Bridge Rehabilitation Project between Gateway and Naturita

Work this Week
July 25 - 29, 2022

The Region 5 - CO HWY 141 Bridge Rehabilitation and Improvements Project will be conducted along CO 141 primarily between Naturita and Gateway at individual MP 59.075, 74.127, and 88.421.

Monday, July 25 to Friday, July 29 work will consist of:

  • Bridge K-01-A - CO HWY 141/ Dolores River - MP 88.421:
    • One-lane road with traffic signal operations 24/7
    • 10 ft. lane restriction
  • Bridge K-02-C - CO HWY 141/ San Miguel River - MP 74.127:
    • One-lane road with traffic signal operations 24/7
    • 10 ft. lane restriction
  • Bridge L-02-B - CO HWY 141/ Naturita Creek - MP 59.075:
    • Traffic is open until work begins on 8/8

The project will be in operation Monday thru Friday from 7 a.m. to 7 p.m.

About the Project:

The project will include restoring bridge deck integrity, waterproofing, resurfacing, and pavement markings along this stretch of CO 141. The project is part of CDOT’s Bridge Preventative Maintenance Program to extend the service life of bridges and other major structures that the state maintains.


Work Schedule

  • Daytime work hours range from 7 a.m. to 7 p.m. Monday through Friday.  

Traffic Impacts

  • Vehicles will encounter single-lane, alternating traffic intermittently in either direction, and the use of portable light signals will be prominent throughout the duration of the project. These lane closures may have up to 15-minute delays. The speed limit will be reduced to 40 mph through the work zone. The project is expected to last until the end of September.

Project Facts

  • Cost: $ 1,000,000
  • Contractor: KSK, LLC
  • Timeline: May - September 2022
  • Location:  Along CO 141 at three individual MP 59.075, 74.127, and 88.421, between Gateway and Naturita.

SW Co. CO 141 Bridge project map 1

SW Co. CO 141 Bridge project map 2

SW Co. CO 141 Bridge project map 3