.67 400.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 6.00 350.00 432.28 605.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 10.00 227.97 1158.84 1020.20 Weighted Average for the First Quarter 224.00 351.32 286.36 252.81 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 5.00 25.00 871.03 432.20 843.26 432.20 843.26 432.20 Weighted Average for the Second Quarter 30.00 505.34 500.71 500.71 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 25.00 497.25 497.25 497.25 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 95.00 365.48 401.00 380.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 6.00 369.78 349.39 349.39 Weighted Average for the Third Quarter 126.00 391.83 406.10 401.81 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 35.00 320.00 567.09 482.00 Weighted Average for the Fourth Quarter 35.00 320.00 567.09 482.00 Weighted Average for the Year 415.00 372.11 343.38 335.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 503-00024 Drilled Shaft (24 In) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 24.00 450.00 608.89 661.70 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,549.00 300.00 200.20 132.19 Weighted Average for the First Quarter 1,573.00 302.29 203.34 140.27 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 10.00 871.21 843.26 843.26 FBR0703-534 I-70 ITSSW03-250 FRONT RANGE 06/26/25 24.00 582.61 728.00 1200.00 Weighted Average for the Second Quarter 34.00 667.49 736.87 1095.08 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10.00 574.60 574.60 574.60 Weighted Average for the Third Quarter 10.00 574.60 574.60 574.60 ITSSW03-417 STATEWIDE 12/04/25 792.00 516.00 1055.75 595.00 Weighted Average for the Fourth Quarter 792.00 516.00 1055.75 595.00 Weighted Average for the Year 2,409.00 378.83 422.17 305.05 503-00036 Drilled Shaft (36 In) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 91.00 800.00 994.95 929.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 313.00 320.00 394.47 430.80 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 38.00 900.00 898.33 900.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 76.00 750.00 868.74 961.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 38.00 1244.30 1622.88 1428.28 Weighted Average for the First Quarter 556.00 560.15 611.79 685.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 503-00036 Drilled Shaft (36 In) Lin Foot STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 126.00 803.63 875.00 850.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 2,216.00 18.00 1380.90 709.81 1386.72 709.81 1386.72 709.81 Weighted Average for the Second Quarter 2,360.00 1344.96 1329.95 1352.90 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 164.00 729.73 858.54 858.54 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 13.00 1000.00 842.75 825.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 17.00 743.74 862.50 810.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 76.00 600.00 718.40 805.00 Weighted Average for the Third Quarter 270.00 707.11 777.51 838.80 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 266.00 1200.00 895.20 1001.84 Weighted Average for the Fourth Quarter 266.00 1200.00 895.20 1001.84 Weighted Average for the Year 3,452.00 1157.49 921.78 1178.07 503-00042 Drilled Shaft (42 In) Lin Foot STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 19.00 1000.00 1007.50 900.00 Weighted Average for the First Quarter 19.00 1000.00 1007.50 900.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 874.00 1551.70 1641.64 1641.64 Weighted Average for the Second Quarter 874.00 1551.70 1641.64 1641.64 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 225.00 854.62 872.28 872.28 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 503-00042 Drilled Shaft (42 In) Lin Foot SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 17.00 1200.00 923.75 835.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 36.00 910.62 901.86 901.86 Weighted Average for the Third Quarter 278.00 882.99 886.15 873.83 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 17.00 550.00 1358.75 1153.00 Weighted Average for the Fourth Quarter 17.00 550.00 1358.75 1153.00 Weighted Average for the Year 1,188.00 1372.06 1414.19 1443.11 503-00048 Drilled Shaft (48 In) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 126.00 750.00 1043.83 950.00 Weighted Average for the First Quarter 126.00 750.00 1043.83 950.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 21.00 1061.54 1050.00 900.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 146.00 62.00 2397.91 890.96 2411.23 890.96 2411.23 890.96 Weighted Average for the Second Quarter 229.00 1867.37 1805.52 1861.04 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 66.00 630.00 896.90 1060.00 Weighted Average for the Fourth Quarter 66.00 630.00 896.90 1060.00 Weighted Average for the Year 421.00 1338.97 1268.87 1462.80 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 503-00054 Drilled Shaft (54 In) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 84.00 850.00 1130.46 1050.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 444.00 600.00 671.88 458.26 Weighted Average for the First Quarter 528.00 639.77 711.51 552.40 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 21.00 1011.42 1125.00 950.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 42.00 1152.17 1152.17 1152.17 Weighted Average for the Second Quarter 63.00 1105.25 1138.59 1084.78 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 21.00 1400.00 1113.25 875.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 272.00 1004.43 927.71 927.71 Weighted Average for the Third Quarter 293.00 1032.78 971.49 923.93 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 294.00 817.63 731.77 565.00 Weighted Average for the Fourth Quarter 294.00 817.63 731.77 565.00 Weighted Average for the Year 1,178.00 806.81 741.37 676.43 503-00072 Drilled Shaft (72 In) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3,581.00 3835.46 3704.62 3704.62 FBR0703-534 I-70 Weighted Average for the Second Quarter 3,581.00 3835.46 3704.62 3704.62 Weighted Average for the Year 3,581.00 3835.46 3704.62 3704.62 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 503-00078 Drilled Shaft (78 In) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 1,106.00 4563.22 4531.53 4531.53 Weighted Average for the Second Quarter 1,106.00 4563.22 4531.53 4531.53 Weighted Average for the Year 1,106.00 4563.22 4531.53 4531.53 503-00084 Drilled Shaft (84 In) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 882.00 6499.03 6505.37 6505.37 FBR0703-534 I-70 Weighted Average for the Second Quarter 882.00 6499.03 6505.37 6505.37 Weighted Average for the Year 882.00 6499.03 6505.37 6505.37 503-00096 Drilled Shaft (96 In) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 973.00 8192.47 8111.69 8111.69 FBR0703-534 I-70 Weighted Average for the Second Quarter 973.00 8192.47 8111.69 8111.69 Weighted Average for the Year 973.00 8192.47 8111.69 8111.69 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 503-00310 CSL Testing Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 13.00 2549.10 4297.60 3360.59 Weighted Average for the First Quarter 13.00 2549.10 4297.60 3360.59 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 213.00 2762.50 2706.28 2706.28 Weighted Average for the Second Quarter 213.00 2762.50 2706.28 2706.28 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10.00 2210.00 2210.00 2210.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 3424.00 7944.75 7944.75 Weighted Average for the Third Quarter 14.00 2556.86 3848.50 3848.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 6.00 1955.34 3279.71 3210.00 Weighted Average for the Fourth Quarter 6.00 1955.34 3279.71 3210.00 Weighted Average for the Year 246.00 2719.83 3184.42 2818.15 503-01100 M Pile (10 In) Lin Foot STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 305.00 800.00 772.98 550.00 Weighted Average for the First Quarter 305.00 800.00 772.98 550.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1,383.00 202.40 197.63 197.63 Weighted Average for the Second Quarter 1,383.00 202.40 197.63 197.63 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 1,688.00 310.38 467.29 261.30 503-01120 M Pile (12 In) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 1,753.00 351.79 344.76 344.76 Weighted Average for the Second Quarter 1,753.00 351.79 344.76 344.76 Weighted Average for the Year 1,753.00 351.79 344.76 344.76 503-02000 Verification Test Pile Each STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 15000.00 14248.64 15000.00 Weighted Average for the First Quarter 1.00 15000.00 14248.64 15000.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 16913.26 17106.56 17106.56 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 16913.26 17106.56 17106.56 Weighted Average for the Year 3.00 16275.51 15201.28 16404.37 504-03500 Retaining Wall(Design Build) Sq Foot NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 67.00 300.00 397.50 145.00 Weighted Average for the Fourth Quarter 67.00 300.00 397.50 145.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 67.00 300.00 397.50 145.00 504-04420 Precast Panel Facing Sq Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 170,462.00 60.58 60.71 60.71 FBR0703-534 I-70 Weighted Average for the Second Quarter 170,462.00 60.58 60.71 60.71 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,258.00 131.82 131.82 131.82 Weighted Average for the Third Quarter 1,258.00 131.82 131.82 131.82 Weighted Average for the Year 171,720.00 61.10 61.23 61.23 504-05000 Wire Mesh Facing Sq Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4,693.00 56.47 58.74 58.74 FBR0703-534 I-70 Weighted Average for the Second Quarter 4,693.00 56.47 58.74 58.74 Weighted Average for the Year 4,693.00 56.47 58.74 58.74 504-06300 Ground Nail Lin Foot NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2,100.00 60.00 89.35 90.00 Weighted Average for the Fourth Quarter 2,100.00 60.00 89.35 90.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2,100.00 60.00 89.35 90.00 504-06400 Soil Nail Wall Sq Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3,468.00 153.74 157.86 157.86 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4,845.00 65.00 54.09 50.00 Weighted Average for the Third Quarter 8,313.00 102.02 62.61 95.00 Weighted Average for the Year 8,313.00 102.02 62.61 95.00 504-06406 Soil Nail Lin Foot STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 3,785.00 65.00 92.16 65.00 Weighted Average for the First Quarter 3,785.00 65.00 92.16 65.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 44,990.00 47.77 44.48 44.48 FBR0703-534 I-70 Weighted Average for the Second Quarter 44,990.00 47.77 44.48 44.48 Weighted Average for the Year 48,775.00 49.10 56.48 46.07 504-06410 Verification Testing Each STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2.00 4500.00 10688.39 10000.00 Weighted Average for the First Quarter 2.00 4500.00 10688.39 10000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 504-06410 Verification Testing Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 20.00 2070.13 2070.13 2070.13 FBR0703-534 I-70 Weighted Average for the Second Quarter 20.00 2070.13 2070.13 2070.13 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5.00 2821.76 2821.76 2821.76 Weighted Average for the Third Quarter 5.00 2821.76 2821.76 2821.76 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 8.00 3000.00 6650.00 6700.00 Weighted Average for the Fourth Quarter 8.00 3000.00 6650.00 6700.00 Weighted Average for the Year 35.00 2528.90 5049.36 3688.90 504-08050 Stone Landscape Wall Sq Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4,192.00 71.60 78.68 78.68 FBR0703-534 I-70 Weighted Average for the Second Quarter 4,192.00 71.60 78.68 78.68 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 100.00 214.06 214.06 214.06 Weighted Average for the Third Quarter 100.00 214.06 214.06 214.06 Weighted Average for the Year 4,292.00 74.92 81.83 81.83 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 504-08150 Soldier Pile Wall Sq Foot NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 210.00 200.00 608.00 465.00 Weighted Average for the First Quarter 210.00 200.00 608.00 465.00 Weighted Average for the Year 210.00 200.00 608.00 465.00 504-08255 Masonry Landscape Wall (Dry Stack) Sq Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 61.00 160.07 160.07 160.07 Weighted Average for the Second Quarter 61.00 160.07 160.07 160.07 Weighted Average for the Year 61.00 160.07 160.07 160.07 506-00000 Riprap Cubic Yard NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 3.00 203.50 963.99 650.50 Weighted Average for the Fourth Quarter 3.00 203.50 963.99 650.50 Weighted Average for the Year 3.00 203.50 963.99 650.50 506-00206 Riprap (6 In) Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,859.00 396.40 332.84 332.84 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 1,859.00 396.40 332.84 332.84 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 965.00 154.90 133.84 133.84 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 15.00 155.03 188.77 188.77 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 16.00 154.90 176.97 176.97 Weighted Average for the Third Quarter 996.00 154.90 135.36 135.36 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 479.00 234.05 185.04 210.25 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 119.00 226.06 150.00 120.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 126.00 214.60 225.75 215.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 126.00 178.83 181.96 165.00 Weighted Average for the Fourth Quarter 850.00 221.86 184.31 191.61 Weighted Average for the Year 3,705.00 291.44 225.18 247.35 506-00209 Riprap (9 In) Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 28.00 203.62 224.93 169.60 BR0761-249 I-76 02/27/25 84.00 207.30 224.00 210.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 105.00 168.82 404.26 367.26 Weighted Average for the First Quarter 217.00 188.21 293.48 280.88 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 99.00 200.00 221.67 140.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 8.00 229.08 229.08 229.08 Weighted Average for the Second Quarter 107.00 202.17 221.86 146.66 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 41.00 288.76 288.76 288.76 CR400-406 REGION-WIDE 07/17/25 9.00 264.74 576.67 1100.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 650.00 151.00 180.66 115.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 551.00 184.26 203.27 203.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 1,251.00 170.98 185.40 166.66 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 15.00 207.07 472.50 450.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 26.00 205.09 402.68 300.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 17.00 275.00 451.01 151.25 Weighted Average for the Fourth Quarter 58.00 226.09 424.29 295.19 Weighted Average for the Year 1,633.00 177.27 209.58 185.09 506-00212 Riprap (12 In) Cubic Yard BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 22.00 200.00 354.49 214.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 16.00 200.00 344.00 475.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 49.00 283.86 401.82 392.76 Weighted Average for the First Quarter 87.00 247.23 382.78 362.68 NHPP0703-517 FBR0703-534 STAR500-228 I-70 TOP OF FLOYD HILL TO VET I-70 REGION 5 04/11/25 05/08/25 1,270.00 36.00 256.49 210.00 242.98 368.33 242.98 300.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 710.00 170.00 218.90 180.00 Weighted Average for the Second Quarter 2,016.00 225.20 229.97 221.82 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 391.00 151.78 151.78 151.78 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3.00 165.60 705.50 705.50 Weighted Average for the Third Quarter 394.00 151.89 156.00 156.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 330.00 146.74 209.23 217.95 Weighted Average for the Fourth Quarter 330.00 146.74 209.23 217.95 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2,827.00 206.50 230.95 216.53 506-00218 Riprap (18 In) Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 297.00 174.62 173.63 173.63 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 162.00 500.00 350.00 350.00 Weighted Average for the Second Quarter 459.00 289.46 235.88 235.88 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1,023.00 121.20 187.58 187.58 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 323.00 174.51 155.73 155.73 Weighted Average for the Third Quarter 1,346.00 133.99 179.94 179.94 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 550.00 200.00 265.45 186.45 Weighted Average for the Fourth Quarter 550.00 200.00 265.45 186.45 Weighted Average for the Year 2,355.00 179.71 228.21 192.36 506-00226 Riprap (24 In) Ton STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1,628.00 166.16 111.34 140.00 Weighted Average for the First Quarter 1,628.00 166.16 111.34 140.00 Weighted Average for the Year 1,628.00 166.16 111.34 140.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 506-00236 Riprap (36 In) Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 3,485.00 130.25 165.39 165.39 Weighted Average for the Second Quarter 3,485.00 130.25 165.39 165.39 Weighted Average for the Year 3,485.00 130.25 165.39 165.39 506-00406 Soil Riprap (6 In) Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 106.00 788.27 526.37 526.37 FBR0703-534 I-70 Weighted Average for the Second Quarter 106.00 788.27 526.37 526.37 Weighted Average for the Year 106.00 788.27 526.37 526.37 506-00412 Soil Riprap (12 In) Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 52.00 788.27 217.85 217.85 FBR0703-534 I-70 Weighted Average for the Second Quarter 52.00 788.27 217.85 217.85 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 82.00 235.35 235.35 235.35 Weighted Average for the Third Quarter 82.00 235.35 235.35 235.35 Weighted Average for the Year 134.00 449.92 228.56 228.56 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 506-00418 Soil Riprap (18 In) Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 108.00 788.27 194.73 194.73 Weighted Average for the Second Quarter 108.00 788.27 194.73 194.73 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,290.00 159.42 172.81 172.81 Weighted Average for the Third Quarter 1,290.00 159.42 172.81 172.81 Weighted Average for the Year 1,398.00 208.00 174.50 174.50 506-00602 In-Channel Boulder Feature (Bldr Cascde) Each STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2.00 300.00 4114.45 6875.00 Weighted Average for the Fourth Quarter 2.00 300.00 4114.45 6875.00 Weighted Average for the Year 2.00 300.00 4114.45 6875.00 506-00700 Void-Filled Riprap Cubic Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 100.00 214.26 214.26 214.26 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 605.00 218.18 241.82 241.82 Weighted Average for the Third Quarter 705.00 217.62 237.91 237.91 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 60.00 200.00 536.39 680.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 153.00 140.00 287.17 210.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 213.00 156.90 372.74 342.39 Weighted Average for the Year 918.00 203.53 327.54 262.15 506-01020 Geogrid Reinforce Sq Yard NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 78.00 8.00 11.75 13.00 Weighted Average for the First Quarter 78.00 8.00 11.75 13.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 620.00 5.00 4.12 4.50 Weighted Average for the Second Quarter 620.00 5.00 4.12 4.50 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 5,333.00 3.00 5.40 2.86 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 750.00 4.00 4.29 4.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 357.00 6.33 6.15 5.30 Weighted Average for the Fourth Quarter 6,440.00 3.30 5.23 3.13 Weighted Average for the Year 7,138.00 3.50 5.20 3.36 507-00000 Conc S and D Pave Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 89.00 1636.68 1688.06 1688.06 FBR0703-534 I-70 Weighted Average for the Second Quarter 89.00 1636.68 1688.06 1688.06 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 92.00 1047.85 1049.37 1049.37 Weighted Average for the Third Quarter 92.00 1047.85 1049.37 1049.37 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 507-00000 Conc S and D Pave Cubic Yard STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 1254.95 6982.63 5650.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.30 1500.00 3590.00 1580.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 5.00 2200.00 2439.83 1298.00 Weighted Average for the Fourth Quarter 7.30 1945.88 3577.20 1944.38 Weighted Average for the Year 188.30 1360.98 1609.16 1385.94 507-00100 Conc S and D Pave (Reinf) Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 11.00 1347.50 1088.86 760.17 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 45.00 1415.95 1539.58 1288.00 Weighted Average for the First Quarter 56.00 1402.50 1418.65 1184.32 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.30 900.35 900.35 900.35 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.30 2000.00 2994.78 1800.00 Weighted Average for the Second Quarter 2.60 1450.18 2575.89 1350.18 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 13.00 1619.92 1619.92 1619.92 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 50.40 960.12 1270.73 1270.73 Weighted Average for the Third Quarter 63.40 1095.41 1342.33 1342.33 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 68.00 800.00 970.17 690.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 3.00 2045.72 3169.51 3650.00 Weighted Average for the Fourth Quarter 71.00 852.64 1033.00 815.07 Weighted Average for the Year 193.00 1099.98 1202.20 1102.62 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 507-00555 Concrete Lined Ditch Cubic Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 163.00 959.67 959.67 959.67 Weighted Average for the Third Quarter 163.00 959.67 959.67 959.67 Weighted Average for the Year 163.00 959.67 959.67 959.67 507-00725 S and D Paving (Special) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 33,149.00 36.40 36.39 36.39 Weighted Average for the Third Quarter 33,149.00 36.40 36.39 36.39 Weighted Average for the Year 33,149.00 36.40 36.39 36.39 508-90000 Paint Existing Structure Lump Sum STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 25000.00 167636.67 85000.00 Weighted Average for the Fourth Quarter 1.00 25000.00 167636.67 85000.00 Weighted Average for the Year 1.00 25000.00 167636.67 85000.00 509-00000 Str Steel Pound 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 327,913.00 2.80 16.26 13.22 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 75.00 350.00 46.05 27.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 327,988.00 2.88 16.26 13.22 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8,056.00 6.04 6.04 6.04 CR400-406 REGION-WIDE 07/17/25 230.00 4.94 151.67 20.00 Weighted Average for the Third Quarter 8,286.00 6.01 17.53 6.43 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 328.00 62.00 122.22 10.34 Weighted Average for the Fourth Quarter 328.00 62.00 122.22 10.34 Weighted Average for the Year 336,602.00 3.01 16.32 13.05 509-00001 Str Steel (Galv) Pound NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 27,044.00 8.80 10.38 10.38 FBR0703-534 I-70 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 34,460.00 12.00 9.30 7.70 Weighted Average for the Second Quarter 61,504.00 10.59 9.48 8.88 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,772.00 12.87 224.65 7.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 3,226.00 16.01 11.30 5.50 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2,116.00 20.00 13.50 8.00 Weighted Average for the Fourth Quarter 7,114.00 16.42 84.37 6.62 Weighted Average for the Year 68,618.00 11.20 19.68 8.64 509-00003 Str Steel (Install Only) Pound STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 594,813.00 2.71 2.67 1.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 594,813.00 2.71 2.67 1.10 Weighted Average for the Year 594,813.00 2.71 2.67 1.10 509-08100 Provide Temporary Support Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 1799066.35 2063613.66 2063613.66 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 712786.45 830544.45 830544.45 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 1013620.88 1309337.53 1309337.53 FBR0703-534 I-70 FBR0703-534 I-70 FBR0703-534 I-70 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 700000.00 463138.10 80000.00 Weighted Average for the Second Quarter 4.00 1056368.42 865149.72 1070873.91 Weighted Average for the Year 4.00 1056368.42 865149.72 1070873.91 509-08120 Temporary Bridge Deck Sq Foot NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 826.00 60.00 227.66 173.00 Weighted Average for the Fourth Quarter 826.00 60.00 227.66 173.00 Weighted Average for the Year 826.00 60.00 227.66 173.00 509-08121 Temp Bridge Deck Lin Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 66.00 1200.00 1676.58 820.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 66.00 1200.00 1676.58 820.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 265.00 800.00 1260.00 1260.00 Weighted Average for the Fourth Quarter 265.00 800.00 1260.00 1260.00 Weighted Average for the Year 331.00 879.76 1419.85 1172.27 509-90004 Paint Existing Structure Sq Foot STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 690.00 100.00 53.05 102.00 Weighted Average for the Fourth Quarter 690.00 100.00 53.05 102.00 Weighted Average for the Year 690.00 100.00 53.05 102.00 512-00101 Bearing Device (Type I) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 16.00 1133.09 6544.99 5469.94 Weighted Average for the First Quarter 16.00 1133.09 6544.99 5469.94 Weighted Average for the Year 16.00 1133.09 6544.99 5469.94 512-00102 Bearing Device (Type II) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 247.00 4560.92 4599.63 4599.63 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 247.00 4560.92 4599.63 4599.63 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8.00 1960.28 1960.28 1960.28 Weighted Average for the Third Quarter 8.00 1960.28 1960.28 1960.28 Weighted Average for the Year 255.00 4479.33 4516.83 4516.83 512-00103 Bearing Device (Type III) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 10.00 19655.60 22176.89 22176.89 FBR0703-534 I-70 Weighted Average for the Second Quarter 10.00 19655.60 22176.89 22176.89 Weighted Average for the Year 10.00 19655.60 22176.89 22176.89 512-00120 Bearing Repair Corbel Each BR0704-265 I-70 EAST 07/24/25 40.00 5622.58 7981.43 6125.70 FBR0704-269 I-70 EAST Weighted Average for the Third Quarter 40.00 5622.58 7981.43 6125.70 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 4.00 5622.58 21994.74 27500.00 Weighted Average for the Fourth Quarter 4.00 5622.58 21994.74 27500.00 Weighted Average for the Year 44.00 5622.58 9538.46 8068.82 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 513-00600 Bridge Drain Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 4523.78 14909.93 17304.59 Weighted Average for the First Quarter 4.00 4523.78 14909.93 17304.59 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 26.00 37467.61 37308.14 37308.14 FBR0703-534 I-70 Weighted Average for the Second Quarter 26.00 37467.61 37308.14 37308.14 Weighted Average for the Year 30.00 33075.10 26557.00 34641.00 513-00690 Bridge Drain (Spec) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 3798.07 12938.57 15399.44 Weighted Average for the First Quarter 4.00 3798.07 12938.57 15399.44 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 8.00 3237.22 4662.30 4662.30 FBR0703-534 I-70 Weighted Average for the Second Quarter 8.00 3237.22 4662.30 4662.30 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 11478.36 11478.36 11478.36 BR0704-265 I-70 EAST 07/24/25 24.00 3849.32 656.46 535.84 FBR0704-269 I-70 EAST Weighted Average for the Third Quarter 30.00 5375.12 1293.04 2724.34 Weighted Average for the Year 42.00 4817.71 3579.96 4300.63 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 514-00000 Pipe Railing Lin Foot C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 30.00 139.55 465.48 600.00 Weighted Average for the Second Quarter 30.00 139.55 465.48 600.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 40.00 530.12 530.12 530.12 Weighted Average for the Third Quarter 40.00 530.12 530.12 530.12 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 513.00 300.00 397.17 380.00 Weighted Average for the Fourth Quarter 513.00 300.00 397.17 380.00 Weighted Average for the Year 583.00 307.53 401.93 401.62 514-00048 Ped Railing (48 In) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,311.00 20.00 366.04 273.24 Weighted Average for the First Quarter 1,311.00 20.00 366.04 273.24 Weighted Average for the Year 1,311.00 20.00 366.04 273.24 514-00100 Hand Rail Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 585.00 90.00 111.18 158.10 Weighted Average for the First Quarter 585.00 90.00 111.18 158.10 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 189.00 160.00 273.83 207.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 514-00100 Hand Rail Lin Foot NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 189.00 160.00 273.83 207.00 Weighted Average for the Year 774.00 107.09 145.68 170.04 514-00200 Pedestrian Railing (Steel) Lin Foot C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 114.00 200.00 471.34 600.00 Weighted Average for the Second Quarter 114.00 200.00 471.34 600.00 Weighted Average for the Year 114.00 200.00 471.34 600.00 514-00201 Ped Railing (Steel) (Spec) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,209.00 368.86 348.38 348.38 FBR0703-534 I-70 Weighted Average for the Second Quarter 1,209.00 368.86 348.38 348.38 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 803.00 207.59 207.59 207.59 Weighted Average for the Third Quarter 803.00 207.59 207.59 207.59 Weighted Average for the Year 2,012.00 304.50 292.19 292.19 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 514-01050 Hand and Bikeway Railing Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 207.00 207.92 207.92 207.92 Weighted Average for the Third Quarter 207.00 207.92 207.92 207.92 Weighted Average for the Year 207.00 207.92 207.92 207.92 515-00120 Waterproofing (Membrane) Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,568.00 30.00 27.94 28.25 BR0761-249 I-76 02/27/25 5,778.00 28.26 25.13 28.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 275.00 35.00 69.19 45.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 920.00 20.00 47.55 45.10 Weighted Average for the First Quarter 8,541.00 27.91 27.57 30.44 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 64,165.00 26.79 24.76 24.76 FBR0703-534 I-70 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 1,530.00 60.00 29.00 38.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 921.00 50.00 37.35 60.00 Weighted Average for the Second Quarter 66,616.00 27.88 25.67 25.55 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 920.00 48.57 47.82 19.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3,404.00 27.94 25.54 25.54 Weighted Average for the Third Quarter 4,324.00 32.33 38.34 24.15 NHPPR500-227 REGION 5 SECTION 7 10/23/25 2,387.00 40.00 36.57 17.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 167.00 57.08 64.50 59.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,422.00 31.01 27.08 29.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 515-00120 Waterproofing (Membrane) Sq Yard STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,382.00 30.60 26.61 21.30 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 644.00 35.00 44.80 62.60 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 6,507.00 10.00 37.23 19.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 15,163.00 30.00 21.05 21.10 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1,265.00 27.62 23.59 22.75 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 74.00 70.00 75.80 64.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,520.00 30.68 23.05 22.50 Weighted Average for the Fourth Quarter 30,531.00 26.88 28.14 22.06 Weighted Average for the Year 110,012.00 27.78 27.56 24.91 515-00400 Concrete Sealer Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,091.00 21.43 14.82 14.65 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 11,208.00 12.00 11.99 10.63 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 175.00 23.00 52.33 25.00 Weighted Average for the First Quarter 12,474.00 12.98 12.89 11.18 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 514.00 16.41 16.41 16.41 CR400-406 REGION-WIDE 07/17/25 339.00 23.08 26.83 25.00 Weighted Average for the Third Quarter 853.00 19.06 23.33 19.82 NHPPR500-227 REGION 5 SECTION 7 10/23/25 125.00 50.00 42.03 45.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 383.00 29.57 7.73 7.50 NHPP1602-194 US 160 MP 174.1 12/11/25 1,292.00 120.00 25.13 29.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 558.00 30.00 35.47 60.50 Weighted Average for the Fourth Quarter 2,358.00 80.30 24.31 33.81 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 15,685.00 23.43 14.82 15.05 518-00000 Brdg Compress Joint Sealer Lin Foot C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 25.00 217.92 376.99 300.00 Weighted Average for the Second Quarter 25.00 217.92 376.99 300.00 BR0704-265 FBR0704-269 NHPP0253-302 I-70 EAST 07/24/25 I-70 EAST I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 158.00 396.00 234.83 107.00 148.07 161.37 152.27 161.37 Weighted Average for the Third Quarter 554.00 143.46 153.19 158.77 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 400.00 98.15 128.30 127.00 Weighted Average for the Fourth Quarter 400.00 98.15 128.30 127.00 Weighted Average for the Year 979.00 126.85 146.27 149.40 518-00010 Rdwy Compress Joint Sealer Lin Foot NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 160.00 70.91 232.10 231.50 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 98.00 62.47 254.68 181.00 Weighted Average for the Fourth Quarter 258.00 67.71 239.53 212.32 Weighted Average for the Year 258.00 67.71 239.53 212.32 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 518-01001 Br Expan Joint (Asphaultic Plug) Lin Foot BR0761-249 I-76 02/27/25 624.00 293.88 294.69 320.00 Weighted Average for the First Quarter 624.00 293.88 294.69 320.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 532.00 500.00 327.00 382.00 Weighted Average for the Second Quarter 532.00 500.00 327.00 382.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 24.00 332.03 425.50 387.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 88.00 426.84 426.06 400.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 300.00 333.72 384.66 330.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 252.00 429.50 356.18 342.00 Weighted Average for the Fourth Quarter 664.00 382.35 379.70 345.89 Weighted Average for the Year 1,820.00 386.41 328.24 347.57 518-01004 Br Expan Device (0-4 In) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 64.00 407.21 469.80 374.77 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 272.00 600.00 836.69 475.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 609.00 1000.00 685.92 630.32 BR0761-249 I-76 02/27/25 120.00 405.98 846.80 380.00 Weighted Average for the First Quarter 1,065.00 795.29 734.47 547.09 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 2,051.00 492.58 519.75 519.75 Weighted Average for the Second Quarter 2,051.00 492.58 519.75 519.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 518-01004 Br Expan Device (0-4 In) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 56.00 647.03 647.03 647.03 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 76.00 477.30 534.98 489.93 Weighted Average for the Third Quarter 132.00 549.30 552.41 556.58 NHPPR500-227 REGION 5 SECTION 7 10/23/25 101.00 700.00 996.68 700.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 68.00 550.56 765.30 600.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 68.00 600.00 745.75 935.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 265.00 500.00 789.00 790.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 60.00 750.00 340.50 342.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 90.00 369.26 436.08 594.00 Weighted Average for the Fourth Quarter 652.00 551.64 664.38 703.08 Weighted Average for the Year 3,900.00 587.04 665.05 559.11 518-01006 Br Expan Device (0-6 In) Lin Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 173.00 3000.00 3607.03 3400.00 Weighted Average for the First Quarter 173.00 3000.00 3607.03 3400.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 52.00 2834.62 3789.63 3789.63 Weighted Average for the Second Quarter 52.00 2834.62 3789.63 3789.63 Weighted Average for the Year 225.00 2961.78 3617.38 3490.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 518-01009 Br Expan Device (0-9 In) Lin Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 245.00 4000.00 4721.87 5020.00 Weighted Average for the First Quarter 245.00 4000.00 4721.87 5020.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 54.00 3946.20 4358.27 4358.27 FBR0703-534 I-70 Weighted Average for the Second Quarter 54.00 3946.20 4358.27 4358.27 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 136.00 3300.00 3369.84 3009.00 Weighted Average for the Fourth Quarter 136.00 3300.00 3369.84 3009.00 Weighted Average for the Year 435.00 3774.47 4307.64 4309.13 518-01012 Br Expan Device (0-12 In) Lin Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 166.00 6000.00 5733.16 5800.00 Weighted Average for the First Quarter 166.00 6000.00 5733.16 5800.00 Weighted Average for the Year 166.00 6000.00 5733.16 5800.00 518-01050 Br Expan Device (Special) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 116.00 6026.80 6903.80 6903.80 FBR0703-534 I-70 Weighted Average for the Second Quarter 116.00 6026.80 6903.80 6903.80 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 116.00 6026.80 6903.80 6903.80 518-01250 Br Expan Cover Plate Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 139.00 475.86 581.23 545.39 Weighted Average for the First Quarter 139.00 475.86 581.23 545.39 Weighted Average for the Year 139.00 475.86 581.23 545.39 518-02030 Polyester Conc End Dam Cubic Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 3,856.00 200.00 231.78 152.50 Weighted Average for the First Quarter 3,856.00 200.00 231.78 152.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 610.00 200.00 319.50 319.00 Weighted Average for the Fourth Quarter 610.00 200.00 319.50 319.00 Weighted Average for the Year 4,466.00 200.00 237.00 175.24 518-03000 Saw and Seal Br Joint Lin Foot BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 609.00 500.00 33.14 26.45 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 48.00 50.00 93.46 30.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 461.00 30.00 43.55 42.10 Weighted Average for the First Quarter 1,118.00 286.88 39.11 33.06 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 518-03000 Saw and Seal Br Joint Lin Foot BR0704-265 I-70 EAST 07/24/25 342.00 37.50 34.81 37.04 FBR0704-269 I-70 EAST FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 80.00 43.55 38.67 38.67 Weighted Average for the Third Quarter 422.00 38.65 35.02 37.35 NHPPR500-227 REGION 5 SECTION 7 10/23/25 130.00 50.00 34.19 25.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 24.00 97.84 50.50 51.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 159.00 35.20 40.89 39.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 188.00 30.38 28.00 27.50 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 349.00 30.00 43.96 38.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 749.00 35.00 9.05 3.90 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 336.00 35.00 31.55 31.60 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 278.00 70.00 46.40 31.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 212.00 30.00 60.08 60.25 Weighted Average for the Fourth Quarter 2,425.00 38.94 29.29 26.44 Weighted Average for the Year 3,965.00 108.82 32.96 29.47 518-03100 Rapid Cure Silicone Jt Seal Lin Foot STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 123.00 48.69 58.63 45.00 NHPP1602-194 US 160 MP 174.1 12/11/25 104.00 100.00 91.56 57.00 Weighted Average for the Fourth Quarter 227.00 72.20 71.92 50.50 Weighted Average for the Year 227.00 72.20 71.92 50.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 519-01000 Epoxy Resin (Injection) Lin Foot NHPPR500-227 REGION 5 SECTION 7 10/23/25 10.00 500.00 773.81 390.00 NHPP1602-194 US 160 MP 174.1 12/11/25 47.00 650.00 917.75 580.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 20.00 449.99 415.62 286.00 Weighted Average for the Fourth Quarter 77.00 578.57 793.15 478.96 Weighted Average for the Year 77.00 578.57 793.15 478.96 519-03035 Place Thin Bond Overlay (Poly Conc) Sq Yard BR0704-265 I-70 EAST 07/24/25 5,594.00 77.49 57.40 59.60 FBR0704-269 I-70 EAST FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 726.00 142.10 142.10 142.10 Weighted Average for the Third Quarter 6,320.00 84.91 60.06 69.08 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 2,494.00 127.87 49.84 50.00 Weighted Average for the Fourth Quarter 2,494.00 127.87 49.84 50.00 Weighted Average for the Year 8,814.00 97.07 56.48 63.68 519-03055 Furnish Thin Bond Overlay (Poly Conc) Cubic Foot BR0704-265 I-70 EAST 07/24/25 3,965.00 168.32 137.53 168.11 FBR0704-269 I-70 EAST FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 409.00 178.15 178.15 178.15 Weighted Average for the Third Quarter 4,374.00 169.24 138.55 169.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 519-03055 Furnish Thin Bond Overlay (Poly Conc) Cubic Foot NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,942.00 181.49 164.60 160.00 Weighted Average for the Fourth Quarter 1,942.00 181.49 164.60 160.00 Weighted Average for the Year 6,316.00 173.01 148.29 166.27 601-01000 Conc CL B Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 2654.86 2267.45 1204.67 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 36.00 1614.54 3079.97 3264.50 Weighted Average for the First Quarter 37.00 1642.66 3047.47 3208.83 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 26.00 1465.47 2826.46 2826.46 FBR0703-534 I-70 Weighted Average for the Second Quarter 26.00 1465.47 2826.46 2826.46 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 2710.16 2710.16 2710.16 CR400-406 REGION-WIDE 07/17/25 4.40 2252.60 5816.67 3850.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 14.00 1013.69 1601.57 1601.57 Weighted Average for the Third Quarter 22.40 1559.99 3527.01 2241.19 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 23.00 1800.00 982.67 1250.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 0.80 2500.00 14205.00 21060.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 3.00 1600.00 3280.00 2400.00 Weighted Average for the Fourth Quarter 26.80 1798.51 1342.41 1970.07 Weighted Average for the Year 112.20 1622.32 2344.35 2631.15 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 601-03000 Conc CL D Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 53.20 2000.00 1897.23 2100.00 Weighted Average for the First Quarter 53.20 2000.00 1897.23 2100.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 129.00 1785.20 2764.68 2764.68 FBR0703-534 I-70 Weighted Average for the Second Quarter 129.00 1785.20 2764.68 2764.68 CR400-406 REGION-WIDE 07/17/25 44.00 2582.86 2433.33 3000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 597.10 1369.32 1219.64 1219.64 Weighted Average for the Third Quarter 641.10 1452.61 1439.37 1341.83 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 2.00 7000.00 6315.32 5000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 285.00 600.00 1166.00 950.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 157.40 1100.00 2164.81 1419.00 Weighted Average for the Fourth Quarter 444.40 805.90 1418.04 1134.34 Weighted Average for the Year 1,267.70 1282.71 1507.13 1445.70 601-03020 Conc CL D (Misc) Cubic Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 112.00 1371.99 1342.28 1342.28 Weighted Average for the Third Quarter 112.00 1371.99 1342.28 1342.28 Weighted Average for the Year 112.00 1371.99 1342.28 1342.28 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 601-03025 Conc CL D (Misc) (C) Cubic Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 101.00 1104.09 2198.77 2198.77 Weighted Average for the Third Quarter 101.00 1104.09 2198.77 2198.77 Weighted Average for the Year 101.00 1104.09 2198.77 2198.77 601-03027 Conc CL D (Spec) Cubic Yard STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 5.00 1200.00 3011.86 2134.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 84.00 1200.00 2679.10 2134.00 Weighted Average for the Fourth Quarter 89.00 1200.00 2697.80 2134.00 Weighted Average for the Year 89.00 1200.00 2697.80 2134.00 601-03030 Conc CL D (Box) Cubic Yard NHPP0703-517 FBR0703-534 NHPP0501-080 I-70 TOP OF FLOYD HILL TO VET I-70 SH50A MP 89.93 CEADAR CREEK 04/11/25 06/12/25 26.00 47.00 2012.05 2500.00 3525.64 2250.57 3525.64 1500.00 Weighted Average for the Second Quarter 73.00 2326.21 2405.48 2221.46 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 103.00 1628.39 1616.21 1616.21 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 184.00 47.40 1500.00 1605.55 1599.81 1514.60 1320.00 1200.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 926.50 1126.29 1141.55 1141.55 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 1,260.90 1239.86 1404.34 1208.56 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 138.00 1200.00 1372.60 1457.60 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 32.00 1400.00 2820.00 2400.00 Weighted Average for the Fourth Quarter 170.00 1237.65 1903.75 1634.99 Weighted Average for the Year 1,503.90 1292.34 1549.36 1305.93 601-03040 Conc CL D (Bridge) Cubic Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 922.00 1500.00 1451.72 1180.31 Weighted Average for the First Quarter 922.00 1500.00 1451.72 1180.31 NHPP0703-517 FBR0703-534 C0405-042 I-70 TOP OF FLOYD HILL TO VET I-70 US 40 IN DEER TRAIL, PINE ST 04/11/25 06/05/25 22,978.00 43.00 1119.69 850.00 1124.09 1434.31 1124.09 1100.00 Weighted Average for the Second Quarter 23,021.00 1119.19 1126.97 1124.05 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 336.00 1741.30 1782.10 1782.10 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 673.00 89.00 1269.65 1941.36 1050.02 3305.67 495.08 3305.67 Weighted Average for the Third Quarter 1,098.00 1468.43 1193.34 1116.74 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 81.00 1526.85 1668.70 1598.50 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 11.00 2500.00 1715.00 1720.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 612.00 1190.00 1036.83 960.60 Weighted Average for the Fourth Quarter 704.00 1249.23 1078.19 1045.86 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 25,745.00 1151.28 1170.84 1123.61 601-03050 Conc CL D (Wall) Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 4,099.00 703.69 683.32 683.32 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 129.00 2700.00 1807.22 1450.00 Weighted Average for the Second Quarter 4,228.00 764.60 808.98 706.71 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 129.00 1599.95 1616.35 1616.35 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 92.60 917.23 1369.90 1100.00 Weighted Average for the Third Quarter 221.60 1314.66 1406.45 1400.58 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 40.00 4000.00 3390.32 1400.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2.00 2588.57 10050.00 10100.00 Weighted Average for the Fourth Quarter 42.00 3932.79 3472.54 1814.29 Weighted Average for the Year 4,491.60 821.36 1047.01 751.30 601-03056 Conc CL DF Cubic Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 27,479.00 1178.51 1201.63 1201.63 Weighted Average for the Second Quarter 27,479.00 1178.51 1201.63 1201.63 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 175.00 2363.65 2462.67 2462.67 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,037.00 1416.54 1393.51 1393.51 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 1,212.00 1553.29 1547.89 1547.89 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 128.00 1000.00 1099.08 865.00 Weighted Average for the Fourth Quarter 128.00 1000.00 1099.08 865.00 Weighted Average for the Year 28,819.00 1193.47 1214.20 1214.70 601-03057 Conc CL DR Cubic Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 12.00 7000.00 4597.48 4570.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 125.00 3000.00 2613.86 1822.75 BR0761-249 I-76 02/27/25 46.00 1439.71 3191.59 3000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.90 3500.00 5146.26 3500.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 3.00 2000.00 6235.00 5970.00 Weighted Average for the First Quarter 187.90 2862.57 2943.12 2369.58 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 56.00 2800.00 3214.00 2202.00 Weighted Average for the Second Quarter 56.00 2800.00 3214.00 2202.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 10.40 3271.49 3414.24 1940.00 Weighted Average for the Third Quarter 10.40 3271.49 3414.24 1940.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 61.80 3000.00 3503.50 2375.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 0.20 5475.47 16350.00 7700.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 21.40 4500.00 3579.10 3600.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 18.00 2787.57 4429.47 4200.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 6.00 3500.00 2855.00 5210.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 25.00 2000.00 2178.51 2200.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 67.00 3000.00 3469.00 3600.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 601-03057 Conc CL DR Cubic Yard NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 143.00 4000.00 3540.00 3480.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 0.20 5317.11 46815.00 25000.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 17.90 2575.19 3780.98 3700.00 Weighted Average for the Fourth Quarter 360.50 3395.65 3491.08 3321.18 Weighted Average for the Year 614.80 3176.37 3249.17 2905.04 601-05045 Conc CL S40 Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 12,483.00 2137.40 2302.58 2302.58 FBR0703-534 I-70 Weighted Average for the Second Quarter 12,483.00 2137.40 2302.58 2302.58 Weighted Average for the Year 12,483.00 2137.40 2302.58 2302.58 601-05060 Concrete Class S60 Cubic Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 296.00 2478.23 3598.61 3598.61 FBR0703-534 I-70 Weighted Average for the Second Quarter 296.00 2478.23 3598.61 3598.61 Weighted Average for the Year 296.00 2478.23 3598.61 3598.61 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 601-06100 Conc (Patching) Cubic Yard NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 31.00 5150.65 3381.50 3307.50 Weighted Average for the Fourth Quarter 31.00 5150.65 3381.50 3307.50 Weighted Average for the Year 31.00 5150.65 3381.50 3307.50 601-06102 Concrete (Patching) Cubic Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 1500.00 1846.00 1830.00 BR0761-249 I-76 02/27/25 488.00 141.95 431.13 250.00 Weighted Average for the First Quarter 492.00 152.99 436.90 262.85 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 300.00 180.36 580.23 415.91 Weighted Average for the Third Quarter 300.00 180.36 580.23 415.91 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 45.00 630.00 781.70 1150.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 49.00 1076.51 914.71 985.00 Weighted Average for the Fourth Quarter 94.00 862.75 851.04 1063.99 Weighted Average for the Year 886.00 237.56 502.21 399.67 601-06150 Conc (Patching) Sq Foot STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2.00 500.00 1608.14 2400.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 2.00 500.00 1608.14 2400.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 15.00 390.57 682.31 285.00 Weighted Average for the Third Quarter 15.00 390.57 682.31 285.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 214.00 300.00 548.73 190.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 254.00 152.90 271.14 200.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 84.00 1000.00 203.50 190.00 NHPP1602-194 US 160 MP 174.1 12/11/25 79.00 850.00 796.76 470.00 Weighted Average for the Fourth Quarter 631.00 402.83 421.46 229.08 Weighted Average for the Year 648.00 402.85 430.85 237.08 601-06300 Cement Grout Cubic Foot NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 109.00 300.00 315.00 315.00 Weighted Average for the Second Quarter 109.00 300.00 315.00 315.00 Weighted Average for the Year 109.00 300.00 315.00 315.00 601-14000 Conc Footing (Ty 1) Lin Foot NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 8.00 3000.00 1165.00 1050.00 Weighted Average for the Fourth Quarter 8.00 3000.00 1165.00 1050.00 Weighted Average for the Year 8.00 3000.00 1165.00 1050.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 601-25730 Precast Deck Panel (3 In) Sq Yard NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 31,039.00 185.09 186.51 186.51 Weighted Average for the Second Quarter 31,039.00 185.09 186.51 186.51 Weighted Average for the Year 31,039.00 185.09 186.51 186.51 601-40300 Struct Conc Coating Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 230.00 23.92 25.31 48.53 Weighted Average for the First Quarter 230.00 23.92 25.31 48.53 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 88,822.00 21.70 19.78 19.78 Weighted Average for the Second Quarter 88,822.00 21.70 19.78 19.78 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 419.00 73.65 50.92 50.92 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 749.00 19.01 19.23 35.00 Weighted Average for the Third Quarter 1,168.00 38.61 21.30 40.71 NHPP1602-194 US 160 MP 174.1 12/11/25 3,539.00 295.00 74.47 79.00 Weighted Average for the Fourth Quarter 3,539.00 295.00 74.47 79.00 Weighted Average for the Year 93,759.00 32.23 26.93 22.35 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 601-40301 Struct Conc Coating Sq Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 401,238.00 2.31 2.19 2.19 FBR0703-534 I-70 Weighted Average for the Second Quarter 401,238.00 2.31 2.19 2.19 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 18,016.00 1.66 1.77 1.77 Weighted Average for the Third Quarter 18,016.00 1.66 1.77 1.77 Weighted Average for the Year 419,254.00 2.28 2.17 2.17 601-40302 Struct Conc Coating (Anti-Graf) Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 16,737.00 2.54 1.94 2.06 Weighted Average for the First Quarter 16,737.00 2.54 1.94 2.06 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 315.00 4.13 7.25 5.00 Weighted Average for the Second Quarter 315.00 4.13 7.25 5.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 18,016.00 1.77 1.77 1.77 Weighted Average for the Third Quarter 18,016.00 1.77 1.77 1.77 Weighted Average for the Year 35,068.00 2.16 1.98 1.94 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 601-40400 Struct Conc Stain Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,865.00 18.81 18.31 21.18 Weighted Average for the First Quarter 1,865.00 18.81 18.31 21.18 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2,335.00 12.31 12.69 12.69 Weighted Average for the Third Quarter 2,335.00 12.31 12.69 12.69 Weighted Average for the Year 4,200.00 15.20 17.34 16.46 601-51005 Galvanic Anodes, use code 602-51010 plea Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 473.00 35.00 47.74 48.25 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 1,782.00 27.00 40.60 65.78 BR0761-249 I-76 02/27/25 1,870.00 26.33 37.73 40.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 83.00 35.00 88.68 35.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 120.00 30.00 92.10 89.20 Weighted Average for the First Quarter 4,328.00 27.82 40.91 52.78 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 10.00 55.20 67.50 51.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 890.00 32.32 39.65 24.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 685.00 38.35 40.37 42.50 Weighted Average for the Fourth Quarter 1,585.00 35.07 40.01 32.17 Weighted Average for the Year 5,913.00 29.76 40.71 47.26 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 602-00000 Reinf Steel Pound NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 550.00 5.00 5.83 5.90 BR0761-249 I-76 02/27/25 2,382.00 3.22 5.79 6.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 96.00 5.00 7.99 7.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,436.00 3.87 3.53 3.06 Weighted Average for the First Quarter 4,464.00 3.69 5.24 5.06 NHPP0703-517 FBR0703-534 NHPP0501-080 I-70 TOP OF FLOYD HILL TO VET I-70 SH50A MP 89.93 CEADAR CREEK 04/11/25 06/12/25 6,549,188.00 25,444.00 1.21 3.00 1.27 2.93 1.27 1.75 Weighted Average for the Second Quarter 6,574,632.00 1.22 1.30 1.27 CR400-406 REGION-WIDE 07/17/25 422.00 6.01 11.00 11.00 BR0704-265 FBR0704-269 MTCER400-411 I-70 EAST I-70 EAST SH157 MP3.518 D-16-DG AND I70 07/24/25 08/21/25 1,420.00 17.00 2.91 5.49 2.81 49.37 3.22 100.00 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 505.00 974.00 3.92 1.46 2.97 1.19 2.50 1.19 Weighted Average for the Third Quarter 3,338.00 3.05 3.98 4.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1,538.00 6.00 3.89 3.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 5,621.00 5.00 3.09 6.50 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 24,675.00 2.42 2.25 2.10 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 840.00 4.13 4.43 3.35 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,274.00 4.17 2.13 2.00 NHPP1602-194 US 160 MP 174.1 12/11/25 150.00 4.00 23.21 13.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 800.00 3.75 4.94 5.00 Weighted Average for the Fourth Quarter 34,898.00 3.13 2.91 2.99 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 6,617,332.00 1.23 1.34 1.28 602-00020 Reinf Steel (Epoxy) Pound 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 191,756.00 3.00 1.62 1.98 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 38,560.00 2.50 4.51 4.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 8,254.00 5.00 3.21 3.12 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 10,739.00 10.00 4.67 5.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 200.00 5.00 1.90 1.80 Weighted Average for the First Quarter 249,509.00 3.29 2.14 2.46 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 8,790,359.00 1.49 1.50 1.50 FBR0703-534 I-70 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 2,481.00 6.00 3.67 3.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 4,180.00 2.83 2.85 1.50 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 10,505.00 3.00 3.89 2.25 Weighted Average for the Second Quarter 8,807,525.00 1.49 1.52 1.50 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 103,172.00 1.36 1.36 1.36 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 23,030.00 2.27 2.93 1.97 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 37,852.00 1.59 1.66 1.66 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 43,756.00 2.50 2.92 2.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 16,400.00 3.14 2.40 1.75 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 448,017.00 1.52 1.39 1.39 Weighted Average for the Third Quarter 672,227.00 1.63 1.99 1.47 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1,880.00 6.36 4.30 3.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 35.00 17.01 15.82 7.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 30,371.00 2.00 2.71 3.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 602-00020 Reinf Steel (Epoxy) Pound STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 60.00 2.60 18.75 15.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,005.00 4.29 5.05 3.05 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 12,080.00 3.97 3.89 4.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 235.00 10.00 11.25 13.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 24,811.00 2.63 2.82 3.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 600.00 5.00 10.21 3.25 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 9,315.00 3.00 5.35 5.45 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1,601.00 5.00 8.95 9.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 16,523.00 2.00 3.36 2.43 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 146,141.00 2.06 1.66 1.55 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 3,291.00 5.00 4.53 4.15 Weighted Average for the Fourth Quarter 247,948.00 2.35 2.04 2.32 Weighted Average for the Year 9,977,209.00 1.57 1.69 1.54 602-00210 Welded Wire Fabric Sq Yard NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 4.00 86.91 210.56 25.50 Weighted Average for the First Quarter 4.00 86.91 210.56 25.50 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 274.00 205.53 22.64 22.64 FBR0703-534 I-70 Weighted Average for the Second Quarter 274.00 205.53 22.64 22.64 CR400-406 REGION-WIDE 07/17/25 707.00 25.76 28.67 34.00 Weighted Average for the Third Quarter 707.00 25.76 28.67 34.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1,284.00 30.00 61.35 113.71 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 1,284.00 30.00 61.35 113.71 Weighted Average for the Year 2,269.00 49.98 48.97 77.72 602-51010 Galvanic Anodes Each BR0704-265 I-70 EAST 07/24/25 23,501.00 5.00 22.77 21.41 FBR0704-269 I-70 EAST FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 420.00 20.00 43.22 39.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 23,921.00 5.26 23.21 21.72 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1,455.00 50.00 46.48 25.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 860.00 80.00 39.17 40.75 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 660.00 35.00 41.10 33.65 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,108.00 50.00 38.18 37.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 200.00 40.00 42.55 39.10 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 2,825.00 20.00 48.38 35.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 408.00 50.00 41.10 43.20 NHPP1602-194 US 160 MP 174.1 12/11/25 20.00 1000.00 277.22 60.00 Weighted Average for the Fourth Quarter 7,536.00 43.12 44.66 34.59 Weighted Average for the Year 31,457.00 14.33 27.80 24.80 603-00000 Culvert Lining Lin Foot NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 75.00 248.24 290.00 145.00 Weighted Average for the Second Quarter 75.00 248.24 290.00 145.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-00000 Culvert Lining Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 140.00 407.63 407.63 407.63 CR400-406 REGION-WIDE 07/17/25 161.00 248.24 260.00 295.00 Weighted Average for the Third Quarter 301.00 322.38 293.18 347.39 Weighted Average for the Year 376.00 307.59 292.33 307.02 603-00001 Annular Space Grouting Cubic Yard STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 75.00 400.00 1265.81 869.00 Weighted Average for the Fourth Quarter 75.00 400.00 1265.81 869.00 Weighted Average for the Year 75.00 400.00 1265.81 869.00 603-00015 Culvert Lining (15 In) Lin Foot NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 44.00 85.00 365.00 260.00 Weighted Average for the Second Quarter 44.00 85.00 365.00 260.00 Weighted Average for the Year 44.00 85.00 365.00 260.00 603-00018 Culvert Lining (18 In) Lin Foot NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 239.00 120.00 251.67 140.00 Weighted Average for the Second Quarter 239.00 120.00 251.67 140.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-00018 Culvert Lining (18 In) Lin Foot CR400-406 REGION-WIDE 07/17/25 46.00 400.00 465.00 215.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 167.00 210.00 163.40 112.00 Weighted Average for the Third Quarter 213.00 251.03 206.18 134.24 Weighted Average for the Year 452.00 181.75 225.48 137.29 603-00024 Prep Culvert Pipe (24 In) Lin Foot NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 3,823.00 150.00 100.00 100.00 Weighted Average for the Second Quarter 3,823.00 150.00 100.00 100.00 Weighted Average for the Year 3,823.00 150.00 100.00 100.00 603-00025 Culvert Lining (24 Inch)(Special) Lin Foot NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 3,823.00 400.00 225.00 225.00 Weighted Average for the Second Quarter 3,823.00 400.00 225.00 225.00 Weighted Average for the Year 3,823.00 400.00 225.00 225.00 603-00026 Culvert Lining (24 In) Lin Foot STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 102.00 647.00 378.53 327.60 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 4,377.00 191.28 251.00 163.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 4,479.00 201.66 253.90 166.75 CR400-406 REGION-WIDE 07/17/25 620.00 358.41 371.00 278.00 C0142-070 SH 14 MP 75.5-85 08/14/25 54.00 821.21 373.33 290.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 4,321.00 183.69 184.00 175.00 Weighted Average for the Third Quarter 4,995.00 212.27 200.02 189.03 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 363.00 390.69 251.35 240.00 Weighted Average for the Fourth Quarter 363.00 390.69 251.35 240.00 Weighted Average for the Year 9,837.00 214.02 221.04 180.76 603-00030 Culvert Lining (30 In) Lin Foot CR400-406 REGION-WIDE 07/17/25 57.00 225.30 485.00 365.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 226.00 190.57 235.60 245.00 Weighted Average for the Third Quarter 283.00 197.56 268.38 269.17 Weighted Average for the Year 283.00 197.56 268.38 269.17 603-00036 Culvert Lining (36 In) Lin Foot STAR500-228 REGION 5 05/08/25 1,656.00 325.00 368.33 310.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 64.00 499.56 550.00 325.00 Weighted Average for the Second Quarter 1,720.00 331.50 375.09 310.56 Weighted Average for the Year 1,720.00 331.50 375.09 310.56 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 603-00048 Culvert Lining (48 In) Lin Foot STAR500-228 REGION 5 05/08/25 587.00 420.00 446.67 390.00 Weighted Average for the Second Quarter 587.00 420.00 446.67 390.00 CR400-406 REGION-WIDE 07/17/25 76.00 606.26 766.67 550.00 C0142-070 SH 14 MP 75.5-85 08/14/25 61.00 614.55 788.33 605.00 Weighted Average for the Third Quarter 137.00 609.95 776.31 574.49 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 105.00 625.12 577.05 565.00 Weighted Average for the Fourth Quarter 105.00 625.12 577.05 565.00 Weighted Average for the Year 829.00 477.37 522.28 442.65 603-00049 Culvert Lining (48 Inch)(Special) Lin Foot CR400-406 REGION-WIDE 07/17/25 64.00 865.38 957.67 773.00 Weighted Average for the Third Quarter 64.00 865.38 957.67 773.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 211.00 600.00 648.73 681.86 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 88.00 600.00 681.08 505.71 Weighted Average for the Fourth Quarter 299.00 600.00 658.25 630.02 Weighted Average for the Year 363.00 646.79 711.04 655.23 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-00054 Culvert Lining (54 In) Lin Foot C0142-070 SH 14 MP 75.5-85 08/14/25 62.00 800.00 821.67 740.00 Weighted Average for the Third Quarter 62.00 800.00 821.67 740.00 Weighted Average for the Year 62.00 800.00 821.67 740.00 603-00060 Culvert Lining (60 In) Lin Foot CR400-406 REGION-WIDE 07/17/25 117.00 449.14 1215.00 1170.00 Weighted Average for the Third Quarter 117.00 449.14 1215.00 1170.00 Weighted Average for the Year 117.00 449.14 1215.00 1170.00 603-01120 12 In RCP Lin Foot NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 543.00 60.11 142.00 120.00 Weighted Average for the Third Quarter 543.00 60.11 142.00 120.00 Weighted Average for the Year 543.00 60.11 142.00 120.00 603-01155 15 In RCP (CIP) Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 125.00 200.00 258.29 173.15 Weighted Average for the Fourth Quarter 125.00 200.00 258.29 173.15 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 125.00 200.00 258.29 173.15 603-01180 18 In RCP Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 125.00 120.00 233.25 259.00 Weighted Average for the First Quarter 125.00 120.00 233.25 259.00 Weighted Average for the Year 125.00 120.00 233.25 259.00 603-01185 18 In RCP (CIP) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 256.00 182.13 160.96 154.76 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 42.00 112.02 888.57 438.67 Weighted Average for the First Quarter 298.00 172.25 232.70 194.77 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2,269.00 231.96 244.87 244.87 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 54.00 233.93 233.93 233.93 Weighted Average for the Second Quarter 2,323.00 232.01 244.62 244.62 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 784.00 180.53 180.53 180.53 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 164.00 102.05 177.41 140.00 Weighted Average for the Third Quarter 948.00 166.95 178.58 173.52 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,624.00 250.00 272.04 158.14 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 47.00 235.73 479.05 346.