Work Schedule
2016
- July - October: CO 7 & Business Route going from west to east
- Mid-July – October: Mile Post 12 going west to Mile Post 9.62
- Mid-July – September 2016: Bridge rehab at MP 13.0
- August – November: MP 6.33 (Lily Lake)
- September – November: MP 8.3- 12X4 Reinforced Concrete Box Culverts (RCBC)
2017
- March - April: Culverts at MP 9.97 & MP 13.62 (42’’ pipe)
- March – June: MP 10.8 (St. Malo)
- April – May: MP 13.65 to MP 13.67, MP 8.7 (8X4 RCBC), MP 10.22 (12X4 RCBC)
- May – July: MP 16.04 east to MP 19.25
- July – October: Paving, guardrail and finish work.
Most culvert crossings are concrete pipe with inlet/outlet structures. Larger culverts are reinforced concrete box culverts (RCBC), which may require wingwalls and riprap drop structures.