Weekly Traffic Impacts - Oct. 15 to Oct. 21
Please be advised of the following closures, restrictions and planned work for next week for the US 385 Resurfacing North of Holyoke project in Phillips County.
*****
Monday, Oct. 16 to Friday, Oct. 20 - US 385 - MP 280 to MP 289 - alternating single lane closures - north of Holyoke
- Single lane closures will exist in both directions of US 385 north of Holyoke from MP 280 to MP 289
- The closures will exist from 6:30 a.m. to approx. 7 p.m.
- Lane closures with alternating traffic flows north of Holyoke will not exceed a distance of two miles
- Closures will not overlap
- Flaggers and/or pilot cars will be present to manage alternating northbound/southbound traffic flows
- Motorists can expect delays up to 10 minutes during traffic holds
- Some Saturday work is expected
- Variable message boards, advanced warning signs and devices will be present to alert motorists to the closures and work underway
- All construction schedules are weather dependent and subject to change
Work includes milling, paving, embankment work, and surveying.
*****
Monday, Oct. 16 to Friday, Oct. 20 - US 385 - MP 278.43 to MP 279.50 &
US 6 - MP 454 to MP 454.6 - shoulder, sidewalk & periodic lane closures
- Curb ramp work will take place on US 6 from Campbell to Worley and as needed on US 385 within the project limits, with restrictions in place
- Shoulder closures and intermittent single lane closures may exist during curb ramp work
- Flaggers, signs and construction devices will be present to manage alternating traffic flows
- The closures will exist from 6:30 a.m. to 7 p.m. Monday to Friday and occasionally on Saturdays
- Flaggers will be present to manage pedestrian traffic during concrete pours
- On-street parking will be temporarily restricted during ramp work activities with construction cones and other devices in place
- The shoulder closures will be mobile with minimal impacts to traffic
- Partial sidewalk closures will also exist with signs and construction devices in place to manage pedestrian traffic
- Signage will exist to alert motorists and pedestrians to the work
- All construction schedules are weather dependent and subject to change
Work includes ADA curb ramp removals and concrete pours.
|
|