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 6.00 265.90 643.28 450.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 1,677.00 249.66 276.66 164.46 Weighted Average for the Year 5,246.00 222.50 248.81 203.31 603-01245 24 In RCP (CIP) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 93.00 229.42 275.34 354.04 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,833.00 184.26 680.58 540.68 Weighted Average for the First Quarter 1,926.00 186.44 651.92 531.67 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3,094.00 275.00 272.66 238.30 307.89 238.30 307.89 238.30 Weighted Average for the Second Quarter 3,369.00 269.86 302.21 302.21 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 220.00 224.97 222.31 222.31 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 150.50 326.58 246.17 180.00 Weighted Average for the Third Quarter 370.50 266.25 242.48 205.12 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 576.00 300.00 377.77 206.09 Weighted Average for the Fourth Quarter 576.00 300.00 377.77 206.09 Weighted Average for the Year 6,241.50 246.68 492.26 358.38 603-01305 30 In RCP (CIP) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 156.00 217.36 227.57 201.40 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 603-01305 30 In RCP (CIP) Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 448.00 230.21 728.46 550.88 Weighted Average for the First Quarter 604.00 226.89 556.60 460.62 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 575.00 292.37 395.93 395.93 Weighted Average for the Second Quarter 575.00 292.37 395.93 395.93 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 566.00 300.00 456.24 244.96 Weighted Average for the Fourth Quarter 566.00 300.00 456.24 244.96 Weighted Average for the Year 1,745.00 272.18 499.19 369.35 603-01365 36 In RCP (CIP) Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 254.00 333.64 742.93 571.29 Weighted Average for the First Quarter 254.00 333.64 742.93 571.29 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 473.00 268.17 390.50 390.50 Weighted Average for the Second Quarter 473.00 268.17 390.50 390.50 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 232.00 319.14 313.29 313.29 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 101.50 411.79 356.44 270.00 Weighted Average for the Third Quarter 333.50 347.34 346.85 300.11 Weighted Average for the Year 1,060.50 308.75 513.87 405.38 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid STAR500-226 603-01420 42 In RCP R5 HWYS 550, 491, 285, 184, 1 12/18/25 Lin Foot 60.00 300.00 884.68 582.88 Weighted Average for the Fourth Quarter 60.00 300.00 884.68 582.88 Weighted Average for the Year 60.00 300.00 884.68 582.88 603-01425 42 In RCP (CIP) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 250.00 339.74 482.17 482.17 FBR0703-534 I-70 Weighted Average for the Second Quarter 250.00 339.74 482.17 482.17 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 349.00 625.00 662.15 363.60 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 84.00 176.76 878.12 375.00 Weighted Average for the Fourth Quarter 433.00 538.04 712.10 365.81 Weighted Average for the Year 683.00 465.46 684.28 408.40 603-01485 48 In RCP (CIP) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 63.00 422.20 554.73 554.73 FBR0703-534 I-70 Weighted Average for the Second Quarter 63.00 422.20 554.73 554.73 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 72.00 680.00 786.91 392.63 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 72.00 680.00 786.91 392.63 Weighted Average for the Year 135.00 559.69 745.23 468.28 603-01540 54 In RCP Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 80.00 500.00 995.63 671.99 Weighted Average for the Fourth Quarter 80.00 500.00 995.63 671.99 Weighted Average for the Year 80.00 500.00 995.63 671.99 603-01600 60 In RCP Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 408.00 350.00 1031.78 767.17 Weighted Average for the Fourth Quarter 408.00 350.00 1031.78 767.17 Weighted Average for the Year 408.00 350.00 1031.78 767.17 603-01605 60 In RCP (CIP) Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 132.00 902.99 1834.72 1407.82 Weighted Average for the First Quarter 132.00 902.99 1834.72 1407.82 Weighted Average for the Year 132.00 902.99 1834.72 1407.82 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 603-02185 23x14 In RCP (CIP) Lin Foot NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL I-70 VASQUEZ BLVD - I270 TO TO VET 04/11/25 64TH - 05/23/25 148.00 63.00 268.63 382.54 332.42 382.54 332.42 382.54 Weighted Average for the Second Quarter 211.00 302.64 347.38 347.38 Weighted Average for the Year 211.00 302.64 347.38 347.38 603-02245 30x19 In RCP (CIP) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 385.00 281.74 349.89 349.89 FBR0703-534 NHPP0062-040 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 166.00 351.38 351.38 351.38 Weighted Average for the Second Quarter 551.00 302.72 350.34 350.34 Weighted Average for the Year 551.00 302.72 350.34 350.34 603-02420 53x34 In RCP Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 184.00 360.00 997.98 936.27 Weighted Average for the Fourth Quarter 184.00 360.00 997.98 936.27 Weighted Average for the Year 184.00 360.00 997.98 936.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-02425 53x34 In RCP (CIP) Lin Foot CR400-406 REGION-WIDE 07/17/25 53.00 262.27 1706.67 2750.00 Weighted Average for the Third Quarter 53.00 262.27 1706.67 2750.00 Weighted Average for the Year 53.00 262.27 1706.67 2750.00 603-02540 68x43 In RCP Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 64.00 450.00 1054.09 694.27 Weighted Average for the Fourth Quarter 64.00 450.00 1054.09 694.27 Weighted Average for the Year 64.00 450.00 1054.09 694.27 603-05018 18 In RCES Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 1200.00 2917.85 3650.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 1820.40 2285.87 1435.24 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 1928.16 4202.19 2907.45 Weighted Average for the First Quarter 10.00 1531.75 2891.00 2837.06 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 14.00 5834.10 7449.29 7449.29 FBR0703-534 I-70 Weighted Average for the Second Quarter 14.00 5834.10 7449.29 7449.29 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8.00 3286.84 2982.97 2982.97 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 6.00 3149.62 2464.48 2000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 14.00 3228.03 2538.55 2561.70 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 2739.93 2936.85 3190.20 Weighted Average for the Fourth Quarter 2.00 2739.93 2936.85 3190.20 Weighted Average for the Year 40.00 3691.68 3275.89 4372.62 603-05024 24 In RCES Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 21.00 2272.89 4580.08 3876.59 Weighted Average for the First Quarter 21.00 2272.89 4580.08 3876.59 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 12.00 6089.24 7730.09 7730.09 FBR0703-534 I-70 Weighted Average for the Second Quarter 12.00 6089.24 7730.09 7730.09 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 3554.25 3250.38 3250.38 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 3.00 2884.88 2854.81 2000.00 Weighted Average for the Third Quarter 9.00 3331.13 2933.92 2833.59 Weighted Average for the Year 42.00 3590.04 4488.14 4754.09 603-05030 30 In RCES Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 7.00 1139.70 5375.98 4284.66 Weighted Average for the First Quarter 7.00 1139.70 5375.98 4284.66 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-05030 30 In RCES Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 6495.57 8184.87 8184.87 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 6495.57 8184.87 8184.87 Weighted Average for the Year 8.00 1809.18 5472.84 4772.19 603-05036 36 In RCES Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 1427.00 6777.84 4896.75 Weighted Average for the First Quarter 3.00 1427.00 6777.84 4896.75 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 5.00 7147.67 8903.27 8903.27 FBR0703-534 I-70 Weighted Average for the Second Quarter 5.00 7147.67 8903.27 8903.27 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 2.00 1467.57 4234.87 2500.00 Weighted Average for the Third Quarter 2.00 1467.57 4234.87 2500.00 Weighted Average for the Year 10.00 4295.45 5866.92 6420.66 603-05042 42 In RCES Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6.00 7282.65 11458.14 11458.14 FBR0703-534 I-70 Weighted Average for the Second Quarter 6.00 7282.65 11458.14 11458.14 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-05042 42 In RCES Each STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2.00 5383.91 5781.54 4370.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2.00 4280.00 6607.55 4345.00 Weighted Average for the Fourth Quarter 4.00 4831.95 6091.29 4357.50 Weighted Average for the Year 10.00 6302.37 7554.98 8617.88 603-05048 48 In RCES Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 7547.53 11748.75 11748.75 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 7547.53 11748.75 11748.75 Weighted Average for the Year 1.00 7547.53 11748.75 11748.75 603-05054 54 In RCES Each STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2.00 3025.00 8677.95 6985.00 Weighted Average for the Fourth Quarter 2.00 3025.00 8677.95 6985.00 Weighted Average for the Year 2.00 3025.00 8677.95 6985.00 603-05118 23x14 In RCES Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 6345.30 8010.90 8010.90 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 2.00 6345.30 8010.90 8010.90 Weighted Average for the Year 2.00 6345.30 8010.90 8010.90 603-05142 53x34 In RCES Each STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 4.00 3000.00 10152.12 10615.00 Weighted Average for the Fourth Quarter 4.00 3000.00 10152.12 10615.00 Weighted Average for the Year 4.00 3000.00 10152.12 10615.00 603-10180 18 In CSP Lin Foot NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 40.00 150.00 216.50 100.00 Weighted Average for the Second Quarter 40.00 150.00 216.50 100.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 15.00 200.00 261.00 258.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 60.00 137.96 124.54 82.00 Weighted Average for the Fourth Quarter 75.00 150.37 142.34 117.20 Weighted Average for the Year 115.00 150.24 156.30 111.22 603-10240 24 In CSP Lin Foot NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 75.00 300.00 140.50 155.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 75.00 300.00 140.50 155.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 125.00 300.00 310.00 310.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 20.00 200.00 430.00 859.99 Weighted Average for the Second Quarter 145.00 286.21 348.92 385.86 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 38.00 188.82 350.37 225.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 16.00 299.04 359.17 412.55 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 32.00 178.30 445.83 305.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 64.00 231.34 170.91 149.00 Weighted Average for the Fourth Quarter 150.00 216.47 290.72 229.65 Weighted Average for the Year 370.00 260.73 279.38 275.73 603-10300 30 In CSP Lin Foot STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 20.00 162.31 575.43 475.00 Weighted Average for the Fourth Quarter 20.00 162.31 575.43 475.00 Weighted Average for the Year 20.00 162.31 575.43 475.00 603-10360 36 In CSP Lin Foot NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 13.00 400.00 441.00 750.00 Weighted Average for the First Quarter 13.00 400.00 441.00 750.00 STAR500-228 REGION 5 05/08/25 12.00 450.00 588.33 410.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 12.00 450.00 588.33 410.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 50.00 239.84 466.70 275.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 140.00 200.00 518.59 416.45 Weighted Average for the Fourth Quarter 190.00 210.49 499.23 379.23 Weighted Average for the Year 215.00 235.31 501.54 403.36 603-10420 42 In CSP Lin Foot STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 32.00 299.95 540.23 350.00 Weighted Average for the Fourth Quarter 32.00 299.95 540.23 350.00 Weighted Average for the Year 32.00 299.95 540.23 350.00 603-15066 66 In Equiv CSPA Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 100.00 350.00 946.37 579.32 Weighted Average for the Fourth Quarter 100.00 350.00 946.37 579.32 Weighted Average for the Year 100.00 350.00 946.37 579.32 603-15072 72 In Equiv CSPA Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 40.00 625.00 1173.13 657.97 Weighted Average for the Fourth Quarter 40.00 625.00 1173.13 657.97 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 40.00 625.00 1173.13 657.97 603-30015 15 In SES Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3.00 947.51 899.76 899.76 Weighted Average for the Third Quarter 3.00 947.51 899.76 899.76 Weighted Average for the Year 3.00 947.51 899.76 899.76 603-30018 18 In SES Each NHPP0703-517 FBR0703-534 NHPPR100-420 I-70 TOP OF FLOYD I-70 VARIOUS LOCATIONS HILL TO VET 04/11/25 IN REGION 1 06/05/25 6.00 1.00 1019.87 859.01 2456.27 1968.33 2456.27 1905.00 Weighted Average for the Second Quarter 7.00 996.89 2293.62 2377.52 CR400-406 REGION-WIDE 07/17/25 2.00 808.58 876.67 550.00 Weighted Average for the Third Quarter 2.00 808.58 876.67 550.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2.00 781.92 762.10 495.00 Weighted Average for the Fourth Quarter 2.00 781.92 762.10 495.00 Weighted Average for the Year 11.00 923.57 1175.56 1702.97 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 603-30024 24 In SES Each NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 1.00 2000.00 1600.00 1600.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 4.00 2700.00 1708.33 1400.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 49.00 356.86 1883.33 1950.00 Weighted Average for the Second Quarter 54.00 560.85 1868.44 1902.78 CR400-406 REGION-WIDE 07/17/25 6.00 880.99 1126.67 770.00 Weighted Average for the Third Quarter 6.00 880.99 1126.67 770.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 3.00 942.67 1166.66 625.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 8.00 864.09 2265.93 1100.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 2.00 1105.60 1656.12 3411.50 Weighted Average for the Fourth Quarter 13.00 919.38 1918.43 1346.00 Weighted Average for the Year 73.00 651.01 1826.87 1710.52 603-30030 30 In SES Each STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 6.00 1076.87 2113.82 1090.00 Weighted Average for the Fourth Quarter 6.00 1076.87 2113.82 1090.00 Weighted Average for the Year 6.00 1076.87 2113.82 1090.00 603-30036 36 In SES Each STAR500-228 REGION 5 05/08/25 9.00 1200.00 2775.00 1900.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 9.00 1200.00 2775.00 1900.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 6.00 747.84 2615.72 1420.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 788.54 3647.13 3300.20 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 2800.00 3206.13 4038.77 Weighted Average for the Fourth Quarter 8.00 1009.44 2725.26 1982.37 STR012A-054 603-30042 Weighted Average for the Year 42 In SES SH12 MP 46.7 to MP 48.1 10/23/25 17.00 Each 1.00 1110.33 1358.20 2746.92 3132.92 1938.76 2000.00 Weighted Average for the Fourth Quarter 1.00 1358.20 3132.92 2000.00 603-30048 Weighted 48 In SES Average for the Year 1.00 Each 1358.20 3132.92 2000.00 STAR500-228 REGION 5 05/08/25 3.00 3000.00 3811.67 2700.00 Weighted Average for the Second Quarter 3.00 3000.00 3811.67 2700.00 STAR500-226 603-30060 Weighted Average for the Year 60 In SES R5 HWYS 550, 491, 285, 184, 1 12/18/25 3.00 Each 2.00 3000.00 3000.00 3811.67 6304.60 2700.00 6579.71 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 2.00 3000.00 6304.60 6579.71 Weighted Average for the Year 2.00 3000.00 6304.60 6579.71 603-31366 66 In Equiv Arch SES Each STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2.00 3000.00 7580.33 8152.71 Weighted Average for the Fourth Quarter 2.00 3000.00 7580.33 8152.71 Weighted Average for the Year 2.00 3000.00 7580.33 8152.71 603-32024 Place 24 In SES Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 4.00 1000.00 991.50 770.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 3000.00 3371.47 2244.34 Weighted Average for the First Quarter 6.00 1666.67 2181.48 1261.45 Weighted Average for the Year 6.00 1666.67 2181.48 1261.45 603-33036 36 In Pipe Safety End Treat Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 1619.65 7023.47 11000.00 Weighted Average for the Third Quarter 1.00 1619.65 7023.47 11000.00 Weighted Average for the Year 1.00 1619.65 7023.47 11000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-50006 6 In Plastic Pipe Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 245.00 41.74 42.00 42.00 Weighted Average for the Third Quarter 245.00 41.74 42.00 42.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 560.00 175.00 76.33 70.00 Weighted Average for the Fourth Quarter 560.00 175.00 76.33 70.00 Weighted Average for the Year 805.00 134.44 74.00 61.48 603-50010 10 In Plastic Pipe Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 50.00 97.58 95.11 95.11 Weighted Average for the Third Quarter 50.00 97.58 95.11 95.11 Weighted Average for the Year 50.00 97.58 95.11 95.11 603-50012 12 In Plastic Pipe Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 265.00 200.00 147.67 106.00 Weighted Average for the Fourth Quarter 265.00 200.00 147.67 106.00 Weighted Average for the Year 265.00 200.00 147.67 106.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-50015 15 In Plastic Pipe Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,525.00 136.67 135.33 135.33 Weighted Average for the Third Quarter 1,525.00 136.67 135.33 135.33 Weighted Average for the Year 1,525.00 136.67 135.33 135.33 603-50018 18 In Plastic Pipe Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,558.00 497.30 481.01 481.01 FBR0703-534 I-70 ER060A-028 CO 60 (MP 9-10) 06/18/25 310.00 175.00 186.00 132.00 Weighted Average for the Second Quarter 1,868.00 443.81 397.03 423.09 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 65.00 323.49 272.48 272.48 Weighted Average for the Third Quarter 65.00 323.49 272.48 272.48 Weighted Average for the Year 1,933.00 439.77 393.42 418.03 603-50024 24 In Plastic Pipe Lin Foot NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 5.00 1500.00 900.00 900.00 Weighted Average for the Second Quarter 5.00 1500.00 900.00 900.00 Weighted Average for the Year 5.00 1500.00 900.00 900.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-70607 6x7 Ft CBC (Precast) Lin Foot BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 64.00 1000.00 3145.00 1975.00 Weighted Average for the Fourth Quarter 64.00 1000.00 3145.00 1975.00 Weighted Average for the Year 64.00 1000.00 3145.00 1975.00 603-70808 8x8 Ft CBC (Precast) Lin Foot NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 384.00 6000.00 2233.54 2950.00 Weighted Average for the Second Quarter 384.00 6000.00 2233.54 2950.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 78.00 5500.00 3788.69 5360.00 Weighted Average for the Fourth Quarter 78.00 5500.00 3788.69 5360.00 Weighted Average for the Year 462.00 5915.58 2682.81 3356.88 603-71006 10x6 Ft CBC (Precast) Lin Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 56.00 3000.00 2830.48 1918.66 Weighted Average for the Fourth Quarter 56.00 3000.00 2830.48 1918.66 Weighted Average for the Year 56.00 3000.00 2830.48 1918.66 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 603-71606 16x6 Ft CBC (Precast) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 86.00 3382.56 3595.93 3595.93 Weighted Average for the Third Quarter 86.00 3382.56 3595.93 3595.93 Weighted Average for the Year 86.00 3382.56 3595.93 3595.93 603-71609 16x8 Ft CBC (Precast) Lin Foot FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 126.00 5000.00 3864.00 4390.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 126.00 5000.00 3864.00 4390.00 Weighted Average for the Year 126.00 5000.00 3864.00 4390.00 604-00305 Inlet Ty C (5 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 3.00 6015.36 9152.92 13540.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 4730.43 6729.42 5326.50 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 10000.00 7002.00 7800.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 6378.94 8344.80 6120.94 Weighted Average for the First Quarter 10.00 6334.67 7445.60 8364.69 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 14.00 10298.69 14623.09 14623.09 FBR0703-534 I-70 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 3.00 10000.00 10000.00 10000.00 Weighted Average for the Second Quarter 17.00 10245.98 13807.25 13807.25 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-00305 Inlet Ty C (5 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 11800.12 11830.57 11830.57 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 9692.28 15180.30 15180.30 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 3155.16 11435.17 19000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 26.00 7616.52 6764.63 6764.63 Weighted Average for the Third Quarter 31.00 7944.43 8369.31 7921.04 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3.00 10000.00 7243.67 8100.00 Weighted Average for the Fourth Quarter 3.00 10000.00 7243.67 8100.00 Weighted Average for the Year 61.00 8423.04 8670.28 9642.99 604-00310 Inlet Ty C (10 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 10992.06 17704.32 17704.32 FBR0703-534 I-70 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 8000.00 14791.09 14000.00 Weighted Average for the Second Quarter 3.00 9994.71 15762.17 16469.55 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 8099.59 9064.72 9064.72 Weighted Average for the Third Quarter 4.00 8099.59 9064.72 9064.72 Weighted Average for the Year 7.00 8911.78 13083.19 12238.22 604-00315 Inlet Ty C (15 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 12539.05 20299.87 20299.87 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-00315 Inlet Ty C (15 Ft) Each FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 12539.05 20299.87 20299.87 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 8206.57 10238.16 10238.16 Weighted Average for the Third Quarter 1.00 8206.57 10238.16 10238.16 Weighted Average for the Year 2.00 10372.81 15269.02 15269.02 604-00505 Inlet Ty D (5 Ft) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 3967.33 10668.30 7141.10 Weighted Average for the First Quarter 3.00 3967.33 10668.30 7141.10 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 1.00 11270.51 14250.01 17745.54 14250.01 17745.54 14250.01 Weighted Average for the Second Quarter 4.00 12015.39 16871.66 16871.66 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 11581.63 13042.43 13042.43 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 8046.09 8478.02 8478.02 Weighted Average for the Third Quarter 5.00 8753.20 9390.90 9390.90 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 4042.70 15649.46 13200.90 Weighted Average for the Fourth Quarter 1.00 4042.70 15649.46 13200.90 Weighted Average for the Year 13.00 8290.17 11902.60 11466.56 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-00510 Inlet Ty D (10 Ft) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 4967.81 13942.21 7549.16 Weighted Average for the First Quarter 1.00 4967.81 13942.21 7549.16 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 13149.02 21341.02 21341.02 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 13149.02 21341.02 21341.02 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 11835.78 13296.59 13296.59 Weighted Average for the Third Quarter 2.00 11835.78 13296.59 13296.59 Weighted Average for the Year 5.00 10987.48 15630.51 15364.88 604-00550 Inlet Ty D (Spec) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 7639.82 14278.95 7573.70 Weighted Average for the First Quarter 1.00 7639.82 14278.95 7573.70 Weighted Average for the Year 1.00 7639.82 14278.95 7573.70 604-13005 Inlet Ty 13 (5 Ft) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 6401.87 8994.09 5916.91 Weighted Average for the First Quarter 1.00 6401.87 8994.09 5916.91 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-13005 Inlet Ty 13 (5 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 10530.16 17900.46 17900.46 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 10530.16 17900.46 17900.46 Weighted Average for the Year 2.00 8466.01 10775.37 11908.69 604-13010 Inlet Ty 13 (10 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 12740.16 23206.70 23206.70 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 12740.16 23206.70 23206.70 Weighted Average for the Year 1.00 12740.16 23206.70 23206.70 604-13505 Inlet Ty 13 (D) (5 Ft) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 12931.21 13604.02 13604.02 Weighted Average for the Third Quarter 2.00 12931.21 13604.02 13604.02 Weighted Average for the Year 2.00 12931.21 13604.02 13604.02 604-13510 Inlet Ty 13 (D) (10 Ft) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 17318.21 19119.25 19119.25 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 2.00 17318.21 19119.25 19119.25 Weighted Average for the Year 2.00 17318.21 19119.25 19119.25 604-13605 Inlet Ty 13 (T) (5 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 18104.87 18129.17 18129.17 Weighted Average for the Third Quarter 1.00 18104.87 18129.17 18129.17 Weighted Average for the Year 1.00 18104.87 18129.17 18129.17 604-16005 Inlet Ty 16 (5 Ft) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 17.00 10200.00 8878.91 7715.63 Weighted Average for the Fourth Quarter 17.00 10200.00 8878.91 7715.63 Weighted Average for the Year 17.00 10200.00 8878.91 7715.63 604-16010 Inlet Ty 16 (10 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 7801.38 12331.81 8070.84 Weighted Average for the First Quarter 1.00 7801.38 12331.81 8070.84 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 12300.00 12032.23 9278.93 Weighted Average for the Fourth Quarter 2.00 12300.00 12032.23 9278.93 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 3.00 10800.46 12160.62 8876.23 604-16050 Inlet Ty 16 (S) (Spec) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 16700.00 14622.91 13651.62 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 9000.00 11751.58 10106.32 Weighted Average for the Fourth Quarter 9.00 14988.89 13984.83 12863.78 Weighted Average for the Year 9.00 14988.89 13984.83 12863.78 604-16505 Inlet Ty 16 (D) (5 Ft) Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 15001.14 15001.14 15001.14 Weighted Average for the Second Quarter 2.00 15001.14 15001.14 15001.14 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6.00 13400.00 16274.74 12748.96 Weighted Average for the Fourth Quarter 6.00 13400.00 16274.74 12748.96 Weighted Average for the Year 8.00 13800.29 16176.77 13312.01 604-16510 Inlet Ty 16 (D) (10 Ft) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3.00 20800.00 20400.28 16276.11 Weighted Average for the Fourth Quarter 3.00 20800.00 20400.28 16276.11 Weighted Average for the Year 3.00 20800.00 20400.28 16276.11 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-16605 Inlet Ty 16 (T) (5 Ft) Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 19733.50 19733.50 19733.50 Weighted Average for the Second Quarter 1.00 19733.50 19733.50 19733.50 Weighted Average for the Year 1.00 19733.50 19733.50 19733.50 604-16650 Inlet Ty 16 (T) (Spec) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 22000.00 25684.38 21237.50 Weighted Average for the Fourth Quarter 1.00 22000.00 25684.38 21237.50 Weighted Average for the Year 1.00 22000.00 25684.38 21237.50 604-19000 Inlet Spec Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6.00 12898.20 17315.38 17315.38 FBR0703-534 I-70 Weighted Average for the Second Quarter 6.00 12898.20 17315.38 17315.38 Weighted Average for the Year 6.00 12898.20 17315.38 17315.38 604-19005 Inlet Spec (5 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 5847.63 3352.21 3352.21 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 2.00 5847.63 3352.21 3352.21 Weighted Average for the Year 2.00 5847.63 3352.21 3352.21 604-19020 Inlet Spec (20 Ft) Each NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 3.00 30000.00 18500.00 18500.00 Weighted Average for the Second Quarter 3.00 30000.00 18500.00 18500.00 Weighted Average for the Year 3.00 30000.00 18500.00 18500.00 604-19105 Inlet Ty R L5 (5 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 6.00 7967.26 8913.03 8253.16 Weighted Average for the First Quarter 6.00 7967.26 8913.03 8253.16 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 11027.42 17713.91 17713.91 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 11027.42 17713.91 17713.91 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 14547.48 14567.65 14567.65 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3.00 11754.21 11307.65 11307.65 Weighted Average for the Third Quarter 4.00 12452.53 12122.65 12122.65 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 12000.00 11917.04 10618.15 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2.00 10000.00 10169.17 12000.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 4.00 11000.00 10868.32 11309.08 Weighted Average for the Year 16.00 10229.28 10034.74 11167.11 604-19110 Inlet Ty R L5 (10 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 5.00 5683.25 10847.41 9159.46 Weighted Average for the First Quarter 5.00 5683.25 10847.41 9159.46 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 1.00 18813.58 12982.30 19491.21 12982.30 19491.21 12982.30 Weighted Average for the Second Quarter 3.00 16869.82 17321.57 17321.57 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 13359.21 14022.92 14022.92 Weighted Average for the Third Quarter 2.00 13359.21 14022.92 14022.92 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 5.00 15000.00 15530.12 13270.47 Weighted Average for the Fourth Quarter 5.00 15000.00 15530.12 13270.47 Weighted Average for the Year 15.00 12049.61 13018.82 12810.68 604-19205 Inlet Ty R L10 (5 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 5.00 5512.59 12975.33 11111.98 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 5562.46 15494.83 11221.72 Weighted Average for the First Quarter 6.00 5520.90 13271.74 11130.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-19205 Inlet Ty R L10 (5 Ft) Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6.00 16344.16 16344.16 16344.16 Weighted Average for the Second Quarter 6.00 16344.16 16344.16 16344.16 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 20491.15 18884.21 18884.21 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 14643.21 15475.10 15475.10 Weighted Average for the Third Quarter 3.00 16592.52 16611.47 16611.47 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 17000.00 19498.53 15694.10 Weighted Average for the Fourth Quarter 1.00 17000.00 19498.53 15694.10 Weighted Average for the Year 16.00 12373.00 14407.08 14398.44 604-19210 Inlet Ty R L10 (10 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 6711.17 16235.59 14513.52 Weighted Average for the First Quarter 2.00 6711.17 16235.59 14513.52 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 20491.15 22138.43 22138.43 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 16890.21 19011.78 19011.78 Weighted Average for the Third Quarter 3.00 18090.52 20054.00 20054.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 15750.00 25209.17 21000.00 Weighted Average for the Fourth Quarter 1.00 15750.00 25209.17 21000.00 Weighted Average for the Year 6.00 13907.32 19051.74 18364.84 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-19310 Inlet Ty R L15 (10 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 8131.27 21629.10 18224.58 Weighted Average for the First Quarter 1.00 8131.27 21629.10 18224.58 Weighted Average for the Year 1.00 8131.27 21629.10 18224.58 604-19712 Inlet Spec (Trench) (12 In) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 7.00 6057.86 865.41 865.41 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 204.00 285.00 498.00 400.00 Weighted Average for the Third Quarter 211.00 476.52 500.50 415.44 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 28.00 400.00 506.61 650.00 Weighted Average for the Fourth Quarter 28.00 400.00 506.61 650.00 Weighted Average for the Year 239.00 467.55 501.36 442.92 604-19724 Inlet Spec (Trench) (24 Inch) Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 14.00 5000.00 1334.33 3750.00 Weighted Average for the Fourth Quarter 14.00 5000.00 1334.33 3750.00 Weighted Average for the Year 14.00 5000.00 1334.33 3750.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-20000 Outlet Structure Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 5.00 33895.84 37634.71 37634.71 FBR0703-534 I-70 Weighted Average for the Second Quarter 5.00 33895.84 37634.71 37634.71 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 50600.56 50878.50 50878.50 Weighted Average for the Third Quarter 1.00 50600.56 50878.50 50878.50 Weighted Average for the Year 6.00 36679.96 39842.01 39842.01 604-20015 Detention Forebay (w/ Energy Dissipator) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 18080.42 17982.07 17982.07 Weighted Average for the Third Quarter 3.00 18080.42 17982.07 17982.07 Weighted Average for the Year 3.00 18080.42 17982.07 17982.07 604-25000 Vane Grate Inlet Spec Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3.00 24373.04 16364.07 16364.07 FBR0703-534 I-70 Weighted Average for the Second Quarter 3.00 24373.04 16364.07 16364.07 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3.00 18021.87 15827.32 15827.32 Weighted Average for the Third Quarter 3.00 18021.87 15827.32 15827.32 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 6.00 21197.46 16095.70 16095.70 604-25005 Vane Grate Inlet (5 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 4027.37 7929.62 5577.72 Weighted Average for the First Quarter 2.00 4027.37 7929.62 5577.72 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 29.00 17601.19 19824.21 19824.21 FBR0703-534 I-70 Weighted Average for the Second Quarter 29.00 17601.19 19824.21 19824.21 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2.00 4054.83 11918.43 6332.00 Weighted Average for the Fourth Quarter 2.00 4054.83 11918.43 6332.00 Weighted Average for the Year 33.00 15957.54 14892.23 18143.08 604-25006 Vane Grate Inlet Spec (5 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4.00 24373.04 16364.29 16364.29 FBR0703-534 I-70 Weighted Average for the Second Quarter 4.00 24373.04 16364.29 16364.29 Weighted Average for the Year 4.00 24373.04 16364.29 16364.29 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-25010 Vane Grate Inlet (10 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 4946.69 9690.45 6937.70 Weighted Average for the First Quarter 2.00 4946.69 9690.45 6937.70 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 5.00 16747.58 22501.27 22501.27 FBR0703-534 I-70 Weighted Average for the Second Quarter 5.00 16747.58 22501.27 22501.27 Weighted Average for the Year 7.00 13375.90 13458.34 18054.54 604-25016 Vane Grate Inlet Spec (15 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 12898.18 37899.25 37899.25 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 12898.18 37899.25 37899.25 Weighted Average for the Year 1.00 12898.18 37899.25 37899.25 604-25025 Vane Grate Inlet (25 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 25668.66 69734.10 69734.10 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 25668.66 69734.10 69734.10 Weighted Average for the Year 1.00 25668.66 69734.10 69734.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-26005 Vane Grate Inlet (D) (5 Ft) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 9.00 20689.67 26947.04 26947.04 Weighted Average for the Second Quarter 9.00 20689.67 26947.04 26947.04 Weighted Average for the Year 9.00 20689.67 26947.04 26947.04 604-26010 Vane Grate Inlet (D) (10 Ft) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 4.00 20505.25 29479.90 29479.90 Weighted Average for the Second Quarter 4.00 20505.25 29479.90 29479.90 Weighted Average for the Year 4.00 20505.25 29479.90 29479.90 604-30005 MH Slab Base (5 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 5081.41 8681.51 10389.06 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 5492.24 12068.30 7141.10 Weighted Average for the First Quarter 4.00 5286.83 10036.23 8765.08 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 5.00 11118.95 15923.80 15923.80 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 11490.09 11490.09 11490.09 Weighted Average for the Second Quarter 8.00 11258.13 14261.16 14261.16 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-30005 MH Slab Base (5 Ft) Each FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 8544.67 13394.56 13394.56 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 6398.71 11500.00 8500.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 12121.33 8670.01 8670.01 Weighted Average for the Third Quarter 6.00 9021.57 11366.37 10188.19 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 8500.00 12675.83 8268.33 Weighted Average for the Fourth Quarter 1.00 8500.00 12675.83 8268.33 Weighted Average for the Year 19.00 9149.57 11405.35 11502.48 604-30010 MH Slab Base (10 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 6805.46 10548.18 10389.06 Weighted Average for the First Quarter 3.00 6805.46 10548.18 10389.06 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 23.00 4.00 14730.22 15000.00 16853.31 10000.00 16853.31 10000.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 12167.10 12167.10 12167.10 Weighted Average for the Second Quarter 30.00 14509.88 15470.91 15470.91 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 12986.47 13079.79 13079.79 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 17197.48 16465.69 16465.69 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 12475.50 20981.90 20981.90 Weighted Average for the Third Quarter 7.00 13442.05 15821.24 15821.24 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4.00 9000.00 20089.58 15358.32 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 604-30010 MH Slab Base (10 Ft) Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 11500.00 9771.50 10600.00 Weighted Average for the Fourth Quarter 5.00 9500.00 17275.56 14406.66 Weighted Average for the Year 45.00 13273.49 14867.60 15068.37 604-30015 MH Slab Base (15 Ft) Each NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 2.00 20000.00 29000.00 29000.00 Weighted Average for the Second Quarter 2.00 20000.00 29000.00 29000.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 15729.84 15729.84 15729.84 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 14187.49 13681.47 13681.47 Weighted Average for the Third Quarter 2.00 14958.67 14705.66 14705.66 Weighted Average for the Year 4.00 17479.33 21852.83 21852.83 604-30020 MH Slab Base (20 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 16937.48 31681.12 31681.12 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 16937.48 31681.12 31681.12 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 15257.49 20283.01 20283.01 Weighted Average for the Third Quarter 1.00 15257.49 20283.01 20283.01 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2.00 16097.49 25982.07 25982.07 604-31010 MH Box Base (10 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 13085.83 35213.87 35213.87 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 13085.83 35213.87 35213.87 Weighted Average for the Year 2.00 13085.83 35213.87 35213.87 604-39000 MH Spec Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 35000.00 13519.00 12614.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 15820.24 20783.79 15303.03 Weighted Average for the First Quarter 3.00 28606.75 15335.20 13510.34 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 17090.16 17090.03 17090.03 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 17090.16 17090.03 17090.03 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 2500.00 2126.67 2800.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 20000.00 28980.00 28960.00 Weighted Average for the Fourth Quarter 5.00 6000.00 4192.31 8032.00 Weighted Average for the Year 9.00 14767.82 8638.45 10864.56 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 604-39005 MH Spec (5 Ft) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 1.00 18214.51 18214.38 18214.38 Weighted Average for the Second Quarter 1.00 18214.51 18214.38 18214.38 Weighted Average for the Year 1.00 18214.51 18214.38 18214.38 604-39050 MH (TMS) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 10.00 20368.11 17090.03 17090.03 FBR0703-534 I-70 Weighted Average for the Second Quarter 10.00 20368.11 17090.03 17090.03 Weighted Average for the Year 10.00 20368.11 17090.03 17090.03 604-50050 IG and F Spec Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2.00 5000.00 4975.83 5380.00 Weighted Average for the Fourth Quarter 2.00 5000.00 4975.83 5380.00 Weighted Average for the Year 2.00 5000.00 4975.83 5380.00 604-83108 8 In PPS (PVC) Lin Foot FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 239.40 511.28 718.56 718.56 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 239.40 511.28 718.56 718.56 Weighted Average for the Year 239.40 511.28 718.56 718.56 605-00040 4 In PP Underdrain Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 45.00 60.76 60.48 60.48 FBR0703-534 I-70 Weighted Average for the Second Quarter 45.00 60.76 60.48 60.48 Weighted Average for the Year 45.00 60.76 60.48 60.48 605-00060 6 In PP Underdrain Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,350.00 80.00 63.83 56.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 359.00 39.43 33.25 52.50 Weighted Average for the Fourth Quarter 1,709.00 71.48 61.34 55.26 Weighted Average for the Year 1,709.00 71.48 61.34 55.26 605-00061 6 In PP Underdrain (Special) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6,018.00 60.68 48.92 48.92 FBR0703-534 I-70 Weighted Average for the Second Quarter 6,018.00 60.68 48.92 48.92 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 6,018.00 60.68 48.92 48.92 605-82100 Pipe Edge Drain Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,595.00 13.08 37.33 34.98 Weighted Average for the First Quarter 1,595.00 13.08 37.33 34.98 Weighted Average for the Year 1,595.00 13.08 37.33 34.98 605-82105 Pipe Edge Drain (Special) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 456.00 49.87 49.87 49.87 Weighted Average for the Third Quarter 456.00 49.87 49.87 49.87 Weighted Average for the Year 456.00 49.87 49.87 49.87 605-83001 Geocomp Drain (w/o Pipe) Sq Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 58.00 119.49 128.93 128.93 Weighted Average for the Third Quarter 58.00 119.49 128.93 128.93 Weighted Average for the Year 58.00 119.49 128.93 128.93 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 605-84000 Subsurface Drain Outlet Lin Foot STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 165.00 80.00 50.09 90.00 Weighted Average for the First Quarter 165.00 80.00 50.09 90.00 Weighted Average for the Year 165.00 80.00 50.09 90.00 606-00301 Gdrail Ty 3 (6-3) Lin Foot NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 3,334.00 55.00 36.03 36.25 Weighted Average for the First Quarter 3,334.00 55.00 36.03 36.25 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 9,341.00 49.28 51.35 51.35 FBR0703-534 I-70 Weighted Average for the Second Quarter 9,341.00 49.28 51.35 51.35 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 19,037.50 45.08 45.07 45.07 Weighted Average for the Third Quarter 19,037.50 45.08 45.07 45.07 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 6,772.00 100.00 32.90 33.60 Weighted Average for the Fourth Quarter 6,772.00 100.00 32.90 33.60 Weighted Average for the Year 38,484.50 56.62 40.57 43.81 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-00302 Gdrail Ty 3 (31 In MGS) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 140.00 65.75 46.07 42.40 BR0761-249 I-76 02/27/25 1,500.00 50.00 52.23 60.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,870.00 55.00 50.98 35.03 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1,762.50 60.00 70.50 42.00 Weighted Average for the First Quarter 5,272.50 55.53 54.62 44.66 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 537.50 43.73 43.73 43.73 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 575.00 50.00 55.71 80.00 Weighted Average for the Second Quarter 1,112.50 46.97 53.44 62.48 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2,688.00 40.63 40.74 40.74 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 175.00 110.28 110.28 110.28 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 313.00 95.48 59.04 45.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 388.00 50.00 54.10 34.50 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 537.50 24.00 60.00 62.22 95.88 73.93 95.00 60.00 Weighted Average for the Third Quarter 4,125.50 51.28 64.87 50.61 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 15,765.00 61.07 40.92 32.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 637.50 52.00 50.57 34.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1,087.50 60.00 37.84 36.90 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2,912.50 55.00 37.38 34.75 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,762.50 95.00 35.02 30.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 912.50 49.05 35.42 28.60 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 825.00 74.98 39.90 35.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 2,096.00 50.00 34.60 32.20 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1,399.00 70.00 41.62 41.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 35,138.00 50.00 43.40 41.80 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 769.00 45.80 43.00 43.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-00302 Gdrail Ty 3 (31 In MGS) Lin Foot NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 23,726.00 55.00 32.90 31.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 762.50 50.00 42.35 44.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2,700.00 50.00 51.86 60.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 63.00 89.62 43.78 46.10 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 750.00 60.00 44.20 37.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 9,213.00 39.55 29.39 29.00 Weighted Average for the Fourth Quarter 100,519.00 53.55 38.97 36.15 Weighted Average for the Year 111,029.50 53.50 41.06 37.35 606-00303 Gdrail Ty 3 (31 In MGS) (Stained) Lin Foot STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 200.00 115.00 75.30 75.30 Weighted Average for the Second Quarter 200.00 115.00 75.30 75.30 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1,900.00 55.80 60.00 60.00 Weighted Average for the Fourth Quarter 1,900.00 55.80 60.00 60.00 Weighted Average for the Year 2,100.00 61.44 61.46 61.46 606-00355 Gdrail Ty 3 (D)(Spec) Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 37.50 145.01 145.01 145.01 Weighted Average for the Second Quarter 37.50 145.01 145.01 145.01 Weighted Average for the Year 37.50 145.01 145.01 145.01 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-00710 Gdrail Ty 7 (Sty CA) Lin Foot STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 68.00 275.00 472.00 409.00 Weighted Average for the First Quarter 68.00 275.00 472.00 409.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 60.00 450.00 700.00 700.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 10.00 254.82 254.82 254.82 Weighted Average for the Second Quarter 70.00 422.12 636.40 636.40 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 311.00 118.34 331.60 240.00 Weighted Average for the Fourth Quarter 311.00 118.34 331.60 240.00 Weighted Average for the Year 449.00 189.42 359.48 327.39 606-00910 Guardrail Type 9 (Style CA) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 494.00 65.80 150.01 141.05 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1,511.00 250.00 169.12 200.00 Weighted Average for the First Quarter 2,005.00 204.62 159.65 185.48 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 7,045.00 168.38 166.14 166.14 FBR0703-534 I-70 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 200.00 450.00 675.00 675.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 641.00 113.85 113.85 113.85 Weighted Average for the Second Quarter 7,886.00 171.09 174.80 174.80 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 137.00 297.67 391.00 350.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-00910 Guardrail Type 9 (Style CA) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 200.00 275.88 311.93 311.93 Weighted Average for the Third Quarter 337.00 284.74 373.13 327.41 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 700.00 200.00 232.00 290.00 Weighted Average for the Fourth Quarter 700.00 200.00 232.00 290.00 Weighted Average for the Year 10,928.00 182.60 185.01 188.84 606-00916 Guardrail Type 9 (Style CA) (Special) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4,376.00 191.23 196.72 196.72 FBR0703-534 I-70 Weighted Average for the Second Quarter 4,376.00 191.23 196.72 196.72 Weighted Average for the Year 4,376.00 191.23 196.72 196.72 606-00930 Guardrail Type 9 (Style CD) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3,224.00 143.43 153.92 153.92 FBR0703-534 I-70 Weighted Average for the Second Quarter 3,224.00 143.43 153.92 153.92 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 895.00 150.00 672.20 220.00 Weighted Average for the Third Quarter 895.00 150.00 672.20 220.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 4,119.00 144.86 511.28 168.28 606-00931 Guardrail Type 9 (Style CD) (Special) Lin Foot NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL I-70 VASQUEZ BLVD - I270 TO TO VET 04/11/25 64TH - 05/23/25 103.00 183.00 352.54 278.80 367.90 278.80 367.90 278.80 Weighted Average for the Second Quarter 286.00 305.36 310.89 310.89 Weighted Average for the Year 286.00 305.36 310.89 310.89 606-00940 Guardrail Type 9 (Style CE) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 2,974.00 360.65 363.37 363.37 Weighted Average for the Second Quarter 2,974.00 360.65 363.37 363.37 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 439.00 391.09 402.19 402.19 Weighted Average for the Third Quarter 439.00 391.09 402.19 402.19 Weighted Average for the Year 3,413.00 364.57 368.36 368.36 606-00941 Guardrail Type 9 (Style CE) (Special) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 260.00 641.56 650.72 650.72 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 260.00 641.56 650.72 650.72 Weighted Average for the Year 260.00 641.56 650.72 650.72 606-00942 Guardrail Type 9 (Style CGE) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 2,998.00 277.00 277.77 277.77 Weighted Average for the Second Quarter 2,998.00 277.00 277.77 277.77 Weighted Average for the Year 2,998.00 277.00 277.77 277.77 606-00943 Guardrail Type 9 (Style CGE) (Special) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 39.00 790.86 814.79 814.79 Weighted Average for the Second Quarter 39.00 790.86 814.79 814.79 Weighted Average for the Year 39.00 790.86 814.79 814.79 606-00944 Guardrail Type 9 (Style CGD) (Special) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 139.00 500.00 400.21 450.28 Weighted Average for the First Quarter 139.00 500.00 400.21 450.28 Weighted Average for the Year 139.00 500.00 400.21 450.28 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 606-01320 End Anchor Ty 3B Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 1312.91 4827.87 1287.88 Weighted Average for the First Quarter 1.00 1312.91 4827.87 1287.88 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 4000.00 2140.34 1500.00 Weighted Average for the Fourth Quarter 4.00 4000.00 2140.34 1500.00 Weighted Average for the Year 5.00 3462.58 2812.23 1457.58 606-01321 End Anchor Ty 3B (31 In MGS) Lin Foot NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 7.00 70.00 2130.00 3000.00 Weighted Average for the Fourth Quarter 7.00 70.00 2130.00 3000.00 Weighted Average for the Year 7.00 70.00 2130.00 3000.00 606-01340 End Anchor Ty 3D Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 2009.36 2339.00 2014.00 Weighted Average for the First Quarter 1.00 2009.36 2339.00 2014.00 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 2700.00 3225.00 3225.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 6.00 1.00 1836.09 2386.71 1836.09 2386.71 1836.09 2386.71 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 3500.00 3548.03 5000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 9.00 2178.14 2568.37 2403.14 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 1757.96 1668.66 1668.66 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 2070.95 2350.00 1750.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 19.00 1385.65 1474.19 1474.19 Weighted Average for the Third Quarter 23.00 1477.62 1769.26 1515.08 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4.00 2400.03 1624.70 1488.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 10.00 2500.00 1702.50 1680.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 8.00 3000.00 1500.00 1525.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 36.00 2400.00 1842.50 2110.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2.00 3500.00 1775.00 1780.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 5.00 1911.50 1832.53 1900.00 Weighted Average for the Fourth Quarter 65.00 2485.50 1740.59 1907.29 Weighted Average for the Year 98.00 2215.87 1811.24 1861.87 606-01370 Transition Ty 3G Each BR0761-249 I-76 02/27/25 8.00 4000.00 6627.87 4200.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 18.00 5700.00 9610.00 3720.00 Weighted Average for the First Quarter 26.00 5176.92 7905.92 3867.69 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 21.00 4.00 8047.53 8407.10 8047.53 8407.10 8047.53 8407.10 Weighted Average for the Second Quarter 25.00 8105.06 8105.06 8105.06 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 7686.38 9343.78 9343.78 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-01370 Transition Ty 3G Each MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 5.00 5524.61 4504.63 4300.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 4320.93 5170.00 4250.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 4022.68 4954.34 3000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10.00 3798.50 4041.22 4041.22 Weighted Average for the Third Quarter 20.00 4682.27 4810.54 4604.99 NHPPR500-227 REGION 5 SECTION 7 10/23/25 8.00 5000.00 4576.28 4140.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 4.00 4151.90 3022.74 2947.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 8.00 5418.42 3642.50 3315.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 3.00 3742.04 3429.21 3200.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 10.00 3919.95 3817.00 3450.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4.00 4185.12 3717.28 3367.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 4.00 5500.00 3155.00 3110.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 6.00 4200.00 3820.55 3200.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 12.00 3000.00 4775.00 4450.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 4.00 4428.32 3800.00 3800.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 16.00 5000.00 4030.00 3200.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 4.00 6000.00 3185.00 3200.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 3698.39 3424.37 3634.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 3963.58 3364.03 3500.00 Weighted Average for the Fourth Quarter 91.00 4425.08 3849.88 3535.99 Weighted Average for the Year 162.00 5145.40 4982.88 4426.30 606-01371 Transition Ty 3G (Spec) Each STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 4.00 3320.90 4642.50 4225.00 Weighted Average for the Fourth Quarter 4.00 3320.90 4642.50 4225.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 4.00 3320.90 4642.50 4225.00 606-01372 Transition Ty GR9-GR3 Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 24.00 7171.41 7336.56 7336.56 FBR0703-534 I-70 Weighted Average for the Second Quarter 24.00 7171.41 7336.56 7336.56 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4.00 7500.00 8801.38 9000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 6955.00 6955.00 6955.00 Weighted Average for the Third Quarter 6.00 7318.33 8692.76 8318.33 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 15000.00 21564.50 13000.00 Weighted Average for the Fourth Quarter 1.00 15000.00 21564.50 13000.00 Weighted Average for the Year 31.00 7452.38 8792.21 7709.27 606-01380 Transition Ty 3H Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 13.00 3454.52 3454.52 3454.52 FBR0703-534 I-70 Weighted Average for the Second Quarter 13.00 3454.52 3454.52 3454.52 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 9.00 1599.65 1701.87 1701.87 Weighted Average for the Third Quarter 9.00 1599.65 1701.87 1701.87 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 4.00 858.53 1642.09 1750.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-01380 Transition Ty 3H Each NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 2.00 869.33 2454.10 2425.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 4.00 2000.00 1955.00 1910.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 11.00 2400.00 2635.00 2820.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2.00 6000.00 2310.00 2320.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 3.00 869.33 1763.93 1800.00 Weighted Average for the Fourth Quarter 26.00 2083.88 2236.12 2328.88 Weighted Average for the Year 48.00 2364.30 2369.02 2516.18 606-01385 Transition Ty 3J Each STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 2.00 4000.00 5705.00 3110.00 Weighted Average for the First Quarter 2.00 4000.00 5705.00 3110.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 1269.11 2806.94 2250.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 1235.85 1314.82 1314.82 Weighted Average for the Third Quarter 5.00 1242.50 2309.57 1501.86 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1.00 1279.07 1637.75 1095.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1.00 3500.00 2333.78 1270.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 4.00 1292.39 2644.00 2405.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 1273.96 2168.00 2620.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 4500.00 2885.57 2400.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 3000.00 1420.00 1400.00 Weighted Average for the Fourth Quarter 9.00 2080.29 2283.65 2045.00 Weighted Average for the Year 16.00 2058.44 2616.90 2008.39 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-01390 End Anchor Ty 3K Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 1214.03 3266.33 2968.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 2.00 4000.00 5125.00 2550.00 Weighted Average for the First Quarter 3.00 3071.34 4009.80 2689.33 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 3813.36 3813.31 3813.31 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 1243.20 2796.14 2200.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 2300.50 2447.50 2447.50 Weighted Average for the Third Quarter 7.00 2581.70 2841.84 2802.37 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1.00 2600.00 3196.45 2840.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 6.00 2326.10 2233.15 2177.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 4.00 1250.36 2527.00 2300.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 2599.35 2300.00 2200.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 4500.00 2895.55 2500.00 Weighted Average for the Fourth Quarter 13.00 2204.42 2499.57 2292.78 Weighted Average for the Year 23.00 2432.32 2854.82 2499.60 606-01395 Transition Ty 3L Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 2243.49 2288.13 2288.13 Weighted Average for the Third Quarter 2.00 2243.49 2288.13 2288.13 Weighted Average for the Year 2.00 2243.49 2288.13 2288.13 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 606-01400 Transition Type BR10M-GR3 Each BR0761-249 I-76 02/27/25 4.00 7000.00 10989.00 8000.00 Weighted Average for the First Quarter 4.00 7000.00 10989.00 8000.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 3566.13 3566.13 3566.13 Weighted Average for the Second Quarter 1.00 3566.13 3566.13 3566.13 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 9010.17 15067.55 15067.55 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 5.00 6630.94 6132.72 3945.00 Weighted Average for the Third Quarter 7.00 7310.72 6944.97 7122.87 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 8.00 10000.00 13145.00 13790.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 5000.00 4960.00 6700.00 Weighted Average for the Fourth Quarter 9.00 9444.44 12235.56 13002.22 Weighted Average for the Year 21.00 7987.67 9851.25 9640.30 606-01402 Transition Type BR10B-GR3 Each STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 14.00 180.00 20145.00 17290.00 Weighted Average for the First Quarter 14.00 180.00 20145.00 17290.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 5797.57 7834.30 7834.30 Weighted Average for the Third Quarter 2.00 5797.57 7834.30 7834.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-01402 Transition Type BR10B-GR3 Each STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 10000.00 15782.02 18000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 4.00 17000.00 19995.00 17000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 3.00 20000.00 26887.50 24795.00 Weighted Average for the Fourth Quarter 11.00 15272.73 19641.12 19489.55 Weighted Average for the Year 27.00 6745.01 19471.39 17485.69 606-01403 Transition Type BR9-GR9 Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 32.00 7705.18 5272.39 5272.39 FBR0703-534 I-70 Weighted Average for the Second Quarter 32.00 7705.18 5272.39 5272.39 Weighted Average for the Year 32.00 7705.18 5272.39 5272.39 606-01407 Transition Type BR9-GR3 Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 8.00 9712.26 7476.58 7476.58 FBR0703-534 I-70 Weighted Average for the Second Quarter 8.00 9712.26 7476.58 7476.58 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 12.00 8815.17 6801.70 6801.70 Weighted Average for the Third Quarter 12.00 8815.17 6801.70 6801.70 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 6860.55 6766.73 6942.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 4.00 6860.55 6766.73 6942.00 Weighted Average for the Year 24.00 8788.43 6868.37 7050.04 606-01460 Median Terminal Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 13767.34 13767.34 13767.34 Weighted Average for the Second Quarter 3.00 13767.34 13767.34 13767.34 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 3.00 14000.00 8545.00 8770.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 4.00 14000.00 9755.00 9950.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 9404.64 6744.10 6900.00 Weighted Average for the Fourth Quarter 11.00 12328.96 8133.59 8519.09 Weighted Average for the Year 14.00 12637.18 8661.76 9643.72 606-02003 End Anchor (Nonflared) Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 5000.00 1950.13 38.25 BR0761-249 I-76 02/27/25 8.00 5000.00 5167.89 4000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 4.00 2441.03 6160.75 3482.42 Weighted Average for the First Quarter 13.00 4212.63 5311.07 3535.99 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 12.00 6244.92 6244.93 6244.93 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 4739.57 4739.57 4739.57 Weighted Average for the Second Quarter 13.00 6129.12 6129.13 6129.13 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-02003 End Anchor (Nonflared) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 4431.16 4464.65 4464.65 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 4.00 2500.00 4340.96 4200.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 19.00 4012.50 4268.89 4268.89 Weighted Average for the Third Quarter 25.00 3803.99 4313.60 4273.53 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 61.00 2501.61 4689.75 5975.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 7.00 4500.00 4857.31 3800.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 16.00 2498.98 3841.93 3746.55 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 34.00 3500.00 3987.50 3625.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 19.00 3200.00 3697.23 3500.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 6.00 2497.48 3938.00 3975.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 11.00 5000.00 3989.85 3400.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 11.00 2498.98 3388.33 3480.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 3700.00 4955.00 4450.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 4.00 6000.00 3485.00 3500.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 3.00 4500.00 5477.59 6050.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 3597.04 3289.65 3670.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 10.00 2433.10 3473.37 3500.00 Weighted Average for the Fourth Quarter 187.00 3108.42 4200.65 4420.21 Weighted Average for the Year 238.00 3406.79 4344.69 4449.85 606-02004 End Anchor (Nonflared) (Stained) Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 8000.00 8495.00 8495.00 Weighted Average for the Second Quarter 1.00 8000.00 8495.00 8495.00 Weighted Average for the Year 1.00 8000.00 8495.00 8495.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 606-02005 End Anchor (Flared) Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 5.00 6000.00 4095.50 4350.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 5.00 4743.16 6832.43 3554.55 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 12.00 6500.00 8390.00 3780.00 Weighted Average for the First Quarter 22.00 5987.08 7017.84 3858.31 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 3.00 5000.00 5358.25 7800.00 Weighted Average for the Second Quarter 3.00 5000.00 5358.25 7800.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 5525.00 8997.91 8997.91 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 1.00 4240.76 4439.38 4500.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 4.00 3960.08 5164.00 4150.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10.00 4039.25 4297.36 4297.36 Weighted Average for the Third Quarter 16.00 4124.91 4943.11 4566.97 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 7.00 4111.89 3912.00 3950.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4.00 4376.08 3620.40 3197.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 10.00 5500.00 3415.00 3330.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 29.00 4000.00 4705.00 4770.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 8.00 4369.44 10000.00 10000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 49.00 5200.00 5820.00 7500.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 9.00 4600.00 5412.55 5808.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 5000.00 3680.00 3500.00 Weighted Average for the Fourth Quarter 120.00 4737.02 4967.19 6048.67 Weighted Average for the Year 161.00 4851.91 5263.28 5634.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 606-02006 End Anchor (Flared) (Stained) Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 8000.00 8090.00 8090.00 Weighted Average for the Second Quarter 4.00 8000.00 8090.00 8090.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 6.00 4969.44 12000.00 12000.00 Weighted Average for the Fourth Quarter 6.00 4969.44 12000.00 12000.00 Weighted Average for the Year 10.00 6181.66 10436.00 10436.00 606-10200 Brdg Rail (Spec) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 103.00 254.40 270.28 270.28 FBR0703-534 I-70 Weighted Average for the Second Quarter 103.00 254.40 270.28 270.28 Weighted Average for the Year 103.00 254.40 270.28 270.28 606-10305 Brdg Rail Ty 3 (Spec) Lin Foot NHPPR500-227 REGION 5 SECTION 7 10/23/25 707.00 295.00 222.19 163.00 Weighted Average for the Fourth Quarter 707.00 295.00 222.19 163.00 Weighted Average for the Year 707.00 295.00 222.19 163.