CO 67 Overlay

Crews are resurfacing, paving and completing other work on Colorado Highway (CO) 67 at two locations (see details below). Crews will also install guardrail, add signage and striping to the highway, and complete bridge work.

The team is aiming to complete the project by the 2018 Memorial Day weekend.

Please note: Daily work measurements are approximate and will vary, depending on production.


A Look Ahead

  • Late February: Crews will temporarily shut down the project. They will restripe for safety purposes, as needed.
  • Early May: The project team will complete striping, delineators, approaches and mainline paving of 1,250 feet at Site A. At Site B, they will patch, seal the bridge and pave approaches.

Work Details

Site A

When:
Through Late February 2018

Where:
CO 67 - Cripple Creek to Divide (mile points 52.3 to 69.6)

Progress:

  • Crews have completed a process called cold in-place recycling, during which crews apply milled asphalt to the roadway and overlay it with 1.5 inches of asphalt.
  • Mainline paving work is 97 percent complete.
  • Crews have placed rumble strips and temporary striping.
  • Weather permitting, the project team will replace guardrail and complete embankment work through February.

Work the Week of Jan. 22:

  • Travel reduced to one lane in both directions during daylight hours for guardrail installation and safety edge operations
    • Monday
      • Southbound from mile point (MP) 58 to MP 59
      • Northbound from MP 64 to MP 67
    • Tuesday:
      • Southbound from MP 58 to MP 59
      • Northbound from MP 64 to MP 67
    • Wednesday:
      • Southbound from MP 59 to MP 60
      • Northbound from MP 64 to MP 67
    • Thursday:
      • Southbound from MP 59 to MP 60
      • Northbound from MP 64 to MP 67

Site B

When:
Through Late February 2018

Where:
CO 67 - Woodland Park to Westcreek (from mile points 77.5 to 91.7)

Progress:

  • Crews have completed mainline paving and temporary striping.
  • Weather permitting, the project team will continue shoulder work, patching and embankment work through February.

Work the Week of Jan. 22:

  • Travel reduced to one lane in both directions for embankment work and guardrail installation
    • Tuesday-Friday:
      • Northbound at mile point (MP) 82
    • Friday:
      • Northbound at MP 82
      • Southbound from MP 79 to MP 82


Resources

Project Facts

  • Cost: $10.4 million
  • Timeline: Early June 2017 - Memorial Day Weekend 2018 

Project Team

  • Contractor(s): Martin Marietta Materials