Week of July 24, 2017

Site A
CO 67 ‐ Cripple Creek to Divide

Work this Week

  • Daylight hours, Monday, July 24 through Thursday, July 27:
    • Slow-vehicle-turnout construction
      • Monday, July 24: Southbound from mile post (MP) 52 to MP 69
      • Wednesday, July 26:Southbound from MP 63 to MP 65
      • Thursday, July 27:Southbound from MP 63 to MP 65
      • 12-foot-wide load restriction during construction hours

  • Friday, July 28
    • No work

Look Ahead:

  • Week of July 31:
    • Paving begins.

Site B
CO 67 ‐ Woodland Park to Westcreek

Work this Week

  • Daylight hours, Monday, July 24 through Friday, July 28
    • Lane restrictions: Travel reduced to one lane in both directions for paving
      • See the weekly construction map.
      • Monday, July 24: Northbound from MP 86.6 to MP 88
      • Tuesday, July 25: Northbound from MP 88 to MP 89.5
      • Wednesday, July 26: Northbound from MP 89.5 to MP 91.7
      • Thursday, July 27: Southbound from MP 91.7 to MP 90
      • Friday, July 28: Southbound from MP 90 to MP 88.5
      • Measurements are approximate and will vary from day to day, depending on production.
    • 12-foot-wide load restriction during construction hours
    • Flaggers will stop bikers and pedestrians and direct them to follow roadway construction rules.



Construction schedules are subject to change based on weather/unforeseen circumstances or schedule changes.