Work Schedule

CO 7 Project Work

Map Key


July - October 2016

April - July 2017

July - September 2016 (bridge work)

2016

  • July - October: CO 7 & Business Route going from west to east
  • Mid-July – October: Mile Post 12 going west to Mile Post 9.62
  • Mid-July – September 2016: Bridge rehab at MP 13.0
  • August – November: MP 6.33 (Lily Lake)
  • September – November: MP 8.3- 12X4 Reinforced Concrete Box Culverts (RCBC)

2017

  • March - April: Culverts at MP 9.97 & MP 13.62 (42’’ pipe)
  • March – June: MP 10.8 (St. Malo)
  • April – May: MP 13.65 to MP 13.67, MP 8.7 (8X4 RCBC), MP 10.22 (12X4 RCBC)
  • May – July: MP 16.04 east to MP 19.25
  • July – October: Paving, guardrail and finish work.

Most culvert crossings are concrete pipe with inlet/outlet structures. Larger culverts are reinforced concrete box culverts (RCBC), which may require wingwalls and riprap drop structures.