CO 121 Rehabilitation in Lakewood

Work this Week
September 15-21

Note: Traffic & Noise Advisory in Place

  • Work hours and locations:  7:30 p.m. to 5:30 a.m. on Wadsworth Blvd between 6th Avenue and Yale
  • Through October 2019, expect single-lane closures and minor delays on Wadsworth Boulevard between 4th Avenue and Yale Avenue as crews remove asphalt and repave.
  • This work requires the use of vehicle back-up alarms, which will cause increased noise levels.

Project Facts

  • Cost: $5.2 million
  • Contractor: Martin Marietta Materials
  • Timeline: March - September 2019
  • Location: CO 121 (Wadsworth Boulevard) between Hampden Avenue and US 6 in Lakewood


CO 121/Wadsworth Boulevard work area map

Crews on this project are repairing more than three miles of Wadsworth Boulevard (aka Colorado Highway 121) between Hampden Avenue and US Highway 6 in the City of Lakewood. Specific work includes:

  • installing and replacing 81 concrete curb ramps to comply with the Americans With Disabilities Act;
  • resurfacing and patching;
  • adjusting manholes;
  • installing signs; and
  • restriping the highway.
ADA ramps before and after project work

Night paving on Wadsworth Blvd.