Projects

Overview

  • 38.9775600796 -103.259124756
    • ARRA
    • ARRA-CDOT
    • Lincoln County
    • Project: US 40/US 287 at Boyero
    • Projects
Project Owner CDOT
CDOT Region 1
County Lincoln
Description of Work This is the next phase of a concrete reconstruction project along this corridor. The project will improve 8.7 miles of US 40/US 287 (mileposts 413-422 approximately). The US 40/US 287 corridor between Campo and Hugo is one of Colorado's 28 high priority strategic projects.
Estimated Total Project Cost $12,499,486
ARRA Funds $12,248,750
Project Status Completed
Start Date July 14, 2009
Completion Date June 2010
Percentage Spent 100%
Contractor Castle Rock Construction Co.
 


 