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0701-257 606-10700 Brdg Rail Ty 7 MP 138-148 ON I-70 IN EAGLE C 12/04/25 Lin Foot 69.00 500.00 1395.00 1390.00 Weighted Average for the Fourth Quarter 69.00 500.00 1395.00 1390.00 Weighted Average for the Year 69.00 500.00 1395.00 1390.00 606-10705 Brdg Rail Ty 7 (Spec) Lin Foot NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 131.00 290.83 444.93 413.00 Weighted Average for the Fourth Quarter 131.00 290.83 444.93 413.00 Weighted Average for the Year 131.00 290.83 444.93 413.00 606-10810 Bridge Rail Type 8R MASH Lin Foot NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 1,180.00 300.00 643.61 510.00 Weighted Average for the First Quarter 1,180.00 300.00 643.61 510.00 Weighted Average for the Year 1,180.00 300.00 643.61 510.00 606-10900 Brdg Rail Ty 9 Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 28,476.00 237.12 235.37 235.37 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 28,476.00 237.12 235.37 235.37 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 790.00 384.29 367.97 367.97 Weighted Average for the Third Quarter 790.00 384.29 367.97 367.97 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 573.00 484.67 320.95 323.00 Weighted Average for the Fourth Quarter 573.00 484.67 320.95 323.00 Weighted Average for the Year 29,839.00 245.77 252.38 240.56 606-10905 Brdg Rail Ty 9 (Spec) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 76.00 239.73 329.82 329.82 FBR0703-534 I-70 Weighted Average for the Second Quarter 76.00 239.73 329.82 329.82 Weighted Average for the Year 76.00 239.73 329.82 329.82 606-11035 Brdg Rail Ty 10 MASH Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 543.00 351.05 295.02 295.02 FBR0703-534 I-70 Weighted Average for the Second Quarter 543.00 351.05 295.02 295.02 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 316.00 340.95 425.89 425.89 Weighted Average for the Third Quarter 316.00 340.95 425.89 425.89 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 859.00 347.33 343.16 343.16 606-11037 Brdg Rail Ty 10R MASH Lin Foot BR0761-249 I-76 02/27/25 760.00 250.00 329.55 350.00 Weighted Average for the First Quarter 760.00 250.00 329.55 350.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 853.00 406.00 376.37 330.00 Weighted Average for the Third Quarter 853.00 406.00 376.37 330.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 741.00 350.00 176.50 173.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 19.00 350.00 1160.00 2120.00 Weighted Average for the Fourth Quarter 760.00 350.00 201.09 221.68 Weighted Average for the Year 2,373.00 338.10 325.81 301.71 606-20010 High-Tension Cable Barrier Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 33,320.00 37.99 41.30 41.30 Weighted Average for the Third Quarter 33,320.00 37.99 41.30 41.30 Weighted Average for the Year 33,320.00 37.99 41.30 41.30 606-21010 End Anchor (High-Tens Cab Bar) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 28.00 6018.75 6403.34 6403.34 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 28.00 6018.75 6403.34 6403.34 Weighted Average for the Year 28.00 6018.75 6403.34 6403.34 606-99999 Gdrail Ty 7 (Precast) Lin Foot NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 681.00 80.00 154.50 135.00 Weighted Average for the Fourth Quarter 681.00 80.00 154.50 135.00 Weighted Average for the Year 681.00 80.00 154.50 135.00 607-00005 End Post Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 5.00 436.61 362.56 275.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 14.00 454.75 468.81 468.81 Weighted Average for the Third Quarter 19.00 449.98 390.10 417.81 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 3.00 800.00 480.90 715.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 16.00 464.69 362.05 395.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 500.00 394.00 335.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 500.00 479.00 335.00 Weighted Average for the Fourth Quarter 27.00 512.41 384.19 412.78 Weighted Average for the Year 46.00 486.62 385.38 414.86 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 607-00010 Corner and Line Br Post Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 22.00 489.65 461.97 375.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 27.00 508.25 523.97 523.97 Weighted Average for the Third Quarter 49.00 499.90 470.22 457.09 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 32.00 463.19 516.00 500.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 9.00 503.27 433.47 479.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 3.00 1000.00 498.00 445.00 Weighted Average for the Fourth Quarter 44.00 507.99 470.45 491.95 Weighted Average for the Year 93.00 503.73 470.32 473.58 607-01000 Fence BW MP Lin Foot STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 6,705.00 3.12 4.85 4.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 383.00 5.08 5.24 5.24 Weighted Average for the Third Quarter 7,088.00 3.23 4.85 4.07 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 6,515.00 3.24 5.46 5.30 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 3,399.00 4.78 4.52 5.15 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 880.00 9.00 6.10 5.00 Weighted Average for the Fourth Quarter 10,794.00 4.20 4.89 5.23 Weighted Average for the Year 17,882.00 3.81 4.87 4.77 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid BR0402-109 607-01010 Fence BW MP (Spec) US40 MP 108.4 OVER SHELTON DI 12/18/25 Lin Foot 840.00 8.00 6.20 5.00 Weighted Average for the Fourth Quarter 840.00 8.00 6.20 5.00 Weighted Average for the Year 840.00 8.00 6.20 5.00 607-01050 Fence Wire MP Lin Foot NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 120.00 26.64 7.84 7.20 Weighted Average for the Fourth Quarter 120.00 26.64 7.84 7.20 Weighted Average for the Year 120.00 26.64 7.84 7.20 607-01100 Fence BW TWP Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 11.00 12.00 300.57 182.50 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 871.00 7.16 14.57 5.62 Weighted Average for the First Quarter 882.00 7.22 16.36 7.83 Weighted Average for the Year 882.00 7.22 16.36 7.83 607-11200 Fence CW MP Lin Foot C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 415.00 11.04 7.91 10.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 415.00 11.04 7.91 10.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2,820.00 5.62 5.79 5.79 Weighted Average for the Third Quarter 2,820.00 5.62 5.79 5.79 Weighted Average for the Year 3,235.00 6.31 6.69 6.33 607-11525 Fence (Plastic) Lin Foot STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 1,142.00 2.95 5.76 5.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3,700.00 2.95 3.41 2.01 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 180.00 15.00 8.98 10.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 150.00 5.00 13.83 23.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 100.00 10.00 4.81 2.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 100.00 6.05 5.78 5.05 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3,449.00 2.73 3.46 3.38 Weighted Average for the First Quarter 8,821.00 3.26 4.00 3.49 NHPP0703-517 FBR0703-534 STAR500-228 I-70 TOP OF I-70 REGION 5 FLOYD HILL TO VET 04/11/25 05/08/25 12,000.00 200.00 5.02 10.00 5.03 11.82 5.03 6.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 500.00 8.00 7.16 2.98 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1,000.00 3.23 3.23 3.23 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 764.00 4.77 6.17 2.50 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 2,250.00 4.26 3.92 1.50 ITSSW03-250 FRONT RANGE 06/26/25 100.00 6.19 7.66 8.00 Weighted Average for the Second Quarter 16,814.00 4.96 4.92 4.30 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,100.00 2.03 2.03 2.03 CR400-406 REGION-WIDE 07/17/25 630.00 4.72 8.00 11.00 BR0704-265 I-70 EAST 07/24/25 672.00 4.81 4.18 3.71 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 607-11525 Fence (Plastic) Lin Foot FBR0704-269 C0142-070 I-70 EAST SH 14 MP 75.5-85 08/14/25 300.00 4.52 8.33 15.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 100.00 4.92 4.92 4.92 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 500.00 4.62 3.65 3.25 STR050A-042 FREMONT COUNTY IN R2 09/11/25 200.00 4.64 8.80 4.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 200.00 2,000.00 5.00 3.76 5.68 3.19 5.50 4.50 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3,000.00 4.28 4.28 4.28 Weighted Average for the Third Quarter 8,702.00 4.01 4.11 4.83 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 400.00 17.00 5.72 5.38 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 200.00 5.32 7.51 4.40 NHPPR500-227 REGION 5 SECTION 7 10/23/25 100.00 15.00 7.80 5.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 200.00 6.00 9.35 4.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,000.00 10.00 4.63 2.50 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 172.00 4.63 22.92 22.20 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 500.00 4.23 5.60 3.90 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 100.00 4.20 4.33 2.75 ITSSW03-417 STATEWIDE 12/04/25 100.00 5.25 41.05 5.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 500.00 4.62 7.50 7.50 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 250.00 6.00 7.25 4.30 NHPP1602-194 US 160 MP 174.1 12/11/25 200.00 10.00 9.80 6.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 200.00 13.00 5.89 6.05 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1,100.00 5.00 4.00 7.50 Weighted Average for the Fourth Quarter 5,022.00 7.63 6.55 5.75 Weighted Average for the Year 39,359.00 4.71 4.65 4.42 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 607-11530 Fence (Spec) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 911.00 100.00 345.28 265.69 Weighted Average for the First Quarter 911.00 100.00 345.28 265.69 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 345.00 132.27 132.27 132.27 Weighted Average for the Third Quarter 345.00 132.27 132.27 132.27 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 550.00 85.00 6.61 5.20 Weighted Average for the Fourth Quarter 550.00 85.00 6.61 5.20 Weighted Average for the Year 1,806.00 101.60 227.91 160.87 607-11580 Fence (Temp) Lin Foot STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 150.00 5.00 11.75 9.00 Weighted Average for the Second Quarter 150.00 5.00 11.75 9.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 300.00 5.00 39.83 8.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 300.00 5.00 39.83 8.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 62.00 30.00 26.44 30.25 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 3,873.00 2.91 10.02 9.70 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 160.00 7.00 17.07 12.10 Weighted Average for the Fourth Quarter 4,095.00 3.48 10.90 10.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 4,545.00 3.63 15.05 9.93 607-15000 Fence Conc (Noise) Sq Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO I-70 VET 04/11/25 5,717.00 96.89 92.30 92.30 Weighted Average for the Second Quarter 5,717.00 96.89 92.30 92.30 Weighted Average for the Year 5,717.00 96.89 92.30 92.30 607-53005 Fence CL (Spec) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 398.00 61.81 61.81 61.81 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 24.00 55.25 55.25 55.25 Weighted Average for the Third Quarter 422.00 61.44 61.44 61.44 Weighted Average for the Year 422.00 61.44 61.44 61.44 607-53137 Fence CL (Spec) (36 In) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO I-70 VET 04/11/25 14,680.00 52.11 52.17 52.17 Weighted Average for the Second Quarter 14,680.00 52.11 52.17 52.17 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 513.00 58.85 60.67 60.67 Weighted Average for the Third Quarter 513.00 58.85 60.67 60.67 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 15,193.00 52.33 52.46 52.46 607-53142 Fence CL (42 In) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 95.00 47.22 47.22 47.22 Weighted Average for the Third Quarter 95.00 47.22 47.22 47.22 Weighted Average for the Year 95.00 47.22 47.22 47.22 607-53172 Fence CL (72 In) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 463.00 22.56 42.36 38.16 Weighted Average for the First Quarter 463.00 22.56 42.36 38.16 Weighted Average for the Year 463.00 22.56 42.36 38.16 607-53185 Fence CL (Spec) (84 In) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 275.00 69.55 71.70 71.70 Weighted Average for the Third Quarter 275.00 69.55 71.70 71.70 Weighted Average for the Year 275.00 69.55 71.70 71.70 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 607-53196 Fence CL (96 In) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 949.00 55.25 55.25 55.25 Weighted Average for the Second Quarter 949.00 55.25 55.25 55.25 Weighted Average for the Year 949.00 55.25 55.25 55.25 607-55050 Mesh Anchor (Spec) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 133.00 3926.40 3926.40 3926.40 FBR0703-534 I-70 Weighted Average for the Second Quarter 133.00 3926.40 3926.40 3926.40 Weighted Average for the Year 133.00 3926.40 3926.40 3926.40 607-55060 Mesh Pin Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 15.00 560.91 560.91 560.91 FBR0703-534 I-70 Weighted Average for the Second Quarter 15.00 560.91 560.91 560.91 Weighted Average for the Year 15.00 560.91 560.91 560.91 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 607-55100 Wire Mesh (Draped) Sq Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 190,000.00 5.91 5.75 5.75 FBR0703-534 I-70 Weighted Average for the Second Quarter 190,000.00 5.91 5.75 5.75 Weighted Average for the Year 190,000.00 5.91 5.75 5.75 607-55110 Safety Rail (Cable) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3,185.00 79.24 68.66 68.66 FBR0703-534 I-70 Weighted Average for the Second Quarter 3,185.00 79.24 68.66 68.66 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 84.00 95.77 98.73 98.73 Weighted Average for the Third Quarter 84.00 95.77 98.73 98.73 Weighted Average for the Year 3,269.00 79.66 69.43 69.43 607-56001 Fence (Animal Protect) Lin Foot FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 48.00 82.88 27.62 27.62 Weighted Average for the Third Quarter 48.00 82.88 27.62 27.62 Weighted Average for the Year 48.00 82.88 27.62 27.62 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 607-60103 3 Ft Gate Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 5000.00 2469.55 3606.06 Weighted Average for the First Quarter 1.00 5000.00 2469.55 3606.06 Weighted Average for the Year 1.00 5000.00 2469.55 3606.06 607-60116 16 Ft Gate Each STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 354.06 2036.00 1200.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 1163.23 831.34 805.55 Weighted Average for the Fourth Quarter 3.00 893.51 1500.59 937.03 Weighted Average for the Year 3.00 893.51 1500.59 937.03 607-60120 20 Ft Gate Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 5.00 1016.50 1047.94 1047.94 Weighted Average for the Third Quarter 5.00 1016.50 1047.94 1047.94 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 757.48 1089.15 1305.00 Weighted Average for the Fourth Quarter 1.00 757.48 1089.15 1305.00 Weighted Average for the Year 6.00 973.33 1075.41 1090.78 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 607-60203 3 Ft Gate S (CL) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 904.09 904.09 904.09 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 904.09 904.09 904.09 Weighted Average for the Year 1.00 904.09 904.09 904.09 607-60220 20 Ft Gate S (CL) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 2176.51 2176.52 2176.52 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 2176.51 2176.52 2176.52 Weighted Average for the Year 2.00 2176.51 2176.52 2176.52 607-60274 24 Ft Gate D (CL) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 2818.31 2818.31 2818.31 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 2818.31 2818.31 2818.31 Weighted Average for the Year 1.00 2818.31 2818.31 2818.31 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 607-60332 32 Ft Gate Twin Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 1444.50 1489.17 1489.17 Weighted Average for the Third Quarter 1.00 1444.50 1489.17 1489.17 Weighted Average for the Year 1.00 1444.50 1489.17 1489.17 607-60620 Road Closure Gate Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 21412.67 56053.41 51010.10 Weighted Average for the First Quarter 1.00 21412.67 56053.41 51010.10 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4.00 42490.57 24791.81 24791.81 FBR0703-534 I-70 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 10020.00 46433.33 46800.00 Weighted Average for the Second Quarter 5.00 35996.46 34066.75 29193.45 NHPP1602-194 US 160 MP 174.1 12/11/25 1.00 45000.00 20374.01 9200.00 Weighted Average for the Fourth Quarter 1.00 45000.00 20374.01 9200.00 Weighted Average for the Year 7.00 35199.28 36278.46 29453.91 608-00000 Conc Sidewalk Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 3,155.00 75.00 103.57 104.80 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 118.00 125.00 119.71 106.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 728.00 120.00 92.45 80.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 608-00000 Conc Sidewalk Sq Yard NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 20.00 163.21 102.90 97.95 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 18.00 207.30 303.36 101.96 Weighted Average for the First Quarter 4,039.00 85.60 103.07 100.32 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 5.00 110.00 107.00 107.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 9.50 165.78 382.00 374.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 15.00 256.67 269.14 269.14 Weighted Average for the Second Quarter 29.50 202.54 303.34 275.43 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1,331.00 70.10 112.13 114.50 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 95.60 108.04 175.09 175.09 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 220.00 115.29 111.22 110.00 Weighted Average for the Third Quarter 1,646.60 78.34 112.74 117.42 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 135.00 150.00 140.30 180.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 56.00 150.00 129.13 125.25 Weighted Average for the Fourth Quarter 191.00 150.00 137.88 163.95 Weighted Average for the Year 5,906.10 86.24 107.62 108.02 608-00005 Conc Sidewalk (Spec) Sq Yard C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6.00 200.00 158.17 120.00 Weighted Average for the Fourth Quarter 6.00 200.00 158.17 120.00 Weighted Average for the Year 6.00 200.00 158.17 120.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 608-00006 Conc Sidewalk (6 In) Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2,641.00 85.00 81.00 71.02 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 20.00 200.00 322.17 350.00 Weighted Average for the First Quarter 2,661.00 85.86 81.91 73.12 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2,880.00 74.62 74.62 74.62 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 95.00 128.89 109.46 84.13 Weighted Average for the Second Quarter 2,975.00 76.35 79.55 74.92 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2,058.00 76.31 76.31 76.31 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 102.00 120.00 119.25 140.00 Weighted Average for the Third Quarter 2,160.00 78.37 83.41 79.32 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3,644.00 85.00 99.11 106.66 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,680.00 90.00 91.67 88.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 19.00 75.00 135.85 138.60 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 71.00 102.39 128.63 131.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 12.00 112.39 166.77 180.00 Weighted Average for the Fourth Quarter 5,426.00 86.80 96.92 101.48 Weighted Average for the Year 13,222.00 82.88 89.88 86.17 608-00010 Conc Curb Ramp Sq Yard NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,614.00 205.00 151.28 153.06 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 40.00 217.92 194.55 137.80 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 34.00 350.00 411.33 450.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 608-00010 Conc Curb Ramp Sq Yard SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 190.00 280.00 211.17 173.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1,804.00 180.00 140.82 145.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 42.00 261.03 174.14 163.25 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 184.00 223.56 245.86 145.66 Weighted Average for the First Quarter 3,908.00 199.98 158.37 152.50 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 13.00 240.00 355.00 355.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 8.00 319.68 758.50 957.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 80.00 364.00 286.51 212.60 269.21 212.60 269.21 212.60 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 14.00 323.59 299.70 156.33 Weighted Average for the Second Quarter 479.00 230.72 251.66 236.71 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 293.00 228.19 228.19 228.19 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 14.00 291.81 276.00 375.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 2,939.00 205.00 201.05 169.20 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 38.00 218.68 263.18 250.00 Weighted Average for the Third Quarter 3,284.00 207.60 203.55 176.28 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 436.00 240.00 191.80 112.19 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 395.00 230.00 175.17 110.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 165.00 165.00 255.35 269.50 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 161.00 300.00 203.60 205.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 128.00 300.00 156.50 134.00 Weighted Average for the Fourth Quarter 1,285.00 240.79 187.60 145.52 Weighted Average for the Year 8,956.00 210.27 181.82 164.72 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 608-00013 Directional Indicator Strip Sq Foot CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 87.00 90.00 73.78 17.10 Weighted Average for the Third Quarter 87.00 90.00 73.78 17.10 Weighted Average for the Year 87.00 90.00 73.78 17.10 608-00014 Detectable Guid Directional Indicator Sq Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 9.00 221.00 221.00 221.00 Weighted Average for the Third Quarter 9.00 221.00 221.00 221.00 Weighted Average for the Year 9.00 221.00 221.00 221.00 608-00015 Detectable Warnings Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 64.00 95.00 116.37 117.75 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 50.00 87.32 85.08 107.15 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 288.00 49.28 101.05 104.04 Weighted Average for the First Quarter 402.00 61.29 101.42 106.61 NHPP0703-517 FBR0703-534 C0405-042 I-70 TOP OF FLOYD HILL TO VET I-70 US 40 IN DEER TRAIL, PINE ST 04/11/25 06/05/25 76.00 15.00 65.73 145.68 66.45 65.23 66.45 67.81 Weighted Average for the Second Quarter 91.00 78.91 65.84 66.67 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 60.00 207.54 207.54 207.54 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 60.00 207.54 207.54 207.54 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 12.00 85.00 93.88 115.50 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 280.00 87.00 73.50 50.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 154.00 100.00 92.07 38.00 Weighted Average for the Fourth Quarter 446.00 91.43 77.86 47.62 Weighted Average for the Year 999.00 85.14 88.43 82.70 608-00017 Curb Ramp (Temp Perpendicular) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 8.00 2200.00 2368.94 3275.76 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 1000.00 2404.00 250.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 2500.00 2982.50 2500.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2.00 2400.00 3017.50 2965.00 Weighted Average for the Fourth Quarter 18.00 2022.22 2518.92 2396.45 Weighted Average for the Year 18.00 2022.22 2518.92 2396.45 608-00018 Curb Ramp (Temp Parallel) (Single) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 8.00 2220.00 2225.73 2952.90 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 750.00 2080.83 250.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 2200.00 2445.83 1800.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 9.00 2400.00 1952.50 1855.00 Weighted Average for the Fourth Quarter 25.00 2046.40 2158.82 1940.73 Weighted Average for the Year 25.00 2046.40 2158.82 1940.73 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 608-00026 Conc Bikeway (6 In) Sq Yard NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 13,251.00 114.30 117.80 117.80 FBR0703-534 I-70 Weighted Average for the Second Quarter 13,251.00 114.30 117.80 117.80 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8,114.00 73.28 73.28 73.28 Weighted Average for the Third Quarter 8,114.00 73.28 73.28 73.28 Weighted Average for the Year 21,365.00 98.72 100.89 100.89 608-00040 Conc Bikeway (Spec) Sq Yard STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 648.00 148.45 148.45 148.45 Weighted Average for the Third Quarter 648.00 148.45 148.45 148.45 Weighted Average for the Year 648.00 148.45 148.45 148.45 608-00350 Conc Sidewalk (C) Sq Yard 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 110.00 87.86 105.47 84.80 Weighted Average for the First Quarter 110.00 87.86 105.47 84.80 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 84.00 132.74 132.74 132.74 Weighted Average for the Third Quarter 84.00 132.74 132.74 132.74 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 194.00 107.30 108.55 105.56 608-01550 Place Asph Millings Sq Yard NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 665.00 10.00 13.45 14.90 Weighted Average for the Fourth Quarter 665.00 10.00 13.45 14.90 Weighted Average for the Year 665.00 10.00 13.45 14.90 608-10010 Sidewalk Drain Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 9.00 28000.00 6207.82 11856.28 Weighted Average for the Fourth Quarter 9.00 28000.00 6207.82 11856.28 Weighted Average for the Year 9.00 28000.00 6207.82 11856.28 609-20000 Curb Ty 2 B (Spec) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 241.00 100.00 50.03 50.60 Weighted Average for the First Quarter 241.00 100.00 50.03 50.60 Weighted Average for the Year 241.00 100.00 50.03 50.60 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 609-20004 Curb and Gutter Ty 2 (Sect II-M)(Spec) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 16.00 105.45 105.45 105.45 Weighted Average for the Third Quarter 16.00 105.45 105.45 105.45 Weighted Average for the Year 16.00 105.45 105.45 105.45 609-20010 Curb Ty 2 B Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 500.00 48.42 46.55 47.10 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 46.00 50.00 54.89 58.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 415.00 50.00 31.93 28.50 Weighted Average for the First Quarter 961.00 49.18 40.16 39.59 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 35.00 50.49 50.49 50.49 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 474.00 42.43 36.78 28.10 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 528.00 122.81 131.28 131.28 Weighted Average for the Third Quarter 1,037.00 83.63 57.26 81.39 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,108.00 42.00 40.09 20.37 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 270.00 55.00 48.83 39.00 Weighted Average for the Fourth Quarter 1,378.00 44.55 42.43 24.02 Weighted Average for the Year 3,376.00 57.87 44.83 46.07 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 609-21000 Concrete Curb Stop Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 299.00 100.00 201.17 100.00 Weighted Average for the Fourth Quarter 299.00 100.00 201.17 100.00 Weighted Average for the Year 299.00 100.00 201.17 100.00 609-21010 C and G Ty 2 I-B Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 388.00 36.71 35.44 28.62 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 2,671.00 50.00 32.55 24.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 438.00 45.62 46.66 58.15 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 113.00 43.20 81.75 59.30 Weighted Average for the First Quarter 3,610.00 47.83 35.76 29.74 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 405.00 45.00 35.90 35.90 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 909.00 7,167.00 48.13 28.93 59.54 28.93 59.54 28.93 Weighted Average for the Second Quarter 8,481.00 31.76 32.54 32.54 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 987.00 36.07 36.07 36.07 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 30.00 68.16 59.75 55.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 580.00 36.72 33.68 46.70 Weighted Average for the Third Quarter 1,597.00 36.91 35.28 40.29 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,599.00 37.00 38.34 30.84 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,973.00 50.00 41.50 44.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 642.00 39.79 41.87 40.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 609-21010 C and G Ty 2 I-B Lin Foot STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 55.00 70.00 87.49 120.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 361.00 45.00 49.75 43.75 Weighted Average for the Fourth Quarter 5,630.00 42.71 40.93 38.23 Weighted Average for the Year 19,318.00 38.38 37.80 34.32 609-21011 C and G Ty 2 I-M Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2,619.00 82.48 82.85 82.85 Weighted Average for the Third Quarter 2,619.00 82.48 82.85 82.85 Weighted Average for the Year 2,619.00 82.48 82.85 82.85 609-21013 C and G Ty 2 I-M (Spec) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 680.00 91.79 93.38 93.38 Weighted Average for the Second Quarter 680.00 91.79 93.38 93.38 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 104.00 45.34 45.34 45.34 Weighted Average for the Third Quarter 104.00 45.34 45.34 45.34 Weighted Average for the Year 784.00 85.63 87.01 87.01 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 609-21020 C and G Ty 2 II-B Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 884.00 47.00 52.37 53.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 833.00 41.16 40.66 29.68 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 37.00 45.00 184.21 180.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 56.00 45.00 60.14 64.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 949.00 60.00 37.27 30.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 310.00 54.77 82.31 55.14 Weighted Average for the First Quarter 3,069.00 50.16 47.69 41.66 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 970.00 50.00 42.00 42.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 16.00 103.80 209.00 138.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 726.00 87.73 89.92 89.92 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 4,265.00 31.24 31.24 31.24 Weighted Average for the Second Quarter 5,977.00 41.34 41.04 40.40 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 774.00 41.70 41.70 41.70 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 99.00 62.19 60.00 55.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1,269.00 39.08 46.10 51.40 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 360.00 38.16 51.08 40.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4,792.00 72.71 75.17 75.17 Weighted Average for the Third Quarter 7,294.00 61.72 57.29 65.47 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,139.00 50.00 48.94 46.26 NHPPR500-227 REGION 5 SECTION 7 10/23/25 20.00 200.00 311.30 125.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1,717.00 55.00 52.67 44.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 233.00 55.00 51.30 46.20 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 125.00 65.83 55.18 53.75 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 696.00 68.50 57.02 55.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 24.00 80.00 107.25 175.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 68.00 70.00 97.50 114.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 609-21020 C and G Ty 2 II-B Lin Foot FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 24.00 62.58 81.40 96.00 Weighted Average for the Fourth Quarter 5,046.00 55.94 53.58 48.95 Weighted Average for the Year 21,386.00 53.00 51.81 51.15 609-21021 C and G Ty 2 II-M Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 289.00 35.00 55.85 56.50 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,842.00 31.91 43.02 37.10 Weighted Average for the First Quarter 2,131.00 32.33 43.95 39.73 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 33.00 66.07 74.13 32.41 Weighted Average for the Second Quarter 33.00 66.07 74.13 32.41 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 20.00 47.12 47.12 47.12 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 164.00 127.02 129.57 129.57 Weighted Average for the Third Quarter 184.00 118.34 120.61 120.61 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 445.00 55.00 58.08 43.00 Weighted Average for the Fourth Quarter 445.00 55.00 58.08 43.00 Weighted Average for the Year 2,793.00 42.01 47.75 45.49 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 609-21023 C and G Ty 2 II-B (Spec) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 746.00 130.32 130.32 130.32 Weighted Average for the Third Quarter 746.00 130.32 130.32 130.32 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 263.00 51.21 79.20 93.50 Weighted Average for the Fourth Quarter 263.00 51.21 79.20 93.50 Weighted Average for the Year 1,009.00 109.70 109.18 120.72 609-21110 C & G Ty 2 I-B (Spec) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 602.00 106.78 106.78 106.78 Weighted Average for the Third Quarter 602.00 106.78 106.78 106.78 Weighted Average for the Year 602.00 106.78 106.78 106.78 609-21900 C and G Ty 2 (Spec) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 736.00 112.89 108.88 108.88 Weighted Average for the Third Quarter 736.00 112.89 108.88 108.88 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,002.00 65.00 54.63 56.52 Weighted Average for the Fourth Quarter 2,002.00 65.00 54.63 56.52 Weighted Average for the Year 2,738.00 77.87 59.20 70.59 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid STU1191-044 609-22022 CGS Ty 2 II-B CO119 AND CO 7 FROM US36 (28T 04/03/25 Lin Foot 30.00 100.00 72.00 72.00 Weighted Average for the Second Quarter 30.00 100.00 72.00 72.00 Weighted Average for the Year 30.00 100.00 72.00 72.00 609-24000 Gutter Ty 2 (Spec) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 283.00 48.43 48.43 48.43 Weighted Average for the Third Quarter 283.00 48.43 48.43 48.43 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3.00 100.00 101.00 200.00 Weighted Average for the Fourth Quarter 3.00 100.00 101.00 200.00 Weighted Average for the Year 286.00 48.97 51.57 50.02 609-24002 Gutter Ty 2 (2 Ft) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 120.00 83.52 99.15 99.15 FBR0703-534 I-70 Weighted Average for the Second Quarter 120.00 83.52 99.15 99.15 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 80.00 66.83 66.83 66.83 Weighted Average for the Third Quarter 80.00 66.83 66.83 66.83 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0705-083 609-24002 Gutter Ty 2 (2 Ft) I-70: SEIBERT EAST PART 2 12/04/25 Lin Foot 55.00 61.96 114.79 91.00 Weighted Average for the Fourth Quarter 55.00 61.96 114.79 91.00 Weighted Average for the Year 255.00 73.63 102.76 87.25 609-24004 Gutter Ty 2 (4 Ft) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 91.00 66.38 52.36 29.68 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 112.00 70.69 188.62 90.52 Weighted Average for the First Quarter 203.00 68.76 113.77 63.25 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 902.00 105.48 120.71 120.71 FBR0703-534 I-70 Weighted Average for the Second Quarter 902.00 105.48 120.71 120.71 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 35.00 81.86 97.82 100.00 Weighted Average for the Third Quarter 35.00 81.86 97.82 100.00 Weighted Average for the Year 1,140.00 98.22 114.60 109.84 609-24005 Gutter Ty 2 (5 Ft) Lin Foot STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 48.00 100.00 60.00 60.00 Weighted Average for the Second Quarter 48.00 100.00 60.00 60.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 48.00 100.00 60.00 60.00 609-24008 Gutter Ty 2 (8 Ft) Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 27.00 70.55 307.30 145.66 Weighted Average for the First Quarter 27.00 70.55 307.30 145.66 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 160.00 121.01 121.01 121.01 Weighted Average for the Second Quarter 160.00 121.01 121.01 121.01 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 48.00 176.84 176.84 176.84 Weighted Average for the Third Quarter 48.00 176.84 176.84 176.84 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 282.00 81.15 196.78 275.00 Weighted Average for the Fourth Quarter 282.00 81.15 196.78 275.00 Weighted Average for the Year 517.00 101.82 195.48 211.48 609-24010 Gutter Ty 2 (10 Ft) Lin Foot NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 140.00 200.00 175.00 175.00 Weighted Average for the Second Quarter 140.00 200.00 175.00 175.00 Weighted Average for the Year 140.00 200.00 175.00 175.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 609-24100 Gutter Ty 2 Variable Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 202.00 20.00 88.75 45.00 Weighted Average for the Fourth Quarter 202.00 20.00 88.75 45.00 Weighted Average for the Year 202.00 20.00 88.75 45.00 609-40010 Curb Ty 4 B Lin Foot STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 242.00 24.30 49.96 39.00 Weighted Average for the Fourth Quarter 242.00 24.30 49.96 39.00 Weighted Average for the Year 242.00 24.30 49.96 39.00 609-40011 Curb Ty 4 M Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 22.00 35.90 35.90 35.90 Weighted Average for the Third Quarter 22.00 35.90 35.90 35.90 Weighted Average for the Year 22.00 35.90 35.90 35.90 609-40120 Curb Median Special Sq Yard NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 21.00 188.06 188.06 188.06 Weighted Average for the Second Quarter 21.00 188.06 188.06 188.06 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 21.00 188.06 188.06 188.06 609-60011 Curb Ty 6 M Lin Foot NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 3,574.00 35.00 13.38 15.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2,025.00 21.00 26.50 24.84 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 17.00 25.00 213.00 201.00 Weighted Average for the First Quarter 5,616.00 29.92 20.78 19.11 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 4,227.00 30.00 33.66 30.00 41.01 195.00 41.01 195.00 Weighted Average for the Second Quarter 4,257.00 33.63 42.10 42.10 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10,003.00 16.90 15.57 15.57 Weighted Average for the Third Quarter 10,003.00 16.90 15.57 15.57 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1,110.00 25.67 23.18 16.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 789.00 17.39 32.94 31.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 80.00 40.84 78.75 75.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 665.00 40.23 25.00 25.00 Weighted Average for the Fourth Quarter 2,644.00 27.32 26.90 24.73 Weighted Average for the Year 22,520.00 24.53 22.99 22.54 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 610-00010 Median Cover Matl (Dec) Sq Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 81.00 50.00 33.64 17.04 Weighted Average for the Fourth Quarter 81.00 50.00 33.64 17.04 Weighted Average for the Year 81.00 50.00 33.64 17.04 610-00020 Median Cover (Pattern Conc) Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 828.00 30.00 25.60 25.90 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 91.00 20.00 51.49 53.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1,097.00 22.50 20.37 25.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 457.00 16.61 42.83 28.09 Weighted Average for the First Quarter 2,473.00 23.83 28.31 27.12 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 9.00 41.00 224.00 358.00 Weighted Average for the Second Quarter 9.00 41.00 224.00 358.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 35.00 45.84 65.50 95.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 266.00 23.58 23.91 23.65 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 11,738.00 17.38 19.10 19.10 Weighted Average for the Third Quarter 12,039.00 17.60 20.00 19.42 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 3,864.00 40.00 20.45 24.65 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 434.00 25.00 33.33 30.00 Weighted Average for the Fourth Quarter 4,298.00 38.49 21.26 25.19 Weighted Average for the Year 18,819.00 23.20 22.29 21.91 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 610-00024 Median Cover (4 In Pattern Conc) Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2,849.00 20.00 14.60 10.60 Weighted Average for the First Quarter 2,849.00 20.00 14.60 10.60 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6,864.00 22.38 22.38 22.38 Weighted Average for the Third Quarter 6,864.00 22.38 22.38 22.38 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4,631.00 15.00 17.36 16.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 66.00 100.00 34.32 38.00 Weighted Average for the Fourth Quarter 4,697.00 16.19 17.48 16.31 Weighted Average for the Year 14,410.00 19.89 17.18 18.07 610-00026 Median Cover (6 In Pattern Conc) Sq Foot NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 7,645.00 20.00 20.75 16.00 Weighted Average for the First Quarter 7,645.00 20.00 20.75 16.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,281.00 24.00 23.50 16.51 Weighted Average for the Fourth Quarter 1,281.00 24.00 23.50 16.51 Weighted Average for the Year 8,926.00 20.57 21.14 16.07 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 610-00030 Median Cover Matl (Conc) Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 863.00 20.00 23.28 23.55 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 80.00 20.00 25.74 29.00 Weighted Average for the First Quarter 943.00 20.00 23.66 24.01 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 4,487.00 31,168.00 23.02 15.11 22.04 15.11 22.04 15.11 Weighted Average for the Second Quarter 35,655.00 16.11 15.98 15.98 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 4,655.00 13.59 19.85 21.38 Weighted Average for the Third Quarter 4,655.00 13.59 19.85 21.38 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 323.00 35.00 17.94 17.90 Weighted Average for the Fourth Quarter 323.00 35.00 17.94 17.90 Weighted Average for the Year 41,576.00 16.06 17.66 16.78 610-00035 Median Cover Matl (Conc)(Spec) Sq Foot C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 264.00 22.00 27.80 26.40 Weighted Average for the Fourth Quarter 264.00 22.00 27.80 26.40 Weighted Average for the Year 264.00 22.00 27.80 26.40 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 610-00055 Median Cover Matl (Stone) Sq Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3,150.00 4.81 6.23 6.23 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10,822.00 5.35 5.00 5.00 Weighted Average for the Third Quarter 13,972.00 5.23 5.28 5.28 Weighted Average for the Year 13,972.00 5.23 5.28 5.28 612-00001 Delin (Ty I) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 230.00 32.00 37.19 37.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 28.00 50.00 35.50 37.00 BR0761-249 I-76 02/27/25 52.00 40.00 62.17 120.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 255.00 31.37 38.70 35.03 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 622.00 25.00 92.05 24.10 Weighted Average for the First Quarter 1,187.00 28.97 60.51 33.60 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 50.00 36.40 36.40 36.40 Weighted Average for the Second Quarter 50.00 36.40 36.40 36.40 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 33.00 56.09 56.09 56.09 C0142-070 SH 14 MP 75.5-85 08/14/25 4.00 45.00 243.33 75.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 9.00 165.75 30.94 30.94 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 22.00 24.90 35.67 32.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 12.00 37.60 55.97 54.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 8.00 42.54 60.40 55.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 12.00 40.00 129.64 220.00 Weighted Average for the Third Quarter 100.00 53.42 75.69 68.61 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 612-00001 Delin (Ty I) Each NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 250.00 30.98 43.91 25.25 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 14.00 33.32 38.99 27.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 10.00 50.00 54.77 60.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 18.00 50.00 45.75 50.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 9.00 36.19 33.88 39.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 414.00 22.12 29.13 18.25 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 187.00 40.78 35.54 41.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 340.00 23.19 14.63 14.25 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 271.00 25.77 67.00 44.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 214.00 50.00 20.00 14.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 31.00 50.00 71.33 48.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 350.00 30.00 27.20 27.40 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 190.00 32.79 25.50 25.50 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 100.00 30.00 27.00 26.50 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 170.00 70.00 46.93 47.75 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 9.00 50.00 108.10 181.50 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 40.00 57.60 35.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 616.00 24.93 21.91 21.50 Weighted Average for the Fourth Quarter 3,197.00 31.73 35.85 26.66 Weighted Average for the Year 4,534.00 31.54 43.57 29.51 612-00002 Delin (Ty II) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 260.00 30.00 40.66 41.25 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 30.00 31.17 43.17 67.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 30.00 34.24 38.42 35.03 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 8.00 30.00 71.55 26.10 Weighted Average for the First Quarter 328.00 30.50 41.28 42.67 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 612-00002 Delin (Ty II) Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 25.00 36.40 36.40 36.40 Weighted Average for the Second Quarter 25.00 36.40 36.40 36.40 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 21.00 56.09 56.09 56.09 Weighted Average for the Third Quarter 21.00 56.09 56.09 56.09 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 2.00 39.60 45.73 27.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 10.00 29.69 47.25 38.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 208.00 27.01 34.38 28.75 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 87.00 35.01 39.25 46.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 2.00 32.84 18.50 18.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 103.00 25.86 72.80 44.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 55.00 94.68 53.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 50.00 35.00 31.55 31.60 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 16.00 34.26 31.00 31.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 35.00 31.35 31.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 40.00 70.00 52.10 53.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 214.00 27.50 26.36 26.00 Weighted Average for the Fourth Quarter 756.00 31.31 43.05 33.83 Weighted Average for the Year 1,130.00 31.65 42.48 36.87 612-00003 Delin (Ty III) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 40.00 44.14 44.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 5.00 60.00 35.50 37.00 BR0761-249 I-76 02/27/25 16.00 40.00 63.82 120.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 35.00 38.64 39.17 35.03 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 40.00 40.00 78.05 28.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 98.00 40.53 55.64 46.37 STAR500-228 REGION 5 05/08/25 40.00 65.00 48.00 29.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 10.00 36.40 36.40 36.40 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 124.00 38.94 75.00 95.00 Weighted Average for the Second Quarter 174.00 44.78 67.78 76.46 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 56.09 56.09 56.09 CR400-406 REGION-WIDE 07/17/25 38.00 41.94 77.33 50.00 C0142-070 SH 14 MP 75.5-85 08/14/25 6.00 55.00 245.00 80.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 5.00 165.75 33.15 33.15 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 7.00 50.76 56.59 54.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 78.23 67.60 85.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 6.00 90.00 138.72 109.00 Weighted Average for the Third Quarter 65.00 59.39 96.46 58.52 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 65.00 62.93 48.54 31.75 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 13.00 35.34 57.52 51.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 4.00 60.20 62.76 75.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 9.00 41.16 36.75 39.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 116.00 22.73 36.25 32.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 127.00 42.91 42.95 51.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 4.00 36.36 23.50 23.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 17.00 37.38 76.80 44.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 26.00 60.00 24.05 17.10 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 12.00 65.00 138.35 59.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 75.00 40.00 31.55 31.60 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 118.00 24.05 41.00 41.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 40.00 31.35 31.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 24.00 70.00 57.40 58.50 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 37.00 80.00 94.07 181.50 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 45.00 63.60 35.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid STM0503-096 612-00003 Delin (Ty III) PUEBLO COUNTY LINE TO PURCELL 12/18/25 Each 40.00 34.61 30.73 30.25 Weighted Average for the Fourth Quarter 711.00 41.09 48.68 46.29 Weighted Average for the Year 1,048.00 42.78 56.77 52.07 612-00021 Delin (Ty I) (Barrier) Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 9.00 95.00 114.00 120.00 Weighted Average for the First Quarter 9.00 95.00 114.00 120.00 Weighted Average for the Year 9.00 95.00 114.00 120.00 612-00031 Delin (Ty I) (Extra Ht) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 20.00 49.66 75.08 70.06 Weighted Average for the First Quarter 20.00 49.66 75.08 70.06 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 32.00 97.69 63.00 63.00 Weighted Average for the Fourth Quarter 32.00 97.69 63.00 63.00 Weighted Average for the Year 52.00 79.22 71.63 65.72 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 612-00032 Delin (Ty II) (Extra Ht) Each 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 4.00 67.41 75.50 75.50 Weighted Average for the Fourth Quarter 4.00 67.41 75.50 75.50 Weighted Average for the Year 4.00 67.41 75.50 75.50 612-00033 Delin (Ty III) (Extra Ht) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 20.00 40.94 77.33 70.06 Weighted Average for the First Quarter 20.00 40.94 77.33 70.06 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 20.00 150.00 250.00 250.00 Weighted Average for the Second Quarter 20.00 150.00 250.00 250.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 34.00 45.87 82.00 82.00 Weighted Average for the Fourth Quarter 34.00 45.87 82.00 82.00 Weighted Average for the Year 74.00 72.68 104.29 124.18 612-00039 Delin (Flex) (Surf Mount) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 58.00 117.79 118.33 118.33 FBR0703-534 I-70 Weighted Average for the Second Quarter 58.00 117.79 118.33 118.33 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 612-00039 Delin (Flex) (Surf Mount) Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 16.00 100.00 109.00 150.00 Weighted Average for the Fourth Quarter 16.00 100.00 109.00 150.00 Weighted Average for the Year 74.00 113.94 112.51 125.18 612-00041 Delin (Flex) (Ty I) Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 81.00 110.00 121.98 125.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 50.00 109.96 84.27 86.70 Weighted Average for the First Quarter 131.00 109.99 110.05 110.38 NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO VET I-70 CO 17 & SOUTH OF CO 14 04/11/25 05/08/25 58.00 72.00 117.79 34.00 118.33 76.20 118.33 93.60 Weighted Average for the Second Quarter 130.00 71.38 85.12 104.63 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 45.00 129.53 211.75 171.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 68.00 106.31 90.00 85.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 40.00 119.81 90.69 90.00 Weighted Average for the Third Quarter 153.00 116.67 121.44 111.60 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3.00 100.00 170.42 201.67 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 106.00 109.68 102.85 111.40 Weighted Average for the Fourth Quarter 109.00 109.41 106.47 113.88 Weighted Average for the Year 523.00 102.23 110.28 110.04 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 612-00042 Delin (Flex) (Ty II) Each NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 50.00 129.77 85.01 86.70 Weighted Average for the First Quarter 50.00 129.77 85.01 86.70 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 110.00 100.00 100.00 Weighted Average for the Second Quarter 4.00 110.00 100.00 100.00 Weighted Average for the Year 54.00 128.30 85.40 87.69 612-00043 Delin (Flex) (Ty III) Each NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 50.00 115.82 86.67 86.70 Weighted Average for the First Quarter 50.00 115.82 86.67 86.70 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 147.24 147.93 147.93 FBR0703-534 I-70 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 17.00 35.00 79.53 93.60 Weighted Average for the Second Quarter 19.00 46.81 82.11 99.32 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 18.00 138.40 93.15 95.00 Weighted Average for the Third Quarter 18.00 138.40 93.15 95.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 18.00 121.59 104.58 111.40 Weighted Average for the Fourth Quarter 18.00 121.59 104.58 111.40 Weighted Average for the Year 105.00 108.19 90.16 94.64 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 612-00052 Reflector Each NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 50.00 50.00 8.43 8.45 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 200.00 30.00 10.43 10.25 Weighted Average for the Fourth Quarter 250.00 34.00 10.03 9.89 Weighted Average for the Year 250.00 34.00 10.03 9.89 612-00070 Reflector Strip (4 In) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 535.00 41.23 41.42 41.42 FBR0703-534 I-70 Weighted Average for the Second Quarter 535.00 41.23 41.42 41.42 Weighted Average for the Year 535.00 41.23 41.42 41.42 612-00081 Delin (PM) (Ty I) Each MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 12.00 66.92 103.33 80.00 Weighted Average for the Third Quarter 12.00 66.92 103.33 80.00 Weighted Average for the Year 12.00 66.92 103.33 80.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 612-00111 Delin (Drv)(Ty I) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 230.00 147.24 147.93 147.93 FBR0703-534 I-70 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 32.00 140.00 94.67 90.00 Weighted Average for the Second Quarter 262.00 146.36 132.25 140.85 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 483.00 144.45 147.40 147.40 Weighted Average for the Third Quarter 483.00 144.45 147.40 147.40 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 350.00 106.97 82.91 69.40 Weighted Average for the Fourth Quarter 350.00 106.97 82.91 69.40 Weighted Average for the Year 1,095.00 132.93 101.37 120.90 612-00112 Delin (Drv)(Ty II) Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 43.00 135.00 85.00 85.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 4.00 140.00 94.67 90.00 Weighted Average for the Second Quarter 47.00 135.43 87.11 85.43 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 113.00 155.15 158.32 158.32 Weighted Average for the Third Quarter 113.00 155.15 158.32 158.32 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 100.00 98.92 92.28 92.00 Weighted Average for the Fourth Quarter 100.00 98.92 92.28 92.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 260.00 129.96 103.03 119.64 612-00113 Delin (Drv)(Ty III) Each NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 36.00 147.24 147.93 147.93 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 8.00 140.00 94.67 90.00 Weighted Average for the Second Quarter 44.00 145.92 126.62 137.40 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 140.00 171.20 174.70 174.70 Weighted Average for the Third Quarter 140.00 171.20 174.70 174.70 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 50.00 102.74 97.43 105.00 Weighted Average for the Fourth Quarter 50.00 102.74 97.43 105.00 Weighted Average for the Year 234.00 151.82 125.36 152.79 612-00118 Med Crossover Delin (Drv) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 52.00 181.90 185.61 185.61 Weighted Average for the Third Quarter 52.00 181.90 185.61 185.61 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 24.00 180.00 358.00 481.00 Weighted Average for the Fourth Quarter 24.00 180.00 358.00 481.00 Weighted Average for the Year 76.00 181.30 268.36 278.89 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 612-00260 Loc Mark (Fib Opt)(Dome) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 10.00 235.04 227.37 110.24 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 328.17 203.05 178.54 Weighted Average for the First Quarter 13.00 256.53 223.32 126.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 39.00 326.06 326.06 326.06 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 8.00 194.10 194.10 194.10 ITSSW03-250 FRONT RANGE 06/26/25 70.00 154.14 232.67 150.00 Weighted Average for the Second Quarter 117.00 214.18 241.07 211.70 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5.00 176.80 187.85 187.85 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 205.20 153.75 100.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 514.67 525.18 525.18 Weighted Average for the Third Quarter 8.00 264.82 236.78 261.20 ITSSW03-417 STATEWIDE 12/04/25 6.00 284.20 174.42 240.00 Weighted Average for the Fourth Quarter 6.00 284.20 174.42 240.00 Weighted Average for the Year 144.00 223.73 235.26 207.89 612-00270 Loc Mark (Util)(Flat Slat) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 8.00 83.67 203.05 178.54 Weighted Average for the First Quarter 8.00 83.67 203.05 178.54 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 25.00 131.70 133.00 72.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 25.00 131.70 133.00 72.00 ITSSW03-417 STATEWIDE 12/04/25 33.00 178.27 122.55 150.00 Weighted Average for the Fourth Quarter 33.00 178.27 122.55 150.00 Weighted Average for the Year 66.00 149.16 136.26 123.91 613-00050 1/2 In Elec Cond Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 825.00 44.20 46.41 46.41 Weighted Average for the Third Quarter 825.00 44.20 46.41 46.41 Weighted Average for the Year 825.00 44.20 46.41 46.41 613-00075 3/4 In Elec Cond Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 160.00 123.76 123.76 123.76 Weighted Average for the Third Quarter 160.00 123.76 123.76 123.76 Weighted Average for the Year 160.00 123.76 123.76 123.76 613-00100 1 In Elec Cond Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 105.00 31.03 31.66 31.66 Weighted Average for the Third Quarter 105.00 31.03 31.66 31.66 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 105.00 31.03 31.66 31.66 613-00102 1 In Elec Cond (GRC) (Special) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 340.00 48.88 38.29 39.22 Weighted Average for the First Quarter 340.00 48.88 38.29 39.22 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 80.00 89.95 89.95 89.95 FBR0703-534 I-70 Weighted Average for the Second Quarter 80.00 89.95 89.95 89.95 Weighted Average for the Year 420.00 56.70 40.24 48.88 613-00150 1-1/2 In Elec Cond Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 35.00 77.58 83.56 83.56 FBR0703-534 I-70 Weighted Average for the Second Quarter 35.00 77.58 83.56 83.56 Weighted Average for the Year 35.00 77.58 83.56 83.56 613-00200 2 In Elec Cond Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,038.00 19.87 28.46 24.38 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 706.00 38.00 40.85 35.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 1,744.00 27.21 32.32 28.68 NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 2,700.00 49.47 49.47 49.47 Weighted Average for the Second Quarter 2,700.00 49.47 49.47 49.47 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 222.00 36.49 24.88 25.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 891.00 17.19 44.13 28.50 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 5,400.00 7.55 15.12 11.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 830.00 36.38 37.12 37.12 Weighted Average for the Third Quarter 7,343.00 12.86 17.80 16.50 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 105.00 23.00 25.10 25.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 140.00 26.47 79.96 82.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 80.00 45.00 62.53 62.75 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 150.00 26.26 55.20 55.00 Weighted Average for the Fourth Quarter 475.00 28.75 61.52 57.63 Weighted Average for the Year 12,262.00 23.58 22.30 27.08 613-00206 2 In Elec Cond (Bored) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,293.00 30.00 36.09 30.60 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,415.00 26.44 38.92 36.04 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 500.00 30.00 29.48 22.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,665.00 46.92 110.14 96.92 Weighted Average for the First Quarter 4,873.00 34.75 58.67 53.96 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2,280.00 20.00 25.50 24.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3,265.00 61.84 61.84 61.84 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-00206 2 In Elec Cond (Bored) Lin Foot FBR0703-534 I-70 C0821-113 CO-82 & Catherine Store Signa 04/17/25 104.00 30.00 30.00 30.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6,800.00 24.83 24.83 24.83 ITSSW03-250 FRONT RANGE 06/26/25 153,825.00 12.50 13.75 11.92 Weighted Average for the Second Quarter 166,274.00 14.09 14.12 13.61 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2,255.00 23.21 23.21 23.21 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 586.00 37.28 26.38 25.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 2,920.00 24.48 30.63 34.50 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 415.00 33.00 22.00 24.50 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 400.00 26.63 29.90 25.00 Weighted Average for the Third Quarter 6,576.00 25.85 28.45 28.57 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,350.00 25.00 26.86 26.24 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 2,735.00 26.04 37.75 30.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 580.00 28.00 53.60 25.00 ITSSW03-417 STATEWIDE 12/04/25 6,020.00 45.12 104.25 135.00 Weighted Average for the Fourth Quarter 11,685.00 35.76 73.16 83.09 Weighted Average for the Year 189,408.00 16.36 18.51 19.45 613-00207 2 In Elec Cond (Bridge) (Spec) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 722.00 31.50 31.48 31.48 Weighted Average for the Second Quarter 722.00 31.50 31.48 31.48 Weighted Average for the Year 722.00 31.50 31.48 31.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 2670252-499 613-00210 2 In Elec Conduit (Spec) I-25:MOBILITY HUB (LONE TREE) 01/16/25 Lin Foot 126.00 50.00 35.09 39.22 Weighted Average for the First Quarter 126.00 50.00 35.09 39.22 Weighted Average for the Year 126.00 50.00 35.09 39.22 613-00300 3 In Elec Cond Lin Foot SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 175.00 32.80 28.40 25.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 50.00 28.89 29.48 29.48 Weighted Average for the Third Quarter 225.00 31.93 28.47 26.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 130.00 23.00 26.50 26.00 Weighted Average for the Fourth Quarter 130.00 23.00 26.50 26.00 Weighted Average for the Year 355.00 28.66 27.96 26.00 613-00306 3 In Elec Cond (Bored) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2,736.00 40.00 37.66 35.30 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 900.00 36.16 57.68 54.06 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2,450.00 40.00 43.97 36.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 750.00 25.00 32.36 25.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 440.00 87.06 127.56 112.22 Weighted Average for the First Quarter 7,276.00 40.82 48.27 41.45 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-00306 3 In Elec Cond (Bored) Lin Foot STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 562.00 97.55 28.50 25.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2,230.00 78.70 78.71 78.71 FBR0703-534 I-70 C0821-113 CO-82 & Catherine Store Signa 04/17/25 2,005.00 50.00 31.00 31.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1,100.00 39.50 39.50 39.50 Weighted Average for the Second Quarter 5,897.00 63.43 48.48 50.06 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3,590.00 28.73 28.73 28.73 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 415.00 39.56 30.23 25.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 276.00 40.79 38.63 44.50 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 825.00 38.00 24.20 27.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 500.00 28.89 29.48 29.48 Weighted Average for the Third Quarter 5,606.00 31.50 28.28 29.04 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3,980.00 28.00 26.76 28.22 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1,210.00 33.00 63.55 26.00 Weighted Average for the Fourth Quarter 5,190.00 29.17 31.61 27.70 Weighted Average for the Year 23,969.00 41.68 39.96 37.69 613-00600 6 In Elec Cond Lin Foot ITSSW03-250 FRONT RANGE 06/26/25 2,495.00 25.49 87.39 96.41 Weighted Average for the Second Quarter 2,495.00 25.49 87.39 96.41 Weighted Average for the Year 2,495.00 25.49 87.39 96.41 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-00607 6 In Elec Cond (Brdg)(Spec) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 220.00 112.44 112.43 112.43 FBR0703-534 I-70 Weighted Average for the Second Quarter 220.00 112.44 112.43 112.43 Weighted Average for the Year 220.00 112.44 112.43 112.43 613-01075 3/4 In Elec Cond (P) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 210.00 14.37 14.37 14.37 Weighted Average for the Third Quarter 210.00 14.37 14.37 14.37 Weighted Average for the Year 210.00 14.37 14.37 14.37 613-01100 1 In Elec Cond (P) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 905.00 43.85 49.82 49.82 FBR0703-534 I-70 Weighted Average for the Second Quarter 905.00 43.85 49.82 49.82 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 355.00 17.68 17.68 17.68 Weighted Average for the Third Quarter 355.00 17.68 17.68 17.68 Weighted Average for the Year 1,260.00 36.48 40.76 40.76 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-01150 1-1/2 In Elec Cond (P) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 20.00 19.89 22.10 22.10 Weighted Average for the Third Quarter 20.00 19.89 22.10 22.10 Weighted Average for the Year 20.00 19.89 22.10 22.10 613-01200 2 In Elec Cond (P) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,190.00 20.00 33.04 30.60 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 7,180.00 12.00 22.95 12.72 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 300.00 30.00 24.15 27.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 10.00 50.00 23.55 24.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,235.00 22.92 40.61 35.71 Weighted Average for the First Quarter 9,915.00 14.90 25.32 18.17 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 218.00 27.01 25.50 24.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 31,347.00 315.00 45.91 30.00 46.45 30.00 46.45 30.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 82.00 30.00 85.63 81.90 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1,205.00 25.96 25.96 25.96 ITSSW03-250 FRONT RANGE 06/26/25 120.00 29.87 42.20 30.00 Weighted Average for the Second Quarter 33,287.00 44.81 45.52 45.43 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10,420.00 17.68 17.68 17.68 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 9,270.00 14.33 22.75 21.