Copy
View this email in your browser
Colorado Department of Transportation logo

US 287/CO 52 Intersection Improvements 

Weekly Traffic Impacts & Work Update


Updated Traffic Impacts - Oct. 22 to Oct. 28


Please be advised of the following project update, lane closures, restrictions and planned work for next week for the US 287/CO 52 Intersection Improvement Project in Boulder County.

**10/20 Update - The right turn lanes are expected to start opening up after Monday, Oct. 23.**


*****
Monday, Oct. 23 to Friday, Oct. 27- CO 52 - intermittent single direction alignment with traffic holds
  • Motorists can expect CO 52 to be reduced to a single direction (one-way) alignment on an intermittent basis during working hours
  • The closures will exist between approx. 9 a.m. and 4 p.m.
  • Motorists can expect delays in excess of 15 minutes during traffic holds
  • Alternate routes are strongly advised
  • Speeds are reduced
  • Advanced warning signs and construction devices are present to alert motorists to the work zone and related closures and restrictions
  • All construction schedules are weather dependent and subject to change
Work includes inspections and final cleanup.
*****
Monday, Oct. 23 to Friday, Oct. 27 - US 287 - intermittent single lane closures
  • Intermittent single lane closures will exist on US 287 Monday to Friday
  • The closures will exist between approx. 9 a.m. and 4 p.m.
  • Flaggers will be present to manage alternating traffic flows
  • Motorists can expect delays up to 15 minutes during traffic holds
  • Speeds are reduced and caution is advised
  • Advanced warning signs and construction devices are present to alert motorists to the work zone and related closures and restrictions
  • Some Saturday work is also expected
  • All construction schedules are weather and supply dependent and subject to change
  • Alternate routes are strongly advised
Work includes final cleanup and inspections.
*****
24/7- right turn lane closures & other restrictions - US 287 & CO 52
  • No right turns are permitted until project completion
  • These turn lanes are expected to start opening up to traffic after Monday, Oct. 23
  • The right turn lane closures exist in all directions of the intersection of US 287 and CO 52
  • A 10-foot width restriction is in place 24/7 through the work zone
  • Caution is advised

Stay Connected!

 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2023 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204

You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA