CO 67 Overlay

In observance of the Thanksgiving holiday weekend, project work is scheduled only on Monday, Nov. 20 and Tuesday, Nov. 21.

Crews are resurfacing, paving and completing other work on Colorado Highway (CO) 67 at two locations. Crews will also install guardrail, add signage and striping to the highway, and complete bridge work.

Please note: Daily work measurements are approximate and will vary, depending on production.


Work Details

Site A

  • Location: An 18-mile stretch between Cripple Creek and Divide (mile points 52.3-69.6)

  • Work Hours:
    • Daylight hours, Monday Nov. 20 and Tuesday, Nov. 21
      • Note: No mainline paving will be done when temperatures are below acceptable levels.
  • Work Details: Crews will work on shoulders and guardrail

  • Travel Impacts:
    • Expect one-lane closures in each direction.
    • Flaggers and a pilot car will direct traffic.
    • Speed limit reductions will be in place.
    • There is a 12-foot-wide load restriction during construction.

  • Specific Work Locations
    • Monday, Nov. 20:
      • Northbound and southbound from mile point (MP) 52.2 to MP 53
      • Northbound and southbound from MP 55 to MP 63
    • Tuesday, Nov. 21:
      • Northbound and southbound from MP 52.5 to MP 54
      • Northbound and southboundfrom MP 57 to MP 67

Site B

  • Location: A 13-mile stretch between Woodland Park and Westcreek (mile points 77.5-91.7)

  • Work Hours: Daylight hours, Monday, Nov. 20 and Tuesday, Nov. 21

  • Work Details: Crews will mark pavement.

  • Travel Impacts:
    • Expect each direction of traffic to be reduced to one lane.
    • There will be a 12-foot-wide load restriction during construction hours.
    • Flaggers and a pilot car will be present, and flaggers will stop bikers and pedestrians, and direct them through the construction zone.
    • Speed limit reductions will be in place.

  • Specific Work Locations
    • Monday, Nov. 20:
      • Northbound and southbound from mile point (MP) MP 52.5 to MP 54
      • Northbound and southbound from MP 57 to MP 67
    • Tuesday, Nov. 21:
      • Northbound and southbound from MP 77.5 to MP 92


Resources

Project Facts

  • Cost: $10.4 million
  • Timeline: Early June - Late Fall 2017

Project Team

  • Contractor(s): Martin Marietta Materials