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1,921.00 27.63 25.07 25.07 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 145.00 27.25 23.50 23.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 6,757.00 26.45 22.93 22.93 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 28,513.00 19.39 21.93 20.53 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 808.00 25.00 29.15 29.62 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 40.00 60.00 58.44 28.75 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 20.00 28.94 71.67 35.00 ITSSW03-417 STATEWIDE 12/04/25 3,030.00 22.81 49.00 35.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 128.00 30.00 74.64 32.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 12.00 30.00 96.40 140.00 Weighted Average for the Fourth Quarter 4,038.00 23.89 45.91 34.08 Weighted Average for the Year 75,753.00 30.21 30.50 31.89 613-01300 3 In Elec Cond (P) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 260.00 25.00 34.61 35.30 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,400.00 15.51 30.65 26.50 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 310.00 40.00 27.62 28.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 475.00 15.00 29.05 29.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 410.00 22.11 46.34 40.81 Weighted Average for the First Quarter 2,855.00 19.90 32.12 29.94 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 218.00 23.79 28.50 25.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 80.00 68.00 53.97 35.00 59.95 31.00 59.95 31.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 190.00 45.14 45.14 45.14 Weighted Average for the Second Quarter 556.00 36.80 36.06 37.64 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 200.00 23.21 23.21 23.21 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 50.00 22.80 33.50 24.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-01300 3 In Elec Cond (P) Lin Foot FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 260.00 40.00 24.00 24.50 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 118.00 28.89 29.48 29.48 Weighted Average for the Third Quarter 628.00 31.20 25.31 24.99 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,658.00 17.00 29.12 32.83 Weighted Average for the Fourth Quarter 2,658.00 17.00 29.12 32.83 Weighted Average for the Year 6,697.00 21.21 30.64 31.26 613-03491 Elec Cond (P) (Mult) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6,210.00 82.63 80.18 80.18 FBR0703-534 I-70 Weighted Average for the Second Quarter 6,210.00 82.63 80.18 80.18 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 65.00 41.73 42.59 42.59 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 25.00 51.36 52.41 52.41 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 600.00 47.08 48.04 48.04 Weighted Average for the Third Quarter 690.00 46.73 47.68 47.68 Weighted Average for the Year 6,900.00 79.04 76.93 76.93 613-03492 Elec Cond (P)(Mult)(Bored) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 485.00 106.81 106.81 106.81 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 485.00 106.81 106.81 106.81 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 270.00 35.36 35.36 35.36 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 115.00 47.08 48.04 48.04 Weighted Average for the Third Quarter 385.00 38.86 39.15 39.15 Weighted Average for the Year 870.00 76.74 76.87 76.87 613-03500 Elec Cond (P) (Mult) (Spec) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 638.00 68.79 51.47 36.04 Weighted Average for the First Quarter 638.00 68.79 51.47 36.04 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,210.00 75.33 81.31 81.31 FBR0703-534 I-70 Weighted Average for the Second Quarter 1,210.00 75.33 81.31 81.31 Weighted Average for the Year 1,848.00 73.07 58.63 65.68 613-04020 Hanger System Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 37216.07 37562.84 37562.84 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 50033.69 50033.32 50033.32 FBR0703-534 I-70 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 43624.88 43798.08 43798.08 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2.00 43624.88 43798.08 43798.08 613-04100 Elect System Mods Lump Sum NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 12000.00 4291.96 3774.75 Weighted Average for the First Quarter 1.00 12000.00 4291.96 3774.75 NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 1.00 18102.08 18101.94 18101.94 Weighted Average for the Second Quarter 1.00 18102.08 18101.94 18101.94 Weighted Average for the Year 2.00 15051.04 7053.95 10938.35 613-04125 1-1/4 In Elec Cond (Liquidtight Flx Met) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8.00 138.13 138.13 138.13 Weighted Average for the Third Quarter 8.00 138.13 138.13 138.13 Weighted Average for the Year 8.00 138.13 138.13 138.13 613-07000 Pull Box (Spec) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 8.00 1592.68 2487.00 1272.00 Weighted Average for the First Quarter 8.00 1592.68 2487.00 1272.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 23.00 2361.11 2361.12 2361.12 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-07000 Pull Box (Spec) Each FBR0703-534 I-70 Weighted Average for the Second Quarter 23.00 2361.11 2361.12 2361.12 Weighted Average for the Year 31.00 2162.80 2446.22 2080.06 613-07001 Type One Pull Box Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 13.00 979.95 1339.60 1388.60 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 13.00 1500.00 1738.15 1800.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 21.00 973.15 1914.58 1683.33 Weighted Average for the First Quarter 47.00 1120.76 1662.14 1634.08 ITSSW03-250 FRONT RANGE 06/26/25 2.00 1004.66 1547.00 1600.00 Weighted Average for the Second Quarter 2.00 1004.66 1547.00 1600.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 5.00 987.04 2007.00 1802.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 47.00 1010.29 1188.75 1200.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 59.00 1558.99 1590.80 1590.80 Weighted Average for the Third Quarter 111.00 1300.89 1338.88 1434.84 Weighted Average for the Year 160.00 1244.28 1484.01 1495.43 613-07002 Type Two Pull Box Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 1500.00 1805.66 2137.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 17.00 1520.05 1654.10 1600.60 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 613-07002 Type Two Pull Box Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 37.00 2000.00 2078.26 2200.00 Weighted Average for the First Quarter 58.00 1824.84 1900.65 2019.97 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 9.00 1300.91 2026.50 2053.00 NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO VET I-70 CO 17 & SOUTH OF CO 14 04/11/25 05/08/25 96.00 1.00 3035.75 1800.00 3035.73 2370.68 3035.73 2182.05 Weighted Average for the Second Quarter 106.00 2876.79 2863.41 2944.24 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 56.00 1574.63 1640.93 1640.93 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 26.00 1265.70 1997.75 1722.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 4.00 2210.00 5355.86 5355.86 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 20.00 1546.40 1519.81 1300.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 9.00 1875.71 1913.99 1913.99 Weighted Average for the Third Quarter 115.00 1545.54 1746.18 1750.55 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 8.00 2200.00 1492.17 1340.68 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 8.00 1269.32 1904.67 2500.00 ITSSW03-417 STATEWIDE 12/04/25 32.00 2682.14 1802.95 1660.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 2500.00 2767.50 2770.00 Weighted Average for the Fourth Quarter 50.00 2371.66 1783.56 1787.71 Weighted Average for the Year 329.00 2149.24 1944.19 2188.29 613-07003 Type Three Pull Box Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 5.00 1100.00 1708.49 2053.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 16.00 2500.00 2629.35 2650.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 21.00 2166.67 2335.46 2507.86 C0821-113 CO-82 & Catherine Store Signa 04/17/25 1.00 2000.00 1940.00 1940.00 ITSSW03-250 FRONT RANGE 06/26/25 1.00 1444.85 1925.40 1750.00 Weighted Average for the Second Quarter 2.00 1722.42 1927.83 1845.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 2071.88 2165.80 2165.80 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 2.00 1347.67 1767.25 1820.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 14.00 1629.47 2475.25 2103.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 1409.42 2031.60 1700.00 Weighted Average for the Third Quarter 20.00 1656.65 2352.88 2063.97 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 2320.00 2302.86 1892.44 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 5.00 1500.00 2129.60 1208.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 1400.00 3025.83 2500.00 Weighted Average for the Fourth Quarter 8.00 1692.50 2323.64 1540.61 Weighted Average for the Year 51.00 1874.86 2328.00 2156.06 613-07004 Type Four Pull Box Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 16.00 2000.00 3344.95 3696.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 9.00 1949.84 2961.05 2761.30 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 6.00 3500.00 2278.52 3000.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 2000.00 2379.56 2948.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 3.00 3000.00 3741.47 3750.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 6.00 1945.44 4219.51 3723.74 Weighted Average for the First Quarter 42.00 2267.17 3191.60 3368.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-07004 Type Four Pull Box Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 10.00 1971.49 3216.00 2932.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO I-70 VET 04/11/25 32.00 4553.63 4553.59 4553.59 C0821-113 CO-82 & Catherine Store Signa 04/17/25 3.00 3400.00 2519.00 2519.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 13.00 3432.80 3432.80 3432.80 ITSSW03-250 FRONT RANGE 06/26/25 68.00 2024.81 2329.20 1890.00 Weighted Average for the Second Quarter 126.00 2840.83 2583.69 2823.32 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 27.00 3171.35 3287.38 3287.38 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 2024.81 2613.50 2525.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 2.00 1989.76 3335.50 2836.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 3.00 2026.63 2481.00 2300.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 3.00 1986.39 2868.40 2400.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 3.00 3145.80 3210.00 3210.00 Weighted Average for the Third Quarter 39.00 2900.19 3019.21 3094.52 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 14.00 2950.00 2594.61 2301.42 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 3.00 2250.00 2378.55 1666.00 ITSSW03-417 STATEWIDE 12/04/25 6.00 2036.86 3361.14 3500.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 3.00 3500.00 3295.00 3300.00 Weighted Average for the Fourth Quarter 26.00 2721.97 2826.16 2619.92 Weighted Average for the Year 233.00 2734.10 2793.31 2944.29 613-07005 Type Five Pull Box Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 2500.00 4284.43 4904.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 3621.89 3977.27 3508.60 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2.00 4500.00 3148.65 3800.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 613-07005 Type Five Pull Box Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 1075.48 6377.37 5611.11 Weighted Average for the First Quarter 13.00 2824.15 4486.81 4467.98 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 11.00 1.00 5661.11 4600.00 5661.07 2749.00 5661.07 2749.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6.00 5026.20 5026.20 5026.20 ITSSW03-250 FRONT RANGE 06/26/25 2.00 2479.12 3552.40 3200.00 Weighted Average for the Second Quarter 20.00 5099.38 4667.93 5078.90 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 4127.18 4292.93 4292.93 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 2440.80 3764.60 3000.00 Weighted Average for the Third Quarter 3.00 3565.05 3915.55 3861.95 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4.00 3900.00 3695.70 3242.80 Weighted Average for the Fourth Quarter 4.00 3900.00 3695.70 3242.80 Weighted Average for the Year 40.00 4124.92 4376.47 4605.47 613-07010 Pull Box (Surf Mtd) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 5.00 3794.69 3794.66 3794.66 Weighted Average for the Second Quarter 5.00 3794.69 3794.66 3794.66 Weighted Average for the Year 5.00 3794.69 3794.66 3794.66 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-07011 Pull Box (11"x18"x12") Each NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL I-70 VASQUEZ BLVD - I270 TO TO VET 04/11/25 64TH - 05/23/25 2.00 4.00 2068.81 886.97 2068.79 886.97 2068.79 886.97 Weighted Average for the Second Quarter 6.00 1280.92 1280.91 1280.91 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 895.61 1545.52 1600.00 Weighted Average for the Fourth Quarter 4.00 895.61 1545.52 1600.00 Weighted Average for the Year 10.00 1126.80 1457.32 1408.55 613-07030 Pull Box (24"x16"x24") Each SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 4.00 5000.00 2481.00 2300.00 Weighted Average for the Third Quarter 4.00 5000.00 2481.00 2300.00 Weighted Average for the Year 4.00 5000.00 2481.00 2300.00 613-07040 Pull Box (30"x48"x24") Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 5.00 3000.00 4493.42 4365.68 Weighted Average for the Fourth Quarter 5.00 3000.00 4493.42 4365.68 Weighted Average for the Year 5.00 3000.00 4493.42 4365.68 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-07195 Proof Conduit Lin Foot ITSSW03-250 FRONT RANGE 06/26/25 200.00 5.84 4.31 2.00 Weighted Average for the Second Quarter 200.00 5.84 4.31 2.00 ITSSW03-417 STATEWIDE 12/04/25 4,000.00 4.62 3.57 6.00 Weighted Average for the Fourth Quarter 4,000.00 4.62 3.57 6.00 Weighted Average for the Year 4,200.00 4.68 3.61 5.81 613-07199 Inst Pull Box Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 11.00 3935.23 3935.20 3935.20 Weighted Average for the Second Quarter 11.00 3935.23 3935.20 3935.20 Weighted Average for the Year 11.00 3935.23 3935.20 3935.20 613-10000 Wiring Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 56362.03 119518.22 105000.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 80000.00 130472.26 112360.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 50000.00 56351.01 76600.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 70000.00 31184.47 25177.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 20000.00 14942.05 30600.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 70000.00 40359.85 35707.07 Weighted Average for the First Quarter 6.00 57727.01 68152.54 64240.68 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-10000 Wiring Lump Sum STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 45000.00 80350.00 62700.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 1.00 1.00 281088.12 15000.00 281086.08 19500.00 281086.08 19500.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 3000.00 8350.00 5850.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 40684.75 40684.75 40684.75 Weighted Average for the Second Quarter 5.00 76954.57 65877.60 81964.17 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 40195.48 54814.63 54814.63 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 177236.48 177236.48 177236.48 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 78289.25 78289.25 78289.25 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 20000.00 24287.50 26825.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 45000.00 92824.75 75500.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 60000.00 21902.00 24500.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 150000.00 47121.75 38000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 10861.57 11083.23 11083.23 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 82459.55 84142.40 84142.40 Weighted Average for the Third Quarter 9.00 73782.48 52326.88 63376.78 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 80000.00 92000.00 78650.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 1.00 4995.96 13006.67 9500.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 60000.00 36192.00 14300.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 60000.00 36192.00 14300.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 20000.00 4749.20 5600.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 20000.00 4749.20 5600.00 ITSSW03-417 STATEWIDE 12/04/25 1.00 40000.00 58086.50 52318.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 80000.00 7384.83 8500.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 1.00 10000.00 30798.60 13770.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 15000.00 4272.50 4280.00 Weighted Average for the Fourth Quarter 10.00 38999.60 34062.87 20681.80 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 30.00 59505.77 52035.87 52415.80 613-13000 Luminaire (LED) (Spec) Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 3.00 1500.00 1036.88 960.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 4.00 1100.00 1326.33 1377.00 Weighted Average for the First Quarter 7.00 1271.43 1247.39 1198.29 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL I-70 VASQUEZ BLVD - I270 TO TO VET 64TH - 04/11/25 05/23/25 3.00 6.00 1686.53 1033.68 1686.52 1033.68 1686.52 1033.68 Weighted Average for the Second Quarter 9.00 1251.30 1251.29 1251.29 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 28.00 10911.88 10911.88 10911.88 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 4.00 1096.71 1070.50 800.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 4.00 2100.00 940.50 900.00 Weighted Average for the Third Quarter 36.00 8842.21 5335.48 8675.91 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 14.00 1700.00 1105.41 1213.63 Weighted Average for the Fourth Quarter 14.00 1700.00 1105.41 1213.63 Weighted Average for the Year 66.00 5489.11 2813.57 5287.47 613-13002 Lumin (LED) (2,000 Lumens) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 8.00 400.00 737.47 932.80 Weighted Average for the First Quarter 8.00 400.00 737.47 932.80 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 8.00 400.00 737.47 932.80 2670252-499 613-13004 Lumin (LED) (4,000 Lumens) I-25:MOBILITY HUB (LONE TREE) 01/16/25 Each 5.00 578.17 1948.57 1791.40 Weighted Average for the First Quarter 5.00 578.17 1948.57 1791.40 613-13006 Weighted Average for the Year Lumin (LED) (6,000 Lumens) 5.00 Each 578.17 1948.57 1791.40 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 3000.00 1615.42 1316.25 Weighted Average for the Second Quarter 1.00 3000.00 1615.42 1316.25 613-13007 Weighted Average for the Year Lumin (LED) (3,000 Lumens) 1.00 Each 3000.00 1615.42 1316.25 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 839.80 1005.55 1005.55 Weighted Average for the Third Quarter 4.00 839.80 1005.55 1005.55 Weighted Average for the Year 4.00 839.80 1005.55 1005.55 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-13008 Lumin (LED) (8,000 Lumens) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 12.00 1095.66 2922.25 1828.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 1086.99 929.07 816.16 Weighted Average for the First Quarter 14.00 1094.42 2722.93 1683.88 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 5.00 1090.77 1167.00 1134.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 15.00 1051.27 1051.26 1051.26 Weighted Average for the Second Quarter 20.00 1061.15 1097.56 1071.95 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 18.00 1906.13 2033.20 2033.20 Weighted Average for the Third Quarter 18.00 1906.13 2033.20 2033.20 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 10.00 3000.00 5797.83 1500.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 4.00 1250.00 999.05 889.00 Weighted Average for the Fourth Quarter 14.00 2500.00 5233.27 1325.43 Weighted Average for the Year 66.00 1603.87 3338.92 1517.68 613-13011 Lumin (LED) (11,000 Lumens) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 23.00 1906.13 2033.20 2033.20 Weighted Average for the Third Quarter 23.00 1906.13 2033.20 2033.20 Weighted Average for the Year 23.00 1906.13 2033.20 2033.20 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-13012 Lumin (LED) (12,000 Lumens) Each NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 9.00 1124.35 1124.35 1124.35 Weighted Average for the Second Quarter 9.00 1124.35 1124.35 1124.35 Weighted Average for the Year 9.00 1124.35 1124.35 1124.35 613-13014 Lumin (LED) (14,000 Lumens) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 15.00 40.00 1432.52 1328.00 Weighted Average for the First Quarter 15.00 40.00 1432.52 1328.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 28.00 674.05 1016.60 1016.60 Weighted Average for the Third Quarter 28.00 674.05 1016.60 1016.60 Weighted Average for the Year 43.00 452.87 1272.99 1125.23 613-13016 Lumin (LED) (16,000 Lumens) Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 20.00 1067.70 1051.56 900.00 Weighted Average for the Third Quarter 20.00 1067.70 1051.56 900.00 Weighted Average for the Year 20.00 1067.70 1051.56 900.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-13020 Lumin (LED) (20,000 Lumens) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 15.00 1210.17 1234.87 1234.87 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 25.00 2981.02 3041.86 3041.86 Weighted Average for the Third Quarter 40.00 2316.95 2364.24 2364.24 Weighted Average for the Year 40.00 2316.95 2364.24 2364.24 613-16000 Luminaire (Spec) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 1000.00 2105.66 1520.00 Weighted Average for the First Quarter 2.00 1000.00 2105.66 1520.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 2281.83 2342.60 2342.60 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 2983.16 3044.04 3044.04 Weighted Average for the Third Quarter 7.00 2682.59 2743.42 2743.42 Weighted Average for the Year 9.00 2308.68 2449.07 2471.55 613-30005 Light Std + Lumin (Pedest) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 28.00 2500.00 6681.33 5618.00 Weighted Average for the First Quarter 28.00 2500.00 6681.33 5618.00 Weighted Average for the Year 28.00 2500.00 6681.33 5618.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-30120 Light Std Alum (12 Ft) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 17.00 1500.00 4285.55 3927.30 Weighted Average for the First Quarter 17.00 1500.00 4285.55 3927.30 Weighted Average for the Year 17.00 1500.00 4285.55 3927.30 613-32250 Light Std Steel (25 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 9.00 4199.00 4199.00 4199.00 Weighted Average for the Third Quarter 9.00 4199.00 4199.00 4199.00 Weighted Average for the Year 9.00 4199.00 4199.00 4199.00 613-32252 Light Std Steel (25 Ft) (2) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 7.00 4392.38 4392.38 4392.38 Weighted Average for the Third Quarter 7.00 4392.38 4392.38 4392.38 Weighted Average for the Year 7.00 4392.38 4392.38 4392.38 613-32300 Light Std Steel (30 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 24.00 4497.41 4497.37 4497.37 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 24.00 4497.41 4497.37 4497.37 Weighted Average for the Year 24.00 4497.41 4497.37 4497.37 613-32400 Light Std Steel (40 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 27.00 4668.63 4768.08 4768.08 Weighted Average for the Third Quarter 27.00 4668.63 4768.08 4768.08 Weighted Average for the Year 27.00 4668.63 4768.08 4768.08 613-33300 Light Std Timber (30 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 3500.00 5017.75 3175.00 Weighted Average for the First Quarter 2.00 3500.00 5017.75 3175.00 Weighted Average for the Year 2.00 3500.00 5017.75 3175.00 613-34140 Light Std Metal (14 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 18.00 3530.48 3530.48 3530.48 Weighted Average for the Third Quarter 18.00 3530.48 3530.48 3530.48 Weighted Average for the Year 18.00 3530.48 3530.48 3530.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-34150 Light Std Metal (15 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 3530.48 885.11 885.11 Weighted Average for the Third Quarter 4.00 3530.48 885.11 885.11 C0063-067 613-34200 Weighted Average for the Year Light Standard Metal (20 Foot) US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 Each 10.00 3530.48 6150.00 885.11 7244.00 885.11 9500.00 Weighted Average for the Fourth Quarter 10.00 6150.00 7244.00 9500.00 Weighted Average for the Year 10.00 6150.00 7244.00 9500.00 613-34300 Light Std Metal (30 Ft) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 25.00 4390.21 4479.80 4479.80 Weighted Average for the Third Quarter 25.00 4390.21 4479.80 4479.80 NHPP2873-206 613-34350 Weighted Average for the Year Light Std Metal (35 Ft) US287:RESURFACING I-70 TO 92N 01/09/25 25.00 Each 2.00 4390.21 4000.00 4479.80 5487.11 4479.80 6342.00 Weighted Average for the First Quarter 2.00 4000.00 5487.11 6342.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2.00 4000.00 5487.11 6342.00 613-34400 Light Std Metal (40 Ft) Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 20.00 2220.77 5237.06 5000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 15.00 4893.11 4992.97 4992.97 Weighted Average for the Third Quarter 35.00 3366.06 5216.14 4996.99 Weighted Average for the Year 35.00 3366.06 5216.14 4996.99 613-40000 Conc Foundation Pad Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 3000.00 3106.86 2285.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 3640.28 3356.92 4054.50 Weighted Average for the First Quarter 5.00 3384.17 3294.40 3346.70 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 17.00 3485.49 3485.47 3485.47 FBR0703-534 I-70 Weighted Average for the Second Quarter 17.00 3485.49 3485.47 3485.47 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 9647.71 9647.71 9647.71 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 5210.08 5491.85 5491.85 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 5.00 3495.69 3567.03 3567.03 Weighted Average for the Third Quarter 12.00 4865.55 5036.16 5036.16 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 2500.00 3552.78 4429.99 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 7.00 2500.00 3552.78 4429.99 Weighted Average for the Year 41.00 3708.80 3681.86 4083.67 613-40010 Light Std Foundation Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 2000.00 3754.44 5210.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 38.00 2615.25 3041.83 3233.00 Weighted Average for the First Quarter 40.00 2584.48 3060.11 3331.85 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 19.00 4.00 9444.56 3925.94 9444.49 3925.94 9444.49 3925.94 Weighted Average for the Second Quarter 23.00 8484.80 8484.74 8484.74 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 65.00 4944.88 4944.88 4944.88 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 20.00 2569.25 4307.19 3900.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 40.00 4778.62 4876.14 4876.14 Weighted Average for the Third Quarter 125.00 4511.58 4549.48 4755.70 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 10.00 5600.00 4997.50 6700.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 6500.00 10620.00 10640.00 Weighted Average for the Fourth Quarter 12.00 5750.00 5348.91 7356.67 Weighted Average for the Year 200.00 4657.38 4196.51 5055.83 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-40012 Light Std Foundation Spec Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 5.00 10625.13 10625.05 10625.05 FBR0703-534 I-70 Weighted Average for the Second Quarter 5.00 10625.13 10625.05 10625.05 Weighted Average for the Year 5.00 10625.13 10625.05 10625.05 613-40020 Transformer Base Alum Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 15.00 758.94 758.94 758.94 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 4.00 1258.25 1258.25 1258.25 Weighted Average for the Second Quarter 19.00 864.06 864.06 864.06 Weighted Average for the Year 19.00 864.06 864.06 864.06 613-50100 Lighting Ctrl Center Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 3.00 12873.84 12873.75 12873.75 FBR0703-534 I-70 Weighted Average for the Second Quarter 3.00 12873.84 12873.75 12873.75 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 2.00 5766.11 13416.50 11000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 10977.13 11201.16 11201.16 Weighted Average for the Third Quarter 3.00 7503.12 13286.18 11067.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 6.00 10188.48 13224.32 11970.40 613-50106 Light Cont Center (Spec) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 9217.35 12961.63 13069.80 Weighted Average for the First Quarter 2.00 9217.35 12961.63 13069.80 Weighted Average for the Year 2.00 9217.35 12961.63 13069.80 613-50109 Meter Power Pedestal Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 12000.00 12119.20 9860.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 10792.53 11531.13 11161.80 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 10974.19 12755.98 11222.22 Weighted Average for the First Quarter 4.00 11441.68 12057.87 10526.01 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 3.00 12000.00 10581.50 8163.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6.00 12873.84 12873.75 12873.75 FBR0703-534 I-70 Weighted Average for the Second Quarter 9.00 12582.56 11727.63 11303.50 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 13591.50 13591.50 13591.50 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 12403.63 12403.63 12403.63 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 14331.85 14331.85 14331.85 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 13293.15 13293.15 13293.15 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 15724.15 15967.25 15967.25 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 13000.00 11407.60 13500.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 2.00 11066.98 11662.38 10000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 10977.13 11201.16 11201.16 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 11.00 12729.45 12041.97 12643.75 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 9500.00 11878.96 10972.63 Weighted Average for the Fourth Quarter 7.00 9500.00 11878.96 10972.63 Weighted Average for the Year 31.00 11791.41 11946.89 11604.04 613-50125 Ctrl Center Box Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 14.00 2016.63 2016.63 2016.63 Weighted Average for the Third Quarter 14.00 2016.63 2016.63 2016.63 Weighted Average for the Year 14.00 2016.63 2016.63 2016.63 613-50127 Local Control Station Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 11934.00 12431.25 12431.25 Weighted Average for the Third Quarter 1.00 11934.00 12431.25 12431.25 Weighted Average for the Year 1.00 11934.00 12431.25 12431.25 613-50150 Secondary Serv Pedestal Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2.00 15000.00 12735.32 13200.00 Weighted Average for the First Quarter 2.00 15000.00 12735.32 13200.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 613-50150 Secondary Serv Pedestal Each C0821-113 CO-82 & Catherine Store Signa 04/17/25 1.00 11000.00 11120.00 11120.00 Weighted Average for the Second Quarter 1.00 11000.00 11120.00 11120.00 Weighted Average for the Year 3.00 13666.67 12504.56 12506.67 613-50210 Temporary Lighting Lump Sum NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 137845.61 129299.60 129299.60 Weighted Average for the Second Quarter 1.00 137845.61 129299.60 129299.60 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 106618.01 108793.89 108793.89 Weighted Average for the Third Quarter 1.00 106618.01 108793.89 108793.89 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 35000.00 99862.50 54450.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1.00 200000.00 323650.00 450000.00 Weighted Average for the Fourth Quarter 2.00 117500.00 224188.89 252225.00 Weighted Average for the Year 4.00 119865.91 205072.14 185635.87 613-50211 Temporary Lighting (Solar) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 5497.38 5497.38 5497.38 Weighted Average for the Third Quarter 4.00 5497.38 5497.38 5497.38 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 4.00 5497.38 5497.38 5497.38 613-50350 Power Transformer Lump Sum NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD I-70 HILL TO VET 04/11/25 1.00 7308.29 43849.44 43849.44 Weighted Average for the Second Quarter 1.00 7308.29 43849.44 43849.44 Weighted Average for the Year 1.00 7308.29 43849.44 43849.44 613-50351 PowerTransformer(10KVA,480-120/240V1Ph) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 10917.21 11140.01 11140.01 Weighted Average for the Third Quarter 1.00 10917.21 11140.01 11140.01 Weighted Average for the Year 1.00 10917.21 11140.01 11140.01 613-50375 Solar Collection System Each ITSSW03-417 STATEWIDE 12/04/25 42.00 14770.84 8569.64 8345.00 Weighted Average for the Fourth Quarter 42.00 14770.84 8569.64 8345.00 Weighted Average for the Year 42.00 14770.84 8569.64 8345.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 613-60700 Troubleshooting Hour 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 20.00 223.57 367.62 365.70 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 124.00 195.06 231.96 204.04 Weighted Average for the First Quarter 144.00 199.02 258.38 226.49 NHPP0703-517 FBR0703-534 ITSSW03-250 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 FRONT RANGE 06/26/25 400.00 100.00 309.20 286.94 309.19 194.00 309.19 170.00 Weighted Average for the Second Quarter 500.00 304.75 245.20 281.35 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 8.00 246.57 168.25 160.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 40.00 267.50 272.96 272.96 Weighted Average for the Third Quarter 48.00 264.01 226.42 254.13 ITSSW03-417 STATEWIDE 12/04/25 100.00 233.80 206.25 250.00 Weighted Average for the Fourth Quarter 100.00 233.80 206.25 250.00 Weighted Average for the Year 792.00 274.10 240.77 265.77 613-80007 Circuit Breaker (70A, 2 Pole) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 1883.30 1883.27 1883.27 Weighted Average for the Second Quarter 1.00 1883.30 1883.27 1883.27 Weighted Average for the Year 1.00 1883.30 1883.27 1883.27 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-80105 Circ Breaker (30A, 2 Pole) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 9.00 1377.33 1377.33 1377.33 Weighted Average for the Second Quarter 9.00 1377.33 1377.33 1377.33 Weighted Average for the Year 9.00 1377.33 1377.33 1377.33 613-80130 Service Meter Cabinet Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 7000.00 11395.85 9860.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 10000.00 10042.83 10562.00 Weighted Average for the First Quarter 7.00 7857.14 10794.51 10060.57 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 3712.67 3712.67 3712.67 ITSSW03-250 FRONT RANGE 06/26/25 1.00 5441.89 12664.40 15000.00 Weighted Average for the Second Quarter 3.00 4289.08 10106.76 7475.11 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 3.00 6688.72 9711.25 9600.00 Weighted Average for the Third Quarter 3.00 6688.72 9711.25 9600.00 ITSSW03-417 STATEWIDE 12/04/25 18.00 14440.13 9536.95 8504.00 Weighted Average for the Fourth Quarter 18.00 14440.13 9536.95 8504.00 Weighted Average for the Year 31.00 11221.15 9876.22 8861.98 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-80274 Struct Mount Disc Switch Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 2023.83 2023.82 2023.82 Weighted Average for the Second Quarter 1.00 2023.83 2023.82 2023.82 Weighted Average for the Year 1.00 2023.83 2023.82 2023.82 613-81010 Pnlbrd (100A, 120/208V, 3Ph, 42 Circuit) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 12086.79 12086.70 12086.70 Weighted Average for the Second Quarter 1.00 12086.79 12086.70 12086.70 Weighted Average for the Year 1.00 12086.79 12086.70 12086.70 613-81500 Panelboard (5KVA Mini Load Center) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 8.00 9332.13 9332.06 9332.06 Weighted Average for the Second Quarter 8.00 9332.13 9332.06 9332.06 Weighted Average for the Year 8.00 9332.13 9332.06 9332.06 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 613-81602 Temp Switchgear Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 46660.64 46660.29 46660.29 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 46660.64 46660.29 46660.29 Weighted Average for the Year 1.00 46660.64 46660.29 46660.29 613-81699 Safe Switch NEMA 3R, 30A, 2-pole, 240 V Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 1933.42 2675.58 2346.46 Weighted Average for the First Quarter 1.00 1933.42 2675.58 2346.46 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6.00 1905.78 1905.76 1905.76 FBR0703-534 I-70 Weighted Average for the Second Quarter 6.00 1905.78 1905.76 1905.76 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 1475.18 1475.18 1475.18 Weighted Average for the Third Quarter 2.00 1475.18 1475.18 1475.18 Weighted Average for the Year 9.00 1813.16 2090.60 1859.04 614-00011 Sign Panel (CL I) Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 688.00 30.00 27.87 28.25 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 177.00 26.16 29.45 31.21 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 30.00 30.00 57.56 82.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-00011 Sign Panel (CL I) Sq Foot SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 49.00 40.00 34.17 31.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 665.00 40.00 27.78 27.50 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 11.00 33.73 61.30 25.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,181.00 26.22 29.89 25.76 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 30.00 25.00 23.55 20.10 Weighted Average for the First Quarter 2,831.00 30.67 29.36 27.74 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 238.50 41.32 59.50 34.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 150.00 37.00 35.34 35.00 35.50 37.00 35.50 37.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 56.00 27.77 26.33 26.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 84.00 27.00 32.36 28.08 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 500.00 27.88 27.88 27.88 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 4.00 46.33 53.24 40.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 2,793.00 27.55 31.88 33.50 Weighted Average for the Second Quarter 3,862.50 28.83 32.78 32.69 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 212.00 33.66 33.66 33.66 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 262.00 147.76 147.76 147.76 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 41.00 33.75 42.88 35.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 4,986.00 35.00 29.00 26.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 3.00 36.94 48.99 35.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 55.50 29.04 44.32 72.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 6.00 53.00 40.00 28.39 160.57 27.20 30.00 20.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 610.00 37.45 38.21 38.21 Weighted Average for the Third Quarter 6,228.50 39.83 31.81 33.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 390.00 30.00 47.56 30.25 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-00011 Sign Panel (CL I) Sq Foot NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 301.00 25.19 36.06 25.25 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 8.00 30.52 52.53 60.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 12.00 33.60 73.06 55.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 268.00 30.00 26.83 25.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 69.83 27.73 28.85 28.95 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 55.92 27.49 25.00 20.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 120.00 24.00 27.90 32.09 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 342.00 34.32 28.04 26.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 331.00 20.46 25.25 24.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 763.00 23.92 29.65 26.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 404.00 26.73 32.32 32.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 378.00 24.55 17.00 17.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 12.00 40.00 29.80 30.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 36.00 29.51 32.26 48.55 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 156.00 24.91 27.43 27.00 Weighted Average for the Fourth Quarter 3,646.75 26.49 31.86 26.63 Weighted Average for the Year 16,568.75 32.76 31.55 30.63 614-00012 Sign Panel (CL II) Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 95.00 33.09 39.90 48.42 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 12.00 45.00 75.60 90.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 80.00 35.00 40.88 42.75 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 51.00 50.00 44.25 47.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 117.00 34.44 46.11 35.70 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,057.00 31.50 43.56 39.15 Weighted Average for the First Quarter 1,412.00 32.83 43.52 40.41 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,337.00 47.12 47.34 47.34 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-00012 Sign Panel (CL II) Sq Foot FBR0703-534 I-70 C0821-113 CO-82 & Catherine Store Signa 04/17/25 3.00 40.00 50.00 50.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 124.00 33.00 42.17 41.50 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 133.00 30.00 50.82 44.46 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 3,773.00 28.30 42.81 38.25 Weighted Average for the Second Quarter 5,370.00 33.14 43.34 40.75 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 367.00 44.87 44.87 44.87 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 36.00 42.62 58.43 42.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 117.00 35.90 58.59 80.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 6,722.00 40.00 36.67 37.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 116.00 35.15 45.88 48.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 16.00 46.49 48.80 35.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 112.00 30.82 33.01 25.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 991.00 42.80 43.68 43.68 SPFS2706-055 I-270 MP 0-3 09/26/25 192.00 70.95 71.63 71.63 Weighted Average for the Third Quarter 8,669.00 41.00 38.01 39.45 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 208.00 36.00 47.84 42.35 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 138.00 31.37 43.99 42.25 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 132.00 30.46 29.59 20.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 331.00 40.00 36.33 35.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 585.67 29.88 42.40 44.55 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,063.88 29.42 37.75 28.50 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 176.00 33.24 59.00 55.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 213.00 26.00 32.45 39.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 226.00 34.90 36.96 33.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 135.00 28.39 30.50 30.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 610.00 32.41 40.81 35.80 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 416.00 34.67 38.94 48.50 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 165.00 31.32 29.25 29.25 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 60.00 24.00 46.61 60.70 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 614-00012 Sign Panel (CL II) Sq Foot STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 621.00 28.76 33.46 34.00 Weighted Average for the Fourth Quarter 5,080.55 31.42 39.15 36.68 Weighted Average for the Year 20,531.55 36.01 40.25 39.17 614-00013 Sign Panel (CL III) Sq Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 129.00 44.70 53.82 49.45 Weighted Average for the First Quarter 129.00 44.70 53.82 49.45 NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 SH287 & LCR 72 AND US287 & OW 04/24/25 3,847.00 21.00 58.90 45.00 59.17 51.40 59.17 51.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 207.00 56.30 56.30 56.30 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 196.00 37.76 55.75 48.00 Weighted Average for the Second Quarter 4,271.00 57.74 58.40 58.48 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,351.00 64.20 65.51 65.51 Weighted Average for the Third Quarter 1,351.00 64.20 65.51 65.51 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 734.00 47.58 47.06 60.50 Weighted Average for the Fourth Quarter 734.00 47.58 47.06 60.50 Weighted Average for the Year 6,485.00 57.67 55.11 59.99 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 614-00025 Inst Sign Panel (CL I) Sq Foot MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 1,283.00 13.00 15.33 12.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 9.00 24.20 32.38 25.00 Weighted Average for the Third Quarter 1,292.00 13.08 15.49 12.09 Weighted Average for the Year 1,292.00 13.08 15.49 12.09 614-00026 Inst Sign Panel (CL I) Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 7.00 500.00 182.40 280.00 Weighted Average for the First Quarter 7.00 500.00 182.40 280.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 10.00 420.00 407.36 54.45 Weighted Average for the Fourth Quarter 10.00 420.00 407.36 54.45 Weighted Average for the Year 17.00 452.94 329.92 147.32 614-00027 Inst Sign Panel (CL II) Sq Foot MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 4,800.00 16.00 20.00 15.00 Weighted Average for the Third Quarter 4,800.00 16.00 20.00 15.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 561.00 21.54 18.55 14.00 Weighted Average for the Fourth Quarter 561.00 21.54 18.55 14.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 5,361.00 16.58 19.85 14.90 614-00028 Inst Sign Panel (CL III) Sq Foot MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 3,717.00 23.00 29.67 22.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 728.00 15.00 23.33 28.00 Weighted Average for the Third Quarter 4,445.00 21.69 28.63 22.98 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 2,939.50 30.00 21.46 19.00 Weighted Average for the Fourth Quarter 2,939.50 30.00 21.46 19.00 Weighted Average for the Year 7,384.50 25.00 25.78 21.40 614-00029 Inst Sign Panel (CL II) Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 4.00 120.00 270.00 495.00 Weighted Average for the First Quarter 4.00 120.00 270.00 495.00 Weighted Average for the Year 4.00 120.00 270.00 495.00 614-00037 Sign Panel (Spec) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 14110.47 5111.06 12109.35 Weighted Average for the First Quarter 3.00 14110.47 5111.06 12109.35 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 1.00 6115.68 4145.00 61.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 1.00 6115.68 4145.00 61.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 38678.99 38678.99 38678.99 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 18.00 3305.31 3305.31 3305.31 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 1892.62 1892.62 1892.62 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 20236.90 20236.90 20236.90 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 7.00 5234.04 8552.01 8552.01 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 5116.81 7547.88 7547.88 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 67.00 1781.27 1781.27 1781.27 Weighted Average for the Third Quarter 106.00 4106.48 4394.39 4394.39 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 3.00 106.30 4816.00 310.00 NHPP1602-194 US 160 MP 174.1 12/11/25 66.00 300.00 158.62 114.00 Weighted Average for the Fourth Quarter 69.00 291.58 409.02 122.52 Weighted Average for the Year 179.00 2814.82 1685.61 2852.79 614-00040 Signpost (Spec) Lin Foot NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 770.00 700.00 23.31 24.00 Weighted Average for the First Quarter 770.00 700.00 23.31 24.00 Weighted Average for the Year 770.00 700.00 23.31 24.00 614-00041 Signpost (Spec) Each MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 23.00 2200.00 4166.67 4250.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 23.00 2200.00 4166.67 4250.00 Weighted Average for the Year 23.00 2200.00 4166.67 4250.00 614-00200 Steel Signpost (U-2) Lin Foot C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 10.00 16.96 70.21 30.00 Weighted Average for the Second Quarter 10.00 16.96 70.21 30.00 Weighted Average for the Year 10.00 16.96 70.21 30.00 614-00216 Steel Signpost (2x2 In T) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 60.00 19.93 23.67 40.78 Weighted Average for the First Quarter 60.00 19.93 23.67 40.78 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,137.00 27.90 9.64 9.64 Weighted Average for the Third Quarter 1,137.00 27.90 9.64 9.64 Weighted Average for the Year 1,197.00 27.50 13.01 11.20 614-00220 Steel Signpost (2.5x2.5 In T) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 312.00 14.73 26.09 26.09 Weighted Average for the Third Quarter 312.00 14.73 26.09 26.09 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 312.00 14.73 26.09 26.09 614-00612 Steel Signpost (W 6x12) Lin Foot MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 289.00 65.00 110.00 120.00 Weighted Average for the Third Quarter 289.00 65.00 110.00 120.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 25.00 90.00 73.60 73.70 Weighted Average for the Fourth Quarter 25.00 90.00 73.60 73.70 Weighted Average for the Year 314.00 66.99 108.02 116.31 614-00615 Steel Signpost (W 6x15) Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 29.00 113.44 178.59 164.85 Weighted Average for the First Quarter 29.00 113.44 178.59 164.85 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 95.00 100.00 123.33 130.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 103.00 175.48 179.06 179.06 Weighted Average for the Third Quarter 198.00 139.26 138.13 155.52 Weighted Average for the Year 227.00 135.97 147.44 156.71 614-00818 Steel Signpost (W 8x18) Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 71.00 56.06 341.19 185.45 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 71.00 56.06 341.19 185.45 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 185.00 199.02 203.09 203.09 Weighted Average for the Third Quarter 185.00 199.02 203.09 203.09 Weighted Average for the Year 256.00 159.37 286.71 198.20 614-00821 Steel Signpost (W 8x21) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 32.00 212.02 213.01 213.01 FBR0703-534 I-70 Weighted Average for the Second Quarter 32.00 212.02 213.01 213.01 Weighted Average for the Year 32.00 212.02 213.01 213.01 614-01022 Steel Signpost (W 10x22) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 40.00 240.75 245.66 245.66 Weighted Average for the Third Quarter 40.00 240.75 245.66 245.66 Weighted Average for the Year 40.00 240.75 245.66 245.66 614-01026 Steel Signpost (W 10x26) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 111.00 223.80 224.85 224.85 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 111.00 223.80 224.85 224.85 Weighted Average for the Year 111.00 223.80 224.85 224.85 614-01226 Steel Signpost (W 12x26) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 168.00 235.58 236.68 236.68 Weighted Average for the Second Quarter 168.00 235.58 236.68 236.68 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 92.00 267.50 272.96 272.96 Weighted Average for the Third Quarter 92.00 267.50 272.96 272.96 Weighted Average for the Year 260.00 246.87 249.52 249.52 614-01401 Steel Sign Support Casting Each MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 162.00 150.00 191.67 200.00 Weighted Average for the Third Quarter 162.00 150.00 191.67 200.00 Weighted Average for the Year 162.00 150.00 191.67 200.00 614-01402 Steel Sign Surf Mnt Base Plate (Slpbase) Each NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 1000.00 1777.50 1780.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 2.00 1000.00 1777.50 1780.00 Weighted Average for the Year 2.00 1000.00 1777.50 1780.00 614-01502 Steel Sign Supp (2-In Rd)(Po&Sock) Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 138.00 34.12 34.12 34.12 Weighted Average for the Second Quarter 138.00 34.12 34.12 34.12 Weighted Average for the Year 138.00 34.12 34.12 34.12 614-01503 Steel Sign Supp (2-In Rd)(Po&Sock) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 75.00 400.00 435.03 440.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 7.00 478.92 395.40 381.41 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 450.00 539.81 428.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 25.00 415.50 351.00 Weighted Average for the First Quarter 94.00 367.05 432.36 425.91 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 51.00 500.61 502.94 502.94 FBR0703-534 I-70 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 5.00 517.90 355.00 345.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 2.00 520.00 434.52 368.55 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 282.00 350.00 474.00 310.00 Weighted Average for the Second Quarter 340.00 376.06 473.55 339.80 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 188.00 379.36 328.33 345.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 3.00 419.55 439.28 500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 191.00 379.99 332.86 347.43 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 10.00 597.42 401.00 290.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.00 456.20 461.85 370.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 4.00 300.00 446.75 462.25 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 21.00 343.65 347.00 144.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 5.00 434.32 460.64 470.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 37.00 327.44 97.50 95.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 41.00 541.80 505.60 568.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 11.00 455.11 220.00 220.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 10.00 509.32 508.85 728.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 30.00 412.22 337.89 350.00 Weighted Average for the Fourth Quarter 171.00 434.33 403.37 338.40 Weighted Average for the Year 796.00 388.46 422.58 351.50 614-01512 Steel Sign Support (2-In Rd)(Post) Lin Foot MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 1,553.00 11.00 20.00 20.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 207.00 56.09 44.81 44.81 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 20.00 26.35 50.88 50.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 12.00 15.54 25.79 21.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 198.00 64.20 65.51 65.51 Weighted Average for the Third Quarter 1,990.00 21.17 23.25 27.42 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 411.00 27.00 19.33 25.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 454.00 17.14 11.67 4.45 Weighted Average for the Fourth Quarter 865.00 21.82 15.66 14.21 Weighted Average for the Year 2,855.00 21.36 19.63 23.42 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-01522 Steel Sign Supp (2-In Rd)(Sock) Each MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 106.00 150.00 258.33 250.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 19.00 448.73 481.50 481.50 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 2.00 233.76 182.63 185.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 2.00 228.01 188.66 130.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 18.00 101.65 103.73 103.73 Weighted Average for the Third Quarter 147.00 184.89 259.13 259.49 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 47.00 300.00 188.83 90.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 85.00 227.18 182.60 139.00 Weighted Average for the Fourth Quarter 132.00 253.11 185.09 121.55 Weighted Average for the Year 279.00 217.17 210.57 194.23 614-01554 Steel Signpost (4 In Rd) (Slip) Lin Foot SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 272.00 57.24 123.05 105.00 Weighted Average for the Third Quarter 272.00 57.24 123.05 105.00 Weighted Average for the Year 272.00 57.24 123.05 105.00 614-01572 Steel Sign Supp (2-1/2 Rd NP40)(Po&Silp) Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 325.00 59.72 59.72 59.72 Weighted Average for the Second Quarter 325.00 59.72 59.72 59.72 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 325.00 59.72 59.72 59.72 614-01573 Steel Sign Supp (2-1/2 Rd NP40)(Po&Slip) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 21.00 500.00 603.62 689.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 6.00 591.27 608.80 596.78 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 6.00 650.00 819.33 680.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 100.00 535.75 717.23 633.64 Weighted Average for the First Quarter 133.00 537.76 703.43 642.81 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 16.00 666.94 648.33 645.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 14.00 700.00 661.77 690.30 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 421.00 538.91 785.25 485.00 Weighted Average for the Second Quarter 451.00 548.45 778.62 497.05 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 540.00 575.00 540.00 600.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 4.00 11.00 750.00 664.07 1031.60 704.20 710.00 600.00 Weighted Average for the Third Quarter 555.00 578.03 554.05 600.79 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 25.00 655.00 412.38 544.50 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 5.00 910.41 709.00 685.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 12.00 601.97 608.45 450.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 24.00 705.92 735.74 724.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 58.00 556.31 595.50 380.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 25.00 602.87 726.10 670.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 33.00 373.04 389.00 378.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 47.00 590.75 757.40 689.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 2.00 961.27 605.00 605.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 4.00 600.00 501.00 500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-01573 Steel Sign Supp (2-1/2 Rd NP40)(Po&Slip) Each FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 6.00 688.59 681.23 1092.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 29.00 644.92 552.04 550.00 Weighted Average for the Fourth Quarter 270.00 591.35 622.54 552.49 Weighted Average for the Year 1,409.00 567.31 663.82 562.30 614-01575 Steel Sign Supp (2-1/2 In Rd NP40)(Po) Lin Foot NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 88.00 25.00 32.38 33.75 Weighted Average for the First Quarter 88.00 25.00 32.38 33.75 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 281.00 56.09 56.09 56.09 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 119.00 35.00 33.18 33.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,734.00 37.45 38.21 38.21 Weighted Average for the Third Quarter 2,134.00 39.77 39.26 40.27 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 403.00 40.00 31.25 35.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 481.00 24.09 24.04 19.50 Weighted Average for the Fourth Quarter 884.00 31.34 27.65 26.57 Weighted Average for the Year 3,106.00 36.95 31.63 36.19 614-01578 Steel Sign Supp (2-1/2 In Rd NP40)(Slip) Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 7.00 350.00 297.00 310.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 7.00 350.00 297.00 310.00 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 96.00 300.00 366.67 400.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 38.00 673.10 673.10 673.10 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 9.00 376.51 349.23 325.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 155.00 331.70 338.47 338.47 Weighted Average for the Third Quarter 298.00 366.38 379.52 400.56 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 48.00 400.00 392.50 450.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 8.00 400.00 698.67 850.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 85.00 351.09 441.20 525.00 Weighted Average for the Fourth Quarter 141.00 370.51 430.55 517.91 Weighted Average for the Year 446.00 367.43 408.27 436.23 614-01583 Stl Sign Supp (2-1/2 In Rd 80)(Po&Slip) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 10.00 702.60 683.99 655.92 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 11.00 642.66 804.71 730.00 Weighted Average for the First Quarter 21.00 671.20 726.82 694.72 NHPP0703-517 FBR0703-534 MTCE0361-135 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 US-36B FROM MP 0.00-33.76 IN 06/05/25 74.00 7.00 765.65 655.00 769.20 996.50 769.20 585.00 Weighted Average for the Second Quarter 81.00 756.09 831.60 753.28 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 21.00 700.00 663.33 690.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 731.13 878.80 650.00 SPFS2706-055 I-270 MP 0-3 09/26/25 12.00 918.41 980.58 980.58 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 34.00 778.00 724.39 791.38 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 7.00 867.84 831.70 843.50 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 7.00 644.97 662.45 660.00 Weighted Average for the Fourth Quarter 14.00 756.40 768.23 751.75 Weighted Average for the Year 150.00 749.20 765.53 753.58 614-01585 Steel Sign Supp (2-1/2 In Rd 80)(Post) Lin Foot MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 1,198.00 20.00 36.67 32.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 12.00 30.55 70.75 120.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 32.00 33.47 51.13 57.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 28.00 53.50 54.59 54.59 Weighted Average for the Third Quarter 1,270.00 21.18 37.72 33.96 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 14.00 40.00 39.17 55.00 Weighted Average for the Fourth Quarter 14.00 40.00 39.17 55.00 Weighted Average for the Year 1,284.00 21.38 37.75 34.19 614-01588 Steel Sign Supp (2-1/2 In Rd 80)(Slip) Each SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 534.74 335.25 400.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 2.00 568.68 420.75 340.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 337.05 343.93 343.93 Weighted Average for the Third Quarter 5.00 469.24 385.35 353.57 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-01588 Steel Sign Supp (2-1/2 In Rd 80)(Slip) Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 50.00 391.67 450.00 Weighted Average for the Fourth Quarter 4.00 50.00 391.67 450.00 Weighted Average for the Year 9.00 282.91 389.34 396.43 614-03001 Conc Footing (Ty 1) Each MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 18.00 1800.00 3033.33 3000.00 Weighted Average for the Third Quarter 18.00 1800.00 3033.33 3000.00 Weighted Average for the Year 18.00 1800.00 3033.33 3000.00 614-03002 Conc Footing (Ty 2) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 1262.31 3803.53 3606.06 Weighted Average for the First Quarter 2.00 1262.31 3803.53 3606.06 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 6.00 2800.00 3183.33 3250.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 6.00 3616.60 3690.41 3690.41 Weighted Average for the Third Quarter 12.00 3208.30 3310.10 3470.21 Weighted Average for the Year 14.00 2930.30 3433.46 3489.61 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0403-063 614-03003 Conc Footing (Ty US40 RESURFACING 3) MP 252-258.3 03/27/25 Each 4.00 1282.35 4175.17 3863.64 Weighted Average for the First Quarter 4.00 1282.35 4175.17 3863.64 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 10.00 3718.25 3794.13 3794.13 Weighted Average for the Third Quarter 10.00 3718.25 3794.13 3794.13 Weighted Average for the Year 14.00 3022.28 4028.62 3813.99 614-03004 Conc Footing (Ty 4) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 4122.71 4141.87 4141.87 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 4122.71 4141.87 4141.87 Weighted Average for the Year 2.00 4122.71 4141.87 4141.87 614-03005 Conc Footing (Ty 5) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 5515.85 5628.42 5628.42 Weighted Average for the Third Quarter 2.00 5515.85 5628.42 5628.42 Weighted Average for the Year 2.00 5515.85 5628.42 5628.42 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 614-03006 Conc Footing (Ty 6) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 6.00 5300.62 5325.26 5325.26 Weighted Average for the Second Quarter 6.00 5300.62 5325.26 5325.26 Weighted Average for the Year 6.00 5300.62 5325.26 5325.26 614-03007 Conc Footing (Ty 7) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 15.00 5654.00 5680.27 5680.27 FBR0703-534 I-70 Weighted Average for the Second Quarter 15.00 5654.00 5680.27 5680.27 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 6393.25 6523.73 6523.73 Weighted Average for the Third Quarter 4.00 6393.25 6523.73 6523.73 Weighted Average for the Year 19.00 5809.63 5857.84 5857.84 614-10035 Paint Ground Sign Each MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 3.00 320.01 985.00 315.00 Weighted Average for the Second Quarter 3.00 320.01 985.00 315.00 Weighted Average for the Year 3.00 320.01 985.00 315.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-10115 Dyn Mesg Sign (Color LED)(O/H) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 151787.60 151786.48 151786.48 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 151787.60 151786.48 151786.48 Weighted Average for the Year 1.00 151787.60 151786.48 151786.48 614-10130 Illuminated Sign Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 5.00 7496.42 7496.42 7496.42 Weighted Average for the Second Quarter 5.00 7496.42 7496.42 7496.42 Weighted Average for the Year 5.00 7496.42 7496.42 7496.42 614-10142 Public Info Display Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 20000.00 25171.77 32605.60 Weighted Average for the First Quarter 4.00 20000.00 25171.77 32605.60 Weighted Average for the Year 4.00 20000.00 25171.77 32605.60 614-10160 Sig Head B-Plates Each C0821-113 CO-82 & Catherine Store Signa 04/17/25 8.00 300.00 347.00 347.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 8.00 300.00 347.00 347.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 8.00 221.10 254.10 320.00 Weighted Average for the Third Quarter 8.00 221.10 254.10 320.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 20.00 245.00 260.30 305.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 460.00 224.13 278.74 259.70 Weighted Average for the Fourth Quarter 480.00 225.00 278.42 261.59 Weighted Average for the Year 496.00 226.15 278.25 263.91 614-31800 Monotube Overhead Sign Cant (18 In Dia) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 57357.58 55782.96 55782.96 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 57357.58 55782.96 55782.96 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 53651.94 54746.88 54746.88 Weighted Average for the Third Quarter 2.00 53651.94 54746.88 54746.88 Weighted Average for the Year 3.00 54887.15 55092.24 55092.24 614-32400 Monotube Overhead Sign Cant (24 In Dia) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 68407.58 66832.96 66832.96 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 58743.33 58743.33 58743.33 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 2.00 63575.46 62788.15 62788.15 Weighted Average for the Year 2.00 63575.46 62788.15 62788.15 614-33000 Monotube Overhead Sign Cant (30 In Dia) Each NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 124871.14 127419.53 127419.53 Weighted Average for the Third Quarter 1.00 124871.14 127419.53 127419.53 Weighted Average for the Year 1.00 124871.14 127419.53 127419.53 614-70024 1310nm SFP Optic Module Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 522.15 482.27 593.60 Weighted Average for the First Quarter 4.00 522.15 482.27 593.60 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 9.00 5.00 477.85 722.22 477.85 722.22 477.85 722.22 ITSSW03-250 FRONT RANGE 06/26/25 95.00 615.78 722.73 290.00 Weighted Average for the Second Quarter 109.00 609.28 718.21 325.34 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 723.78 723.78 723.78 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 723.78 723.78 723.78 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 723.78 723.78 723.78 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 2.00 589.83 760.00 680.00 Weighted Average for the Third Quarter 14.00 704.64 738.27 717.53 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-70024 1310nm SFP Optic Module Each ITSSW03-417 STATEWIDE 12/04/25 10.00 550.02 692.37 612.00 Weighted Average for the Fourth Quarter 10.00 550.02 692.37 612.00 Weighted Average for the Year 137.00 612.15 707.23 394.17 614-70026 CWDM Multiplexor Demultiplexor Module Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 9182.27 11135.11 9793.94 Weighted Average for the First Quarter 2.00 9182.27 11135.11 9793.94 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 9158.13 9345.03 9345.03 Weighted Average for the Third Quarter 1.00 9158.13 9345.03 9345.03 Weighted Average for the Year 3.00 9174.22 10936.21 9644.30 614-70028 CWDM SFP Optic Module Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 990.21 1249.60 1494.60 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 4.00 993.85 1392.36 1224.24 Weighted Average for the First Quarter 8.00 992.03 1306.70 1359.42 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 19.00 1293.01 1292.99 1292.99 FBR0703-534 I-70 Weighted Average for the Second Quarter 19.00 1293.01 1292.99 1292.99 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-70028 CWDM SFP Optic Module Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 1547.00 1547.00 1547.