Weekly Traffic Impacts - Nov. 19 to Nov. 25
Please be advised of the following traffic impacts, restrictions and planned work for next week for the US 385 Resurfacing North of Holyoke project in Phillips County. This project is expected to be substantially complete by late November, with full completion pending final inspections.
**No work will be performed and no lane closures will be taken during the Thanksgiving holiday weekend from Thursday through Sunday**
*****
Monday, Nov. 20 to Wednesday, Nov. 22 - US 385 - MP 280 to MP 289 - alternating single lane closures with traffic holds - north of Holyoke
- Single lane closures will exist in both directions of US 385 north of Holyoke from MP 280 to MP 289
- The closures will exist from 6:30 a.m. to approx. 7 p.m.
- The closures will be managed by a combination of pilot cars, flaggers and signs
- Lane closures with alternating traffic flows will not exceed a distance of three miles
- Closures will not overlap
- Motorists can expect delays up to 15 minutes during traffic holds
- Some Saturday work is expected (except over holiday weekends)
- Variable message boards, advanced warning signs and devices will be present to alert motorists to the closures and work underway
- All construction schedules are weather dependent and subject to change
Work includes pavement grinding, striping, seeding, and placing riprap.
*****
Monday, Nov. 20 to Wednesday, Nov. 22 - US 385 - MP 278.43 to MP 279.50 & US 6 - MP 454 to MP 454.6 - no planned lane or shoulder closures
- No additional lane or shoulder closures are planned on US 385 from Johnson to Bignel, and on US 6 east of US 385 to Worley
- All construction schedules are weather dependent and subject to change
Work includes final inspections.
|
|