Projects

I-25 and Fillmore Street Interchange

Fillmore Plan Color withURSPond Reduced Size

Overview

In February 2015, the Colorado Department of Transportation (CDOT) began an interchange reconstruction project at I-25 and Fillmore Street in El Paso County in Colorado Springs. The project will convert the existing interchange into a Diverging Diamond Interchange (DDI), the second along the Front Range and the third in the State of Colorado.

SEMA Construction Inc. is the primary construction contractor for this project, which cost $15.1 million.

Upcoming Closure

On Thursday, July 9, and Sunday, July 12, from 9 p.m. to 5 a.m., both northbound and southbound I-25 will be closed at the Fillmore Street exits.

During this time, crews will set bridge girders for the westbound Fillmore Street bridge structure over the Interstate, marking a major milestone on the project.

These closures will be in place to ensure the safety of the traveling public, so motorists do not drive through the construction zone while crews set girders above the highway. Each girder weighs approximately 180,000 pounds — more than the weight of two semi trucks and their trailers combined.

Detours

At Fillmore Street, I-25 through traffic will be detoured off the highway at the off-ramps and routed back onto the highway using the on-ramps. Fillmore Street will be closed between the I-25 northbound and southbound ramps.

Motorists can turn right off the ramps, but will not be able to turn left onto Fillmore Street.

There will be signed detours along I-25 to direct motorists around the work. Detours will include utilizing the Garden of the Gods and Fontanero exits.

Project Progress

To date the project is approximately 20 percent complete and on pace to conclude in summer 2016. Upcoming work will focus on constructing the northbound off-ramp, which will include some permanent paving as well as paving for a temporary ramp to get vehicles around the construction zone.

Schedule and Traffic Impacts

Normal working hours are from Monday through Friday from 7 a.m. to 5 p.m. There will be some nighttime and weekend work as needed.

The speed limit is reduced in the construction zone on I-25 to 55 mph for both the safety of the traveling public as well as construction crews working along the highway.

Business access will be maintained. Construction crews will accommodate pedestrians and bicyclists through the construction zone as much as possible. Please use caution and stay alert while traveling through the construction zone. Follow flaggers’ directions and reduced posted speed limits.

About the DDI

The Diverging Diamond Interchange transitions traffic from one side of the road to the opposite side. This innovative interchange will improve safety and traffic flow through the corridor to meet existing and future travel demands.

As part of this project, two new bridges will be constructed to replace the current bridge structure, which was built in 1960 and widened in the 1970s. Each bridge will be approximately 220 feet long, with a 14-foot-wide sidewalk on the eastbound side for pedestrian use. There also will be 5-foot-wide bicycle lanes eastbound and westbound on both bridges. In addition, the southbound off-ramp and northbound

on-ramp for I-25 will be lengthened to accommodate the amount of traffic utilizing this route.

Project Contacts

If you have questions about the project, contact the Public Information Team. You will receive a response within 24 hours.
Phone: 719-367-4884
Email: i25fillmore@publicinfoteam.com

Media Contact:
Bob Wilson
CDOT Communciations Manager
bob.j.wilson@state.co.us

Colorado: The Official State Web Portal