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 1334.29 1361.52 1361.52 Weighted Average for the Third Quarter 7.00 1425.45 1441.01 1441.01 ITSSW03-417 STATEWIDE 12/04/25 5.00 1060.55 657.10 118.00 Weighted Average for the Fourth Quarter 5.00 1060.55 657.10 118.00 Weighted Average for the Year 39.00 1225.24 1163.53 1182.54 614-70030 Optical Attenuator Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 5.00 212.16 212.16 212.16 ITSSW03-250 FRONT RANGE 06/26/25 95.00 187.05 55.40 120.00 Weighted Average for the Second Quarter 100.00 188.31 57.03 124.61 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 15.00 491.73 491.73 491.73 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 247.17 252.22 252.22 Weighted Average for the Third Quarter 19.00 440.24 441.31 441.31 ITSSW03-417 STATEWIDE 12/04/25 15.00 223.37 133.26 31.00 Weighted Average for the Fourth Quarter 15.00 223.37 133.26 31.00 Weighted Average for the Year 134.00 227.95 78.28 159.03 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 614-70032 Optical Filter Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 685.82 605.52 832.10 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 4.00 740.88 1622.88 1428.28 Weighted Average for the First Quarter 8.00 713.35 1012.46 1130.19 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 28.00 1545.98 1545.97 1545.97 FBR0703-534 I-70 Weighted Average for the Second Quarter 28.00 1545.98 1545.97 1545.97 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10.00 1663.03 1663.03 1663.03 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 1231.57 1256.70 1256.70 Weighted Average for the Third Quarter 14.00 1539.76 1546.94 1546.94 Weighted Average for the Year 50.00 1411.02 1285.89 1479.72 614-70112 Traf Sig Face (12) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 600.00 658.05 606.21 Weighted Average for the Fourth Quarter 2.00 600.00 658.05 606.21 Weighted Average for the Year 2.00 600.00 658.05 606.21 614-70150 Ped Sig Face (16) (Countdown) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 41.00 700.00 1060.50 1000.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 14.00 900.00 837.26 1100.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-70150 Ped Sig Face (16) (Countdown) Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 10.00 700.00 683.51 680.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 4.00 1015.02 1131.75 994.70 Weighted Average for the First Quarter 69.00 758.84 932.47 973.61 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 20.00 970.26 960.00 720.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 2.00 4.00 983.81 850.00 983.80 675.00 983.80 675.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 7.00 899.39 899.39 899.39 Weighted Average for the Second Quarter 33.00 941.47 931.38 768.59 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 9.00 1044.23 1044.23 1044.23 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 4.00 691.77 852.75 775.00 Weighted Average for the Third Quarter 13.00 935.78 921.68 961.39 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 32.00 1040.00 727.99 742.94 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 16.00 650.00 690.80 676.00 Weighted Average for the Fourth Quarter 48.00 910.00 720.55 720.63 Weighted Average for the Year 163.00 854.44 861.00 856.63 614-70200 Access Ped Sig Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 58.00 1500.00 2051.32 2225.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 4.00 2308.88 2809.32 3570.00 Weighted Average for the First Quarter 62.00 1552.19 2100.22 2311.77 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-70200 Access Ped Sig Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8.00 2873.00 2873.00 2873.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 2376.82 8628.00 8050.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 43.00 3000.00 2315.25 2374.00 Weighted Average for the Third Quarter 52.00 2968.48 2476.73 2559.92 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 2000.00 1250.67 1750.00 Weighted Average for the Fourth Quarter 4.00 2000.00 1250.67 1750.00 Weighted Average for the Year 118.00 2191.49 2224.31 2402.08 614-70336 Traf Sig Face (12-12-12) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 96.00 850.00 1512.68 1420.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 949.73 1495.23 1526.40 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 15.00 1300.00 1153.57 1600.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 18.00 900.00 1202.81 1259.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 12.00 1015.64 1798.45 1581.31 Weighted Average for the First Quarter 143.00 918.79 1440.59 1433.64 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 39.00 850.00 1353.00 906.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 8.00 1770.86 1770.84 1770.84 FBR0703-534 I-70 C0821-113 CO-82 & Catherine Store Signa 04/17/25 14.00 1200.00 757.00 757.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 22.00 1265.02 1265.02 1265.02 Weighted Average for the Second Quarter 83.00 1107.80 1296.14 1059.39 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 22.00 1723.80 1723.80 1723.80 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 1867.45 1867.45 1867.45 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-70336 Traf Sig Face (12-12-12) Each SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 15.00 1300.00 1435.50 1315.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 16.00 883.00 1039.90 1450.00 Weighted Average for the Third Quarter 56.00 1377.75 1289.99 1543.77 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 43.00 1300.00 1064.11 976.45 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 20.00 820.00 844.75 742.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 5.00 980.31 1712.80 1720.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 58.00 825.19 1167.70 1051.51 Weighted Average for the Fourth Quarter 126.00 992.56 1135.24 1003.29 Weighted Average for the Year 408.00 1043.02 1285.92 1239.72 614-70448 Traf Sig Face (12-12-12-12) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 26.00 1200.00 1797.30 1600.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 4.00 1100.00 1423.16 1509.00 Weighted Average for the First Quarter 30.00 1186.67 1709.27 1587.87 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 9.00 1200.00 1593.00 1086.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 2.00 2.00 2501.69 1200.00 2501.66 976.00 2501.66 976.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 4.00 1640.80 1640.80 1640.80 Weighted Average for the Second Quarter 17.00 1456.86 1622.79 1370.15 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 1500.00 1328.70 1283.81 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 16.00 1200.00 1019.95 885.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 27.00 1069.98 1546.51 1400.53 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 44.00 1127.03 1442.87 1210.41 NHPP070A-042 614-70560 Weighted Average for the Year Traf Sig Face (12-12-12-12-12) I70B EAST OF 3RD STREET 10/16/25 91.00 Each 1.00 1208.31 2500.00 1549.40 1206.57 1364.69 1171.28 Weighted Average for the Fourth Quarter 1.00 2500.00 1206.57 1171.28 Weighted Average for the Year 1.00 2500.00 1206.57 1171.28 614-72740 Blank Out Sign(LED)(Sing Fac) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 4674.15 4674.15 4674.15 Weighted Average for the Third Quarter 1.00 4674.15 4674.15 4674.15 Weighted Average for the Year 1.00 4674.15 4674.15 4674.15 614-72830 Communications Cabinet Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 12878.46 25232.33 21094.00 Weighted Average for the First Quarter 3.00 12878.46 25232.33 21094.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 6.00 27827.73 27827.52 27827.52 FBR0703-534 I-70 ITSSW03-250 FRONT RANGE 06/26/25 1.00 13358.76 23360.40 28000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 7.00 25760.73 25797.01 27852.16 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 38315.88 38315.88 38315.88 Weighted Average for the Third Quarter 3.00 38315.88 38315.88 38315.88 Weighted Average for the Year 13.00 25685.24 26653.02 28707.29 614-72831 Comm Cabinet (Type 1) Each ITSSW03-250 FRONT RANGE 06/26/25 27.00 7000.00 17109.80 24000.00 Weighted Average for the Second Quarter 27.00 7000.00 17109.80 24000.00 Weighted Average for the Year 27.00 7000.00 17109.80 24000.00 614-72832 Comm Cabinet (Type 2) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 25860.11 25859.92 25859.92 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 25860.11 25859.92 25859.92 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 26989.63 26989.63 26989.63 Weighted Average for the Third Quarter 1.00 26989.63 26989.63 26989.63 ITSSW03-417 STATEWIDE 12/04/25 64.00 15000.00 16441.88 14039.00 Weighted Average for the Fourth Quarter 64.00 15000.00 16441.88 14039.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 67.00 15503.13 16555.33 14585.16 614-72836 Conflict Monitor Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 1000.00 1694.08 1850.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 1395.62 1744.01 1530.30 Weighted Average for the First Quarter 6.00 1065.94 1704.59 1796.72 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 1908.24 1908.24 1908.24 Weighted Average for the Second Quarter 2.00 1908.24 1908.24 1908.24 Weighted Average for the Year 8.00 1276.51 1723.99 1824.60 614-72854 Traf Ctrl Cabinet Each C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 2.00 26000.00 35288.50 35352.00 Weighted Average for the Fourth Quarter 2.00 26000.00 35288.50 35352.00 Weighted Average for the Year 2.00 26000.00 35288.50 35352.00 614-72855 Traf Sig Ctrl Cabinet Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 25000.00 33281.34 33600.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2.00 62000.00 46042.63 50500.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 30000.00 46266.29 52079.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 31408.94 30700.99 27035.35 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 10.00 34040.89 39283.12 40019.34 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 40000.00 45375.00 44750.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 1.00 1.00 38227.98 35000.00 38227.71 45550.00 38227.71 45550.00 Weighted Average for the Second Quarter 4.00 38307.00 44212.95 43319.43 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 46852.00 46852.00 46852.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 35000.00 36812.00 31695.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 4.00 19840.55 28865.75 29000.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 49100.00 28298.70 29500.00 Weighted Average for the Third Quarter 8.00 32145.77 31270.28 33862.38 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6.00 36000.00 53747.27 56054.06 Weighted Average for the Fourth Quarter 6.00 36000.00 53747.27 56054.06 Weighted Average for the Year 28.00 34528.68 40989.20 42167.66 614-72858 Ped Pole (3.5 In) Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 4.00 1015.10 1926.50 1053.00 Weighted Average for the Second Quarter 4.00 1015.10 1926.50 1053.00 Weighted Average for the Year 4.00 1015.10 1926.50 1053.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 614-72860 Ped Push Button Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 14.00 800.00 740.95 950.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 11.00 850.00 1726.17 1842.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 44.00 1000.00 1022.75 525.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 4.00 248.11 1913.33 1683.33 Weighted Average for the First Quarter 73.00 897.84 1185.55 868.43 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 3.00 257.61 683.00 466.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 CO-82 & Catherine Store Signa 04/17/25 2.00 4.00 730.83 1200.00 730.82 547.00 730.82 547.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 7.00 1840.53 1840.53 1840.53 Weighted Average for the Second Quarter 16.00 1244.89 1085.86 1120.71 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 19.00 835.00 1924.79 1789.15 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 1000.00 1292.93 1800.00 Weighted Average for the Fourth Quarter 23.00 863.70 1838.63 1791.04 Weighted Average for the Year 112.00 940.41 1322.10 1093.93 614-72863 Ped Push Button Post Assem Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 32.00 2000.00 1748.81 1820.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 4.00 2000.00 2161.38 3200.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 4.00 2000.00 1688.12 1440.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 44.00 3500.00 2447.01 2850.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 4.00 3000.00 4926.98 3570.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 1776.02 2202.79 1938.38 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 89.00 2784.00 2262.18 2454.14 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 1161.20 1161.20 1161.20 Weighted Average for the Second Quarter 1.00 1161.20 1161.20 1161.20 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 1668.55 1668.55 1668.55 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 43.00 2500.00 3058.25 3300.00 Weighted Average for the Third Quarter 44.00 2481.10 3050.22 3262.92 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 13.00 1800.00 3746.99 3662.95 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 3000.00 1469.33 2250.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 9.00 2000.00 3059.17 2600.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 8.00 4000.00 1330.00 1350.00 Weighted Average for the Fourth Quarter 34.00 2511.76 2806.60 2671.13 Weighted Average for the Year 168.00 2639.92 2586.35 2702.18 614-72864 Fire Preempt Unit Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 4773.60 4773.60 4773.60 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 8290.35 7436.00 7700.00 Weighted Average for the Third Quarter 6.00 5945.85 6675.31 5749.07 Weighted Average for the Year 6.00 5945.85 6675.31 5749.07 614-72866 Fire Preempt Unit + Timer Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 3200.00 6027.91 5902.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 1.00 3200.00 6027.91 5902.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 4.00 4350.26 4350.26 4350.26 Weighted Average for the Second Quarter 4.00 4350.26 4350.26 4350.26 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 4800.00 10516.75 9850.00 Weighted Average for the Third Quarter 1.00 4800.00 10516.75 9850.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 4.00 4850.00 4684.65 4408.00 Weighted Average for the Fourth Quarter 4.00 4850.00 4684.65 4408.00 Weighted Average for the Year 10.00 4480.10 6050.58 5078.50 614-72870 Coordination Unit Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 5000.00 5075.00 1150.00 Weighted Average for the Second Quarter 2.00 5000.00 5075.00 1150.00 Weighted Average for the Year 2.00 5000.00 5075.00 1150.00 614-72875 Loop Detect Wire Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,200.00 3.25 24.30 21.42 Weighted Average for the First Quarter 1,200.00 3.25 24.30 21.42 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 1,456.00 13.00 42.00 42.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 1,456.00 13.00 42.00 42.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 736.00 25.00 46.45 38.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,500.00 4.33 28.10 29.00 Weighted Average for the Fourth Quarter 2,236.00 11.14 32.62 31.96 Weighted Average for the Year 4,892.00 9.76 30.47 32.36 614-72884 Detect (Micro Wave) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 21.00 8000.00 12434.18 12975.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 8805.06 12064.93 11299.60 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 4.00 8805.06 14615.38 12854.55 Weighted Average for the First Quarter 27.00 8178.90 12768.99 12833.05 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 7.00 11299.74 12932.26 11299.66 12932.26 11299.66 12932.26 Weighted Average for the Second Quarter 10.00 12442.50 12442.48 12442.48 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 5.00 9257.77 13664.50 12500.00 Weighted Average for the Third Quarter 5.00 9257.77 13664.50 12500.00 Weighted Average for the Year 42.00 9322.48 12890.03 12700.41 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-72885 Detect (Spec) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 14110.38 13339.15 11732.32 Weighted Average for the First Quarter 1.00 14110.38 13339.15 11732.32 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 8.00 10300.00 10041.55 8686.00 Weighted Average for the Fourth Quarter 8.00 10300.00 10041.55 8686.00 Weighted Average for the Year 9.00 10723.38 10701.07 9024.48 614-72886 Intersection Detect Sys (Camera) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 18.00 12000.00 13005.25 12975.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2.00 25000.00 33580.79 25000.00 Weighted Average for the First Quarter 20.00 13300.00 15062.80 14177.50 C0821-113 CO-82 & Catherine Store Signa 04/17/25 4.00 12000.00 10610.00 10610.00 Weighted Average for the Second Quarter 4.00 12000.00 10610.00 10610.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 25000.00 28752.00 25995.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 4.00 12500.00 12422.30 12500.00 Weighted Average for the Third Quarter 5.00 15000.00 15143.92 15199.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6.00 25000.00 24636.47 26095.87 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 3.00 20000.00 15720.00 15800.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 4.00 20000.00 16900.00 15500.00 Weighted Average for the Fourth Quarter 13.00 22307.69 21599.87 20459.63 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 42.00 16166.67 16908.39 15903.81 614-72887 Detect (Microwave Veh) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 26.00 15000.00 12829.01 13360.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 20000.00 19109.93 17659.60 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 20154.54 15369.12 13517.68 Weighted Average for the First Quarter 28.00 15362.66 13372.72 13519.19 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 7.00 4.00 13604.67 11950.51 13604.56 11950.51 13604.56 11950.51 Weighted Average for the Second Quarter 11.00 13003.16 13003.09 13003.09 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 9.00 13518.67 10697.00 9700.00 Weighted Average for the Third Quarter 9.00 13518.67 10697.00 9700.00 Weighted Average for the Year 48.00 14476.19 12629.07 12684.82 614-72894 Emergency Telephone Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 4387.84 10768.13 5278.80 Weighted Average for the First Quarter 3.00 4387.84 10768.13 5278.80 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 5552.63 5552.63 5552.63 Weighted Average for the Third Quarter 3.00 5552.63 5552.63 5552.63 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 6.00 4970.24 10023.06 5415.72 614-72895 Vehicle Detect Sys (Single Camera) Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 4.00 10000.00 9363.67 12152.00 Weighted Average for the First Quarter 4.00 10000.00 9363.67 12152.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 3.00 8688.86 6433.50 5067.00 Weighted Average for the Second Quarter 3.00 8688.86 6433.50 5067.00 Weighted Average for the Year 7.00 9438.08 8777.63 9115.57 614-73005 Piezo (Elec)(CL II) Each STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 12166.55 4962.72 5000.00 Weighted Average for the Fourth Quarter 4.00 12166.55 4962.72 5000.00 Weighted Average for the Year 4.00 12166.55 4962.72 5000.00 614-75855 Inst Traf Sig Ctrler Cab Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 7040.52 7040.52 7040.52 Weighted Average for the Second Quarter 2.00 7040.52 7040.52 7040.52 Weighted Average for the Year 2.00 7040.52 7040.52 7040.52 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-80000 Flash Beacon Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 7034.80 7902.00 6004.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 4850.00 15959.33 15678.00 Weighted Average for the Second Quarter 3.00 6306.53 11355.14 9228.67 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 14.00 3247.89 5584.00 6400.00 Weighted Average for the Third Quarter 14.00 3247.89 5584.00 6400.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 4.00 4019.13 6014.67 3800.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 16.00 4000.00 527.73 786.50 Weighted Average for the Fourth Quarter 20.00 4003.83 1625.12 1389.20 Weighted Average for the Year 37.00 3904.50 3981.28 3920.81 614-80001 Flash Beacon (Solar Pwred) Each STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 1.00 5159.84 5271.33 5050.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 160.00 16059.33 15678.00 Weighted Average for the Second Quarter 2.00 2659.92 10665.33 10364.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 9143.88 9143.88 9143.88 Weighted Average for the Third Quarter 4.00 9143.88 9143.88 9143.88 Weighted Average for the Year 6.00 6982.56 10056.75 9550.59 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0403-063 614-80003 Rect Rapid Flash US40 RESURFACING Beacon MP 252-258.3 03/27/25 Each 4.00 8686.07 12179.06 10712.12 Weighted Average for the First Quarter 4.00 8686.07 12179.06 10712.12 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 12.00 12000.00 11803.33 7000.00 Weighted Average for the Fourth Quarter 12.00 12000.00 11803.33 7000.00 Weighted Average for the Year 16.00 11171.52 11871.65 7928.03 614-80321 Barricade (Ty 3 M-A) Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 37.00 150.00 95.00 95.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 2.00 500.00 541.25 530.00 Weighted Average for the Second Quarter 39.00 167.95 174.33 117.31 NHPP1602-194 US 160 MP 174.1 12/11/25 4.00 500.00 818.01 182.00 Weighted Average for the Fourth Quarter 4.00 500.00 818.01 182.00 Weighted Average for the Year 43.00 198.84 343.17 123.33 614-80385 Rumble Strip Lin Foot NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 32,086.00 0.43 0.53 0.41 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 76,153.00 3.12 0.27 0.19 Weighted Average for the First Quarter 108,239.00 2.32 0.33 0.26 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-80385 Rumble Strip Lin Foot STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 6,472.00 1.00 2.13 0.50 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 25,084.00 1.00 1.28 0.35 Weighted Average for the Second Quarter 31,556.00 1.00 1.46 0.38 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 66,231.00 0.11 0.11 0.11 Weighted Average for the Third Quarter 66,231.00 0.11 0.11 0.11 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 96,972.00 0.09 0.71 0.35 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 7,500.00 0.63 1.76 1.40 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 48.00 1.31 312.50 80.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 88,181.00 0.15 0.35 0.40 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 72,606.00 0.18 0.30 0.27 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 83,624.00 0.75 0.24 0.17 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 172,295.00 0.50 0.23 0.15 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 245,781.00 0.06 0.20 0.18 Weighted Average for the Fourth Quarter 767,007.00 0.27 0.36 0.24 Weighted Average for the Year 973,033.00 0.51 0.39 0.24 614-80386 Rumble Strip (Spec) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 34.00 11.05 113.75 113.75 Weighted Average for the Second Quarter 34.00 11.05 113.75 113.75 Weighted Average for the Year 34.00 11.05 113.75 113.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-80387 Rumble Strip (Grind) Lin Foot NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 150,006.00 0.25 0.20 0.20 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1,265.00 2.00 4.28 5.55 Weighted Average for the Fourth Quarter 151,271.00 0.26 0.28 0.24 Weighted Average for the Year 151,271.00 0.26 0.28 0.24 614-80390 Rumble Strip (Grinding)(Asphalt)(Sin) Lin Foot MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 245,604.00 0.50 1.03 0.70 Weighted Average for the First Quarter 245,604.00 0.50 1.03 0.70 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 155,760.00 0.64 0.81 1.30 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 27,050.00 0.62 0.88 0.75 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 101,941.00 0.42 0.75 0.39 Weighted Average for the Fourth Quarter 284,751.00 0.56 0.79 0.92 Weighted Average for the Year 530,355.00 0.53 0.90 0.82 614-80391 Rumble Strip (Grind)(Asphalt) Lin Foot NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 19,508.00 0.50 0.84 1.00 Weighted Average for the First Quarter 19,508.00 0.50 0.84 1.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 38,567.00 0.35 0.72 0.72 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 38,567.00 0.35 0.72 0.72 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 42,880.00 0.90 0.34 0.42 Weighted Average for the Fourth Quarter 42,880.00 0.90 0.34 0.42 Weighted Average for the Year 100,955.00 0.61 0.55 0.65 614-80392 Rumble Strip (Grind)(Conc) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 150,965.00 1.14 1.20 1.20 Weighted Average for the Third Quarter 150,965.00 1.14 1.20 1.20 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 96.00 1.00 70.30 33.00 Weighted Average for the Fourth Quarter 96.00 1.00 70.30 33.00 Weighted Average for the Year 151,061.00 1.14 1.42 1.22 614-81000 Sig-Light Pole Steel Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 8000.00 20279.26 19677.02 Weighted Average for the Fourth Quarter 2.00 8000.00 20279.26 19677.02 Weighted Average for the Year 2.00 8000.00 20279.26 19677.02 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0062-040 614-81011 Inst Sig-Light Pole VASQUEZ BLVD - I270 Steel (1) TO 64TH - 05/23/25 Each 5.00 1858.59 1858.59 1858.59 Weighted Average for the Second Quarter 5.00 1858.59 1858.59 1858.59 Weighted Average for the Year 5.00 1858.59 1858.59 1858.59 614-81020 Sig-Light Pole Steel (2) Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 65000.00 40381.72 38500.00 Weighted Average for the First Quarter 1.00 65000.00 40381.72 38500.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 1.00 41601.04 41600.74 41600.74 Weighted Average for the Second Quarter 1.00 41601.04 41600.74 41600.74 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 57460.00 57460.00 57460.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 40000.00 62221.50 59860.00 Weighted Average for the Third Quarter 3.00 51640.00 60634.33 58260.00 Weighted Average for the Year 5.00 52304.21 52655.19 50976.15 614-81120 Sig-Light Pole Steel (1-20 Ft) Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 22000.00 19895.63 20336.00 Weighted Average for the First Quarter 2.00 22000.00 19895.63 20336.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2.00 22000.00 19895.63 20336.00 614-81130 Sig-Light Pole Steel (1-30 Ft) Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 28000.00 22329.92 21500.00 Weighted Average for the First Quarter 1.00 28000.00 22329.92 21500.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 25000.00 22321.50 22485.00 Weighted Average for the Third Quarter 1.00 25000.00 22321.50 22485.00 Weighted Average for the Year 2.00 26500.00 22325.11 21992.50 614-81135 Sig-Light Pole Steel (1-35 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 20000.00 23942.55 25000.00 Weighted Average for the First Quarter 2.00 20000.00 23942.55 25000.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 3.00 28217.50 24186.00 25872.00 Weighted Average for the Second Quarter 3.00 28217.50 24186.00 25872.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 32500.00 24153.38 33168.52 Weighted Average for the Fourth Quarter 1.00 32500.00 24153.38 33168.52 Weighted Average for the Year 6.00 26192.08 24086.55 26797.42 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-81140 Sig-Light Pole Steel (1-40 Ft) Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 22000.00 22137.66 21417.00 Weighted Average for the First Quarter 2.00 22000.00 22137.66 21417.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 30000.00 23058.00 22116.00 Weighted Average for the Second Quarter 1.00 30000.00 23058.00 22116.00 Weighted Average for the Year 3.00 24666.67 22269.14 21650.00 614-81145 Sig-Light Pole Steel (1-45 Ft) Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 28000.00 25081.08 24661.00 Weighted Average for the First Quarter 2.00 28000.00 25081.08 24661.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 35000.00 23570.00 22640.00 NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 1.00 26984.46 26984.27 26984.27 Weighted Average for the Second Quarter 3.00 32328.15 24252.85 24088.09 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 9.00 35000.00 31816.25 33275.00 Weighted Average for the Fourth Quarter 9.00 35000.00 31816.25 33275.00 Weighted Average for the Year 14.00 33427.46 29577.78 30075.81 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-81150 Sig-Light Pole Steel (1-50 Ft) Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 35000.00 25420.27 25000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 35000.00 29577.90 26015.15 Weighted Average for the First Quarter 2.00 35000.00 27796.06 25507.58 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 40000.00 24454.50 23409.00 Weighted Average for the Second Quarter 1.00 40000.00 24454.50 23409.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 30000.00 26546.00 26960.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 23000.00 24557.40 24000.00 Weighted Average for the Third Quarter 3.00 25333.33 25125.57 24986.67 Weighted Average for the Year 6.00 31000.00 25879.97 24897.36 614-81155 Sig-Light Pole Steel (1-55 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 25000.00 30854.25 33400.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 45000.00 32367.33 24804.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 40000.00 30170.82 26525.25 Weighted Average for the First Quarter 7.00 30000.00 31108.04 31189.89 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 42000.00 24762.50 23525.00 Weighted Average for the Second Quarter 1.00 42000.00 24762.50 23525.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 25000.00 25231.30 24500.00 Weighted Average for the Third Quarter 2.00 25000.00 25231.30 24500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-81155 Sig-Light Pole Steel (1-55 Ft) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 36000.00 33971.04 34284.14 Weighted Average for the Fourth Quarter 2.00 36000.00 33971.04 34284.14 Weighted Average for the Year 12.00 31166.67 30029.05 29951.88 614-81160 Sig-Light Pole Steel (1-60 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 3.00 40000.00 35571.19 37500.00 Weighted Average for the First Quarter 3.00 40000.00 35571.19 37500.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 24333.57 37275.00 36050.00 Weighted Average for the Second Quarter 1.00 24333.57 37275.00 36050.00 Weighted Average for the Year 4.00 36083.39 35880.97 37137.50 614-81165 Sig-Light Pole Steel (1-65 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 45000.00 41435.84 45500.00 Weighted Average for the First Quarter 1.00 45000.00 41435.84 45500.00 Weighted Average for the Year 1.00 45000.00 41435.84 45500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-81170 Sig-Light Pole Steel (1-70 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 30000.00 44772.57 49000.00 Weighted Average for the First Quarter 2.00 30000.00 44772.57 49000.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 45000.00 39830.00 38660.00 Weighted Average for the Second Quarter 1.00 45000.00 39830.00 38660.00 Weighted Average for the Year 3.00 35000.00 43536.93 45553.33 614-81175 Sig-Light Pole Steel (1-75 Ft) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 35000.00 45258.19 50000.00 Weighted Average for the First Quarter 2.00 35000.00 45258.19 50000.00 Weighted Average for the Year 2.00 35000.00 45258.19 50000.00 614-81250 Sig-Light Pole Steel (2-50 Ft) Each C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 44200.00 61304.70 60357.00 Weighted Average for the Fourth Quarter 1.00 44200.00 61304.70 60357.00 Weighted Average for the Year 1.00 44200.00 61304.70 60357.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-81550 Sig-Light Pole Steel (2-50&60 Ft) Each C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 70000.00 66265.45 68318.00 Weighted Average for the Fourth Quarter 1.00 70000.00 66265.45 68318.00 Weighted Average for the Year 1.00 70000.00 66265.45 68318.00 614-81555 Sig-Light Pole Steel (2-55&65 Ft) Each C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 40000.00 73891.20 69782.00 Weighted Average for the Fourth Quarter 1.00 40000.00 73891.20 69782.00 Weighted Average for the Year 1.00 40000.00 73891.20 69782.00 614-81560 Sig-Light Pole Steel (2-60&65 Ft) Each C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 40000.00 78368.00 70007.00 Weighted Average for the Fourth Quarter 1.00 40000.00 78368.00 70007.00 Weighted Average for the Year 1.00 40000.00 78368.00 70007.00 614-84000 Traf Sig Ped Pole Steel Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 8.00 2000.00 3524.62 4100.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 9.00 4500.00 3372.01 3700.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 6560.62 4980.01 4386.87 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 19.00 3664.28 3652.12 3940.72 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 5.00 1826.59 4143.00 2686.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 1.00 3.00 3260.62 5116.48 3260.60 5116.48 3260.60 5116.48 Weighted Average for the Second Quarter 9.00 3082.56 4288.57 3560.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5.00 2502.83 2502.83 2502.83 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 3.00 5000.00 4100.00 5500.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 3727.88 3803.96 3803.96 Weighted Average for the Third Quarter 9.00 3471.34 3639.90 3646.46 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 7000.00 4086.30 4585.21 Weighted Average for the Fourth Quarter 7.00 7000.00 4086.30 4585.21 Weighted Average for the Year 44.00 4036.51 3827.31 3905.19 614-84100 Traf Sig Ped Pole Alum Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 2000.00 2195.66 2901.00 Weighted Average for the First Quarter 1.00 2000.00 2195.66 2901.00 Weighted Average for the Year 1.00 2000.00 2195.66 2901.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 614-85001 Impact Atten Each FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 62605.06 65105.54 65105.54 Weighted Average for the Third Quarter 2.00 62605.06 65105.54 65105.54 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 25000.00 33265.00 30000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2.00 25000.00 38050.00 38200.00 NHPP1602-194 US 160 MP 174.1 12/11/25 2.00 8500.00 25040.20 2900.00 Weighted Average for the Fourth Quarter 5.00 18400.00 29932.26 22440.00 Weighted Average for the Year 7.00 31030.02 34328.92 34630.15 614-85003 Impact Atten (LM) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 38985.56 37231.48 28388.89 Weighted Average for the First Quarter 1.00 38985.56 37231.48 28388.89 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 38687.71 39350.71 39350.71 Weighted Average for the Third Quarter 2.00 38687.71 39350.71 39350.71 Weighted Average for the Year 3.00 38786.99 37761.29 35696.77 614-85130 Impact Atten (Quadguard II) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 49596.64 63267.25 63267.25 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 2.00 49596.64 63267.25 63267.25 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 3.00 22602.41 32262.18 25000.00 Weighted Average for the Third Quarter 3.00 22602.41 32262.18 25000.00 Weighted Average for the Year 5.00 33400.10 34647.19 40306.90 614-86105 Telemetry (Field) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 8489.76 2670.58 2346.46 Weighted Average for the First Quarter 2.00 8489.76 2670.58 2346.46 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 3.00 2906.24 3948.50 3200.00 Weighted Average for the Third Quarter 3.00 2906.24 3948.50 3200.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 2.00 3200.00 5484.65 5420.00 Weighted Average for the Fourth Quarter 2.00 3200.00 5484.65 5420.00 Weighted Average for the Year 7.00 4585.46 3778.55 3590.42 614-86248 Traf Ctrler (Type 2070LC) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 7000.00 8237.85 7650.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 7853.71 10439.55 9181.82 Weighted Average for the First Quarter 8.00 7320.14 9216.38 8224.43 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 9744.35 9744.35 9744.35 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 2.00 9744.35 9744.35 9744.35 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 4.00 8195.86 8372.00 7100.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 9500.00 8397.00 8000.00 Weighted Average for the Third Quarter 5.00 8456.69 8377.95 7280.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 2.00 1000.00 10121.50 7425.00 Weighted Average for the Fourth Quarter 2.00 1000.00 10121.50 7425.00 Weighted Average for the Year 17.00 7196.07 8976.93 8031.42 614-86741 Weather Monitor System Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 113559.60 113558.77 113558.77 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 113559.60 113558.77 113558.77 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 87626.50 87626.50 87626.50 Weighted Average for the Third Quarter 1.00 87626.50 87626.50 87626.50 Weighted Average for the Year 2.00 100593.05 100592.64 100592.64 614-86748 Ctrler (Ty 2070) Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 6359.66 8024.00 8248.00 Weighted Average for the Second Quarter 2.00 6359.66 8024.00 8248.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2.00 6359.66 8024.00 8248.00 614-86800 Uninterrupted Power Supply Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 20000.00 9064.83 8235.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 11467.00 15976.87 14861.20 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 7076.90 11585.89 10202.02 Weighted Average for the First Quarter 10.00 14855.48 12591.30 10616.26 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 9396.78 9396.78 9396.78 ITSSW03-250 FRONT RANGE 06/26/25 1.00 7259.40 19253.40 21000.00 Weighted Average for the Second Quarter 3.00 8684.32 16437.22 13264.52 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 9119.13 14164.50 18100.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 4.00 10148.66 8157.25 8000.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 12588.48 8880.20 7500.00 Weighted Average for the Third Quarter 6.00 10383.71 9263.00 9600.00 Weighted Average for the Year 19.00 12468.95 11820.26 10713.48 614-87006 Fiber Optic Term Panel (6 Fiber) Each ITSSW03-250 FRONT RANGE 06/26/25 27.00 802.02 669.12 1000.00 Weighted Average for the Second Quarter 27.00 802.02 669.12 1000.00 Weighted Average for the Year 27.00 802.02 669.12 1000.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 614-87010 Fiber Optic Cable (S Mode) (12 Fiber) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 800.00 10.00 11.17 12.95 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2,330.00 5.89 7.85 8.48 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 325.00 8.99 5.81 5.10 Weighted Average for the First Quarter 3,455.00 7.13 8.15 9.20 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 150.00 12.44 17.00 16.00 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 8,765.00 155.00 5.06 25.96 5.06 25.96 5.06 25.96 ITSSW03-250 FRONT RANGE 06/26/25 6,910.00 5.09 6.44 3.80 Weighted Average for the Second Quarter 15,980.00 5.34 6.30 4.82 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,470.00 11.05 11.05 11.05 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 185.00 10.09 10.00 8.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 950.00 8.56 8.73 8.73 Weighted Average for the Third Quarter 2,605.00 10.07 10.11 9.99 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 405.00 15.00 22.87 23.96 ITSSW03-417 STATEWIDE 12/04/25 7,200.00 5.60 3.84 3.00 Weighted Average for the Fourth Quarter 7,605.00 6.10 4.86 4.12 Weighted Average for the Year 29,645.00 6.16 6.31 5.60 614-87011 Fiber Optic Cable (S Mode) (24 Fiber) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3,580.00 11.05 11.05 11.05 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 3,580.00 11.05 11.05 11.05 Weighted Average for the Year 3,580.00 11.05 11.05 11.05 614-87012 Fiber Optic Term Panel (12 Fiber) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 2000.00 1379.23 1625.00 Weighted Average for the First Quarter 4.00 2000.00 1379.23 1625.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 1421.71 561.00 522.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 1173.61 1173.61 1173.61 ITSSW03-250 FRONT RANGE 06/26/25 7.00 1077.04 1402.80 1070.00 Weighted Average for the Second Quarter 11.00 1157.26 1309.49 989.20 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 1768.00 1768.00 1768.00 Weighted Average for the Third Quarter 3.00 1768.00 1768.00 1768.00 ITSSW03-417 STATEWIDE 12/04/25 4.00 1087.42 1639.81 3974.50 Weighted Average for the Fourth Quarter 4.00 1087.42 1639.81 3974.50 Weighted Average for the Year 22.00 1381.07 1413.63 1753.78 614-87015 Buffer Tube Fan Out Kit Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 317.58 406.78 594.66 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 583.79 144.76 127.53 Weighted Average for the First Quarter 4.00 384.14 359.14 477.88 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-87015 Buffer Tube Fan Out Kit Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 346.87 349.00 308.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 8.00 730.83 730.82 730.82 FBR0703-534 I-70 Weighted Average for the Second Quarter 10.00 654.04 603.55 646.26 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 305.09 409.50 400.00 Weighted Average for the Third Quarter 1.00 305.09 409.50 400.00 Weighted Average for the Year 15.00 558.80 441.62 584.94 614-87024 Fiber Optic Term Panel (24 Fiber) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 1843.37 1187.52 1115.12 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 2477.26 811.95 714.14 Weighted Average for the First Quarter 4.00 2001.84 1119.23 1014.88 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 10.00 730.83 730.82 730.82 FBR0703-534 I-70 Weighted Average for the Second Quarter 10.00 730.83 730.82 730.82 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 2431.00 2431.00 2431.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 2621.39 1609.00 1200.00 Weighted Average for the Third Quarter 4.00 2478.60 1961.29 2123.25 Weighted Average for the Year 18.00 1401.67 1170.78 1103.37 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-87096 Fiber Optic Termi Panel (96 Fiber) Each ITSSW03-250 FRONT RANGE 06/26/25 1.00 5615.57 5197.40 3800.00 Weighted Average for the Second Quarter 1.00 5615.57 5197.40 3800.00 Weighted Average for the Year 1.00 5615.57 5197.40 3800.00 614-87100 Auto Traf Rec Sta Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 18758.37 25525.71 22444.44 Weighted Average for the First Quarter 1.00 18758.37 25525.71 22444.44 Weighted Average for the Year 1.00 18758.37 25525.71 22444.44 614-87144 Fiber Optic Termi Panel (144 Fiber) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4.00 10512.70 10512.62 10512.62 FBR0703-534 I-70 Weighted Average for the Second Quarter 4.00 10512.70 10512.62 10512.62 Weighted Average for the Year 4.00 10512.70 10512.62 10512.62 614-87312 Traffic Management Sys Bldg Generator Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 41938.35 52988.04 52988.04 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 1.00 41938.35 52988.04 52988.04 Weighted Average for the Year 1.00 41938.35 52988.04 52988.04 614-87320 CCTV Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 11.00 6617.91 6981.17 4187.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 6000.00 6524.43 5682.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 6781.49 7753.47 6835.35 Weighted Average for the First Quarter 15.00 6557.33 6989.28 4739.45 NHPP0703-517 FBR0703-534 ITSSW03-250 I-70 TOP OF FLOYD HILL TO VET I-70 FRONT RANGE 04/11/25 06/26/25 8.00 29.00 2417.36 5646.57 2417.34 6206.40 2417.34 6000.00 Weighted Average for the Second Quarter 37.00 4948.36 6008.28 5225.37 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 2099.50 2210.00 2210.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 2707.25 2873.00 2873.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 3038.75 3204.50 3204.50 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 7.00 2221.05 2320.50 2320.50 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 5226.65 8066.50 8066.50 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 6482.63 6836.25 7100.00 Weighted Average for the Third Quarter 18.00 2992.50 3922.57 3451.61 ITSSW03-417 STATEWIDE 12/04/25 66.00 6357.73 4793.20 4569.00 Weighted Average for the Fourth Quarter 66.00 6357.73 4793.20 4569.00 Weighted Average for the Year 136.00 5550.92 5473.52 4618.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-87325 CCTV Pole Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 39034.13 39034.13 39034.13 Weighted Average for the Third Quarter 1.00 39034.13 39034.13 39034.13 Weighted Average for the Year 1.00 39034.13 39034.13 39034.13 614-87333 CCTV Camera (Traf Surveil) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 4000.00 8762.39 5900.00 Weighted Average for the First Quarter 1.00 4000.00 8762.39 5900.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 8166.52 6215.00 6030.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 6477.41 6477.41 6477.41 ITSSW03-250 FRONT RANGE 06/26/25 6.00 7674.68 5741.60 6100.00 Weighted Average for the Second Quarter 10.00 7533.59 5835.08 6161.48 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 7581.88 6348.25 5650.00 Weighted Average for the Third Quarter 1.00 7581.88 6348.25 5650.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 2.00 9110.00 9682.10 6933.00 Weighted Average for the Fourth Quarter 2.00 9110.00 9682.10 6933.00 Weighted Average for the Year 14.00 7509.84 6393.01 6216.49 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-87350 Test Fiber Optic Cable Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 15000.00 5901.25 6625.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 20000.00 7802.63 5225.80 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 20000.00 4059.69 3570.71 Weighted Average for the First Quarter 3.00 18333.33 6212.18 5140.50 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 23611.41 23611.23 23611.23 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 11924.55 11924.55 11924.55 ITSSW03-250 FRONT RANGE 06/26/25 1.00 15000.00 15377.80 10000.00 Weighted Average for the Second Quarter 3.00 16845.32 16060.68 15178.59 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 37431.88 74863.75 74863.75 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 20000.00 3248.75 1750.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 9668.52 9865.84 9865.84 Weighted Average for the Third Quarter 3.00 22366.80 16287.43 28826.53 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 7000.00 1890.38 1996.50 ITSSW03-417 STATEWIDE 12/04/25 1.00 11100.00 4960.00 4881.00 Weighted Average for the Fourth Quarter 2.00 9050.00 3425.19 3438.75 Weighted Average for the Year 11.00 17339.67 9362.03 14028.58 614-87364 CCTV Pole w Low Dev (50 Ft) Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 4.00 50933.17 50932.80 50932.80 FBR0703-534 I-70 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 4.00 50933.17 50932.80 50932.80 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 41012.74 35035.25 25500.00 Weighted Average for the Third Quarter 1.00 41012.74 35035.25 25500.00 Weighted Average for the Year 5.00 614-87368 CCTV Pole w Low Dev (70 Ft) Each 48949.08 42984.03 45846.24 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 54531.10 54530.70 54530.70 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 54531.10 54530.70 54530.70 Weighted Average for the Year 1.00 54531.10 54530.70 54530.70 614-87400 Brkaway Taper ITS Pole Steel (30 Ft) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 14243.45 17903.21 17903.21 Weighted Average for the Third Quarter 1.00 14243.45 17903.21 17903.21 Weighted Average for the Year 1.00 14243.45 17903.21 17903.21 614-87402 Brkaway Taper ITS Pole Steel (40 Ft) Each ITSSW03-250 FRONT RANGE 06/26/25 2.00 11224.04 6855.60 8300.00 Weighted Average for the Second Quarter 2.00 11224.04 6855.60 8300.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2.00 11224.04 6855.60 8300.00 614-87424 Fiber Optic Cable (S Mode) (24 S) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 17,635.00 5.62 5.62 5.62 Weighted Average for the Second Quarter 17,635.00 5.62 5.62 5.62 Weighted Average for the Year 17,635.00 5.62 5.62 5.62 614-87440 Non-Break Tapered ITS Steel Pole (40 Ft) Each ITSSW03-417 STATEWIDE 12/04/25 66.00 8500.00 7457.63 7945.00 Weighted Average for the Fourth Quarter 66.00 8500.00 7457.63 7945.00 Weighted Average for the Year 66.00 8500.00 7457.63 7945.00 614-87496 Fiber Optic Cable (S Mode) (96 S) Lin Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,320.00 9.21 8.08 7.14 Weighted Average for the First Quarter 1,320.00 9.21 8.08 7.14 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 5,810.00 5.64 5.64 5.64 ITSSW03-250 FRONT RANGE 06/26/25 80,090.00 2.75 3.47 2.17 Weighted Average for the Second Quarter 85,900.00 2.95 3.50 2.40 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 87,220.00 3.04 3.56 2.48 614-87498 Fiber Optic Cable (S Mode) (144 S) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 42,030.00 6.75 6.75 6.75 FBR0703-534 I-70 Weighted Average for the Second Quarter 42,030.00 6.75 6.75 6.75 Weighted Average for the Year 42,030.00 6.75 6.75 6.75 614-87512 Splice FO Cable (12 S) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 850.00 1204.23 1100.00 Weighted Average for the First Quarter 4.00 850.00 1204.23 1100.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 1627.98 810.00 770.00 Weighted Average for the Second Quarter 2.00 1627.98 810.00 770.00 Weighted Average for the Year 6.00 1109.33 1105.67 990.00 614-87612 Term FO Cable (12 S) Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2.00 1500.15 705.00 660.00 Weighted Average for the Second Quarter 2.00 1500.15 705.00 660.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 2.00 1500.15 705.00 660.00 614-87650 Fiber Optic Cable (S Mode) (216 S) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 37,815.00 7.87 7.87 7.87 FBR0703-534 I-70 Weighted Average for the Second Quarter 37,815.00 7.87 7.87 7.87 Weighted Average for the Year 37,815.00 7.87 7.87 7.87 614-87690 Ethernet Switch Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 6000.00 5521.17 5890.00 Weighted Average for the First Quarter 2.00 6000.00 5521.17 5890.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3.00 7641.08 7641.08 7641.08 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 5464.11 7931.50 7260.00 Weighted Average for the Third Quarter 4.00 7096.84 7807.03 7545.81 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 6000.00 12387.74 16570.95 Weighted Average for the Fourth Quarter 1.00 6000.00 12387.74 16570.95 Weighted Average for the Year 7.00 6626.76 7411.05 8362.03 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 614-87691 Ethernet Switch Type I Each NHPP0703-517 FBR0703-534 ITSSW03-250 I-70 TOP OF I-70 FRONT RANGE FLOYD HILL TO VET 04/11/25 06/26/25 1.00 27.00 10119.17 6092.38 10119.10 6878.60 10119.10 6650.00 Weighted Average for the Second Quarter 28.00 6236.20 6902.43 6773.90 Weighted Average for the Year 28.00 6236.20 6902.43 6773.90 614-87692 Ethernet Switch Type II Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 5.00 7000.00 12277.70 14550.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3.00 10759.34 13726.83 9911.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 10466.98 10331.17 9079.80 Weighted Average for the First Quarter 9.00 8638.33 12772.25 12395.87 NHPP0703-517 FBR0703-534 NHPP0062-040 I-70 TOP OF FLOYD HILL TO VET I-70 VASQUEZ BLVD - I270 TO 64TH - 04/11/25 05/23/25 7.00 2.00 10681.35 9629.24 10681.27 9629.24 10681.27 9629.24 ITSSW03-250 FRONT RANGE 06/26/25 6.00 5082.43 7003.60 5050.00 Weighted Average for the Second Quarter 15.00 8301.50 7798.34 8288.49 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 8840.00 8840.00 8840.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 4.00 4826.44 8151.25 9200.00 Weighted Average for the Third Quarter 5.00 5629.15 8191.76 9128.00 ITSSW03-417 STATEWIDE 12/04/25 4.00 10135.52 9335.06 5342.00 Weighted Average for the Fourth Quarter 4.00 10135.52 9335.06 5342.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 33.00 8210.77 9773.67 9178.73 614-87693 Ethernet Switch Type III Each NHPP0703-517 FBR0703-534 ITSSW03-250 I-70 TOP OF I-70 FRONT RANGE FLOYD HILL TO VET 04/11/25 06/26/25 2.00 1.00 13492.23 6846.56 13492.14 7552.80 13492.14 5050.00 Weighted Average for the Second Quarter 3.00 11277.01 9249.75 10678.09 Weighted Average for the Year 3.00 11277.01 9249.75 10678.09 614-87698 Ethernet Agg Switch Type II Each ITSSW03-250 FRONT RANGE 06/26/25 1.00 36140.84 9740.80 10600.00 Weighted Average for the Second Quarter 1.00 36140.84 9740.80 10600.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 7679.75 7679.75 7679.75 Weighted Average for the Third Quarter 2.00 7679.75 7679.75 7679.75 Weighted Average for the Year 3.00 17166.78 9151.93 8653.17 614-87708 Cellular Modem (CDMA) Each ITSSW03-417 STATEWIDE 12/04/25 60.00 2484.00 2057.00 1501.00 Weighted Average for the Fourth Quarter 60.00 2484.00 2057.00 1501.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 60.00 2484.00 2057.00 1501.00 615-00030 Emb Prot Ty 3 Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 3805.43 7332.12 7332.12 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 3805.43 7332.12 7332.12 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 39.00 2431.78 1955.26 1955.26 Weighted Average for the Third Quarter 39.00 2431.78 1955.26 1955.26 Weighted Average for the Year 41.00 2498.79 2217.55 2217.55 615-00050 Emb Prot Ty 5 Each NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 8.00 2500.00 2034.00 2000.00 Weighted Average for the First Quarter 8.00 2500.00 2034.00 2000.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 3805.43 8031.31 8031.31 FBR0703-534 I-70 Weighted Average for the Second Quarter 2.00 3805.43 8031.31 8031.31 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 9386.80 9386.80 9386.80 Weighted Average for the Third Quarter 1.00 9386.80 9386.80 9386.80 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 4.00 2936.36 3825.00 3650.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0705-083 615-00050 Emb Prot Ty 5 I-70: SEIBERT EAST PART 2 12/04/25 Each 4.00 4000.00 8117.76 14704.00 Weighted Average for the Fourth Quarter 8.00 3468.18 6891.26 9177.00 Weighted Average for the Year 19.00 3407.53 5339.33 6045.55 615-21804 18 In Sl Hdgate (4 Ft) Each FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 4972.50 10116.62 10116.62 Weighted Average for the Third Quarter 1.00 4972.50 10116.62 10116.62 Weighted Average for the Year 1.00 4972.50 10116.62 10116.62 616-29180 18 In Culvert Siphon Pipe Lin Foot ER060A-028 CO 60 (MP 9-10) 06/18/25 40.00 85.00 211.50 183.00 Weighted Average for the Second Quarter 40.00 85.00 211.50 183.00 Weighted Average for the Year 40.00 85.00 211.50 183.00 618-00000 Prestress Steel Bar Pound 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 15,165.00 4.00 23.30 36.63 Weighted Average for the First Quarter 15,165.00 4.00 23.30 36.63 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 15,165.00 4.00 23.30 36.63 618-00002 Prestress Steel Strand M Kip Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 87,308.00 64.00 78.83 78.83 FBR0703-534 I-70 Weighted Average for the Second Quarter 87,308.00 64.00 78.83 78.83 Weighted Average for the Year 87,308.00 64.00 78.83 78.83 618-00005 Prestress Steel Bar M Kip Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 158.00 612.20 816.05 816.05 FBR0703-534 I-70 Weighted Average for the Second Quarter 158.00 612.20 816.05 816.05 Weighted Average for the Year 158.00 612.20 816.05 816.05 618-00500 Prestress Conc I (BT Variable) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 3,534.00 923.20 980.67 980.67 Weighted Average for the Second Quarter 3,534.00 923.20 980.67 980.67 Weighted Average for the Year 3,534.00 923.20 980.67 980.67 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 618-00510 Prestress Conc I (Spec) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 12,331.00 601.21 634.77 634.77 FBR0703-534 I-70 Weighted Average for the Second Quarter 12,331.00 601.21 634.77 634.77 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 848.00 582.09 583.15 583.15 Weighted Average for the Third Quarter 848.00 582.09 583.15 583.15 Weighted Average for the Year 13,179.00 599.98 631.45 631.45 618-01145 Prestress Conc I (CBT45) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,907.00 570.20 542.00 542.00 FBR0703-534 I-70 Weighted Average for the Second Quarter 1,907.00 570.20 542.00 542.00 Weighted Average for the Year 1,907.00 570.20 542.00 542.00 618-01172 Prestress Conc I (CBT72) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 991.00 647.61 658.22 658.22 FBR0703-534 I-70 Weighted Average for the Second Quarter 991.00 647.61 658.22 658.22 Weighted Average for the Year 991.00 647.61 658.22 658.22 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 618-01181 Prestress Conc I (CBT81) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 11,181.00 516.60 507.36 507.36 Weighted Average for the Second Quarter 11,181.00 516.60 507.36 507.36 Weighted Average for the Year 11,181.00 516.60 507.36 507.36 618-01190 Prestress Conc I (CBT90) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 29,225.00 540.60 556.05 556.05 FBR0703-534 I-70 Weighted Average for the Second Quarter 29,225.00 540.60 556.05 556.05 Weighted Average for the Year 29,225.00 540.60 556.05 556.05 618-01992 Prestress Conc Box (Depth Less Than 32") Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4,047.00 85.00 92.93 106.57 Weighted Average for the First Quarter 4,047.00 85.00 92.93 106.57 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 3,576.00 86.91 86.91 86.91 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 5,271.00 93.02 91.36 91.36 Weighted Average for the Third Quarter 8,847.00 90.55 89.56 89.56 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 10,993.00 95.21 87.45 85.25 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 10,993.00 95.21 87.45 85.25 Weighted Average for the Year 23,887.00 91.76 88.51 90.46 618-01994 Prestress Conc Box (Depth 32" Thru 48") Sq Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 5,974.00 94.74 88.93 88.93 Weighted Average for the Third Quarter 5,974.00 94.74 88.93 88.93 Weighted Average for the Year 5,974.00 94.74 88.93 88.93 618-06036 Prestress Conc Slab (Depth Gr Than 13") Sq Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 5,330.00 91.95 86.88 86.88 Weighted Average for the Third Quarter 5,330.00 91.95 86.88 86.88 Weighted Average for the Year 5,330.00 91.95 86.88 86.88 619-00000 Water Meter and Vault Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 12500.00 7158.57 1084.26 Weighted Average for the Fourth Quarter 1.00 12500.00 7158.57 1084.26 Weighted Average for the Year 1.00 12500.00 7158.57 1084.26 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 619-00001 Water Meter Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 7000.00 4075.83 8350.00 Weighted Average for the Fourth Quarter 1.00 7000.00 4075.83 8350.00 C0063-067 619-00005 Weighted Average for the Year Water Line US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 Lump Sum 1.00 7000.00 8000.00 4075.83 31866.67 8350.00 30000.00 Weighted Average for the Fourth Quarter 1.00 8000.00 31866.67 30000.00 C0063-067 619-00006 Weighted Average for the Year Connect to New Waterline US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 Each 9.00 8000.00 2500.00 31866.67 2096.67 30000.00 2100.00 Weighted Average for the Fourth Quarter 9.00 2500.00 2096.67 2100.00 Weighted Average for the Year 9.00 2500.00 2096.67 2100.00 619-00007 Connect To Existing Waterline Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 2301.64 2301.64 2301.64 Weighted Average for the Second Quarter 1.00 2301.64 2301.64 2301.64 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 619-00007 Connect To Existing Waterline Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 8.00 2800.00 3258.25 1132.98 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 21.00 3000.00 3371.00 2380.00 Weighted Average for the Fourth Quarter 29.00 2944.83 3348.16 2035.99 Weighted Average for the Year 30.00 2923.39 3341.58 2044.85 619-06060 6 In Duct Iron Pipe Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 10.00 471.83 471.83 471.83 Weighted Average for the Second Quarter 10.00 471.83 471.83 471.83 Weighted Average for the Year 10.00 471.83 471.83 471.83 619-10000 Temp Water Line Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,070.00 15.00 39.86 52.45 Weighted Average for the Fourth Quarter 2,070.00 15.00 39.86 52.45 Weighted Average for the Year 2,070.00 15.00 39.86 52.45 619-10160 16 In Weld Steel Pipe Lin Foot FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 151.80 340.53 279.35 279.35 Weighted Average for the Third Quarter 151.80 340.53 279.35 279.35 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 151.80 340.53 279.35 279.35 619-10180 18 In Weld Steel Pipe Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 35.00 300.00 500.00 480.00 Weighted Average for the Fourth Quarter 35.00 300.00 500.00 480.00 Weighted Average for the Year 35.00 300.00 500.00 480.00 619-10247 24 In Weld Steel Pipe (J) Lin Foot ER060A-028 CO 60 (MP 9-10) 06/18/25 20.00 316.80 5520.00 4540.00 Weighted Average for the Second Quarter 20.00 316.80 5520.00 4540.00 Weighted Average for the Year 20.00 316.80 5520.00 4540.00 619-30800 10 In Galv Pipe Lin Foot BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 4.00 120.00 727.65 592.25 Weighted Average for the First Quarter 4.00 120.00 727.65 592.25 Weighted Average for the Year 4.00 120.00 727.65 592.25 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 619-40060 3/4 In Copper Pipe Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 431.00 100.00 114.33 82.31 Weighted Average for the Fourth Quarter 431.00 100.00 114.33 82.31 Weighted Average for the Year 431.00 100.00 114.33 82.31 619-40080 1 In Copper Pipe Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 38.00 100.00 163.69 255.76 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 205.00 275.00 101.33 218.00 Weighted Average for the Fourth Quarter 243.00 247.63 108.19 223.90 Weighted Average for the Year 243.00 247.63 108.19 223.90 619-40160 2 In Copper Pipe Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 54.00 150.00 184.54 211.17 Weighted Average for the Fourth Quarter 54.00 150.00 184.54 211.17 Weighted Average for the Year 54.00 150.00 184.54 211.17 619-40300 3 In Copper Pipe Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 51.00 200.00 198.60 242.40 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 51.00 200.00 198.60 242.40 Weighted Average for the Year 51.00 200.00 198.60 242.40 619-50160 2 In Plastic Pipe Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 8.00 30.00 72.00 50.00 Weighted Average for the Fourth Quarter 8.00 30.00 72.00 50.00 Weighted Average for the Year 8.00 30.00 72.00 50.00 619-50320 4 In Plastic Pipe Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 853.00 250.00 138.83 121.00 Weighted Average for the Fourth Quarter 853.00 250.00 138.83 121.00 Weighted Average for the Year 853.00 250.00 138.83 121.00 619-50480 6 In Plastic Pipe Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 159.00 90.00 200.36 132.42 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 50.00 250.00 201.33 202.00 Weighted Average for the Fourth Quarter 209.00 128.28 200.67 149.07 Weighted Average for the Year 209.00 128.28 200.67 149.07 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 619-50640 8 In Plastic Pipe Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,737.00 250.00 187.73 165.90 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 495.00 300.00 168.00 142.00 Weighted Average for the Fourth Quarter 2,232.00 261.09 181.82 160.60 Weighted Average for the Year 2,232.00 261.09 181.82 160.60 619-50800 10 In Plastic Pipe Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 29.00 275.00 250.33 210.00 Weighted Average for the Fourth Quarter 29.00 275.00 250.33 210.00 Weighted Average for the Year 29.00 275.00 250.33 210.00 619-50960 12 In Plastic Pipe Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 674.00 300.00 324.60 238.40 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 145.00 280.00 211.50 145.00 Weighted Average for the Fourth Quarter 819.00 296.46 297.01 221.86 Weighted Average for the Year 819.00 296.46 297.01 221.86 619-71516 2 In Air and Vacuum Valve Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3.00 6500.00 2163.33 1300.