Pikes Peak Area Traffic Signal Enhancement

Work This Week

April 6-10
  • Monday through Friday on US 24/Fountain Blvd. at Murray Blvd., Jet Wing Dr., and Aeroplaza Dr. from MP 307 to 309.
  • Periodic east and westbound signal lane closures on US 24/Fountain Blvd at Murray Blvd, Jet Wing Dr, and Aeroplaza Dr.
  • North and southbound periodic single lane closure on Murray Blvd, Jet Wing Dr, and Aeroplaza Dr at US 24/Fountain Blvd.

Project Facts

  • Cost: $2.6 million
  • Contractor: Arrow Electric
  • Timeline: February - December 2020
  • Location: US 24/Fountain Boulevard at Murray Boulevard, Jet Wing Drive, Aeroplaza Drive; CO 21/Powers Boulevard; US 24/Powers Boulevard at Airport Drive and Aeroplaza Drive.; CO 16/Mesa Ridge Parkway (Safeway Business Access).

Screen Shot 2020-02-10 at 11.54.14 AM.png

Pike's Peak Signal Enhancement Project on US 24

Screen Shot 2020-02-10 at 11.56.46 AM.png

Pike's Peak Signal Enhancement Project on CO 16

The Colorado Department of Transportation (CDOT) and contract partner Arrow Electric will begin traffic signal enhancements at 7 locations along the US 24 and CO 16 corridor in Pikes Peak on February 17, 2020. As part of CDOT’s Whole System Whole Safety initiative, the project will focus on adding 3 new advance flashing beacon signs to increase driver yielding rates by adding increased driver awareness of crosswalks, which will help reduce the risk of multi-threat crashes on multilane roads. Crews will also install 13 Americans with Disabilities Act (ADA) compliant curb ramps which will provide functional accessibility to all travelers using our state and U.S. highways.

The project will take place at the following locations:

  • US 24/Fountain Boulevard at Murray Boulevard, Jet Wing Drive, Aeroplaza Drive, and CO 21/Powers Boulevard.
  • US 24/Powers Boulevard at Airport Drive and Aeroplaza Drive.
  • CO 16/Mesa Ridge Parkway (Safeway Business Access).

Enhancements for the $2.6M project include:

  • Crews will install new ADA curb ramps and advance flashing beacons
  • remove and replace signal poles, mast arms, signal heads, conduit, cabinet/controllers, and detection controls.

Work Schedule

  • The project will be in operation:

    • Monday through Friday 8 am-5 pm at CO 16/Mesa Ridge Parkway (Safeway Business Access).
    • Sunday through Thursday with lane closures from 9 pm-6 am and crews present 8 am-4:30 pm at US 24/Fountain Boulevard at
      Murray Boulevard, Jet Wing Drive, Aeroplaza Drive, and CO 21/Powers Boulevard.
    • Sunday through Thursday with lane closures from 7 pm-6 am and crews present 8 am-4:30 pm at US 24/Powers Boulevard at
      Airport Drive and Aeroplaza Drive.
    • The project has an anticipated completion date the end of December 2020.

Traffic Impacts

  • Motorists can expect a north, south, east, and westbound single lane and shoulder closure.