CO 340 Bike/Pedestrian Improvements

Work this Week
7 a.m. - 5 p.m.
Aug. 20-24

Crews will place concrete from 23 Road east, clean, prepare to pave and install fence.

Project Facts

  • Cost: $1 million
  • Contractor: United Companies
  • Timeline: May - October 2018
  • Location: On CO 340, between Kansas Avenue (mile point 9.6) and Grande Vista Drive (mile point 10.5)

In May, crews on this project started moving vegetation on Colorado Highway 340 between Kansas Avenue and Grande Vista Drive, west of Grand Junction, to make way for a bicycle and pedestrian path.

This work will further improve bicyclist and pedestrian access, and interconnectivity in the area.

The project team will build a five-foot-wide concrete path, landscape, add fencing, restore the site and seed, and complete curb-and-gutter and culvert work.


Schedule

Normal working hours are 9 a.m. to 5 p.m., Monday through Friday. Work is expected to be complete in October 2018.


Travel Impacts

  • Through October 2018
    Expect a westbound shoulder closure with possible eastbound and westbound one-lane alternating traffic.