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 3.00 6500.00 2163.33 1300.00 Weighted Average for the Year 3.00 6500.00 2163.33 1300.00 619-75016 2 In Gate Valve Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 1500.00 1676.33 1200.00 Weighted Average for the Fourth Quarter 1.00 1500.00 1676.33 1200.00 Weighted Average for the Year 1.00 1500.00 1676.33 1200.00 619-75032 4 In Gate Valve Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 5.00 6000.00 2576.17 3300.00 Weighted Average for the Fourth Quarter 5.00 6000.00 2576.17 3300.00 Weighted Average for the Year 5.00 6000.00 2576.17 3300.00 619-75048 6 In Gate Valve Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 4718.35 4718.35 4718.35 Weighted Average for the Second Quarter 1.00 4718.35 4718.35 4718.35 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 9.00 2000.00 3627.18 4643.30 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 3.00 2700.00 3058.50 4000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 12.00 2175.00 3437.62 4482.48 Weighted Average for the Year 13.00 2370.64 3460.91 4500.62 619-75064 8 In Gate Valve Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4.00 3000.00 4055.68 3392.72 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6.00 4000.00 4214.67 5100.00 Weighted Average for the Fourth Quarter 10.00 3600.00 4165.75 4417.09 Weighted Average for the Year 10.00 3600.00 4165.75 4417.09 619-75080 10 In Gate Valve Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 6000.00 5553.83 6800.00 Weighted Average for the Fourth Quarter 1.00 6000.00 5553.83 6800.00 Weighted Average for the Year 1.00 6000.00 5553.83 6800.00 619-75096 12 In Gate Valve Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 3.00 4000.00 7065.22 5595.87 Weighted Average for the Fourth Quarter 3.00 4000.00 7065.22 5595.87 Weighted Average for the Year 3.00 4000.00 7065.22 5595.87 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 619-77206 6-In Restrained Coupling Adapter Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 32.00 200.00 317.46 259.84 Weighted Average for the Fourth Quarter 32.00 200.00 317.46 259.84 Weighted Average for the Year 32.00 200.00 317.46 259.84 619-77208 8-In Restrained Coupling Adapter Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 44.00 250.00 405.05 345.19 Weighted Average for the Fourth Quarter 44.00 250.00 405.05 345.19 Weighted Average for the Year 44.00 250.00 405.05 345.19 619-77212 12-In Restrained Coupling Adapter Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 42.00 300.00 570.21 515.85 Weighted Average for the Fourth Quarter 42.00 300.00 570.21 515.85 Weighted Average for the Year 42.00 300.00 570.21 515.85 619-77300 Corporation Stop Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 19.00 2000.00 853.02 592.09 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 10.00 1800.00 955.00 1000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 29.00 1931.03 898.01 732.75 Weighted Average for the Year 29.00 1931.03 898.01 732.75 619-78048 6 In Fire Hydrant Each NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 9321.62 9321.62 9321.62 Weighted Average for the Second Quarter 1.00 9321.62 9321.62 9321.62 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 15000.00 10247.67 10850.00 Weighted Average for the Fourth Quarter 1.00 15000.00 10247.67 10850.00 Weighted Average for the Year 2.00 12160.81 10115.37 10085.81 619-78049 Inst 6 In Fire Hydrant Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 5.00 15000.00 6436.45 6685.78 Weighted Average for the Fourth Quarter 5.00 15000.00 6436.45 6685.78 Weighted Average for the Year 5.00 15000.00 6436.45 6685.78 620-00001 Field Office (CL 1) Each STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 50000.00 65372.73 22000.00 Weighted Average for the First Quarter 1.00 50000.00 65372.73 22000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 620-00001 Field Office (CL 1) Each NHPPR500-227 REGION 5 SECTION 7 10/23/25 1.00 50000.00 96016.13 69000.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 40000.00 59382.65 29856.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2.00 60000.00 91488.89 90750.00 Weighted Average for the Fourth Quarter 4.00 52500.00 87646.93 70089.00 Weighted Average for the Year 5.00 52000.00 82078.38 60471.20 620-00002 Field Office (CL 2) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 75000.00 101997.01 64552.08 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 50000.00 53318.72 75000.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1.00 35000.00 58046.74 60000.00 BR0761-249 I-76 02/27/25 1.00 11954.12 68854.67 50000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 21666.63 63446.44 19700.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 21739.93 69640.13 38663.67 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 50000.00 41115.00 17230.00 Weighted Average for the First Quarter 7.00 37908.67 70928.31 46449.39 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 50000.00 28765.54 23796.63 Weighted Average for the Second Quarter 1.00 50000.00 28765.54 23796.63 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 1.00 1.00 22366.34 89007.19 106983.78 102973.05 87935.10 102973.05 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 39500.00 28645.50 22000.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 1.00 22257.55 26246.00 9230.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 1.00 1.00 35000.00 22254.95 29826.40 57058.16 12000.00 33000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 6.00 38397.67 50391.53 44523.03 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 30000.00 98583.71 101984.85 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1.00 22389.15 37170.00 50000.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 21512.26 63313.00 70000.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 50000.00 71087.90 95000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 50000.00 61271.67 60000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 50000.00 69592.88 70391.05 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 22378.54 58625.00 65250.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 71500.00 70275.17 74100.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 70000.00 81000.00 70000.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 22366.34 77369.49 51000.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1.00 50000.00 107982.38 104033.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 50000.00 40530.00 21060.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 45000.00 38985.00 60000.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 45000.00 44216.67 17650.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 22401.43 75000.00 75000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 50000.00 53475.00 70000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 45000.00 23805.00 40000.00 NHPP1602-194 US 160 MP 174.1 12/11/25 1.00 70000.00 77801.46 53000.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 22389.15 66709.36 66730.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 70000.00 63292.83 61500.00 Weighted Average for the Fourth Quarter 20.00 43996.84 66800.82 63834.95 NHPP2873-206 620-00005 Weighted Average for the Year Field Office (Spec) US287:RESURFACING I-70 TO 92N 01/09/25 34.00 Each 1.00 41931.87 250000.00 63326.21 97546.61 55669.98 135900.00 Weighted Average for the First Quarter 1.00 250000.00 97546.61 135900.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 620-00005 Field Office (Spec) Each NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 1.00 381600.70 316334.98 316334.98 Weighted Average for the Second Quarter 1.00 381600.70 316334.98 316334.98 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 50000.00 35260.00 10520.00 Weighted Average for the Fourth Quarter 1.00 50000.00 35260.00 10520.00 Weighted Average for the Year 3.00 227200.23 113249.14 154251.66 620-00011 Field Lab (CL 1) Each FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 1.00 35000.00 28288.96 10900.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 1.00 35000.00 28288.96 10900.00 Weighted Average for the Year 1.00 35000.00 28288.96 10900.00 620-00012 Field Lab (CL 2) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 120000.00 59047.65 79000.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 85000.00 64798.51 44991.04 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 50000.00 48600.05 65000.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1.00 35000.00 48012.54 32000.00 BR0761-249 I-76 02/27/25 1.00 10000.00 52118.86 50000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 16766.07 56301.48 20450.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 16429.19 55680.88 31889.17 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 50000.00 32990.00 10980.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 8.00 47899.41 54183.51 41788.78 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 50000.00 39000.00 39000.00 NHPP0703-517 FBR0703-534 STMM153-003 I-70 TOP OF FLOYD HILL TO VET I-70 CO 17 & SOUTH OF CO 14 04/11/25 05/08/25 1.00 1.00 132123.92 50000.00 142141.83 24461.50 142141.83 20884.50 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 1.00 20000.00 34664.33 33993.00 Weighted Average for the Second Quarter 4.00 63030.98 44814.92 59004.83 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 59379.97 67520.27 67520.27 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 16734.33 51489.60 33000.00 Weighted Average for the Third Quarter 2.00 38057.15 53270.78 50260.14 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 25000.00 86075.21 59150.85 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 16276.29 55280.50 70000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 55000.00 69360.00 70000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 50000.00 50605.29 45526.60 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 16822.69 42000.00 41000.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 76500.00 52783.55 45000.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 16814.38 51971.75 35000.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1.00 50000.00 73258.50 56557.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 50000.00 37530.00 20060.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 45000.00 38328.33 65000.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 40000.00 40166.67 15500.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 65000.00 40395.00 20790.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 16860.04 35000.00 35000.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 16860.04 35000.00 35000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 50000.00 53650.00 45000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 45000.00 24295.00 35000.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 16842.03 44736.95 42465.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 70000.00 52128.94 57500.00 Weighted Average for the Fourth Quarter 18.00 40109.75 52912.89 44086.11 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 32.00 44794.03 52693.79 45762.49 620-00015 Field Lab (State Furn) Each STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 4539.84 16250.00 15500.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 70000.00 20250.00 20500.00 Weighted Average for the Fourth Quarter 2.00 37269.92 18250.00 18000.00 Weighted Average for the Year 2.00 37269.92 18250.00 18000.00 620-00020 Sanitary Facility Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 6000.00 10033.53 10500.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 1.00 3407.62 6596.11 15000.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 4076.45 6420.71 2224.25 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 2.00 5000.00 9688.14 7500.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 4000.00 3115.18 1500.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 2.00 2648.74 3624.59 1897.50 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 5000.00 12750.00 10000.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 3000.00 2772.50 1902.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 2.00 3000.00 4399.09 2500.00 BR0761-249 I-76 02/27/25 1.00 2244.46 5502.33 8000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 6000.00 5270.23 4000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 4390.72 4937.71 3950.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 3806.88 11215.70 3825.00 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 1.00 4000.00 1341.67 625.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 4000.00 12380.00 4760.00 Weighted Average for the First Quarter 21.00 4052.71 6629.46 5077.64 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 620-00020 Sanitary Facility Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 8000.00 7500.00 7500.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2.00 26520.00 6630.00 6630.00 FBR0703-534 I-70 C0821-113 CO-82 & Catherine Store Signa 04/17/25 1.00 5000.00 1830.00 1830.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 1.00 1000.00 1875.67 532.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 1.00 4000.00 4414.50 2358.00 STAR500-228 REGION 5 05/08/25 1.00 4000.00 2041.67 1800.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 2.00 3600.00 2561.67 3510.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 2.00 2247.62 3041.33 1824.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 2.00 2424.53 2424.53 2424.53 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 2.00 3601.29 4416.67 650.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 4500.00 12086.62 5600.00 ITSSW03-250 FRONT RANGE 06/26/25 1.00 2507.26 9596.80 5000.00 Weighted Average for the Second Quarter 17.00 6223.18 4960.41 3217.47 CR400-406 REGION-WIDE 07/17/25 2.00 2054.82 2326.67 4500.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 2.00 2285.61 1440.75 1000.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 2.00 3800.00 3000.00 3000.00 BR0704-265 I-70 EAST 07/24/25 2.00 2314.66 11175.75 5203.00 FBR0704-269 I-70 EAST CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1.00 3338.02 4548.25 3978.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 15544.04 10773.63 10773.63 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 1.00 1965.51 3432.08 125.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 2632.71 654.60 900.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 2296.37 691.00 410.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 1.00 3763.97 4568.00 1440.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 2.00 4191.62 4454.40 1800.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 5065.18 10199.63 8000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 4.00 3210.00 6120.40 6120.40 Weighted Average for the Third Quarter 24.00 4050.52 4460.24 3883.24 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 620-00020 Sanitary Facility Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 3000.00 16640.63 24502.50 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1.00 5039.22 5392.50 7000.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.00 4434.03 6488.40 9000.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 2.00 3000.00 6537.50 2325.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 2.00 6000.00 4207.73 10000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 5500.00 8094.17 5000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 4062.10 5401.92 4026.25 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2.00 5497.80 4725.00 6750.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 4000.00 3260.75 2716.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2.00 4729.01 6652.08 7200.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 2.00 10000.00 6350.00 5500.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 5.00 3518.75 6014.00 6500.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 3.00 4500.00 8508.20 11311.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 4000.00 12760.00 5520.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 1.00 2879.41 5972.25 4750.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 5000.00 16691.17 30000.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 8000.00 4275.00 6325.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 5000.00 12105.00 4210.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 5207.41 20000.00 20000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2.00 5000.00 8170.00 10000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 5000.00 9575.00 3800.00 NHPP1602-194 US 160 MP 174.1 12/11/25 1.00 5000.00 6232.88 4500.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2.00 7500.00 18742.30 21780.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2.00 3239.42 5476.60 2125.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 5000.00 7410.00 10000.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 2.00 10000.00 5369.01 5175.00 Weighted Average for the Fourth Quarter 43.00 5131.27 7278.24 8430.67 Weighted Average for the Year 105.00 4845.31 6265.04 5876.61 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 621-00425 Detour Lump Sum FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 408344.15 330152.52 330152.52 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 1.00 100000.00 259333.30 204100.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 2.00 254172.08 271136.50 267126.26 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 50000.00 73741.05 35000.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 25460.00 97214.95 18663.04 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 25460.00 92484.49 7168.04 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 25460.00 13133.81 7168.04 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 25460.00 69410.77 7168.04 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 50000.00 331000.00 250000.00 Weighted Average for the Fourth Quarter 6.00 33640.00 122466.42 54194.53 Weighted Average for the Year 8.00 88773.02 151241.27 107427.46 621-00430 Detour Sq Yard NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 600.00 60.00 125.29 135.16 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,178.00 60.00 112.41 119.62 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 400.00 120.00 106.00 146.00 Weighted Average for the Fourth Quarter 2,178.00 71.02 114.04 128.75 Weighted Average for the Year 2,178.00 71.02 114.04 128.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 621-00450 Detour Pvmt Sq Yard NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 2,256.00 100.00 97.80 100.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 916.00 130.00 167.51 175.00 Weighted Average for the First Quarter 3,172.00 108.66 114.89 121.66 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 25,351.00 104.27 103.23 103.23 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 645.00 87.73 87.73 87.73 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 2,300.00 90.00 124.81 79.50 Weighted Average for the Second Quarter 28,296.00 102.73 108.59 100.95 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 400.00 107.28 107.28 107.28 CR400-406 REGION-WIDE 07/17/25 410.00 694.60 304.17 467.50 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,094.00 95.63 93.36 93.36 Weighted Average for the Third Quarter 1,904.00 227.06 190.59 176.85 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 19,987.00 120.00 134.36 120.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 3,279.00 98.95 232.16 173.00 Weighted Average for the Fourth Quarter 23,266.00 117.03 158.52 127.47 Weighted Average for the Year 56,638.00 113.12 146.01 115.55 621-00451 Detour Pavement Ton NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,000.00 139.02 143.99 143.99 FBR0703-534 I-70 Weighted Average for the Second Quarter 1,000.00 139.02 143.99 143.99 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid NHPP0701-260 621-00451 Detour Pavement I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 Ton 35.00 200.00 511.50 323.00 Weighted Average for the Fourth Quarter 35.00 200.00 511.50 323.00 Weighted Average for the Year 1,035.00 141.08 168.03 150.04 621-00500 Temp Brdg Lump Sum FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 758099.66 854877.88 854877.88 Weighted Average for the Third Quarter 1.00 758099.66 854877.88 854877.88 Weighted Average for the Year 1.00 758099.66 854877.88 854877.88 621-00650 Ped Stair Str Lump Sum 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 65000.00 158428.42 105570.50 Weighted Average for the First Quarter 1.00 65000.00 158428.42 105570.50 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 3867.50 15398.75 15398.75 Weighted Average for the Third Quarter 1.00 3867.50 15398.75 15398.75 Weighted Average for the Year 2.00 34433.75 137995.61 60484.63 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 622-00010 Bicycle Rack Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 6.00 1157.03 1128.28 932.67 Weighted Average for the First Quarter 6.00 1157.03 1128.28 932.67 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 6.00 967.60 967.60 967.60 Weighted Average for the Third Quarter 6.00 967.60 967.60 967.60 Weighted Average for the Year 12.00 1062.32 1105.32 950.14 622-00100 Shade Shelter Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 25000.00 77998.40 43890.42 Weighted Average for the First Quarter 2.00 25000.00 77998.40 43890.42 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2.00 77186.58 89028.08 89028.08 Weighted Average for the Third Quarter 2.00 77186.58 89028.08 89028.08 Weighted Average for the Year 4.00 51093.29 79574.07 66459.25 622-00250 Bench Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 2.00 640.23 3356.45 2418.68 Weighted Average for the First Quarter 2.00 640.23 3356.45 2418.68 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10.00 2083.65 2321.57 2321.57 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 10.00 2083.65 2321.57 2321.57 Weighted Average for the Year 12.00 1843.08 2886.05 2337.76 622-00252 Precast Concrete Bench Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 2500.00 5033.72 7752.33 Weighted Average for the First Quarter 4.00 2500.00 5033.72 7752.33 Weighted Average for the Year 4.00 2500.00 5033.72 7752.33 622-00270 Bollard Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 17.00 1000.00 759.41 730.00 Weighted Average for the First Quarter 17.00 1000.00 759.41 730.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 2.00 2000.00 1152.44 500.00 Weighted Average for the Second Quarter 2.00 2000.00 1152.44 500.00 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 5.00 1822.12 874.32 874.32 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 51.00 1158.40 3660.50 1875.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2.00 2140.00 1505.18 1505.18 Weighted Average for the Third Quarter 58.00 1249.46 3574.05 1775.98 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 4.00 1000.00 711.75 1120.00 Weighted Average for the Fourth Quarter 4.00 1000.00 711.75 1120.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 81.00 1203.32 2770.98 1492.56 622-00350 Trash Receptacle Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 1845.03 2829.83 3075.98 Weighted Average for the First Quarter 4.00 1845.03 2829.83 3075.98 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 4.00 1685.85 2127.85 2127.85 Weighted Average for the Third Quarter 4.00 1685.85 2127.85 2127.85 Weighted Average for the Year 8.00 1765.44 2729.55 2601.92 622-00827 Glazing Panel Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 5,555.00 55.00 144.43 108.56 Weighted Average for the First Quarter 5,555.00 55.00 144.43 108.56 Weighted Average for the Year 5,555.00 55.00 144.43 108.56 622-00836 Metal Roofing Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4,532.00 16.00 35.34 27.06 Weighted Average for the First Quarter 4,532.00 16.00 35.34 27.06 Weighted Average for the Year 4,532.00 16.00 35.34 27.06 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 2670252-499 622-00851 Dog Waste Station I-25:MOBILITY HUB (LONE TREE) 01/16/25 Each 3.00 300.00 1474.23 1345.40 Weighted Average for the First Quarter 3.00 300.00 1474.23 1345.40 Weighted Average for the Year 3.00 300.00 1474.23 1345.40 622-04035 Water Storage Facility Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 45567.01 57509.17 57509.17 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 45567.01 57509.17 57509.17 Weighted Average for the Year 1.00 45567.01 57509.17 57509.17 623-00162 Drip Emit Tubing Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,248.00 3.20 3.92 3.26 Weighted Average for the Fourth Quarter 2,248.00 3.20 3.92 3.26 Weighted Average for the Year 2,248.00 3.20 3.92 3.26 623-00164 Drip Emit Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,183.00 100.53 105.65 105.65 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 623-00164 Drip Emit Each FBR0703-534 I-70 Weighted Average for the Second Quarter 1,183.00 100.53 105.65 105.65 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 18.00 77.00 61.16 78.65 Weighted Average for the Fourth Quarter 18.00 77.00 61.16 78.65 Weighted Average for the Year 1,201.00 100.18 103.10 105.25 623-00206 6 In Pop-Up Spray Spr Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 64.00 70.00 70.83 60.28 Weighted Average for the Fourth Quarter 64.00 70.00 70.83 60.28 Weighted Average for the Year 64.00 70.00 70.83 60.28 623-00600 1-1/2 In Plastic Pipe Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 9,049.00 12.87 13.53 13.53 FBR0703-534 I-70 Weighted Average for the Second Quarter 9,049.00 12.87 13.53 13.53 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,656.00 4.00 6.28 4.18 Weighted Average for the Fourth Quarter 1,656.00 4.00 6.28 4.18 Weighted Average for the Year 10,705.00 11.50 10.47 12.08 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 623-00601 1 In Plastic Pipe Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 24,352.00 5.70 5.99 5.99 FBR0703-534 I-70 Weighted Average for the Second Quarter 24,352.00 5.70 5.99 5.99 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 4,676.00 4.00 6.37 3.94 Weighted Average for the Fourth Quarter 4,676.00 4.00 6.37 3.94 Weighted Average for the Year 29,028.00 5.43 6.16 5.66 623-00602 2 In Plastic Pipe (Irrig/Sleeve) Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,370.00 5.00 15.97 6.36 Weighted Average for the Fourth Quarter 1,370.00 5.00 15.97 6.36 Weighted Average for the Year 1,370.00 5.00 15.97 6.36 623-00603 3 In Plastic Pipe (Irrig/Sleeve) Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 486.00 12.00 18.57 7.81 Weighted Average for the Fourth Quarter 486.00 12.00 18.57 7.81 Weighted Average for the Year 486.00 12.00 18.57 7.81 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 623-01708 1 Inch Backflow Preventer Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 5000.00 3642.94 4446.75 Weighted Average for the Fourth Quarter 1.00 5000.00 3642.94 4446.75 Weighted Average for the Year 1.00 5000.00 3642.94 4446.75 623-01712 1-1/2 In Backflow Preventer Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 6635.69 6973.37 6973.37 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 6635.69 6973.37 6973.37 Weighted Average for the Year 1.00 6635.69 6973.37 6973.37 623-02016 2 In Drain Valve Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 20.00 592.37 622.51 622.51 FBR0703-534 I-70 Weighted Average for the Second Quarter 20.00 592.37 622.51 622.51 Weighted Average for the Year 20.00 592.37 622.51 622.51 623-03004 3/4 In Drip Zone Crtl Valve Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 190.00 888.56 933.77 933.77 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 623-03004 3/4 In Drip Zone Crtl Valve Each FBR0703-534 I-70 Weighted Average for the Second Quarter 190.00 888.56 933.77 933.77 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 12.00 910.00 690.86 924.44 Weighted Average for the Fourth Quarter 12.00 910.00 690.86 924.44 Weighted Average for the Year 202.00 889.83 884.78 933.22 623-03112 1-1/2 In Auto Ctrl Val Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 1264.48 1328.83 1328.83 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 1264.48 1328.83 1328.83 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 6.00 2200.00 951.90 1282.60 Weighted Average for the Fourth Quarter 6.00 2200.00 951.90 1282.60 Weighted Average for the Year 7.00 2066.35 966.98 1289.20 623-04000 Ctrl Wire 24 Volt Lin Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1,644.00 0.50 1.81 1.34 Weighted Average for the Fourth Quarter 1,644.00 0.50 1.81 1.34 Weighted Average for the Year 1,644.00 0.50 1.81 1.34 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 623-04012 1-1/2 In Quick-Coupler Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 11.00 288.21 302.88 302.88 FBR0703-534 I-70 Weighted Average for the Second Quarter 11.00 288.21 302.88 302.88 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 8.00 410.00 366.19 407.77 Weighted Average for the Fourth Quarter 8.00 410.00 366.19 407.77 Weighted Average for the Year 19.00 339.49 350.00 347.04 623-05012 1-1/2 In Gate Valve Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 14.00 404.41 424.98 424.98 FBR0703-534 I-70 Weighted Average for the Second Quarter 14.00 404.41 424.98 424.98 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 11.00 230.00 144.73 108.90 Weighted Average for the Fourth Quarter 11.00 230.00 144.73 108.90 Weighted Average for the Year 25.00 327.67 212.37 285.90 623-06900 Valve Box Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 38.00 200.00 258.66 199.65 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 38.00 200.00 258.66 199.65 Weighted Average for the Year 38.00 200.00 258.66 199.65 623-07008 1 In Water Meter Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 5000.00 5750.18 8750.72 Weighted Average for the Fourth Quarter 1.00 5000.00 5750.18 8750.72 Weighted Average for the Year 1.00 5000.00 5750.18 8750.72 623-07510 Weather Station Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 700.00 1166.38 665.50 Weighted Average for the Fourth Quarter 1.00 700.00 1166.38 665.50 Weighted Average for the Year 1.00 700.00 1166.38 665.50 623-07601 1 In Flow Sensor Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 1100.00 881.30 917.18 Weighted Average for the Fourth Quarter 1.00 1100.00 881.30 917.18 Weighted Average for the Year 1.00 1100.00 881.30 917.18 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 623-08120 20 Station Auto Ctrler Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 10000.00 9645.00 16940.00 Weighted Average for the Fourth Quarter 1.00 10000.00 9645.00 16940.00 Weighted Average for the Year 1.00 10000.00 9645.00 16940.00 623-08200 Master Ctrler Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 5188.95 5453.00 5453.00 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 5188.95 5453.00 5453.00 Weighted Average for the Year 1.00 5188.95 5453.00 5453.00 623-09000 Booster Pump Each NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 59259.90 62275.49 62275.49 FBR0703-534 I-70 Weighted Average for the Second Quarter 1.00 59259.90 62275.49 62275.49 Weighted Average for the Year 1.00 59259.90 62275.49 62275.49 624-20019 18 In Drainage Pipe (CL 0) (CIP) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 410.00 297.69 354.50 354.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 624-20019 18 In Drainage Pipe (CL 0) (CIP) Lin Foot FBR0703-534 I-70 Weighted Average for the Second Quarter 410.00 297.69 354.50 354.50 Weighted Average for the Year 410.00 297.69 354.50 354.50 624-20025 24 In Drainage Pipe (CL 0) (CIP) Lin Foot BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 80.00 80.00 265.00 145.00 Weighted Average for the Fourth Quarter 80.00 80.00 265.00 145.00 Weighted Average for the Year 80.00 80.00 265.00 145.00 624-20300 Detour Drainage Pipe (CL 0) Lin Foot NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 94.00 402.37 307.51 307.51 FBR0703-534 I-70 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 520.00 100.00 152.30 110.00 Weighted Average for the Second Quarter 614.00 146.29 159.01 140.24 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 320.00 250.00 231.15 172.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 320.00 250.00 231.15 172.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,610.00 94.42 79.75 41.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 552.00 97.00 388.05 291.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 2,162.00 95.08 205.16 104.83 Weighted Average for the Year 3,096.00 121.25 201.77 118.79 624-20301 Detour Drainage Pipe (CL 0) Lump Sum C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 1.00 10000.00 11625.01 2500.00 Weighted Average for the Second Quarter 1.00 10000.00 11625.01 2500.00 Weighted Average for the Year 1.00 10000.00 11625.01 2500.00 624-27016 15 In Drainage Pipe (CL 7) (CIP) Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 232.00 255.78 255.78 255.78 Weighted Average for the Second Quarter 232.00 255.78 255.78 255.78 Weighted Average for the Year 232.00 255.78 255.78 255.78 624-27019 18 In Drainage Pipe (CL 7) (CIP) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1,219.00 95.00 134.61 109.18 Weighted Average for the First Quarter 1,219.00 95.00 134.61 109.18 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 236.00 227.01 227.01 227.01 Weighted Average for the Second Quarter 236.00 227.01 227.01 227.01 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 1,455.00 116.41 137.50 128.29 2670252-499 624-27025 24 In Drainage Pipe (CL 7) (CIP) I-25:MOBILITY HUB (LONE TREE) 01/16/25 Lin Foot 90.00 105.00 171.37 127.20 Weighted Average for the First Quarter 90.00 105.00 171.37 127.20 2670252-499 624-27031 Weighted Average for the Year 30 In Drainage Pipe (CL 7) (CIP) I-25:MOBILITY HUB (LONE TREE) 01/16/25 90.00 Lin Foot 263.00 105.00 112.00 171.37 213.53 127.20 180.20 Weighted Average for the First Quarter 263.00 112.00 213.53 180.20 C0063-067 624-29011 Weighted Average for the Year 10 In Drainage Pipe (CL 9) (CIP) US 6 PALISADE IMPROVEMENTS MP 10/30/25 263.00 Lin Foot 142.00 112.00 260.00 213.53 160.58 180.20 135.00 Weighted Average for the Fourth Quarter 142.00 260.00 160.58 135.00 Weighted Average for the Year 142.00 260.00 160.58 135.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 624-29013 12 In Drainage Pipe (CL 9) (CIP) Lin Foot C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 97.00 280.00 173.67 151.00 Weighted Average for the Fourth Quarter 97.00 280.00 173.67 151.00 NHPP0253-302 624-29016 Weighted Average for the Year 15 In Drainage Pipe (CL 9) (CIP) I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 97.00 Lin Foot 74.00 280.00 205.94 173.67 271.52 151.00 271.52 Weighted Average for the Third Quarter 74.00 205.94 271.52 271.52 NHPP0253-302 624-29019 Weighted Average for the Year 18 In Drainage Pipe (CL 9) (CIP) I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 74.00 Lin Foot 2,282.00 205.94 161.10 271.52 149.75 271.52 149.75 Weighted Average for the Third Quarter 2,282.00 161.10 149.75 149.75 NHPP0253-302 624-29025 Weighted Average for the Year 24 In Drainage Pipe (CL 9) (CIP) I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 2,282.00 Lin Foot 1,234.00 161.10 189.24 149.75 200.04 149.75 200.04 Weighted Average for the Third Quarter 1,234.00 189.24 200.04 200.04 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 1,234.00 189.24 200.04 200.04 NHPP0253-302 624-29061 60 In Drainage Pipe (CL 9) (CIP) I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 Lin Foot 521.00 732.38 784.87 784.87 Weighted Average for the Third Quarter 521.00 732.38 784.87 784.87 NHPP0253-302 624-30019 Weighted Average for the Year 18 In Drainage Pipe (CL 10) (CIP) I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 521.00 Lin Foot 224.00 732.38 162.47 784.87 145.02 784.87 145.02 Weighted Average for the Third Quarter 224.00 162.47 145.02 145.02 NHPP0253-302 624-30025 Weighted Average for the Year 24 In Drainage Pipe (CL 10) (CIP) I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 224.00 Lin Foot 511.00 162.47 178.60 145.02 213.17 145.02 213.17 Weighted Average for the Third Quarter 511.00 178.60 213.17 213.17 Weighted Average for the Year 511.00 178.60 213.17 213.17 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 624-30049 48 In Drainage Pipe (CL 10) (CIP) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 170.00 524.96 530.79 530.79 Weighted Average for the Third Quarter 170.00 524.96 530.79 530.79 Weighted Average for the Year 170.00 524.96 530.79 530.79 624-47018 18 In Equiv Drain Pipe E (CL 7) Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 141.00 397.32 397.32 397.32 Weighted Average for the Second Quarter 141.00 397.32 397.32 397.32 Weighted Average for the Year 141.00 397.32 397.32 397.32 624-49025 24 In Equiv Drain Pipe E (CL 9) (CIP) Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 64.00 360.49 360.49 360.49 Weighted Average for the Second Quarter 64.00 360.49 360.49 360.49 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,047.00 270.95 263.04 263.04 Weighted Average for the Third Quarter 1,047.00 270.95 263.04 263.04 Weighted Average for the Year 1,111.00 276.11 268.65 268.65 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 624-50025 24 In Equiv Drain Pipe E (CL 10) (CIP) Lin Foot NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 46.00 270.96 414.03 414.03 Weighted Average for the Third Quarter 46.00 270.96 414.03 414.03 Weighted Average for the Year 46.00 270.96 414.03 414.03 625-00000 Const Surveying Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 15000.00 82053.86 90000.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 50000.00 191210.98 187265.85 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 150000.00 32961.93 46000.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 150000.00 141823.01 160000.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 30000.00 18280.50 14653.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1.00 20000.00 132284.32 195000.00 BR0761-249 I-76 02/27/25 1.00 15000.00 54466.67 120000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 35000.00 40620.66 25000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 10000.00 38885.31 48500.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 75000.00 107478.50 128787.88 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 1.00 7000.00 4716.67 5550.00 Weighted Average for the First Quarter 11.00 50636.36 78745.05 92796.07 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 90000.00 62000.00 62000.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 1.00 1.00 5797230.01 5000.00 5789565.51 2000.00 5789565.51 2000.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 1.00 18000.00 9195.00 11750.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 1.00 8000.00 48000.00 48000.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 40000.00 48223.33 59670.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 1.00 30000.00 67689.33 56068.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 143101.21 143101.21 143101.21 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 625-00000 Const Surveying Lump Sum C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 1.00 5000.00 19640.05 8000.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 30000.00 58159.41 36000.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 30000.00 25770.51 28000.00 ITSSW03-250 FRONT RANGE 06/26/25 1.00 60000.00 138385.60 340000.00 Weighted Average for the Second Quarter 12.00 521360.93 235807.43 548679.56 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 281926.39 370276.66 370276.66 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 9814.61 31690.30 31690.30 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 18264.55 19656.85 19656.85 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 12000.00 9274.50 6000.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 1.00 10000.00 75000.00 75000.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1.00 12000.00 119442.00 28410.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 35000.00 18243.75 15000.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 68644.59 68591.40 68591.40 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 29791.40 20239.76 14198.81 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 40000.00 4830.20 4200.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 1.00 1.00 40000.00 60000.00 59044.00 91724.75 50000.00 35000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 910794.70 932706.89 932706.89 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 80250.00 64321.64 64321.64 Weighted Average for the Third Quarter 14.00 114891.87 78677.44 122503.75 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 500000.00 237125.00 181500.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 66000.00 27557.50 15730.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 47600.57 82785.00 84000.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 20000.00 27111.74 25000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 125000.00 168490.83 88885.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 80000.00 26767.67 9450.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 50000.00 138909.77 100269.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 50000.00 87500.00 80000.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 25000.00 30439.40 33220.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 625-00000 Const Surveying Lump Sum NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 70000.00 37056.69 39000.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 10000.00 50500.00 41000.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 55077.33 100120.00 70100.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1.00 200000.00 317569.90 152143.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 50000.00 15115.00 10230.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 1.00 20000.00 49077.26 34000.00 ITSSW03-417 STATEWIDE 12/04/25 1.00 25000.00 54134.00 52445.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 70000.00 49383.33 13150.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 150000.00 49590.00 39180.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 40000.00 47000.00 60000.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 60000.00 203959.22 336319.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 125000.00 79440.21 99425.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 20000.00 49400.00 70000.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 50000.00 71344.01 109000.00 Weighted Average for the Fourth Quarter 23.00 82986.00 91099.76 75828.13 Weighted Average for the Year 60.00 172174.92 108158.61 184400.18 625-00001 Const Surveying (Hour) Hour NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 40.00 200.00 218.69 210.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 300.00 305.50 301.00 Weighted Average for the First Quarter 50.00 220.00 236.05 228.20 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 200.00 40.00 287.30 200.00 287.30 700.00 287.30 700.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 40.00 300.00 223.83 275.00 Weighted Average for the Second Quarter 280.00 276.64 303.18 344.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 625-00001 Const Surveying (Hour) Hour CR400-406 REGION-WIDE 07/17/25 16.00 245.29 413.33 350.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 10.00 262.99 341.62 341.62 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 20.00 250.00 310.44 158.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 46.00 251.19 343.67 264.70 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 200.00 230.00 228.53 254.10 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 20.00 250.00 367.41 451.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 100.00 225.00 205.00 190.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 40.00 300.00 190.50 191.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 20.00 300.00 339.50 225.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 20.00 200.00 195.00 196.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 10.00 250.00 353.00 190.00 Weighted Average for the Fourth Quarter 410.00 239.02 237.80 236.10 Weighted Average for the Year 786.00 251.93 255.25 275.89 626-00000 Mobilization Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 1214139.23 1097207.31 1269983.85 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 1.00 204072.43 276921.17 175000.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 1.00 1556140.84 1403560.14 1279275.84 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 1.00 1200000.00 871893.67 202850.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 225000.00 263236.14 123000.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 1.00 327147.09 334346.28 142352.41 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 850000.00 1121500.00 865000.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1.00 113723.25 120205.24 50387.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1.00 918270.00 1090866.54 625000.00 BR0761-249 I-76 02/27/25 1.00 299775.65 317425.87 200000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 330000.00 249571.76 207000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 626-00000 Mobilization Lump Sum MTCER500-233 REGION 5 03/06/25 1.00 250000.00 120908.33 27500.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 1.00 219664.10 112500.00 115000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 813312.98 574382.36 390500.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 2059753.64 1241513.92 749649.65 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 1.00 62810.00 70500.00 23500.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 1000000.00 590000.00 500000.00 Weighted Average for the First Quarter 17.00 684929.95 562852.65 408588.16 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 500000.00 569659.03 569659.03 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 286420.02 174450.00 228900.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 1.00 1.00 535925.00 65000.00 511348.39 162000.00 511348.39 162000.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 1.00 97612.55 54125.00 40000.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 1.00 130000.00 206487.50 303950.00 MTCER300-288 I-70 MM 0-205 REGION WIDE 05/08/25 1.00 50000.00 75000.00 50000.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 1.00 500000.00 330000.00 330000.00 STAR500-228 REGION 5 05/08/25 1.00 300000.00 255441.67 151000.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 1.00 479000.00 397590.36 312771.07 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 1.00 454945.53 445333.33 436000.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 666264.40 666264.40 666264.40 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 1.00 438289.45 317055.00 287165.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 1.00 46090.56 79390.23 67000.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 1.00 64000.00 146144.00 47750.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 700000.00 580917.62 475000.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 1.00 26000.00 106750.00 72500.00 ITSSW03-250 FRONT RANGE 06/26/25 1.00 450000.00 436990.20 361200.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 1.00 180617.75 150000.00 150000.00 Weighted Average for the Second Quarter 19.00 314219.22 282171.56 274868.84 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 1.00 43000.00 100666.67 100000.00 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 1.00 35000.00 22500.00 25000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 626-00000 Mobilization Lump Sum CR400-406 REGION-WIDE 07/17/25 1.00 120000.00 211666.67 175000.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 48498.62 69123.50 52322.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 1.00 142285.18 565000.00 565000.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 1.00 1.00 508884.26 170410.24 1147017.76 288375.00 859669.55 163000.00 C0142-070 SH 14 MP 75.5-85 08/14/25 1.00 42042.23 43665.00 39000.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 1.00 377911.03 135476.75 65000.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 2502769.97 2611388.51 2611388.51 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 1.00 207439.43 240666.67 126000.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 1.00 68752.75 75774.73 69000.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 82732.06 107400.00 80000.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 55000.00 51052.80 31000.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 1.00 134771.16 155470.00 137600.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 1.00 1.00 362424.16 339261.39 404445.14 640979.98 260000.00 270000.00 SPFS2706-055 I-270 MP 0-3 09/26/25 1.00 476748.88 505942.02 505942.02 Weighted Average for the Third Quarter 18.00 317662.85 324616.55 340829.00 MTCER400-415 REGION 4 10/16/25 1.00 70000.00 17950.00 15900.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 1700000.00 1549638.73 1477554.93 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1.00 900000.00 465575.02 375000.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 423821.71 457688.70 380000.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1.00 300000.00 379132.16 497000.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 200000.00 326872.45 205000.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 1.00 42327.36 31426.67 14780.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 1000000.00 655420.00 203484.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 765735.69 683049.13 468458.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 807773.11 797710.50 712421.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 1.00 52687.70 22979.67 31000.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 180000.00 236876.10 162000.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 1116170.52 829212.96 665000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 626-00000 Mobilization Lump Sum STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 1240843.68 771500.00 815000.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 785023.00 877074.08 650000.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1.00 2500000.00 2973844.48 1706784.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 1300000.00 717750.00 585000.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 1.00 344459.36 443164.98 225000.00 ITSSW03-417 STATEWIDE 12/04/25 1.00 228000.00 746777.00 577010.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 600000.00 580486.49 465000.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 351000.00 508000.00 519000.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 1.00 58285.35 66810.00 40000.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 2100000.00 1362385.00 1599770.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 1000000.00 1000000.00 1000000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 1600000.00 1230000.00 960000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 1100000.00 496500.00 363000.00 NHPP1602-194 US 160 MP 174.1 12/11/25 1.00 260000.00 275381.61 425000.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 1200000.00 1321487.55 946861.30 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 450000.00 492851.71 475625.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 160000.00 299590.80 336000.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 833030.88 616636.67 683292.94 Weighted Average for the Fourth Quarter 31.00 763521.24 668023.69 567094.89 Weighted Average for the Year 85.00 552953.70 503867.64 422157.30 626-00010 Erection Equip Lump Sum NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 04/11/25 1.00 1656383.80 1672958.85 1672958.85 Weighted Average for the Second Quarter 1.00 1656383.80 1672958.85 1672958.85 Weighted Average for the Year 1.00 1656383.80 1672958.85 1672958.85 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 626-00100 Mobilization (w/o Autopay) Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 74547060.40 69838705.17 69838705.17 FBR0703-534 I-70 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 1730954.27 1730954.25 1730954.25 Weighted Average for the Second Quarter 2.00 38139007.34 35784829.71 35784829.71 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 2083577.70 2082603.21 2082603.21 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 1434410.76 1418495.66 1418495.66 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 11903191.75 13661025.09 13661025.09 Weighted Average for the Third Quarter 3.00 5140393.40 5720707.99 5720707.99 Weighted Average for the Year 5.00 18339838.98 17746356.68 17746356.68 626-01101 Public Info Services (Tier I) Lump Sum NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 92287.50 89714.15 89714.15 Weighted Average for the Third Quarter 1.00 92287.50 89714.15 89714.15 Weighted Average for the Year 1.00 92287.50 89714.15 89714.15 626-01103 Public Info Services (Tier III) Lump Sum NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1.00 50000.00 22271.24 20600.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 1.00 22000.00 36404.94 45000.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1.00 90.00 3138.25 4500.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 15000.00 15851.00 21000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 4.00 21772.50 22304.24 22775.00 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 7000.00 7000.00 7000.00 C0821-113 CO-82 & Catherine Store Signa 04/17/25 1.00 10000.00 7683.00 7683.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 1.00 15000.00 11500.00 11500.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 10000.00 44896.47 110000.00 Weighted Average for the Second Quarter 4.00 10500.00 29395.55 34045.75 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 32045.00 32707.64 32707.64 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 1.00 15000.00 14371.31 11000.00 Weighted Average for the Third Quarter 2.00 23522.50 16408.68 21853.82 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 50.00 49202.00 23958.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 1.00 12600.00 9889.50 8500.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1.00 10000.00 21282.25 11600.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 1.00 30000.00 30250.00 35000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 20000.00 14398.03 16386.70 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 25000.00 13941.25 13000.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 7500.00 13660.00 7320.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 10000.00 16579.33 20000.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 20000.00 15160.00 10320.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 33600.00 15280.00 20000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 10000.00 7205.00 7250.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 20000.00 17800.00 20000.00 Weighted Average for the Fourth Quarter 12.00 16562.50 20792.59 16111.23 Weighted Average for the Year 22.00 17040.23 21386.96 21105.70 626-01104 Public Info Services (Tier IV) Lump Sum STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 1.00 15000.00 11319.39 12500.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 626-01104 Public Info Services (Tier IV) Lump Sum STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 10000.00 27049.16 10000.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 1.00 5000.00 5500.00 6000.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 25000.00 10355.00 4510.00 Weighted Average for the First Quarter 4.00 13750.00 14609.49 8252.50 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 10000.00 8600.00 7700.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 1.00 6000.00 3678.33 3750.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 1.00 4800.00 8596.00 4134.00 STAR500-228 REGION 5 05/08/25 1.00 50000.00 8031.67 8700.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 1.00 18000.00 9628.75 8300.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 1.00 8500.00 12500.00 12500.00 Weighted Average for the Second Quarter 6.00 16216.67 8101.71 7514.00 CR400-406 REGION-WIDE 07/17/25 1.00 7500.00 5616.67 4950.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 5000.00 5234.00 4550.00 C0142-070 SH 14 MP 75.5-85 08/14/25 1.00 15000.00 3335.00 2800.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 1.00 10000.00 14291.67 14000.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 1.00 15000.00 5423.75 4435.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 1.00 4500.00 5508.00 7665.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 1.00 7000.00 12185.20 7600.00 Weighted Average for the Third Quarter 7.00 9142.86 7438.04 6571.43 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1.00 16000.00 13421.25 4825.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 15000.00 12620.53 6500.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 1.00 8000.00 4413.33 3000.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 8500.00 13500.00 7000.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 1.00 10000.00 5216.67 5000.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 5600.00 4387.75 3894.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 15000.00 5750.00 6500.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 1.00 15000.00 5248.86 4084.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 626-01104 Public Info Services (Tier IV) Lump Sum 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 7000.00 20000.00 20000.00 NHPP1602-194 US 160 MP 174.1 12/11/25 1.00 11500.00 14680.47 10700.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 1.00 92.00 33283.19 50820.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1.00 21000.00 16485.19 15600.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 15000.00 10448.71 10100.00 Weighted Average for the Fourth Quarter 13.00 11360.92 12636.57 11386.41 Weighted Average for the Year 30.00 12133.07 10913.09 9070.58 626-01111 Public Info Manage (Tier I) Day NHPP0703-517 FBR0703-534 I-70 TOP OF I-70 FLOYD HILL TO VET 04/11/25 1,674.00 288.32 288.34 288.34 Weighted Average for the Second Quarter 1,674.00 288.32 288.34 288.34 Weighted Average for the Year 1,674.00 288.32 288.34 288.34 626-01113 Public Info Manage (Tier III) Day 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 250.00 88.69 105.68 90.10 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 142.00 80.23 91.49 151.80 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 150.00 81.48 96.60 117.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 200.00 74.18 128.52 151.52 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 10.00 83.00 477.33 487.00 Weighted Average for the First Quarter 752.00 81.72 110.84 128.83 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 521.00 96.46 96.46 96.46 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 626-01113 Public Info Manage (Tier III) Day ITSSW03-250 FRONT RANGE 06/26/25 300.00 75.84 93.20 92.00 Weighted Average for the Second Quarter 821.00 88.92 94.04 94.83 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 45.00 120.00 135.00 135.00 BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 180.00 88.91 110.34 156.36 Weighted Average for the Third Quarter 225.00 95.13 111.79 152.09 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 300.00 65.91 89.88 80.00 ITSSW03-417 STATEWIDE 12/04/25 300.00 113.45 103.63 92.00 Weighted Average for the Fourth Quarter 600.00 89.68 96.75 86.00 Weighted Average for the Year 2,398.00 87.44 102.99 108.66 626-01114 Public Info Manage (Tier IV) Day SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 60.00 80.00 100.05 59.00 Weighted Average for the First Quarter 60.00 80.00 100.05 59.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 225.00 131.71 89.00 85.00 Weighted Average for the Second Quarter 225.00 131.71 89.00 85.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 1.00 94.86 6261.00 285.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 50.00 123.38 134.50 91.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 70.00 85.00 76.80 55.00 Weighted Average for the Third Quarter 121.00 100.94 142.28 71.78 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 406.00 114.90 110.08 77.22 627-00001 Pvmt Mkg Paint Gallon STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 5.00 90.00 150.00 150.00 Weighted Average for the Second Quarter 5.00 90.00 150.00 150.00 Weighted Average for the Year 5.00 90.00 150.00 150.00 627-00002 Thermoplastic Pvmt Mkg Sq Foot NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 162.00 27.00 37.99 38.72 Weighted Average for the Fourth Quarter 162.00 27.00 37.99 38.72 Weighted Average for the Year 162.00 27.00 37.99 38.72 627-00005 Epoxy Pvmt Mkg Gallon NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 2,274.00 181.32 181.33 181.33 FBR0703-534 I-70 Weighted Average for the Second Quarter 2,274.00 181.32 181.33 181.33 Weighted Average for the Year 2,274.00 181.32 181.33 181.33 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 627-00007 Epoxy Pvmt Mkg (Spec) Gallon MTCER400-415 REGION 4 10/16/25 200.00 200.00 168.50 250.00 Weighted Average for the Fourth Quarter 200.00 200.00 168.50 250.00 Weighted Average for the Year 200.00 200.00 168.50 250.00 627-00008 Mod Epoxy Pvmt Mkg Gallon NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 390.00 200.00 161.03 147.15 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 30.00 257.78 422.50 318.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 5.00 1000.00 810.90 320.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 28.00 475.00 697.05 879.18 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 248.00 200.00 175.50 150.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 276.00 145.00 190.02 165.00 BR0761-249 I-76 02/27/25 90.00 466.80 228.11 117.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 3,767.00 120.00 112.50 115.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 808.00 205.09 182.97 168.35 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 766.00 141.53 188.34 190.61 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1,223.00 150.00 147.50 143.00 Weighted Average for the First Quarter 7,631.00 150.08 157.38 141.08 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,001.00 181.33 181.33 181.33 FBR0703-534 I-70 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 134.00 317.40 194.00 172.00 MTCER300-288 I-70 MM 0-205 REGION WIDE 05/08/25 17,840.00 105.00 99.12 94.99 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 165.00 210.00 204.92 204.75 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 156.10 203.63 203.63 203.63 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 30.00 300.00 246.46 80.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 10.00 697.12 400.00 550.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 17,364.00 88.00 112.50 112.50 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 36,700.10 101.03 107.18 106.98 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 213.00 224.37 224.37 224.37 CR400-406 REGION-WIDE 07/17/25 20.00 362.20 246.67 400.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 4.00 1040.54 660.00 615.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 240.00 230.00 250.00 250.00 BR0704-265 I-70 EAST 07/24/25 549.00 236.95 209.25 161.98 FBR0704-269 I-70 EAST CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 3.00 733.77 1497.25 569.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 12.00 614.85 712.00 810.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 29.00 531.76 222.00 125.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 7,074.00 131.70 131.70 131.70 Weighted Average for the Third Quarter 8,144.00 147.49 160.80 141.68 MTCER400-415 REGION 4 10/16/25 22,321.00 85.00 84.50 82.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1.00 1000.00 1553.09 1800.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 107.00 250.00 240.75 205.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1,083.00 100.00 182.83 211.90 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,174.00 180.00 141.95 123.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1,064.00 134.74 141.49 128.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 661.00 210.98 201.66 204.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 743.00 125.00 147.50 145.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 31.00 600.56 321.03 179.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1,124.00 85.00 161.50 163.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2,014.00 180.00 131.50 130.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1,318.00 160.00 137.75 132.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 30.00 361.37 275.85 425.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 21.00 320.00 450.00 150.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,680.00 172.42 141.21 140.80 Weighted Average for the Fourth Quarter 33,372.00 108.33 113.50 104.41 Weighted Average for the Year 85,847.10 112.63 119.56 112.30 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 627-00009 Mod Epoxy (Inlaid) Gallon STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 80.00 290.00 508.50 508.50 Weighted Average for the Second Quarter 80.00 290.00 508.50 508.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 140.00 272.97 360.23 350.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,085.00 140.40 148.50 132.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 275.00 200.00 191.00 246.00 Weighted Average for the Fourth Quarter 1,500.00 163.70 198.10 173.25 Weighted Average for the Year 1,580.00 170.10 204.68 190.22 627-00011 Pvmt Mkg Paint (Waterborne) Gallon NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 25.00 96.16 96.16 96.16 Weighted Average for the Second Quarter 25.00 96.16 96.16 96.16 CR400-406 REGION-WIDE 07/17/25 30.00 76.78 108.33 125.00 Weighted Average for the Third Quarter 30.00 76.78 108.33 125.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2,370.00 68.31 88.00 115.00 Weighted Average for the Fourth Quarter 2,370.00 68.31 88.00 115.00 Weighted Average for the Year 2,425.00 68.70 88.42 114.93 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 627-00013 Pvmt Mkg Paint (High Build) Gallon 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 27.00 145.72 151.75 79.50 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 30.00 120.00 421.35 5.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 447.00 50.00 159.00 195.00 BR0761-249 I-76 02/27/25 68.00 144.60 129.08 118.00 MTCER500-233 REGION 5 03/06/25 39,054.00 48.00 41.50 40.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 1,817.00 60.00 57.50 65.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1,705.00 53.46 88.45 86.70 Weighted Average for the First Quarter 43,148.00 49.01 43.60 44.63 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 9.00 100.00 309.25 59.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 5.00 318.72 641.67 125.00 Weighted Average for the Second Quarter 14.00 178.11 407.02 82.57 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 300.00 84.13 84.13 84.13 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 26.00 292.83 292.82 292.82 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 62.00 412.93 143.20 60.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 7.00 188.00 401.83 89.91 365.40 103.34 109.00 80.00 Weighted Average for the Third Quarter 583.00 134.08 112.86 89.84 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 97.00 850.00 577.57 1355.27 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1,079.00 57.76 79.85 49.50 NHPPR500-227 REGION 5 SECTION 7 10/23/25 17.00 500.00 267.06 55.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 4.00 250.00 522.19 350.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 4,191.00 59.85 62.63 50.25 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2,000.00 65.00 99.13 98.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,257.00 80.00 118.15 94.30 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 40.00 388.58 253.43 69.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 541.00 80.00 82.87 73.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 627-00013 Pvmt Mkg Paint (High Build) Gallon NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 722.00 55.00 127.15 84.30 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1,392.00 67.00 72.00 72.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2,036.00 80.00 88.60 108.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 18.00 61.00 241.06 544.50 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 28.00 206.66 105.90 122.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 40.00 120.00 218.00 225.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 2,100.00 81.87 108.72 95.00 Weighted Average for the Fourth Quarter 15,562.00 75.44 97.22 87.22 Weighted Average for the Year 59,307.00 56.81 51.86 56.26 627-00016 Pvmt Mkg Paint (High Build)(Temporary) Gallon NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 451.00 115.00 99.27 88.30 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 91.00 175.00 235.80 309.93 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 516.00 75.00 89.81 75.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 763.00 80.00 77.50 65.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 903.00 133.00 116.59 108.18 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1,979.00 90.00 73.10 50.70 Weighted Average for the First Quarter 4,703.00 99.03 95.85 75.34 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 112.00 150.00 118.67 72.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 50.00 100.00 497.33 482.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 71.00 85.00 104.45 24.00 Weighted Average for the Second Quarter 233.00 119.46 187.19 145.36 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 8.00 198.00 600.00 100.00 426.68 125.29 109.00 80.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 206.00 119.42 132.71 81.13 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 542.00 44.17 135.80 173.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 174.00 100.00 171.16 250.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 10.00 450.00 267.06 55.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 100.00 120.00 355.50 95.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2,474.00 90.00 76.53 88.70 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2,054.00 135.00 91.99 94.