CO 69 Improvements Between Westcliffe and Walsenburg

Project Facts

  • Cost: $4.2 million
  • Contractor(s): A & S Construction Co.
  • Location: On CO 69 near the town of Gardner, from mile points 25.7 to 50.1
  • Timeline: March through August 2018

From March through August 2018, crews paved Colorado Highway 69 between Westcliffe and Walsenburg, near the town of Gardner.

Other work included:

  • placing shouldering materials;
  • replacing guardrail;
  • adding signage;
  • striping; and
  • landscaping.