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 1,122.00 90.58 100.61 116.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 662.00 70.00 123.00 173.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 209.00 100.00 85.67 148.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1,505.00 85.00 125.00 125.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1,699.00 100.00 108.80 125.50 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 11.00 175.00 253.36 605.00 Weighted Average for the Fourth Quarter 10,562.00 97.18 110.16 117.73 Weighted Average for the Year 15,704.00 98.36 108.02 104.97 627-00025 4 In Pvmt Mkg Tape (Rem) Lin Foot FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 100.00 5.00 21.40 5.50 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 100.00 5.00 21.40 5.50 Weighted Average for the Year 100.00 5.00 21.40 5.50 627-00031 Raised Pvmt Marker Each C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 10.00 200.00 222.92 50.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 10.00 200.00 222.92 50.00 Weighted Average for the Year 10.00 200.00 222.92 50.00 627-01010 Preform Plastic Pvmt Mkg (TY I)(Inlaid) Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 6,091.00 25.00 21.18 18.85 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 1,017.00 24.00 38.01 40.48 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 7,579.00 19.15 25.01 22.20 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3,164.00 22.55 25.95 23.44 Weighted Average for the First Quarter 17,851.00 22.03 24.92 22.32 NHPP0703-517 FBR0703-534 NHPP2254-095 I-70 TOP OF FLOYD HILL TO VET I-70 I-225 @ 2ND AND 6TH AVES 04/11/25 05/22/25 41,699.00 972.00 26.08 40.00 26.07 42.67 26.07 41.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 9,315.00 17.00 16.75 16.75 Weighted Average for the Second Quarter 51,986.00 24.71 25.36 24.68 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2,370.00 24.69 24.69 24.69 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 3,129.00 21.00 42.00 42.00 BR0704-265 FBR0704-269 NHPP0253-302 I-70 EAST I-70 EAST I-25 SEGMENT 5 (MP 242.5 TO 2 07/24/25 09/26/25 1,410.00 78.00 28.43 23.54 27.41 24.14 26.65 24.14 Weighted Average for the Third Quarter 6,987.00 23.78 30.88 32.83 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 601.00 29.17 35.81 35.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 10,541.00 25.00 22.05 22.10 NHPP1602-194 US 160 MP 174.1 12/11/25 1,977.00 25.00 36.89 37.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 18,300.00 19.61 22.54 23.30 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 31,419.00 21.94 24.10 23.98 Weighted Average for the Year 108,243.00 23.40 25.02 24.61 627-01011 Preform Plastic Pvmt Mkg (Contr)(Inlaid) Sq Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 100.00 27.02 59.10 63.60 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 350.00 24.00 40.83 40.48 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 596.00 30.15 24.68 22.20 Weighted Average for the First Quarter 1,046.00 27.79 36.10 32.27 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 12,625.00 28.33 28.33 28.33 FBR0703-534 I-70 Weighted Average for the Second Quarter 12,625.00 28.33 28.33 28.33 BR0704-265 I-70 EAST 07/24/25 1,410.00 24.42 27.41 26.65 FBR0704-269 I-70 EAST NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 19,351.00 24.61 25.24 25.24 Weighted Average for the Third Quarter 20,761.00 24.60 25.73 25.34 Weighted Average for the Year 34,432.00 26.06 27.47 26.64 627-02010 Preform Plastic Pvmt Mkg (Ty II)(Inlaid) Sq Foot NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 54.00 37.22 27.41 25.00 Weighted Average for the First Quarter 54.00 37.22 27.41 25.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 7,685.00 18.00 17.25 17.25 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 7,685.00 18.00 17.25 17.25 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 13,525.00 11.20 24.57 23.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 5,062.00 25.00 25.67 23.00 Weighted Average for the Fourth Quarter 18,587.00 14.96 24.77 23.36 Weighted Average for the Year 26,326.00 15.89 24.14 21.58 627-30205 Thermoplastic Pvmt Mkg (WS) Sq Foot SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 138.00 27.45 29.75 35.00 Weighted Average for the Third Quarter 138.00 27.45 29.75 35.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1,772.00 35.78 21.53 21.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 69.00 40.00 41.00 40.00 Weighted Average for the Fourth Quarter 1,841.00 35.94 22.25 21.71 Weighted Average for the Year 1,979.00 35.35 23.23 22.64 627-30210 Thermoplastic Pvmt Mkg (XS) Sq Foot STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 2,448.00 22.50 17.00 13.00 Weighted Average for the Second Quarter 2,448.00 22.50 17.00 13.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 689.00 20.73 17.13 18.00 Weighted Average for the Third Quarter 689.00 20.73 17.13 18.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 627-30210 Thermoplastic Pvmt Mkg (XS) Sq Foot STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 86.00 25.00 34.00 33.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 56.00 30.00 15.15 15.00 Weighted Average for the Fourth Quarter 142.00 26.97 26.57 25.90 Weighted Average for the Year 3,279.00 22.32 17.39 14.61 627-30323 Preform Plastic Pvmt Mkg (WS)(Typ I)(In) Sq Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 599.00 45.25 45.25 45.25 Weighted Average for the Second Quarter 599.00 45.25 45.25 45.25 Weighted Average for the Year 599.00 45.25 45.25 45.25 627-30328 Pre Plastic Pvmt Mkg (XWalk)(Typ1)(In) Sq Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 4,370.00 16.97 16.97 16.97 Weighted Average for the Second Quarter 4,370.00 16.97 16.97 16.97 Weighted Average for the Year 4,370.00 16.97 16.97 16.97 627-30405 Preform Thermoplastic Pvmt Mkg (WS) Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,941.00 23.00 19.55 18.85 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 82.00 26.29 39.57 42.40 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 264.00 40.00 32.75 36.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 627-30405 Preform Thermoplastic Pvmt Mkg (WS) Sq Foot NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1,634.00 21.00 20.94 19.00 MTCER500-233 REGION 5 03/06/25 4,629.00 16.00 19.53 16.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1,323.00 24.15 25.42 23.20 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 877.00 19.98 25.94 24.47 Weighted Average for the First Quarter 10,750.00 20.02 21.01 19.24 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 630.00 20.00 26.95 26.95 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 91.90 26.52 24.00 16.00 NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET I-70 SH287 & LCR 72 AND US287 & OW 04/11/25 04/24/25 804.00 264.00 34.00 25.88 34.00 27.67 34.00 21.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 15,301.00 13.50 18.00 18.00 Weighted Average for the Second Quarter 17,090.90 14.97 19.54 19.12 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 2,690.00 41.50 41.50 41.50 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 48.30 28.71 28.45 22.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 33.00 35.36 35.36 35.36 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 210.00 32.06 27.26 25.00 Weighted Average for the Third Quarter 2,981.30 40.56 35.70 39.95 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 65.00 25.21 45.71 33.25 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 174.00 30.33 30.53 24.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 23.00 37.03 48.50 58.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 211.00 20.00 32.27 28.93 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 2,450.00 20.41 21.86 21.25 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 398.00 20.00 33.00 23.00 Weighted Average for the Fourth Quarter 3,321.00 21.07 24.03 22.58 Weighted Average for the Year 34,143.20 19.38 22.02 21.31 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 627-30407 Preform Thermoplastic Pvmt Mkg (WS)(Sp) Sq Foot STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 65.00 30.00 25.39 26.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 4,632.00 25.00 24.91 25.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 176.00 25.00 33.05 32.10 Weighted Average for the First Quarter 4,873.00 25.07 25.07 25.27 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 7,123.40 16.50 17.00 16.75 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1,869.00 25.68 26.34 26.34 Weighted Average for the Third Quarter 8,992.40 18.41 18.08 18.74 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 458.00 27.00 37.87 38.72 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 431.00 25.00 40.00 28.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 891.00 18.00 30.46 35.30 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 757.00 30.00 22.16 20.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 261.00 25.00 15.78 15.80 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 803.00 25.00 19.25 19.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 879.00 25.00 19.18 13.25 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 741.00 29.00 22.14 22.10 Weighted Average for the Fourth Quarter 5,221.00 25.27 27.40 23.71 Weighted Average for the Year 19,086.40 21.99 23.49 21.77 627-30408 Pre Thermo Pvmt Mkg (Shield) Sq Foot NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 814.00 26.73 35.27 29.36 Weighted Average for the First Quarter 814.00 26.73 35.27 29.36 Weighted Average for the Year 814.00 26.73 35.27 29.36 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 627-30410 Preform Thermoplastic Pvmt Mkg (XS) Sq Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 20,922.00 15.00 14.10 14.15 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 276.00 18.85 22.20 21.20 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 1,492.00 20.00 18.99 20.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 14,441.00 16.00 15.07 14.00 MTCER500-233 REGION 5 03/06/25 3,768.00 17.00 17.17 18.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 17,017.00 13.37 15.77 15.30 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 952.00 16.41 20.20 18.55 Weighted Average for the First Quarter 58,868.00 15.07 15.50 14.94 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 6,408.00 15.00 14.65 14.65 NHPP0703-517 FBR0703-534 STM2873-232 I-70 TOP OF FLOYD HILL TO VET I-70 SH287 & LCR 72 AND US287 & OW 04/11/25 04/24/25 652.00 24.00 22.67 24.85 22.66 20.17 22.66 10.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 124.00 32.00 36.68 38.03 Weighted Average for the Second Quarter 7,208.00 16.02 16.49 15.76 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1,202.00 15.70 15.70 15.70 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 730.00 18.82 29.25 29.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 54.00 23.04 22.05 19.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 154.00 21.46 23.14 18.00 Weighted Average for the Third Quarter 2,140.00 17.36 24.84 20.49 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 24.00 27.37 29.50 32.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1,764.00 15.00 19.02 17.33 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 4,850.00 15.61 16.03 14.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 474.00 20.45 27.30 15.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1,510.00 17.00 16.97 15.90 Weighted Average for the Fourth Quarter 8,622.00 16.03 17.24 15.43 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 76,838.00 15.33 15.95 15.23 627-30411 Preform Thermoplastic Pvmt Mkg (XS)(Sp) Sq Foot STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 1,864.00 15.00 21.41 19.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 9,609.00 16.00 18.70 18.50 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 90.00 20.00 29.05 28.10 Weighted Average for the First Quarter 11,563.00 15.87 19.08 18.66 C0821-113 CO-82 & Catherine Store Signa 04/17/25 778.00 15.00 23.00 23.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 41,330.00 11.75 13.75 13.75 Weighted Average for the Second Quarter 42,108.00 11.81 13.92 13.92 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 19,900.00 13.00 12.38 12.25 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 32.00 23.54 24.14 24.14 Weighted Average for the Third Quarter 19,932.00 13.02 12.38 12.27 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2,661.00 20.00 26.58 27.83 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2,360.00 20.00 21.92 20.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 912.00 18.40 19.63 22.75 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 2,698.00 20.00 14.68 13.25 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1,584.00 21.00 18.20 19.50 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,939.00 20.94 15.79 15.70 Weighted Average for the Fourth Quarter 12,154.00 20.16 20.53 19.67 Weighted Average for the Year 85,757.00 13.82 16.61 14.99 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 628-00100 Brdg Girder + Deck Unit (100-105) Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 1.00 128000.00 221586.32 272500.00 Weighted Average for the Second Quarter 1.00 128000.00 221586.32 272500.00 FBR0063-066 628-00120 Weighted Average for the Year Bridge Girder and Deck Unit (120-125) US 6D IN GARFIELD COUNTY 08/15/25 1.00 Each 1.00 128000.00 284823.23 221586.32 287338.43 272500.00 287338.43 Weighted Average for the Third Quarter 1.00 284823.23 287338.43 287338.43 Weighted Average for the Year 1.00 284823.23 287338.43 287338.43 628-00180 Bridge Girder and Deck Unit (180-185) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 1145296.37 936536.67 936536.67 Weighted Average for the Third Quarter 1.00 1145296.37 936536.67 936536.67 Weighted Average for the Year 1.00 1145296.37 936536.67 936536.67 629-01001 Survey Monument (Ty 1) Each STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 24.00 170.95 369.26 500.00 Weighted Average for the Third Quarter 24.00 170.95 369.26 500.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 629-01001 Survey Monument (Ty 1) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 210.00 822.25 605.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 14.00 320.00 502.33 450.00 Weighted Average for the Fourth Quarter 21.00 283.33 582.31 501.67 Weighted Average for the Year 45.00 223.40 447.75 500.78 629-01004 Survey Monument (Ty 4) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 1800.00 1260.28 2069.10 Weighted Average for the Fourth Quarter 7.00 1800.00 1260.28 2069.10 Weighted Average for the Year 7.00 1800.00 1260.28 2069.10 629-01006 Survey Monument (Ty 6) Each NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 2.00 800.00 1408.60 800.00 Weighted Average for the Second Quarter 2.00 800.00 1408.60 800.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 8.00 200.00 623.93 810.70 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 15.00 150.00 169.67 94.00 Weighted Average for the Fourth Quarter 23.00 167.39 288.82 343.29 Weighted Average for the Year 25.00 218.00 357.73 379.82 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 629-01011 Survey Monument (Ty 1A) Each NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 1.00 400.00 2148.96 1200.00 Weighted Average for the Second Quarter 1.00 400.00 2148.96 1200.00 Weighted Average for the Year 1.00 400.00 2148.96 1200.00 629-01031 Survey Monument (Ty 3A) Each STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 6.00 1800.00 2161.30 3123.90 Weighted Average for the Second Quarter 6.00 1800.00 2161.30 3123.90 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 5.00 500.00 689.17 450.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 1000.00 1789.70 3170.00 Weighted Average for the Fourth Quarter 6.00 583.33 789.22 903.33 Weighted Average for the Year 12.00 1191.67 1273.48 2013.62 629-01050 Monument Box Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 8.00 2500.00 919.38 1685.00 Weighted Average for the First Quarter 8.00 2500.00 919.38 1685.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 7.00 500.00 1317.06 1603.25 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 5.00 500.00 1040.00 450.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 2500.00 2487.89 1300.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 13.00 653.85 1238.38 1136.37 Weighted Average for the Year 21.00 1357.14 1128.62 1345.37 629-01110 Locate Monuments Hour NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 8.00 258.27 864.77 2050.00 Weighted Average for the First Quarter 8.00 258.27 864.77 2050.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 60.00 198.03 192.38 250.00 Weighted Average for the Third Quarter 60.00 198.03 192.38 250.00 Weighted Average for the Year 68.00 205.12 224.39 461.76 630-00000 Flagging Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 6,500.00 45.00 48.79 53.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 4,000.00 40.00 43.66 41.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 600.00 30.37 49.31 50.88 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 3,900.00 50.00 25.90 5.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2,000.00 50.00 43.00 50.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 40.00 80.00 60.68 94.88 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 3,000.00 50.00 51.00 53.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 40.00 45.00 38.52 34.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 4,000.00 50.00 189.83 52.60 BR0761-249 I-76 02/27/25 300.00 50.00 48.03 55.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 600.00 60.00 51.28 33.00 MTCER500-233 REGION 5 03/06/25 528.00 50.00 27.83 20.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 100.00 45.31 31.00 12.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1,200.00 41.83 49.83 45.40 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00000 Flagging Hour NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 500.00 42.00 55.98 48.94 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 160.00 53.00 56.33 55.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 3,500.00 50.00 44.55 47.10 Weighted Average for the First Quarter 30,968.00 47.06 61.94 43.07 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1,200.00 50.00 49.50 49.50 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 30.00 37.11 43.00 36.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 18,235.00 160.00 62.30 45.00 62.44 55.00 62.44 55.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 850.00 50.00 45.50 42.50 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 600.00 45.00 34.00 37.00 STAR500-228 REGION 5 05/08/25 2,400.00 45.00 29.33 30.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 200.00 35.00 49.65 40.95 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 160.00 41.03 41.03 41.03 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 1,000.00 50.00 55.00 60.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 44.31 44.30 42.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 500.00 38.08 45.25 51.50 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 200.00 45.00 39.35 56.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 150.00 40.65 47.50 50.00 ITSSW03-250 FRONT RANGE 06/26/25 400.00 35.03 47.19 50.50 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 10.00 46.88 39.25 39.25 Weighted Average for the Second Quarter 26,115.00 57.24 50.40 56.63 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 80.00 25.00 35.00 40.00 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 300.00 14.00 9.00 13.00 CR400-406 REGION-WIDE 07/17/25 550.00 40.00 64.07 57.20 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 60.00 30.00 38.88 39.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 150.00 33.00 52.50 52.50 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 1,920.00 500.00 37.75 37.39 53.42 45.00 62.18 40.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00000 Flagging Hour C0142-070 SH 14 MP 75.5-85 08/14/25 300.00 43.72 41.33 15.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 40.00 39.62 43.63 38.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 4,500.00 55.25 55.25 55.25 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 3,000.00 30.00 31.17 40.50 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 400.00 50.00 47.60 39.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 2,500.00 40.00 40.40 49.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 540.00 3,000.00 49.14 30.00 35.52 40.79 1.00 38.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 6,000.00 56.71 57.75 57.75 Weighted Average for the Third Quarter 23,840.00 44.31 43.48 48.80 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 13,200.00 48.00 46.60 48.40 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 4,000.00 37.71 52.66 48.25 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 4,000.00 40.00 34.06 30.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 3,300.00 50.00 37.03 30.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 1,200.00 50.00 51.95 40.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 25.00 40.48 33.13 5.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6,000.00 45.00 47.50 48.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 8,000.00 35.51 54.28 54.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 5,000.00 55.00 50.88 42.75 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1,600.00 25.00 47.84 35.48 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 6,912.00 80.00 48.51 39.25 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 2,536.00 31.99 42.70 42.65 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 8,000.00 50.00 41.97 37.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 3,500.00 39.82 54.95 66.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,800.00 45.00 46.80 42.10 ITSSW03-417 STATEWIDE 12/04/25 300.00 50.00 69.58 30.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 5,000.00 45.00 46.55 42.40 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 9,600.00 50.00 46.00 46.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1,500.00 45.00 51.45 57.90 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 3,200.00 37.27 52.00 52.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 7,000.00 45.00 51.40 50.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00000 Flagging Hour NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 5,000.00 45.00 43.88 44.75 NHPP1602-194 US 160 MP 174.1 12/11/25 500.00 50.00 56.39 65.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 8,500.00 48.00 55.60 76.44 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 1,640.00 35.02 44.32 42.25 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 2,500.00 45.00 54.00 50.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 2,000.00 33.72 50.52 52.00 Weighted Average for the Fourth Quarter 115,813.00 46.72 47.49 47.85 Weighted Average for the Year 196,736.00 47.88 49.95 48.38 630-00001 Pilot Car Operation Hour MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 20.00 42.81 150.00 100.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 750.00 50.00 72.65 95.30 Weighted Average for the First Quarter 770.00 49.81 74.66 95.42 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1,752.00 129.61 129.63 129.63 FBR0703-534 I-70 Weighted Average for the Second Quarter 1,752.00 129.61 129.63 129.63 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 4,000.00 43.08 89.55 89.10 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,000.00 43.08 92.50 75.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1,000.00 60.00 100.50 95.00 Weighted Average for the Fourth Quarter 6,000.00 45.90 91.87 87.73 Weighted Average for the Year 8,522.00 63.46 94.46 97.04 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00003 Uniformed Traf Ctrl Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 1,200.00 200.00 121.42 175.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 200.00 200.00 185.20 160.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 130.00 145.20 162.22 164.30 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 1,322.00 150.00 144.39 151.80 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 160.00 187.01 150.00 150.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 600.00 140.25 123.19 102.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 800.00 146.00 197.24 123.64 Weighted Average for the First Quarter 4,412.00 165.02 151.78 146.91 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 600.00 200.00 242.50 242.50 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 65.00 132.48 222.50 165.00 NHPP0703-517 FBR0703-534 NHPP2254-095 I-70 TOP OF FLOYD HILL TO VET I-70 I-225 @ 2ND AND 6TH AVES 04/11/25 05/22/25 6,235.00 690.00 223.37 800.00 212.71 206.33 212.71 200.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 160.00 227.93 227.93 227.93 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 120.00 350.00 165.00 165.00 Weighted Average for the Second Quarter 7,870.00 273.42 213.00 213.05 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 40.00 164.55 228.25 227.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 40.00 156.78 107.75 110.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 173.95 144.60 129.00 SPFS2706-055 I-270 MP 0-3 09/26/25 200.00 105.00 116.03 116.03 Weighted Average for the Third Quarter 300.00 124.44 147.46 130.89 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 400.00 300.00 134.33 133.65 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 240.00 169.92 182.34 124.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 600.00 142.76 138.53 172.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 100.00 150.00 165.00 200.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1,500.00 122.32 185.01 190.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 2,840.00 156.66 166.23 173.04 Weighted Average for the Year 15,422.00 218.01 171.62 185.16 630-00004 Traf Ctrl Vehicle Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 3000.00 20515.60 12950.00 Weighted Average for the First Quarter 2.00 3000.00 20515.60 12950.00 Weighted Average for the Year 2.00 3000.00 20515.60 12950.00 630-00006 Uniformed Traf Ctrl (Vehicle) Hour 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 130.00 56.33 53.37 47.70 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 1,322.00 30.00 62.26 151.80 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 600.00 30.89 75.27 102.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 800.00 93.00 103.63 123.64 Weighted Average for the First Quarter 2,852.00 49.06 75.71 128.68 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 40.00 54.13 52.50 110.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 46.22 49.80 40.00 SPFS2706-055 I-270 MP 0-3 09/26/25 200.00 45.00 49.73 49.73 Weighted Average for the Third Quarter 260.00 46.50 50.71 58.25 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 275.00 28.94 114.30 50.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 400.00 75.19 134.33 133.65 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 240.00 66.19 81.17 42.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 600.00 42.67 49.48 56.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 1,515.00 52.49 79.79 73.19 Weighted Average for the Year 4,627.00 50.04 76.14 106.55 630-00007 Traf Ctrl Inspection Day NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 80.00 250.00 409.41 325.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 58.00 500.00 250.16 250.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 90.00 300.00 356.83 371.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 75.00 750.00 678.88 900.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 24.00 150.00 495.66 750.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 64.00 500.00 311.31 316.25 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 50.00 450.00 381.00 375.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 8.00 250.00 250.26 108.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 67.00 300.00 813.11 550.00 BR0761-249 I-76 02/27/25 64.00 300.00 514.83 380.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 37.00 500.00 586.37 600.00 MTCER500-233 REGION 5 03/06/25 28.00 150.00 358.33 250.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 55.00 600.00 221.89 219.40 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 60.00 500.00 470.07 324.55 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 2.00 400.00 190.33 178.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 35.00 400.00 338.00 376.00 Weighted Average for the First Quarter 797.00 416.75 444.47 419.91 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 26.00 450.00 350.00 350.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 10.00 400.00 655.00 550.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 478.00 16.00 589.19 500.00 589.17 550.00 589.17 550.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 19.00 200.00 161.33 158.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 20.00 500.00 530.50 212.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 64.00 500.00 615.00 615.00 STAR500-228 REGION 5 05/08/25 46.00 500.00 415.00 550.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00007 Traf Ctrl Inspection Day STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 32.00 133.00 392.00 351.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 28.00 1800.00 287.00 278.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 266.00 455.86 455.86 455.86 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 76.00 300.00 598.33 685.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 8.00 121.09 316.48 415.90 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 83.00 300.00 586.05 600.00 ITSSW03-250 FRONT RANGE 06/26/25 10.00 126.56 272.30 270.00 Weighted Average for the Second Quarter 1,182.00 507.60 507.69 528.84 CR400-406 REGION-WIDE 07/17/25 18.00 164.83 415.33 396.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 8.00 350.00 249.25 247.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 20.00 290.00 375.00 375.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 70.00 45.00 165.58 600.00 334.13 325.50 313.50 228.00 C0142-070 SH 14 MP 75.5-85 08/14/25 8.00 120.74 340.00 340.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 20.00 126.72 413.50 380.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 120.00 442.00 442.00 442.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 1.00 250.00 391.67 400.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 18.00 126.03 293.13 470.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 300.00 274.00 237.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 24.00 150.00 183.00 230.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 34.00 200.00 300.00 275.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 45.00 20.00 550.00 300.00 555.11 263.26 708.00 150.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 440.00 428.00 435.84 435.84 SPFS2706-055 I-270 MP 0-3 09/26/25 15.00 373.23 412.42 412.42 Weighted Average for the Third Quarter 926.00 378.28 368.47 403.30 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 86.00 420.00 286.44 90.75 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 37.00 150.61 304.44 309.75 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00007 Traf Ctrl Inspection Day STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 46.00 600.00 491.20 400.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 47.00 650.00 385.09 420.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 52.00 450.00 658.22 400.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 77.00 500.00 372.67 800.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 60.00 300.00 274.26 272.90 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 60.00 500.00 370.50 356.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 1.00 123.03 292.33 300.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 14.00 195.00 253.80 247.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 60.00 119.12 448.18 415.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 30.00 159.66 357.13 357.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 70.00 168.81 276.39 290.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 128.00 450.00 1003.20 441.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 36.00 350.00 510.50 421.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 50.00 450.00 480.26 345.00 ITSSW03-417 STATEWIDE 12/04/25 80.00 164.05 636.25 250.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 45.00 500.00 405.57 80.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 20.00 400.00 273.00 274.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 70.00 350.00 527.00 474.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 34.00 142.20 400.00 400.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 64.00 350.00 487.50 500.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 19.00 500.00 260.75 265.50 NHPP1602-194 US 160 MP 174.1 12/11/25 55.00 800.00 549.70 435.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 160.00 435.00 433.19 229.14 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 193.00 350.00 253.85 150.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 61.00 200.00 624.00 600.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 70.00 165.58 165.95 171.00 Weighted Average for the Fourth Quarter 1,725.00 370.35 438.01 334.54 Weighted Average for the Year 4,630.00 414.96 438.93 412.59 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-00012 Traf Ctrl Mgmt Day NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 155.00 1600.00 1727.88 1650.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 116.00 1750.00 1450.28 1300.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 180.00 950.00 1334.49 1191.91 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 188.00 2500.00 2142.87 3000.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 60.00 2000.00 1522.25 1400.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 128.00 2000.00 1681.04 1644.50 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 138.00 2000.00 1618.00 1600.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 40.00 1800.00 1280.86 1188.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 140.00 1600.00 1359.47 1840.00 BR0761-249 I-76 02/27/25 125.00 1600.00 1156.60 450.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 80.00 1800.00 1589.54 1200.00 MTCER500-233 REGION 5 03/06/25 66.00 1200.00 650.00 200.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 10.00 1200.00 337.50 175.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 70.00 1600.00 1648.87 1377.50 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 126.00 1500.00 2771.27 1493.94 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 10.00 1700.00 1143.33 1200.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 80.00 1200.00 1450.00 1400.00 Weighted Average for the First Quarter 1,712.00 1687.62 1574.26 1507.81 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 70.00 1750.00 1700.00 1700.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 69.00 1200.00 1556.50 1513.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 CO-82 & Catherine Store Signa 04/17/25 1,575.00 40.00 1293.09 1800.00 1296.19 1925.00 1296.19 1925.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 17.00 850.00 1383.33 1010.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 48.00 1500.00 1501.75 742.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 151.00 2500.00 1700.00 1700.00 STAR500-228 REGION 5 05/08/25 90.00 1800.00 1000.00 1400.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 45.00 550.00 1484.67 1404.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 69.00 1800.00 830.00 805.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 250.00 1413.15 1413.15 1413.15 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 152.00 1600.00 1878.33 2235.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00012 Traf Ctrl Mgmt Day C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 5.00 538.12 1316.00 1250.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 70.00 573.47 1381.25 1525.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 208.00 1200.00 1407.35 1200.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 7.00 538.27 975.00 1100.00 ITSSW03-250 FRONT RANGE 06/26/25 365.00 900.00 1330.32 1500.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 149.00 1200.00 125.00 125.00 Weighted Average for the Second Quarter 3,380.00 1328.05 1346.94 1338.92 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 60.00 1500.00 1126.33 1504.00 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 45.00 500.00 162.50 125.00 CR400-406 REGION-WIDE 07/17/25 45.00 542.78 2126.33 1914.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 30.00 1200.00 1294.50 1226.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 25.00 1200.00 1450.00 1450.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 160.00 100.00 720.11 1300.00 1264.38 1196.25 940.50 825.00 C0142-070 SH 14 MP 75.5-85 08/14/25 14.00 537.29 1156.67 1140.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 50.00 573.98 1558.75 1550.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 235.00 1602.25 1602.23 1602.23 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 200.00 1300.00 628.33 1525.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 35.00 1100.00 1311.25 1540.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 32.00 1000.00 1679.20 1446.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 30.00 1300.00 1208.40 1200.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 68.00 2000.00 1287.00 975.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 100.00 160.00 1500.00 1300.00 1560.32 1313.38 1350.00 1100.00 SPFS2706-055 I-270 MP 0-3 09/26/25 25.00 3516.85 3886.12 3886.12 Weighted Average for the Third Quarter 1,414.00 1281.69 1278.43 1325.05 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 220.00 2200.00 1874.00 1936.00 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 80.00 626.63 1859.88 1657.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00012 Traf Ctrl Mgmt Day STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 110.00 1600.00 935.01 1120.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 105.00 1200.00 1392.38 1125.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 120.00 1500.00 1569.08 1195.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 20.00 850.00 1497.47 1300.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 193.00 1700.00 1827.67 2480.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 135.00 2000.00 1791.03 1782.10 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 120.00 1500.00 1970.00 1940.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 14.00 543.46 1447.33 1800.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 47.00 770.00 1142.35 1071.40 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 144.00 850.00 2172.04 2900.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 70.00 617.17 1333.00 1156.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 160.00 1200.00 1611.80 1325.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 326.00 1400.00 2548.00 1700.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 90.00 2000.00 1585.00 1420.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 150.00 1500.00 1520.37 1700.00 ITSSW03-417 STATEWIDE 12/04/25 450.00 1500.00 2218.50 1464.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 100.00 1500.00 1718.50 1750.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 100.00 1600.00 1638.00 1645.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 47.00 574.84 1336.60 1100.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 140.00 1600.00 2462.50 1760.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 75.00 624.26 1600.00 1600.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 151.00 1700.00 1555.00 1500.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 70.00 1500.00 1252.50 1275.00 NHPP1602-194 US 160 MP 174.1 12/11/25 100.00 1900.00 1416.56 1600.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 350.00 1650.00 1524.38 2292.09 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 82.00 1300.00 1379.10 755.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 126.00 1400.00 1470.00 1500.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 130.00 720.72 1890.10 2050.00 Weighted Average for the Fourth Quarter 4,025.00 1456.59 1782.14 1703.39 Weighted Average for the Year 10,531.00 1429.41 1577.75 1503.81 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00015 Uniformed Traf Ctrl Coordination Hour NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 60.00 60.00 31.23 47.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 10.00 30.98 58.33 151.80 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 100.00 22.00 42.53 27.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 16.00 48.72 85.00 20.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 25.00 40.35 40.09 45.90 Weighted Average for the First Quarter 211.00 37.43 42.29 40.31 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 18.00 28.50 142.00 59.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 40.00 60.62 53.00 30.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 18.00 47.68 20.00 20.00 Weighted Average for the Second Quarter 76.00 49.95 68.00 34.50 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 20.00 1200.00 64.63 90.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 40.00 45.00 156.52 170.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 24.00 100.00 55.00 55.00 Weighted Average for the Fourth Quarter 84.00 335.71 117.90 118.10 Weighted Average for the Year 371.00 107.53 62.93 56.73 630-00017 Traffic Control Management (Special) Day NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 100.00 1822.08 1826.45 1826.45 Weighted Average for the Second Quarter 100.00 1822.08 1826.45 1826.45 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 400.00 1626.40 1656.19 1656.19 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 400.00 1626.40 1656.19 1656.19 Weighted Average for the Year 500.00 1665.54 1690.24 1690.24 630-00019 Uniformed Traffic Ctrl (Special) Hour BR0704-265 FBR0704-269 I-70 EAST I-70 EAST 07/24/25 100.00 400.00 268.32 308.28 Weighted Average for the Third Quarter 100.00 400.00 268.32 308.28 Weighted Average for the Year 100.00 400.00 268.32 308.28 630-00030 Courtesy Patrol Day NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 530.00 573.77 573.77 573.77 Weighted Average for the Third Quarter 530.00 573.77 573.77 573.77 Weighted Average for the Year 530.00 573.77 573.77 573.77 630-00040 Develop Traf Incident Mgmt Plan Lump Sum NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 3745.00 3813.59 3813.59 Weighted Average for the Third Quarter 1.00 3745.00 3813.59 3813.59 Weighted Average for the Year 1.00 3745.00 3813.59 3813.59 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-00041 Implement Traf Incident Mgmt Plan Month NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 24.00 2140.00 2140.00 2140.00 Weighted Average for the Third Quarter 24.00 2140.00 2140.00 2140.00 Weighted Average for the Year 24.00 2140.00 2140.00 2140.00 630-10123 Port Variable Message Sign Panel (SWZ) Month STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 64.00 1000.00 1328.74 1100.00 Weighted Average for the Fourth Quarter 64.00 1000.00 1328.74 1100.00 Weighted Average for the Year 64.00 1000.00 1328.74 1100.00 630-80001 Flash Beacon (Port) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 20.00 893.71 1522.17 1802.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 4.00 1600.00 1492.61 2000.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 4.00 1600.00 971.67 1650.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 15.00 1000.00 1125.19 695.75 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 2200.00 647.50 675.00 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 10.00 800.00 478.33 445.00 Weighted Average for the First Quarter 55.00 1055.90 1254.57 1215.93 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 6.00 1600.00 650.00 650.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 4.00 2000.00 1800.00 1800.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 10.00 864.60 1689.00 1637.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 20.00 1312.30 1544.25 1373.50 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 6.00 1800.00 12.00 12.00 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 295.00 8.00 887.32 1712.75 48.81 1712.73 52.25 1712.73 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 4.00 734.06 260.60 170.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 2.00 721.40 935.98 500.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 20.00 1712.00 1743.35 1743.35 SPFS2706-055 I-270 MP 0-3 09/26/25 12.00 382.38 39.65 39.65 Weighted Average for the Third Quarter 347.00 949.48 100.56 190.81 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 4.00 727.93 238.60 205.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 8.00 1700.00 1322.09 1000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 40.00 896.57 352.61 350.85 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 12.00 867.04 291.00 155.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 8.00 1000.00 898.65 620.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 8.00 846.92 965.90 661.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 8.00 2000.00 675.50 216.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 12.00 864.60 1305.65 403.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 20.00 1500.00 708.33 710.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 4.00 1700.00 997.50 1470.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 4.00 1600.00 1415.00 1300.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 8.00 1500.00 1410.00 1100.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 734.06 889.93 900.00 Weighted Average for the Fourth Quarter 140.00 1157.61 872.87 565.79 Weighted Average for the Year 562.00 1024.65 447.62 426.63 630-80002 Flash Beacon (Solar) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 10.00 2000.00 975.19 825.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80002 Flash Beacon (Solar) Each BR0761-249 I-76 02/27/25 2.00 670.20 1351.67 415.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 7.00 716.09 1381.07 669.70 Weighted Average for the First Quarter 19.00 1387.00 1202.08 724.63 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 17.00 2115.98 2015.20 2015.20 FBR0703-534 I-70 Weighted Average for the Second Quarter 17.00 2115.98 2015.20 2015.20 STR050A-042 FREMONT COUNTY IN R2 09/11/25 4.00 1631.28 1259.00 2785.00 Weighted Average for the Third Quarter 4.00 1631.28 1259.00 2785.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 8.00 2500.00 1677.54 1550.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 6.00 1053.44 207.00 207.00 Weighted Average for the Fourth Quarter 14.00 1880.05 1047.31 974.43 Weighted Average for the Year 54.00 1762.42 1280.81 1348.30 630-80305 Flagging Station Light Each MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 2.00 919.18 300.00 500.00 Weighted Average for the First Quarter 2.00 919.18 300.00 500.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2.00 1652.32 2580.09 1550.00 Weighted Average for the Fourth Quarter 2.00 1652.32 2580.09 1550.00 Weighted Average for the Year 4.00 1285.75 1440.04 1025.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80331 Barricade (3 F-A) (Temp) Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 6.00 236.12 140.00 220.00 Weighted Average for the Second Quarter 6.00 236.12 140.00 220.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 6.00 210.31 285.40 330.00 Weighted Average for the Fourth Quarter 6.00 210.31 285.40 330.00 Weighted Average for the Year 12.00 223.22 243.86 275.00 630-80335 Barricade (3 M-A) (Temp) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 12.00 250.00 175.03 175.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 16.00 173.97 377.67 371.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 4.00 200.00 236.08 500.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 25.00 114.02 305.12 398.48 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 6.00 150.00 197.83 54.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 12.00 160.00 137.82 89.00 BR0761-249 I-76 02/27/25 6.00 121.81 288.50 138.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 6.00 120.23 192.27 155.00 Weighted Average for the First Quarter 87.00 157.54 270.19 266.07 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 15.00 6.00 411.42 300.00 391.84 220.00 391.84 220.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 4.00 500.00 370.00 370.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 8.00 155.00 207.67 234.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 4.00 125.63 266.33 258.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 15.00 227.93 227.93 227.93 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80335 Barricade (3 M-A) (Temp) Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 3.00 85.00 90.18 15.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 10.00 200.00 178.89 180.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 3.00 113.25 67.50 60.00 ITSSW03-250 FRONT RANGE 06/26/25 6.00 187.76 89.23 60.00 Weighted Average for the Second Quarter 74.00 254.79 190.82 234.94 CR400-406 REGION-WIDE 07/17/25 11.00 177.38 85.17 82.50 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 12.00 4.00 128.60 497.25 247.07 497.24 308.28 497.24 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 4.00 139.73 90.40 75.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 5.00 112.88 59.00 38.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 4.00 194.35 275.45 210.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 40.00 374.50 381.36 381.36 Weighted Average for the Third Quarter 80.00 279.55 214.24 289.75 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 10.00 600.00 482.88 181.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.00 241.08 530.85 455.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 6.00 200.00 328.29 350.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 10.00 112.54 70.83 50.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 198.03 220.38 362.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 6.00 178.19 167.76 155.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 42.00 177.56 228.10 110.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 4.00 200.00 377.00 289.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 9.00 119.46 230.00 200.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 10.00 350.00 81.67 82.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 6.00 200.00 317.00 474.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 4.00 160.67 190.00 190.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 4.00 151.34 470.00 465.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 160.00 308.00 350.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 3.00 168.51 163.95 160.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 122.00 218.84 255.73 186.39 Weighted Average for the Year 363.00 224.86 245.08 238.16 630-80336 Barricade (3 M-B) (Temp) Each STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 4.00 500.00 85.67 12.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 3.00 200.00 320.50 315.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2.00 500.00 561.71 397.00 MTCER500-233 REGION 5 03/06/25 4.00 300.00 252.83 50.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 10.00 231.41 464.79 334.85 Weighted Average for the First Quarter 23.00 309.31 356.71 231.98 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 6.00 243.62 205.00 105.00 Weighted Average for the Second Quarter 6.00 243.62 205.00 105.00 CR400-406 REGION-WIDE 07/17/25 9.00 229.97 171.67 165.00 FBR2851-014 NHPP2851-009 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES 09/18/25 6.00 280.50 233.08 164.00 Weighted Average for the Third Quarter 15.00 250.18 203.99 164.60 NHPPR500-227 REGION 5 SECTION 7 10/23/25 6.00 250.00 307.59 310.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 8.00 400.00 340.17 150.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 4.00 241.96 373.50 320.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 8.00 224.74 363.03 270.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 4.00 400.00 554.00 948.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 242.11 307.90 425.00 Weighted Average for the Fourth Quarter 34.00 295.12 345.04 352.71 Weighted Average for the Year 78.00 286.70 316.48 261.88 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80337 Barricade (3 M-C) (Temp) Each MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 3.00 315.00 40.00 40.00 Weighted Average for the Third Quarter 3.00 315.00 40.00 40.00 Weighted Average for the Year 3.00 315.00 40.00 40.00 630-80338 Barricade (3 M-D) (Temp) Each NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 15.00 518.00 240.00 225.00 Weighted Average for the First Quarter 15.00 518.00 240.00 225.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 10.00 500.00 313.89 720.00 Weighted Average for the Second Quarter 10.00 500.00 313.89 720.00 Weighted Average for the Year 25.00 510.80 274.77 423.00 630-80340 Pedestrian Barricade (ADA) Lin Foot NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 100.00 42.99 23.56 59.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 100.00 100.00 28.33 37.00 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 20.00 100.00 48.00 45.00 Weighted Average for the First Quarter 220.00 74.09 27.95 47.73 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 150.00 75.00 13.30 13.30 C0821-113 CO-82 & Catherine Store Signa 04/17/25 6.00 100.00 77.00 77.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid NHPP0062-040 630-80340 Pedestrian Barricade (ADA) VASQUEZ BLVD - I270 TO 64TH - 05/23/25 Lin Foot 500.00 39.89 39.89 39.89 Weighted Average for the Second Quarter 656.00 48.47 34.15 34.15 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 100.00 39.44 37.50 29.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 300.00 38.68 38.67 38.67 Weighted Average for the Third Quarter 400.00 38.87 38.00 36.25 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 400.00 25.00 35.30 24.20 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 200.00 80.00 36.33 40.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 200.00 54.00 25.91 30.91 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 216.00 20.00 27.27 40.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 20.00 52.18 23.67 24.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 100.00 40.00 31.10 31.50 Weighted Average for the Fourth Quarter 1,136.00 40.64 33.05 31.81 Weighted Average for the Year 2,412.00 45.52 33.18 34.63 630-80341 Const Traf Sign (A) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 122.00 70.00 37.12 53.00 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 28.00 130.00 72.02 75.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 111.00 49.40 107.78 100.70 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 30.00 100.00 46.23 5.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 87.00 140.00 33.74 2.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 10.00 47.64 73.72 94.88 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 14.00 85.00 84.00 80.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 16.00 65.00 59.27 27.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 281.00 65.00 57.54 61.50 BR0761-249 I-76 02/27/25 20.00 150.00 91.67 75.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80341 Const Traf Sign (A) Each STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 28.00 60.00 90.15 82.00 MTCER500-233 REGION 5 03/06/25 64.00 50.00 51.14 10.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 16.00 49.66 3.00 5.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 63.00 49.73 75.41 40.80 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 144.00 51.46 76.95 61.82 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 35.00 96.00 45.33 42.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 53.00 50.00 60.15 90.30 Weighted Average for the First Quarter 1,122.00 70.45 66.23 55.34 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 328.00 100.00 94.50 94.50 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 4.00 49.35 57.50 55.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 170.00 28.00 111.69 85.00 106.36 38.00 106.36 38.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 11.00 47.70 27.33 42.50 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 2.00 100.00 71.00 53.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 22.00 130.00 25.00 25.00 STAR500-228 REGION 5 05/08/25 36.00 50.00 36.67 55.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 94.00 50.00 57.78 64.35 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 20.00 51.45 44.33 43.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 58.00 91.17 91.17 91.17 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 29.00 50.50 97.33 70.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 14.00 47.47 59.24 20.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 16.00 47.55 48.00 85.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 126.00 90.00 28.32 24.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 45.00 49.30 33.50 17.00 ITSSW03-250 FRONT RANGE 06/26/25 24.00 50.74 63.80 54.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 36.00 51.28 10.00 10.00 Weighted Average for the Second Quarter 1,063.00 84.93 58.68 70.34 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 18.00 10.00 25.00 10.00 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 21.00 50.00 25.00 25.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80341 Const Traf Sign (A) Each CR400-406 REGION-WIDE 07/17/25 33.00 49.29 57.33 55.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 8.00 28.00 50.00 50.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 8.00 62.00 45.00 45.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 36.00 44.00 51.16 49.26 51.01 75.75 47.03 69.00 C0142-070 SH 14 MP 75.5-85 08/14/25 26.00 50.63 23.67 17.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 20.00 49.80 49.50 43.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 34.00 99.45 99.45 99.45 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 8.00 20.00 36.67 15.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 5.00 46.72 46.38 35.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 15.00 47.44 33.00 25.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 14.00 47.47 25.50 20.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 23.00 51.00 57.66 85.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 6.00 12.00 69.18 47.43 45.23 56.79 54.00 50.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 500.00 101.65 103.51 103.51 SPFS2706-055 I-270 MP 0-3 09/26/25 16.00 64.51 62.22 62.22 Weighted Average for the Third Quarter 847.00 81.54 66.25 81.79 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 168.00 140.00 53.81 30.25 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 46.00 49.07 64.18 48.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 16.00 49.25 74.79 65.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 24.00 50.00 57.55 52.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 14.00 50.00 132.65 130.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 15.00 50.43 65.37 15.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 86.00 90.00 51.50 10.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 24.00 50.71 78.35 77.95 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 32.00 51.47 56.00 45.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 10.00 47.57 16.00 20.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 90.00 50.00 38.38 13.75 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 58.00 46.64 44.36 10.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80341 Const Traf Sign (A) Each STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 28.00 50.30 35.50 35.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 50.00 49.85 179.37 160.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 97.00 52.13 152.00 44.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 34.00 35.00 50.00 18.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 22.00 51.20 99.14 52.00 ITSSW03-417 STATEWIDE 12/04/25 16.00 49.66 64.00 65.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 44.00 50.00 39.35 26.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 26.00 40.00 49.08 49.25 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 10.00 47.50 49.30 49.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 37.00 50.00 78.75 105.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 32.00 51.48 52.00 52.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 24.00 80.00 88.90 88.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 44.00 50.00 20.88 21.25 NHPP1602-194 US 160 MP 174.1 12/11/25 11.00 50.00 33.69 38.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 56.00 55.00 124.53 113.44 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 25.00 50.97 72.27 152.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 20.00 55.00 84.00 80.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 66.00 51.42 71.93 72.00 Weighted Average for the Fourth Quarter 1,225.00 65.56 78.96 50.92 Weighted Average for the Year 4,257.00 74.86 69.42 63.08 630-80342 Const Traf Sign (B) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 118.00 85.00 52.73 76.50 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 107.00 66.01 161.60 116.60 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 106.00 110.00 46.23 5.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 22.00 150.00 33.74 2.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 56.00 63.59 139.22 94.88 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 80.00 120.00 101.70 100.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 16.00 75.00 82.83 38.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80342 Const Traf Sign (B) Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 74.00 80.00 2121.50 61.50 BR0761-249 I-76 02/27/25 78.00 80.00 140.43 315.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 10.00 70.00 96.93 88.00 MTCER500-233 REGION 5 03/06/25 8.00 60.00 90.63 10.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 24.00 61.65 3.00 5.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 74.00 64.73 78.81 51.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 86.00 65.36 85.89 72.12 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 30.00 98.00 45.33 42.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 138.00 60.00 62.65 95.30 Weighted Average for the First Quarter 1,027.00 80.69 249.75 88.21 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 17.00 130.00 250.50 250.50 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 42.00 65.84 90.50 61.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 55.00 16.00 129.31 115.00 123.15 55.00 123.15 55.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 45.00 64.11 41.50 85.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 41.00 110.00 112.75 212.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 53.00 150.00 25.00 25.00 STAR500-228 REGION 5 05/08/25 48.00 70.00 57.67 90.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 4.00 60.00 64.78 64.35 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 82.00 61.95 152.67 148.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 39.00 91.17 91.17 91.17 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 103.00 74.45 114.00 70.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 50.00 62.55 53.75 85.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 30.00 115.00 27.98 24.00 ITSSW03-250 FRONT RANGE 06/26/25 80.00 73.91 100.80 102.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 64.00 65.71 10.00 10.00 Weighted Average for the Second Quarter 769.00 85.66 90.10 90.46 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 78.00 10.00 26.67 10.00 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 15.00 60.00 25.00 25.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-80342 Const Traf Sign (B) Each CR400-406 REGION-WIDE 07/17/25 166.00 74.47 56.00 55.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 22.00 84.00 60.00 60.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 64.00 4.00 74.27 60.28 132.69 86.00 156.75 80.00 C0142-070 SH 14 MP 75.5-85 08/14/25 4.00 60.28 28.33 17.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 90.00 74.03 52.25 43.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 118.00 121.55 121.55 121.55 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 32.00 20.00 36.67 15.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 11.00 60.28 58.38 47.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 11.00 60.19 38.20 30.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 22.00 58.94 31.70 27.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 12.00 60.33 67.69 95.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 60.00 36.00 67.39 63.50 48.72 65.97 54.00 60.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 400.00 117.70 119.85 119.85 SPFS2706-055 I-270 MP 0-3 09/26/25 48.00 193.19 164.10 164.10 Weighted Average for the Third Quarter 1,193.00 91.20 71.33 87.61 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 43.00 185.00 51.81 30.25 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 32.00 62.47 84.13 51.50 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 30.00 62.10 99.26 90.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 10.00 60.00 59.46 47.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 48.00 70.00 122.73 130.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 25.00 64.04 34.08 45.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 26.00 100.00 53.42 10.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 54.00 64.69 100.75 100.25 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 80.00 74.05 73.50 56.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 18.00 60.85 18.00 20.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 40.00 72.00 50.65 30.80 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 94.00 60.15 50.38 10.50 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 116.00 65.50 16.00 16.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80342 Const Traf Sign (B) Each STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 50.00 64.00 230.27 205.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 163.00 74.61 223.20 55.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 118.00 45.00 56.30 19.60 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 54.00 64.66 124.75 100.00 ITSSW03-417 STATEWIDE 12/04/25 50.00 64.06 76.05 75.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 118.00 70.00 39.35 26.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 110.00 150.00 60.08 60.25 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 46.00 63.31 67.50 71.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 112.00 55.00 89.25 126.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 82.00 74.04 55.00 55.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 79.00 90.00 109.50 108.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 106.00 60.00 20.88 21.25 NHPP1602-194 US 160 MP 174.1 12/11/25 18.00 50.00 40.01 38.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 24.00 67.00 131.46 128.56 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 5.00 60.12 96.24 182.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 36.00 75.00 110.20 110.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 183.00 74.59 95.02 97.00 Weighted Average for the Fourth Quarter 1,970.00 74.38 99.95 64.77 Weighted Average for the Year 4,959.00 81.48 131.82 79.10 630-80343 Const Traf Sign (C) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 10.00 76.93 191.87 127.20 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 6.00 73.52 175.88 107.53 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 8.00 77.14 3.00 5.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 6.00 73.50 89.03 81.65 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 26.00 74.02 97.43 82.42 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 2.00 100.00 45.33 42.00 Weighted Average for the First Quarter 58.00 75.74 121.88 80.59 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80343 Const Traf Sign (C) Each STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 16.00 74.36 143.00 66.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 40.00 180.00 25.00 25.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 6.00 73.56 183.33 178.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 3.00 91.17 91.17 91.17 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 24.00 74.60 10.00 10.00 Weighted Average for the Second Quarter 89.00 122.42 80.25 40.87 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 8.00 10.00 26.67 10.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 4.00 45.00 50.13 51.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 16.00 20.00 36.67 15.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 8.00 77.15 39.20 30.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 5.00 73.57 38.90 38.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 18.00 78.05 84.52 140.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 15.00 128.40 130.75 130.75 SPFS2706-055 I-270 MP 0-3 09/26/25 4.00 2246.56 1711.04 1711.04 Weighted Average for the Third Quarter 78.00 177.98 84.56 157.43 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 300.00 57.56 30.25 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 15.00 79.79 108.57 50.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 5.00 110.00 65.25 10.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 8.00 77.12 111.95 111.40 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 4.00 73.44 24.00 20.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 10.00 79.10 277.30 250.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 8.00 77.06 294.60 66.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 12.00 76.91 72.10 71.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 56.00 60.00 94.75 137.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 12.00 100.00 119.50 118.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 73.49 276.02 275.00 Weighted Average for the Fourth Quarter 136.00 76.78 137.29 116.95 Weighted Average for the Year 361.00 109.73 113.66 101.10 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80344 Const Traf Sign (Spec) Sq Foot BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 300.00 80.00 25.55 28.46 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 40.00 30.00 31.64 30.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 52.00 20.00 62.50 100.00 Weighted Average for the First Quarter 392.00 66.94 28.84 38.11 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 144.00 45.00 48.40 48.40 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 320.00 192.00 64.67 100.00 105.30 25.00 105.30 25.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 48.00 28.49 28.49 28.49 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 96.00 30.00 26.73 36.00 Weighted Average for the Second Quarter 800.00 63.28 52.48 62.86 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 48.00 27.63 71.82 71.82 Weighted Average for the Third Quarter 48.00 27.63 71.82 71.82 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 600.00 37.00 22.80 24.20 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 32.00 30.54 36.90 33.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 98.00 25.00 24.08 20.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 80.00 35.00 39.98 45.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 100.00 40.00 36.33 50.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 200.00 23.05 28.15 21.30 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 820.00 27.21 114.00 33.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 40.00 30.00 34.05 32.10 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 104.00 25.00 19.16 25.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 32.00 40.00 26.30 31.60 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 560.00 35.00 36.50 36.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 64.00 25.00 15.70 16.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80344 Const Traf Sign (Spec) Sq Foot STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 128.00 38.00 27.18 18.26 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 140.00 27.75 25.56 61.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 60.00 30.00 46.20 35.00 Weighted Average for the Fourth Quarter 3,058.00 31.45 55.53 31.56 Weighted Average for the Year 4,298.00 40.57 52.88 38.43 630-80348 Const Info Sign Each STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 4.00 118.28 86.02 75.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 500.00 127.00 125.00 Weighted Average for the First Quarter 6.00 245.52 91.14 91.67 STR050A-042 FREMONT COUNTY IN R2 09/11/25 8.00 120.32 199.95 560.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4.00 100.00 260.38 200.00 Weighted Average for the Third Quarter 12.00 113.54 226.81 440.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 101.89 123.13 122.50 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2.00 287.59 196.00 270.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 6.00 146.91 227.93 155.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 8.00 196.17 124.00 124.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 250.00 2753.00 506.00 Weighted Average for the Fourth Quarter 20.00 186.49 425.19 185.95 Weighted Average for the Year 38.00 172.78 251.77 251.29 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-80350 Vert Panel Each STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 20.00 31.33 59.27 75.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 200.00 30.86 55.25 53.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 220.00 60.00 46.63 50.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 50.00 70.00 26.94 22.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 6.00 35.12 33.91 44.28 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 50.00 40.00 41.49 38.00 BR0761-249 I-76 02/27/25 30.00 70.00 65.75 42.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 15.00 60.00 270.04 44.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 75.00 45.38 3.00 5.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 100.00 34.74 38.06 40.80 Weighted Average for the First Quarter 766.00 46.46 50.80 42.74 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 CO-82 & Catherine Store Signa 04/17/25 100.00 90.00 58.79 60.00 55.98 27.00 55.98 27.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 50.00 40.00 44.00 37.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 20.00 30.00 38.32 40.95 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 60.00 36.02 37.33 31.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 50.00 51.28 51.28 51.28 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 150.00 32.53 35.33 25.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 50.00 33.15 38.50 85.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 20.00 33.31 21.00 17.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 150.00 45.36 5.00 5.00 Weighted Average for the Second Quarter 740.00 44.07 35.26 32.72 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 26.00 10.00 15.00 10.00 CR400-406 REGION-WIDE 07/17/25 60.00 35.54 19.72 18.15 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 50.00 35.55 39.13 40.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 30.00 45.99 47.50 40.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 220.00 27.63 27.62 27.62 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 50.00 35.62 20.00 15.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80350 Vert Panel Each MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 12.00 31.03 29.38 35.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 33.31 15.20 12.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 20.00 33.31 15.90 6.50 STR050A-042 FREMONT COUNTY IN R2 09/11/25 36.00 52.43 43.46 49.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 60.00 53.50 54.48 54.48 Weighted Average for the Third Quarter 584.00 34.61 29.90 29.45 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 45.00 33.23 44.68 49.50 NHPPR500-227 REGION 5 SECTION 7 10/23/25 60.00 30.00 49.95 39.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 10.00 40.00 194.19 50.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 50.00 35.55 18.23 10.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 100.00 45.00 34.17 50.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 100.00 35.43 55.98 55.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 20.00 32.91 45.75 36.50 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 150.00 31.11 3.50 3.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 50.00 35.58 42.66 29.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 25.00 32.46 59.00 22.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 240.00 40.00 17.70 9.65 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 460.00 50.00 37.78 38.35 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 100.00 35.42 37.20 33.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 220.00 35.00 43.20 35.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 100.00 35.53 44.23 44.20 Weighted Average for the Fourth Quarter 1,730.00 39.78 38.98 31.66 Weighted Average for the Year 3,820.00 41.16 40.89 33.75 630-80351 Vert Panel (Plastic) Each C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 5.00 27.99 26.18 15.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 5.00 27.99 26.18 15.00 Weighted Average for the Year 5.00 27.99 26.18 15.00 630-80354 Vert Panel (Light) (SB) Each SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 30.00 52.65 72.50 60.50 Weighted Average for the Fourth Quarter 30.00 52.65 72.50 60.50 Weighted Average for the Year 30.00 52.65 72.50 60.50 630-80355 Port Mesg Panel Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 8.00 6000.00 6546.91 9420.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 5191.79 12713.33 13780.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 2.00 10000.00 7917.28 20000.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 4.00 150.00 5576.67 6500.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 4.00 5200.09 8645.00 13915.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 8000.00 13175.00 14000.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 6000.00 3453.93 1620.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 8.00 6000.00 8510.10 7500.00 BR0761-249 I-76 02/27/25 3.00 12000.00 8761.67 4000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2.00 10000.00 8015.40 4000.00 MTCER500-233 REGION 5 03/06/25 2.00 6000.00 5958.33 1000.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 2.00 5105.07 1000.00 1000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 4.00 5172.24 8948.34 7140.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 5.00 5518.20 17373.00 11848.48 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 2.00 9600.00 2900.00 2500.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 2.00 6000.00 11145.00 12290.00 Weighted Average for the First Quarter 56.00 6140.31 8840.74 8656.47 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80355 Port Mesg Panel Each STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 4.00 5000.00 5650.00 5650.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 4.00 5247.14 6825.00 7150.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 10.00 2.00 19984.02 3600.00 19032.42 3960.00 19032.42 3960.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 3.00 1000.00 2251.67 2120.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 2.00 12000.00 6957.50 4505.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 2.00 15000.00 15000.00 15000.00 STAR500-228 REGION 5 05/08/25 2.00 8200.00 6713.33 7500.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 6.00 5000.00 4200.00 4680.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 10.00 8000.00 8858.67 8568.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6.00 10826.61 10826.61 10826.61 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 12.00 9200.00 8883.33 4750.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 2.00 5116.03 3012.50 3800.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 4.00 9500.00 5863.61 13600.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 2.00 5117.37 1565.00 1130.00 ITSSW03-250 FRONT RANGE 06/26/25 2.00 5118.41 9799.00 9500.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 2.00 5105.60 500.00 500.00 Weighted Average for the Second Quarter 75.00 9142.71 7658.86 8397.25 CR400-406 REGION-WIDE 07/17/25 4.00 5267.93 7238.33 6215.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 2.00 20000.00 3311.50 3336.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 2.00 6600.00 7500.00 7500.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 4.00 2.00 5268.28 5105.60 15788.13 6653.75 15152.50 4546.00 C0142-070 SH 14 MP 75.5-85 08/14/25 2.00 5105.60 1873.33 1320.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 18453.50 18453.29 18453.29 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 2.00 5112.57 2833.33 5500.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2.00 5116.89 3410.00 3030.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 5105.07 2641.40 2700.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 2.00 5103.09 7480.00 8225.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 2.00 5000.00 9517.60 7000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80355 Port Mesg Panel Each NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4.00 5250.59 8152.13 6000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 7.00 18190.00 18523.14 18523.14 SPFS2706-055 I-270 MP 0-3 09/26/25 2.00 5287.03 5842.17 5842.17 Weighted Average for the Third Quarter 41.00 8840.39 8028.67 9122.85 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 20000.00 12387.50 6050.00 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 2.00 5118.93 8390.00 8950.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.00 5037.40 6257.41 5100.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 2.00 5500.00 6193.75 6385.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 2.00 6000.00 17924.44 8500.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 2.00 12000.00 2444.87 1500.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 4.00 10000.00 7896.67 3000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 5115.11 10690.25 10637.05 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 4.00 5269.61 4175.00 420.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 2.00 20000.00 1192.33 1800.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 4.00 5600.00 6531.15 7122.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 6.00 5191.26 9442.80 6250.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 4.00 5089.47 7500.00 7500.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 11.00 5628.22 14205.00 11025.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 2.00 10000.00 13790.00 11580.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 5.00 5596.59 8115.50 8700.00 ITSSW03-417 STATEWIDE 12/04/25 2.00 5115.11 9944.75 5500.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 9000.00 6306.17 5300.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 8.00 12000.00 6111.67 6135.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 2.00 5118.93 3128.60 1650.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 4.00 8000.00 13845.00 17690.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 2.00 5120.81 7300.00 7300.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2.00 15000.00 14890.00 15000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 3.00 10000.00 6257.50 6375.00 NHPP1602-194 US 160 MP 174.1 12/11/25 2.00 5000.00 13204.78 10000.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 4.00 8800.00 14534.16 5445.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 4.00 5272.11 7756.50 10920.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80355 Port Mesg Panel Each BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 2.00 5000.00 12500.00 15000.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 5269.30 8815.99 8750.00 Weighted Average for the Fourth Quarter 99.00 7621.17 9567.06 7726.99 Weighted Average for the Year 271.00 7920.71 8769.71 8315.74 630-80356 Flash Arrow Panel (A Ty) Each SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 2.00 2000.00 1811.80 864.00 Weighted Average for the First Quarter 2.00 2000.00 1811.80 864.00 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 1.00 1316.65 2150.00 1100.00 Weighted Average for the Second Quarter 1.00 1316.65 2150.00 1100.00 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 2.00 1000.00 478.67 500.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 4.00 1252.14 1048.70 412.50 Weighted Average for the Fourth Quarter 6.00 1168.09 917.15 441.67 Weighted Average for the Year 9.00 1369.47 1247.19 608.67 630-80357 Flash Arrow Panel (B Ty) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 4.00 2000.00 2211.53 2060.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 2.00 1700.00 2508.00 2600.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 5.00 2500.00 2256.12 2800.00 MTCER500-233 REGION 5 03/06/25 2.00 5000.00 1016.83 1.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80357 Flash Arrow Panel (B Ty) Each NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 2.00 1059.06 2684.93 1840.00 Weighted Average for the First Quarter 15.00 2401.21 2053.93 2074.80 C0821-113 CO-82 & Catherine Store Signa 04/17/25 2.00 2200.00 1100.00 1100.00 Weighted Average for the Second Quarter 2.00 2200.00 1100.00 1100.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 1.00 1052.82 2120.00 1180.00 Weighted Average for the Third Quarter 1.00 1052.82 2120.00 1180.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 2.00 1500.00 2431.75 885.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2.00 2000.00 3172.50 2000.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 4.00 1000.00 1434.70 258.50 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 2.00 1063.20 1800.00 1800.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 4.00 2830.00 10471.90 27225.00 Weighted Average for the Fourth Quarter 14.00 1746.17 4720.58 8521.71 Weighted Average for the Year 32.00 2059.92 3115.04 4806.44 630-80358 Flash Arrow Panel (C Ty) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 6.00 1240.26 2538.67 1272.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 2.00 3500.00 4460.37 10000.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 4.00 1189.59 2043.75 2530.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 2000.00 2848.00 2800.00 BR0761-249 I-76 02/27/25 2.00 1143.89 4313.33 1650.00 MTCER500-233 REGION 5 03/06/25 2.00 3000.00 1058.33 100.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 2.00 1148.60 550.00 1000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 4.00 1172.47 2684.93 1840.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80358 Flash Arrow Panel (C Ty) Each NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 3.00 1141.64 3124.50 2472.73 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 1.00 2700.00 312.67 278.00 Weighted Average for the First Quarter 28.00 1592.85 2623.13 2282.44 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 1.00 3200.00 2350.00 2350.00 NHPP0703-517 FBR0703-534 NHPP0703-536 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 DILLON TO EJMT MM 204 TO 04/11/25 05/08/25 4.00 2.00 2938.82 6000.00 2798.89 4900.00 2798.89 4900.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 3.00 800.00 2753.67 2661.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 1.00 5470.29 5470.28 5470.28 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 6.00 1256.34 4273.33 2120.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 4.00 1154.04 1215.75 1500.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 2.00 2500.00 3157.05 4600.00 ITSSW03-250 FRONT RANGE 06/26/25 2.00 1154.04 3587.40 3000.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 4.00 1254.52 500.00 500.00 Weighted Average for the Second Quarter 29.00 2045.03 2919.19 2507.55 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 1.00 1000.00 1416.67 1000.00 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 2.00 1200.00 400.00 500.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 1.00 1900.00 3000.00 3000.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 2.00 2.00 1156.48 1148.60 3304.95 3112.25 4174.78 1705.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 2.00 1157.61 1679.50 1650.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 2044.25 2044.23 2044.23 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 1.00 1136.73 566.67 700.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 1140.11 2086.00 1790.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 1148.60 729.90 700.00 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 2.00 5.00 2000.00 2675.00 1212.60 2724.00 315.00 2724.00 SPFS2706-055 I-270 MP 0-3 09/26/25 2.00 1271.07 1404.54 1404.54 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 25.00 1632.20 1821.68 1803.88 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 8000.00 6980.00 2420.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 2.00 1154.04 1201.60 800.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 1160.35 2518.64 2506.10 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 4.00 1400.00 1532.65 258.50 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2.00 1188.67 2977.54 4150.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 2.00 1159.34 12966.20 2756.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 2.00 3000.00 3240.00 2980.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 2.00 1150.88 3096.25 2300.00 ITSSW03-417 STATEWIDE 12/04/25 2.00 1160.35 3013.75 2500.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 4.00 3000.00 2278.10 2700.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 4.00 3000.00 1910.00 1915.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 2500.00 5460.00 3420.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2.00 3000.00 1900.00 1900.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2.00 3500.00 2607.50 2655.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 2.00 1500.00 1916.00 750.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 1206.30 1322.23 1312.00 Weighted Average for the Fourth Quarter 40.00 2284.31 3508.06 2075.41 SHER100-414 630-80359 Weighted Average for the Year Port Mesg Panel SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 122.00 Day 20.00 1935.11 68.58 2808.79 137.50 2170.00 165.00 Weighted Average for the Third Quarter 20.00 68.58 137.50 165.00 Weighted Average for the Year 20.00 68.58 137.50 165.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-80360 Drum Channel Dev Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 150.00 50.00 29.34 53.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 75.00 27.01 60.05 58.30 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 100.00 100.00 41.63 25.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 50.00 50.00 27.27 23.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 250.00 36.93 44.76 44.28 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 200.00 35.00 45.75 45.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 100.00 35.00 45.33 38.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 300.00 46.00 35.60 22.50 BR0761-249 I-76 02/27/25 50.00 33.94 74.92 45.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 10.00 35.00 58.21 50.00 MTCER500-233 REGION 5 03/06/25 58.00 30.00 22.31 1.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 40.00 29.80 3.00 5.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 70.00 27.62 46.65 40.80 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 350.00 40.89 52.80 46.36 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 10.00 45.00 24.33 23.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 150.00 35.00 30.05 30.10 Weighted Average for the First Quarter 1,963.00 42.02 43.49 37.41 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 160.00 60.00 37.50 37.50 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 36.00 34.90 21.50 17.00 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET 04/11/25 I-70 CO-82 & Catherine Store Signa 04/17/25 180.00 90.00 64.67 60.00 61.57 27.00 61.57 27.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 75.00 24.19 23.58 53.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 50.00 75.00 36.50 53.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 200.00 60.00 37.00 37.00 STAR500-228 REGION 5 05/08/25 25.00 50.00 35.33 45.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 25.00 25.00 41.98 40.95 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 200.00 36.63 43.67 42.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 150.00 51.28 51.28 51.28 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 300.00 42.58 35.33 25.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 7.00 100.00 34.30 25.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid NHPP0501-080 630-80360 Drum Channel Dev SH50A MP 89.93 CEADAR CREEK 06/12/25 Each 300.00 60.00 46.76 24.00 Weighted Average for the Second Quarter 1,798.00 52.19 40.81 37.41 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 26.00 20.00 18.33 10.00 CR400-406 REGION-WIDE 07/17/25 75.00 31.40 25.92 24.75 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 100.00 35.54 39.63 42.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 165.00 38.00 25.00 25.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 320.00 60.00 35.26 75.00 46.76 81.75 47.03 86.00 C0142-070 SH 14 MP 75.5-85 08/14/25 30.00 46.09 27.67 12.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 90.00 49.73 49.72 49.72 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 40.00 29.37 20.00 15.00 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 5.00 28.08 50.75 47.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 15.00 31.35 14.40 10.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 25.00 28.10 20.00 8.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 50.00 200.00 15.00 32.73 40.69 73.18 38.00 75.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 600.00 58.85 59.93 59.93 SPFS2706-055 I-270 MP 0-3 09/26/25 34.00 121.85 70.64 70.64 Weighted Average for the Third Quarter 1,835.00 45.55 53.10 50.10 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 350.00 75.00 24.54 18.15 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 35.00 21.67 45.80 58.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 50.00 38.37 26.07 22.50 NHPPR500-227 REGION 5 SECTION 7 10/23/25 20.00 35.00 53.40 39.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 60.00 40.00 103.11 65.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 25.00 31.49 20.80 10.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 200.00 50.00 36.25 50.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 150.00 43.03 55.98 55.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 40.00 41.26 50.50 46.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80360 Drum Channel Dev Each MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 100.00 33.35 16.50 15.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 193.00 34.00 39.90 6.60 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 100.00 23.04 35.34 10.50 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 150.00 29.15 6.00 6.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 300.00 29.22 47.00 33.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 451.00 32.69 78.60 55.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 100.00 35.00 30.05 29.10 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 90.00 30.93 48.30 52.00 ITSSW03-417 STATEWIDE 12/04/25 10.00 50.50 66.75 75.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 150.00 35.00 23.36 26.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 60.00 60.00 37.78 38.35 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 200.00 25.00 42.05 31.60 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 50.00 19.32 62.00 62.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 100.00 60.00 25.70 25.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 25.00 35.00 41.70 42.50 NHPP1602-194 US 160 MP 174.1 12/11/25 20.00 40.00 33.57 25.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 430.00 35.00 26.42 66.55 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 35.00 32.35 59.35 79.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 90.00 45.00 52.40 40.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 300.00 30.72 46.31 46.00 Weighted Average for the Fourth Quarter 3,884.00 38.55 45.69 38.90 Weighted Average for the Year 9,480.00 43.21 45.80 40.48 630-80363 Drum Channel Dev (Light) (F) Each NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 50.00 120.00 41.63 25.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 50.00 40.21 54.88 56.93 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 20.00 45.00 61.00 60.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 50.00 75.00 35.47 24.65 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 4.00 100.00 98.60 115.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-80363 Drum Channel Dev (Light) (F) Each NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 10.00 35.41 60.48 45.90 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 10.00 40.00 32.55 35.10 Weighted Average for the First Quarter 194.00 71.21 46.24 40.20 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 10.00 60.00 61.00 61.00 STAR500-228 REGION 5 05/08/25 25.00 65.00 60.00 75.00 Weighted Average for the Second Quarter 35.00 63.57 60.12 71.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 25.00 55.25 55.25 55.25 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 2.00 48.89 23.33 15.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 50.00 33.13 73.15 98.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 77.00 40.72 70.50 81.96 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 100.00 80.00 28.29 18.15 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 15.00 35.29 69.91 65.25 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 10.00 45.00 137.08 75.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 25.00 38.83 23.00 10.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4.00 36.63 76.40 66.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 60.00 40.00 51.60 67.20 ITSSW03-417 STATEWIDE 12/04/25 5.00 41.24 88.55 125.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 25.00 35.00 24.56 26.50 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 20.00 70.00 43.58 43.75 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 20.00 45.00 44.70 36.90 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 10.00 33.03 70.00 70.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 70.00 30.85 30.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 25.00 35.00 62.20 63.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 25.00 35.00 64.40 45.00 Weighted Average for the Fourth Quarter 364.00 53.18 48.54 41.18 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Year 670.00 57.51 50.90 47.14 630-80364 Drum Channel Dev (Light) (SB) Each NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 50.00 120.00 41.63 25.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 20.00 45.00 61.00 60.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 20.00 37.36 3.00 5.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 25.00 40.00 32.55 35.10 Weighted Average for the First Quarter 115.00 75.19 38.41 29.80 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 8.00 70.00 48.75 80.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 10.00 60.00 61.00 61.00 STAR500-228 REGION 5 05/08/25 25.00 65.00 57.00 70.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 40.00 75.00 57.65 48.00 Weighted Average for the Second Quarter 83.00 69.70 56.57 59.28 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 50.00 55.25 55.25 55.25 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 16.00 37.45 23.33 15.00 Weighted Average for the Third Quarter 66.00 50.94 39.62 45.49 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 50.00 80.00 28.79 18.15 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 50.00 43.81 55.34 49.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 8.00 65.00 79.11 78.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 10.00 50.00 137.08 75.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 100.00 60.00 43.00 50.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 15.00 37.39 72.76 72.40 MTCER200-297 REGION 2 EL PASO COUNTY COLOR 11/13/25 28.00 36.00 20.50 15.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 100.00 42.42 64.66 21.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 200.00 43.49 76.09 55.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 20.00 37.38 76.40 66.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 80.00 45.00 50.60 65.20 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80364 Drum Channel Dev (Light) (SB) Each STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 25.00 35.00 26.56 26.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 20.00 50.00 44.70 36.90 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 20.00 80.00 30.85 30.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 25.00 35.00 62.20 63.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 200.00 45.00 54.35 96.80 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 50.00 45.00 64.40 45.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 150.00 43.49 75.14 75.00 Weighted Average for the Fourth Quarter 1,151.00 47.08 60.88 58.48 Weighted Average for the Year 1,415.00 50.87 58.52 55.59 630-80367 Port Traf Speed Monitor Each NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 2.00 9000.00 3333.26 10000.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 4000.00 5894.50 3000.00 Weighted Average for the First Quarter 4.00 6500.00 4065.04 6500.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 2.00 12000.00 4900.00 4900.00 Weighted Average for the Second Quarter 2.00 12000.00 4900.00 4900.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 2.00 10221.25 10221.14 10221.14 Weighted Average for the Third Quarter 2.00 10221.25 10221.14 10221.14 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 2500.00 3782.50 605.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 2.00 4000.00 7610.00 7220.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 3500.00 4527.50 8530.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 2.00 6000.00 7175.00 6700.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 2.00 3500.00 6960.00 5000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 10.00 3900.00 5903.67 5611.00 Weighted Average for the Year 18.00 6080.14 5505.48 6241.79 630-80370 Barrier (Temp) Lin Foot 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 3,520.00 45.00 61.42 49.52 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 1,000.00 100.00 230.06 60.00 BR0761-249 I-76 02/27/25 2,000.00 42.06 59.62 60.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 150.00 200.00 150.89 70.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1,400.00 80.00 105.10 51.10 Weighted Average for the First Quarter 8,070.00 60.04 86.69 54.07 NHPP0703-517 FBR0703-534 STAR500-223 I-70 TOP OF FLOYD HILL TO VET I-70 SH50 MM 189.71, US550 MM 98.3 04/11/25 05/01/25 38,432.00 150.00 96.29 100.00 92.49 189.00 92.49 96.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 200.00 100.00 410.00 410.00 Weighted Average for the Second Quarter 38,782.00 96.33 95.58 94.14 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 500.00 46.09 46.09 46.09 CR400-406 REGION-WIDE 07/17/25 260.00 240.00 72.00 110.00 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 2,750.00 1,140.00 67.70 70.37 80.87 84.55 68.47 84.55 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 523.00 95.00 101.32 115.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 2,520.00 60.00 40.25 46.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 100.00 54.70 67.50 52.00 FBR2851-014 NHPP2851-009 STR025A-054 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25C NORTH OUT OF WALSENBURG 09/18/25 09/18/25 1,600.00 2,000.00 92.45 55.12 82.02 54.54 60.00 15.00 SPFS2706-055 I-270 MP 0-3 09/26/25 3,480.00 106.74 117.83 117.83 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Third Quarter 14,873.00 79.86 66.98 70.84 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 4,500.00 100.00 79.02 30.50 NHPPR500-227 REGION 5 SECTION 7 10/23/25 400.00 85.00 170.63 95.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 600.00 100.00 166.41 200.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 5,740.00 65.00 37.28 35.20 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,900.00 110.00 43.25 25.50 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4,186.00 54.77 86.06 124.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1,000.00 80.00 71.00 100.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 1,000.00 49.95 90.01 95.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2,000.00 80.00 59.15 84.30 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 600.00 100.00 32.40 31.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1,500.00 65.00 115.00 100.00 Weighted Average for the Fourth Quarter 23,426.00 76.96 82.13 68.17 Weighted Average for the Year 85,151.00 84.68 81.59 79.13 630-80371 Reset Concrete Barrier (Temp) Lin Foot STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 8,450.00 20.40 20.40 20.40 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 950.00 13.01 6.46 5.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 136,479.00 4.52 5.34 5.34 Weighted Average for the Third Quarter 145,879.00 5.50 6.23 6.21 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1,800.00 11.56 24.50 28.00 Weighted Average for the Fourth Quarter 1,800.00 11.56 24.50 28.00 Weighted Average for the Year 147,679.00 5.57 6.65 6.48 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80372 Conc Barrier (Temp) (Furnish & Install) Lin Foot NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 5,800.00 70.37 70.37 70.37 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 855.00 160.00 104.58 82.00 Weighted Average for the Second Quarter 6,655.00 81.89 83.06 71.86 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 500.00 120.00 113.28 133.10 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1,000.00 120.00 83.52 120.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 800.00 178.49 63.00 63.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 400.00 110.00 400.87 102.85 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 455.00 66.16 47.22 45.00 Weighted Average for the Fourth Quarter 3,155.00 125.80 105.92 94.63 Weighted Average for the Year 9,810.00 96.01 95.77 79.19 630-80377 Port Water Filled Barrier (Temp) Lin Foot STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 400.00 50.00 55.05 35.10 Weighted Average for the First Quarter 400.00 50.00 55.05 35.10 NHPP0501-071 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-80378 Glare Screen (Temp) Lin Foot NHPP0703-517 FBR0703-534 I-70 TOP OF FLOYD HILL I-70 TO VET 04/11/25 5,832.00 26.11 32.73 32.73 Weighted Average for the Second Quarter 5,832.00 26.11 32.73 32.73 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 500.00 25.48 22.32 22.32 Weighted Average for the Third Quarter 500.00 25.48 22.32 22.32 Weighted Average for the Year 6,332.00 26.06 31.91 31.91 630-80380 Traffic Cone Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 400.00 15.00 15.22 17.65 STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 40.00 9.47 10.91 10.00 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 60.00 8.61 19.07 15.90 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 200.00 20.00 18.11 2.00 STM0132-025 CO13 MM 90.2, US40Z MM 0.65, 01/30/25 100.00 20.00 9.33 2.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 300.00 9.10 19.68 18.98 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 500.00 15.00 15.25 15.00 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 100.00 12.00 14.11 11.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 250.00 15.00 2252.80 11.50 BR0761-249 I-76 02/27/25 50.00 15.00 25.43 15.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 30.00 15.00 23.70 13.00 MTCER500-233 REGION 5 03/06/25 44.00 12.00 13.46 1.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 350.00 8.69 5.00 5.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 633.00 9.40 25.48 15.30 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 175.00 8.47 13.92 15.45 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 50.00 18.00 8.83 8.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 300.00 10.00 12.50 10.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 3,582.00 12.33 208.49 12.54 STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 100.00 17.00 12.15 12.15 NHPP0703-517 FBR0703-534 C0821-113 I-70 TOP OF FLOYD HILL TO VET I-70 CO-82 & Catherine Store Signa 04/11/25 04/17/25 100.00 30.00 17.62 15.00 16.80 16.00 16.80 16.00 STM2873-232 SH287 & LCR 72 AND US287 & OW 04/24/25 100.00 20.00 7.73 10.50 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 25.00 15.00 13.38 5.50 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 200.00 20.00 1.50 1.50 STAR500-228 REGION 5 05/08/25 100.00 10.00 9.00 14.00 STMM153-003 CO 17 & SOUTH OF CO 14 05/08/25 100.00 8.00 10.84 10.53 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 300.00 10.48 17.67 17.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 50.00 11.40 11.40 11.40 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 300.00 12.07 12.00 8.00 C0405-042 US 40 IN DEER TRAIL, PINE ST 06/05/25 20.00 10.40 7.46 5.00 MTCE0361-135 US-36B FROM MP 0.00-33.76 IN 06/05/25 500.00 7.00 11.50 25.00 ER060A-028 CO 60 (MP 9-10) 06/18/25 50.00 9.35 15.50 6.00 ITSSW03-250 FRONT RANGE 06/26/25 300.00 8.61 16.08 18.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 500.00 8.52 5.00 5.00 Weighted Average for the Second Quarter 2,775.00 10.97 12.36 13.04 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 250.00 10.00 8.33 10.00 MTCE0402-112 REGION 3 STENCIL PROJECT ON H 07/03/25 200.00 10.00 3.00 5.00 CR400-406 REGION-WIDE 07/17/25 75.00 8.31 10.78 9.35 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 100.00 10.35 11.25 11.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 50.00 25.00 12.00 12.00 CR400-400 VARIOUS LOCATIONS THROUGHOUT 08/14/25 100.00 8.55 40.75 6.00 C0142-070 SH 14 MP 75.5-85 08/14/25 30.00 8.88 7.67 10.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 100.00 7.88 11.55 13.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 200.00 11.05 11.05 11.05 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 250.00 8.00 6.67 5.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 20.00 9.84 8.60 6.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 50.00 9.30 9.15 6.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 50.00 10.30 21.24 15.00 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 20.00 10.00 22.19 5.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80380 Traffic Cone Each NHPP2851-009 US 285 CONEJOS RIVER BRIDGES STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 500.00 8.34 9.67 10.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 600.00 16.05 16.34 16.34 SPFS2706-055 I-270 MP 0-3 09/26/25 200.00 35.84 34.71 34.71 Weighted Average for the Third Quarter 2,795.00 12.83 11.99 12.37 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 200.00 24.00 6.51 6.05 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 130.00 8.61 29.21 46.25 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 100.00 9.09 4.21 3.25 NHPPR500-227 REGION 5 SECTION 7 10/23/25 60.00 10.00 24.17 13.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 60.00 10.00 39.87 25.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 200.00 8.97 14.20 10.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 200.00 10.00 13.67 15.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 300.00 11.11 16.79 16.70 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 450.00 9.95 15.13 8.25 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 300.00 10.00 28.33 6.16 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 200.00 9.58 12.59 1.10 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 300.00 7.74 5.50 5.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 100.00 10.56 25.16 18.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 175.00 8.85 27.60 10.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 200.00 15.00 7.00 4.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 200.00 10.04 15.77 13.00 ITSSW03-417 STATEWIDE 12/04/25 300.00 8.97 11.25 10.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 200.00 10.00 12.53 15.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 100.00 20.00 16.50 16.50 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 300.00 5.00 18.38 10.50 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 200.00 7.19 45.00 45.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 300.00 25.00 10.30 10.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 500.00 10.00 1.53 1.05 NHPP1602-194 US 160 MP 174.1 12/11/25 40.00 10.00 10.52 20.00 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 30.00 10.12 19.60 25.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 200.00 10.00 12.40 5.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 400.00 8.78 14.25 14.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 5,745.00 10.94 15.39 11.43 Weighted Average for the Year 14,897.00 11.63 63.75 12.18 CR400-406 630-80384 Tubular Marker REGION-WIDE 07/17/25 Each 75.00 29.70 14.58 13.75 Weighted Average for the Third Quarter 75.00 29.70 14.58 13.75 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 78.00 200.00 88.75 50.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 200.00 25.15 29.32 10.50 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 500.00 37.74 63.13 37.00 Weighted Average for the Fourth Quarter 778.00 50.77 62.67 31.49 Weighted Average for the Year 853.00 48.92 59.66 29.93 630-80390 Channel Dev (Spec) Each NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 200.00 75.00 26.33 36.30 Weighted Average for the Fourth Quarter 200.00 75.00 26.33 36.30 Weighted Average for the Year 200.00 75.00 26.33 36.30 630-80391 Channel Dev (Fixed) Each NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 368.00 44.05 40.60 44.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 368.00 44.05 40.60 44.00 Weighted Average for the Year 368.00 44.05 40.60 44.00 630-80392 Stackable Tubular Marker Each NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 20.00 23.51 31.10 27.50 Weighted Average for the Fourth Quarter 20.00 23.51 31.10 27.50 Weighted Average for the Year 20.00 23.51 31.10 27.50 630-80393 Stackable Vertical Panels Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 200.00 40.00 27.37 49.45 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 12.00 45.00 48.25 50.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 50.00 28.91 51.55 46.36 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 20.00 18.00 16.33 15.00 Weighted Average for the First Quarter 282.00 36.69 32.66 46.48 ITSSW03-250 FRONT RANGE 06/26/25 200.00 29.14 52.70 54.00 Weighted Average for the Second Quarter 200.00 29.14 52.70 54.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 20.00 29.25 33.13 38.00 Weighted Average for the Third Quarter 20.00 29.25 33.13 38.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 100.00 29.16 44.01 23.00 ITSSW03-417 STATEWIDE 12/04/25 50.00 29.30 45.18 45.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Fourth Quarter 150.00 29.20 44.40 30.33 Weighted Average for the Year 652.00 32.42 43.24 44.81 630-80401 Delin (Ty I) (Temp) Each NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 45.00 28.00 121.73 66.00 Weighted Average for the Second Quarter 45.00 28.00 121.73 66.00 Weighted Average for the Year 45.00 28.00 121.73 66.00 630-80402 Delin (Ty II) (Temp) Each NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 15.00 30.00 80.74 66.00 Weighted Average for the Second Quarter 15.00 30.00 80.74 66.00 Weighted Average for the Year 15.00 30.00 80.74 66.00 630-80403 Delin (Ty III) (Temp) Each NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 10.00 31.00 85.54 66.00 Weighted Average for the Second Quarter 10.00 31.00 85.54 66.00 Weighted Average for the Year 10.00 31.00 85.54 66.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80430 Rumble Strip (Port) Each NHPPR500-227 REGION 5 SECTION 7 10/23/25 4.00 2000.00 2070.75 1300.00 Weighted Average for the Fourth Quarter 4.00 2000.00 2070.75 1300.00 Weighted Average for the Year 4.00 2000.00 2070.75 1300.00 630-80440 Port Rumble Strips (Temp) Each STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 6.00 1700.00 1650.38 800.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 24.00 1500.00 700.00 1200.00 Weighted Average for the First Quarter 30.00 1540.00 1016.79 1120.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 6.00 1500.00 1598.00 2417.00 STAR500-228 REGION 5 05/08/25 4.00 1500.00 1288.33 1200.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 6.00 1722.66 1576.67 1730.00 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 12.00 1750.00 744.05 1650.00 Weighted Average for the Second Quarter 28.00 1654.85 1155.94 1767.21 FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 6.00 1200.00 1949.20 1900.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 6.00 1200.00 1949.20 1900.00 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 12.00 2000.00 913.54 504.17 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 6.00 2000.00 2331.67 2500.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 6.00 1594.62 811.55 807.50 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 12.00 1245.09 350.00 425.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 12.00 2000.00 638.09 150.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 12.00 2000.00 1252.50 1275.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-80440 Port Rumble Strips (Temp) Each STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 12.00 2800.00 3431.90 9075.00 Weighted Average for the Fourth Quarter 72.00 1973.73 1493.09 2180.49 Weighted Average for the Year 136.00 1778.27 1362.14 1849.10 630-80511 Mobile Pvmt Marking Zone Lump Sum NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 1.00 15000.00 6894.50 5000.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1.00 7500.00 19266.04 8500.00 MTCER500-233 REGION 5 03/06/25 1.00 80000.00 66666.67 35000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 1.00 20000.00 13098.88 12878.79 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 1.00 10000.00 16270.00 12540.00 Weighted Average for the First Quarter 5.00 26500.00 31988.26 14783.76 MTCER400-415 REGION 4 10/16/25 1.00 35000.00 20000.00 20000.00 NHPP0241-070 US 24 MP 192.73 TO 202.30 10/23/25 1.00 16000.00 12636.25 9555.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 14000.00 13542.73 15696.90 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 1.00 20000.00 11325.00 13500.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 12000.00 13458.81 15000.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 1.00 22000.00 12400.00 12400.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 20000.00 8037.50 10000.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 20000.00 7300.00 7300.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 25000.00 11460.00 15000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 20000.00 8800.00 7500.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 1000.00 13294.74 13500.00 Weighted Average for the Fourth Quarter 11.00 18636.36 12152.59 12677.45 Weighted Average for the Year 16.00 21093.75 20455.89 13335.67 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-80520 Mobile Pvmt Mkg Zone Day MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 30.00 308.01 175.00 150.00 Weighted Average for the First Quarter 30.00 308.01 175.00 150.00 MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 99.00 190.00 125.00 125.00 Weighted Average for the Second Quarter 99.00 190.00 125.00 125.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 40.00 2996.00 3050.87 3050.87 Weighted Average for the Third Quarter 40.00 2996.00 3050.87 3050.87 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 4.00 1248.65 5600.40 5402.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 4.00 2000.00 1577.50 1580.00 Weighted Average for the Fourth Quarter 8.00 1624.33 4451.00 3491.00 Weighted Average for the Year 177.00 908.95 1187.39 942.59 630-85010 Impact Atten (Temp) Each 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 4.00 4765.33 10218.38 9510.28 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 4.00 10000.00 10007.00 10000.00 BR0761-249 I-76 02/27/25 2.00 24698.36 12950.00 25000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2.00 10000.00 7146.63 4000.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 2.00 4744.72 10277.27 8757.58 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 4.00 12000.00 4685.00 7770.00 Weighted Average for the First Quarter 18.00 10330.42 9720.65 10257.57 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 23.00 16448.47 18993.24 18993.24 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-85010 Impact Atten (Temp) Each FBR0703-534 I-70 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 2.00 3600.00 7110.75 7008.00 NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 2.00 15000.00 12000.00 12000.00 NHPP0062-040 VASQUEZ BLVD - I270 TO 64TH - 05/23/25 6.00 11444.09 11444.09 11444.09 NHPP0501-080 SH50A MP 89.93 CEADAR CREEK 06/12/25 4.00 10000.00 1666.84 2750.00 Weighted Average for the Second Quarter 37.00 14167.01 11146.63 14987.16 STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 10.00 9899.53 10409.24 10409.24 CR400-406 REGION-WIDE 07/17/25 2.00 7000.00 8266.67 11000.00 BR0704-265 FBR0704-269 FBR0063-066 I-70 EAST I-70 EAST US 6D IN GARFIELD COUNTY 07/24/25 08/15/25 4.00 4.00 4938.02 11878.75 9287.63 12794.55 5650.50 12794.55 MTCER400-411 SH157 MP3.518 D-16-DG AND I70 08/21/25 3.00 4604.40 4385.50 5500.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 4950.47 10588.00 9640.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 2.00 8800.00 3624.20 2200.00 FBR2851-014 NHPP2851-009 NHPP0253-302 US 50 CONEJOS RIVER BRIDGE ST US 285 CONEJOS RIVER BRIDGES I-25 SEGMENT 5 (MP 242.5 TO 2 09/18/25 09/26/25 6.00 30.00 4890.52 11413.34 4712.00 11609.31 5400.00 11609.31 SPFS2706-055 I-270 MP 0-3 09/26/25 8.00 10289.61 11370.02 11370.02 Weighted Average for the Third Quarter 70.00 9581.23 8212.83 10029.32 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 9000.00 4419.50 2178.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 4.00 4664.78 1516.62 550.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 2.00 5000.00 8731.88 8500.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 4.00 10000.00 4180.03 5000.00 C0063-067 US 6 PALISADE IMPROVEMENTS MP 10/30/25 2.00 9000.00 5067.00 5000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 6.00 5335.30 11239.33 11791.45 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 4.00 4959.53 4350.00 3100.00 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 2.00 6000.00 5590.00 275.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 6.00 5343.19 10874.70 10473.50 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 4.00 10000.00 6895.00 6590.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 2.00 10000.00 19735.00 3000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-85010 Impact Atten (Temp) Each NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 4.00 2400.00 8260.00 8270.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 2.00 4694.26 6000.00 6000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 4.00 140.00 6635.00 6200.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 2.00 10000.00 2605.00 2650.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 4.00 8000.00 11516.87 15881.25 FBR086A-061 CO 86 (MP 22.75-22.89) 12/18/25 2.00 4951.20 8226.03 7900.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 4.00 5000.00 10520.00 8000.00 Weighted Average for the Fourth Quarter 60.00 6033.65 7552.50 6982.68 Weighted Average for the Year 185.00 9420.71 8490.27 10055.00 630-85013 Impact Atten (Temp)(Reset) Each STA119A-078 CO 119 (MM 44.237-55.5) 07/11/25 1.00 2838.99 2838.99 2838.99 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 1.00 1607.58 2430.00 2120.00 Weighted Average for the Third Quarter 2.00 2223.29 2498.17 2479.50 Weighted Average for the Year 2.00 2223.29 2498.17 2479.50 630-85020 Mobile Attenuator Each STRR200-288 CO 9B, US 24A, US 24G, CO 67C 01/16/25 1.00 65000.00 59162.50 65000.00 NHPP0403-069 US 40 MP 215.90 - 219.88 IN G 02/06/25 2.00 25000.00 45750.00 25000.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 2.00 26765.49 59409.74 21430.00 Weighted Average for the First Quarter 5.00 33706.20 56093.88 31572.00 C0821-113 CO-82 & Catherine Store Signa 04/17/25 2.00 22000.00 22000.00 22000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-85020 Mobile Attenuator Each NHPP0703-536 I-70 DILLON TO EJMT MM 204 TO 05/08/25 1.00 115000.00 74000.00 74000.00 NHPP2254-095 I-225 @ 2ND AND 6TH AVES 05/22/25 4.00 50000.00 39418.00 36254.00 ITSSW03-250 FRONT RANGE 06/26/25 2.00 31046.04 40351.80 31000.00 Weighted Average for the Second Quarter 9.00 46788.01 39781.36 36112.89 CR400-406 REGION-WIDE 07/17/25 6.00 36822.93 14633.33 4400.00 BR0704-265 FBR0704-269 CR400-400 I-70 EAST I-70 EAST VARIOUS LOCATIONS THROUGHOUT 07/24/25 08/14/25 1.00 1.00 31319.33 30000.00 59143.75 68500.00 36575.00 58000.00 STR050A-042 FREMONT COUNTY IN R2 09/11/25 4.00 30656.79 18376.00 25095.00 Weighted Average for the Third Quarter 12.00 33740.34 24815.11 18446.25 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 2.00 5500.00 13837.50 6050.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 2.00 26224.57 28259.35 25000.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 2.00 50000.00 17121.67 8500.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 2.00 31438.42 47574.37 47337.60 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2.00 31438.42 17000.00 11000.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 2.00 27294.61 34567.79 21000.00 STR3501-019 MINDEMAN TO EAST OF SH 71 JUN 11/20/25 2.00 27294.61 2850.00 2500.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 1000.00 52710.00 25420.00 ITSSW03-417 STATEWIDE 12/04/25 2.00 31438.42 98122.50 30488.00 SHER200-309 REGION 2 WIDE VARIOUS LOCATIO 12/04/25 1.00 31593.84 18300.40 7150.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 2.00 35000.00 91500.00 99000.00 NHPP0501-071 US50 DELTA RESURFACE MP 72 WE 12/11/25 1.00 40000.00 15637.50 15925.00 BR0402-109 US40 MP 108.4 OVER SHELTON DI 12/18/25 1.00 35000.00 52600.00 35000.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 4.00 30987.18 33289.11 33500.00 Weighted Average for the Fourth Quarter 26.00 29338.49 37764.60 27663.32 Weighted Average for the Year 52.00 33794.38 36357.01 27374.56 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-85040 Impact Atten (T-M-A) (Temp) Each NHPP2873-206 US287:RESURFACING I-70 TO 92N 01/09/25 2.00 30000.00 112652.19 136875.00 BR0761-249 I-76 02/27/25 2.00 16665.05 31416.67 25000.00 MTCER500-233 REGION 5 03/06/25 2.00 14219.72 8166.67 2000.00 Weighted Average for the First Quarter 6.00 20294.92 38363.77 54625.00 NHPPR100-420 VARIOUS LOCATIONS IN REGION 1 06/05/25 6.00 15106.93 52661.67 59485.00 Weighted Average for the Second Quarter 6.00 15106.93 52661.67 59485.00 FSA052A-053 SH 52 AND WCR 41 SIGNALIZATIO 09/11/25 1.00 13432.07 14815.40 16000.00 Weighted Average for the Third Quarter 1.00 13432.07 14815.40 16000.00 Weighted Average for the Year 13.00 17372.55 40998.12 53896.92 630-85041 Mobile Attenuator Day 2670252-499 I-25:MOBILITY HUB (LONE TREE) 01/16/25 30.00 2000.00 1114.50 1007.00 NHPP0702-428 I-70 THROUGH GLENWOOD CANYON 01/30/25 500.00 875.00 346.60 300.00 BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 168.00 1100.00 676.41 917.13 SHE0881-032 FEDERAL BLVD SIGNALS 41st and 02/13/25 50.00 1200.00 708.13 378.00 MTCER200-296 REGION 2 VARIOUS HIGHWAYS AND 03/13/25 10.00 1200.00 150.00 100.00 NHPP0403-063 US40 RESURFACING MP 252-258.3 03/27/25 65.00 1500.00 1255.88 875.76 Weighted Average for the First Quarter 823.00 1034.99 524.83 499.53 STAM765-015 US50/MAPLE & US287/CEDAR, LAM 04/10/25 60.00 230.37 544.00 798.00 NHPP0703-517 FBR0703-534 MTCE0361-135 I-70 TOP OF FLOYD HILL TO VET I-70 US-36B FROM MP 0.00-33.76 IN 04/11/25 06/05/25 1,894.00 120.00 1116.78 919.44 1119.44 925.00 1119.44 1000.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 630-85041 Mobile Attenuator Day MTCER200-299 R2 VARIOUS HIGHWAYS AND COUTN 06/26/25 50.00 275.00 100.00 100.00 Weighted Average for the Second Quarter 2,124.00 1060.77 1035.57 1079.61 MTCE0702-434 I-70 MP 130 TO 168, REGION 3 07/03/25 60.00 400.00 800.00 750.00 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 30.00 912.91 560.25 548.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 20.00 800.00 1200.00 1200.00 SHER100-414 SH 74/KERRGULCH;SH83/GILLIAN, 08/14/25 50.00 835.27 768.50 540.00 MTCER200-301 R2 VARIOUS HIGHWAYS AND COUNT 08/21/25 40.00 1200.00 966.67 800.00 NHPP0704-260 I-70 AND PENA BLVD OVERPASS 08/21/25 25.00 981.69 772.00 480.00 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 30.00 1024.20 1023.75 1000.00 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 350.00 1177.00 1198.56 1198.56 SPFS2706-055 I-270 MP 0-3 09/26/25 75.00 1369.40 1513.19 1513.19 Weighted Average for the Third Quarter 680.00 1069.23 965.12 1057.98 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 210.00 1100.00 816.50 785.00 NHPP0705-083 I-70: SEIBERT EAST PART 2 12/04/25 5.00 492.81 2399.00 2205.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 150.00 1000.00 769.53 980.00 NHPP1602-194 US 160 MP 174.1 12/11/25 100.00 450.00 525.51 375.00 Weighted Average for the Fourth Quarter 465.00 921.43 765.89 775.00 Weighted Average for the Year 4,092.00 1041.16 768.21 924.73 630-86801 Traffic Signal (Temp) Lump Sum NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 1.00 230492.28 230490.59 230490.59 NHPP0703-517 FBR0703-534 FBR0703-534 I-70 TOP OF FLOYD HILL TO VET I-70 I-70 04/11/25 1.00 230492.30 230490.59 230490.59 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 2.00 230492.29 230490.59 230490.59 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 125000.00 23685.00 22990.00 Weighted Average for the Fourth Quarter 1.00 125000.00 23685.00 22990.00 Weighted Average for the Year 3.00 195328.19 92620.20 161323.73 630-86802 Traffic Signal (Temporary) Day STU1191-044 CO119 AND CO 7 FROM US36 (28T 04/03/25 20.00 500.00 600.00 600.00 Weighted Average for the Second Quarter 20.00 500.00 600.00 600.00 CR400-406 REGION-WIDE 07/17/25 50.00 1100.00 218.17 214.50 Weighted Average for the Third Quarter 50.00 1100.00 218.17 214.50 Weighted Average for the Year 70.00 928.57 263.09 324.64 630-86810 Traffic Signal (Temp) Each NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 4.00 35000.00 48312.08 23000.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 1.00 30000.00 37433.43 25000.00 STM141A-057 SH141 GATEWAY MP 120 SOUTH 03/27/25 2.00 50000.00 15530.00 21060.00 Weighted Average for the First Quarter 7.00 38571.43 41035.29 22731.43 C0821-113 CO-82 & Catherine Store Signa 04/17/25 1.00 40000.00 18150.00 18150.00 STAR500-223 SH50 MM 189.71, US550 MM 98.3 05/01/25 1.00 35000.00 32490.75 28463.00 Weighted Average for the Second Quarter 2.00 37500.00 29622.60 23306.50 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid 630-86810 Traffic Signal (Temp) Each FBR2851-014 US 50 CONEJOS RIVER BRIDGE ST 09/18/25 1.00 40000.00 32614.40 27300.00 NHPP2851-009 US 285 CONEJOS RIVER BRIDGES Weighted Average for the Third Quarter 1.00 40000.00 32614.40 27300.00 STR012A-054 SH12 MP 46.7 to MP 48.1 10/23/25 5.00 30000.00 8778.00 6100.00 NHPPR500-227 REGION 5 SECTION 7 10/23/25 1.00 35000.00 33547.75 23651.00 STM318A-002 SH 318 MP 1.25 IN MOFFAT COUN 10/23/25 2.00 700.00 24346.46 15000.00 STR069A-036 SH 69 M.P. 71.53 TO M.P. 82.6 11/06/25 2.00 16750.76 10125.00 14250.00 2670171-111 SH 17 FROM APPROXIMATE MP 2.4 12/04/25 1.00 26925.01 40000.00 40000.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 30000.00 41700.00 38000.00 STAR500-226 R5 HWYS 550, 491, 285, 184, 1 12/18/25 2.00 30000.00 89466.59 164862.50 Weighted Average for the Fourth Quarter 14.00 24059.04 24894.55 37169.71 Weighted Average for the Year 24.00 30076.11 29781.70 31392.04 632-00000 Night Work Lighting Lump Sum BRR100-400 VAR LOCATIONS R1 I25, I225 & 02/06/25 1.00 100000.00 67584.69 31625.00 NHPP0072-033 CO7 28TH ST TO CHERRYVALE RD 02/20/25 1.00 50000.00 109552.76 65000.00 MTCER500-233 REGION 5 03/06/25 1.00 15000.00 7016.67 100.00 NHPP085A-020 US85:I-76 TO 124TH AVENUE OVE 03/20/25 1.00 50000.00 36100.89 25500.00 NHPP2706-054 I-270/SAND CREEK DRIVE REPAIR 03/27/25 1.00 20000.00 14167.67 29503.00 Weighted Average for the First Quarter 5.00 47000.00 45072.77 30345.60 NHPP0703-517 FBR0703-534 NHPP2254-095 I-70 TOP OF FLOYD HILL TO VET I-70 I-225 @ 2ND AND 6TH AVES 04/11/25 05/22/25 1.00 1.00 317159.50 15000.00 294412.40 105866.67 294412.40 66100.00 ITSSW03-250 FRONT RANGE 06/26/25 1.00 70000.00 47526.60 2000.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the Second Quarter 3.00 134053.17 94405.04 120837.47 SHE1211-107 WADSWORTH BLVD & EVANS AVE 07/17/25 1.00 12000.00 12164.25 5950.00 MTCE0703-541 I-70 EISENHOWER-JOHNSON MEMOR 07/24/25 1.00 25000.00 25000.00 25000.00 FBR0063-066 US 6D IN GARFIELD COUNTY 08/15/25 1.00 10445.65 9275.63 9275.63 NHPP0253-302 I-25 SEGMENT 5 (MP 242.5 TO 2 09/26/25 1.00 128776.60 153864.79 153864.79 SPFS2706-055 I-270 MP 0-3 09/26/25 1.00 12343.77 13639.87 13639.87 Weighted Average for the Third Quarter 5.00 37713.20 31304.66 41546.06 NHPP070A-042 I70B EAST OF 3RD STREET 10/16/25 1.00 35000.00 37978.00 81312.00 MTCER100-428 I-25 (DENVER TO MONUMENT), I- 10/23/25 1.00 15000.00 13406.67 11000.00 NH0243-097 US 24 - MP 332.02 TO MP 342.6 11/06/25 1.00 60000.00 62066.39 30802.10 C1601-088 US 160 SIGNALS MILDRED & HARR 11/13/25 1.00 25000.00 12872.70 10900.00 NH160A-036 US160A HUERFANO MP 294.4 TO 3 11/20/25 1.00 20000.00 91833.19 86000.00 STM052A-062 CO52A RESURFACING I25 TO US85 11/20/25 1.00 60000.00 104722.45 75000.00 NHPP0701-260 I-70 MP 80.5 TO MP 88 IN GARF 12/04/25 1.00 30000.00 40000.00 40000.00 NHPP2706-048 I-270 MP 0 - MP 5 12/04/25 1.00 60000.00 85703.11 20000.00 STM340A-022 CO 340 GRAND AVE TO REDLANDS 12/04/25 1.00 50000.00 108633.33 100000.00 STA157A-013 CO 157 (MM 2.8-4.5) 12/04/25 1.00 50000.00 56833.33 33500.00 NHPP0701-257 MP 138-148 ON I-70 IN EAGLE C 12/04/25 1.00 100000.00 65800.00 31600.00 NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 1.00 25000.00 53510.00 50000.00 STM0503-096 PUEBLO COUNTY LINE TO PURCELL 12/18/25 1.00 32000.00 9102.72 7500.00 Weighted Average for the Fourth Quarter 13.00 43230.77 60389.98 44431.85 Weighted Average for the Year 26.00 53374.06 57242.80 49984.03 641-10000 Shotcrete Sq Yard NHPP0402-107 R3 US 40 MILNER EAST AND WEST 12/11/25 113.00 125.00 903.50 910.00 Weighted Average for the Fourth Quarter 113.00 125.00 903.50 910.00 Project Number Item Number/ Item Description/ Project Location Date Let Unit/ Quantity Engr. Est. Average Bid Awarded Bid 641-10010 Weighted Average Initial Shotcrete for the Year Facing 113.00 Sq Foot 125.00 903.50 910.00 STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 2,059.00 30.00 67.71 46.00 Weighted Average for the First Quarter 2,059.00 30.00 67.71 46.00 NHPP0703-517 I-70 TOP OF FLOYD HILL TO VET 04/11/25 53,444.00 37.13 36.38 36.38 FBR0703-534 I-70 Weighted Average for the Second Quarter 53,444.00 37.13 36.38 36.38 STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 4,845.00 50.00 36.82 23.00 Weighted Average for the Third Quarter 4,845.00 50.00 36.82 23.00 Weighted Average for the Year 60,348.00 37.92 39.12 35.63 641-10070 Shotcrete Sculpting Sq Yard STR025A-054 I-25C NORTH OUT OF WALSENBURG 09/18/25 539.00 197.99 298.68 230.00 Weighted Average for the Third Quarter 539.00 197.99 298.68 230.00 Weighted Average for the Year 539.00 197.99 298.68 230.00 641-11003 Shotcrete (CL D) Cubic Yard STR141A-056 SH 141 MP 85.5 K-01-B BRIDGE 02/28/25 50.80 1000.00 2512.16 1900.00 Item Number/ Item Description/ Unit/ Project Number Project Location Date Let Quantity Engr. Est. Average Bid Awarded Bid Weighted Average for the First Quarter 50.80 1000.00 2512.16 1900.00 Weighted Average for the Year 50.80 1000.00 2512.16 1900.00