Copy
View this email in your browser
Colorado Department of Transportation logo

US 285/CO 9 Fairplay Intersection Improvements & Bridge Replacement

Weekly Traffic Impacts & Work Update


Weekly Traffic Impacts - Feb. 11 to Feb. 17


Please be advised of the following traffic impacts, restrictions and planned work for next week as well as a winter work schedule for the Colorado Department of Transportation's US 285/CO 9 Intersection Improvements and Bridge Replacement project in Park County.

Sunday, Feb. 11 to Saturday, Feb. 17 - US 285 & CO 9 - intermittent overnight lane closures & 24/7 shoulder closures 

  • There are no planned overnight lane closures during this period
  • For the duration of the project, motorists can expect intermittent overnight single lane closures in both directions of U.S. Highway 285 and Colorado Highway 9 from 10 p.m. to 6 a.m. on Sunday and from 8 p.m. to 6 a.m. Monday to Thursday, as needed (except holidays) 
  • During these lane closures, alternating directions of traffic will be shifted into the open lane to bypass the closed lane
  • Flaggers, signs, construction devices and light plants will be present to safely manage traffic flows
  • Lane closure distances will not exceed one mile in length
  • Motorists can expect some delays
  • Shoulder closures and lane narrowing exist on both highways within the project limits
  • Working hours are 7 a.m. to 7 p.m. (sunrise to sunset) Monday to Friday & overnight from 10 p.m. to 6 a.m. Sunday and 8 p.m. to 6 a.m. Monday to Thursday
  • Some Saturday work is also expected
  • No closures will be taken during blackout periods (see below)
  • An 11-foot width restriction is in place
  • Barrier and construction devices are present within the work zone
  • All construction schedules are weather and work dependent and subject to change
Work includes preparing the bridge deck for panels, trenching utilities, installing manholes and inlets, and drilling and pouring lighting caissons.

No Closure/Blackout Periods


No lane closures will be in place during the following holiday periods, weekends or events in Fairplay:

Presidents' Day (Monday, Feb. 19)
Memorial Day Weekend (Friday, May 24 through Monday, May 27)
South Park Trails Marathon (June 2024 - exact dates TBD )
Independence Day Weekend (Thursday, July 4 through Sunday, July 7)

Burro Days (Friday, July 26 through Sunday, July 28)
Living History Days (August 2024 - exact dates TBD)
Labor Day Weekend (Friday, Aug. 30 through Monday, Sept. 2)

 
Views of recent overnight girder placement on the new US 285 bridge superstructure in Fairplay. Ground photography by Basis Partners.


General Project Impacts & Scope of Work

  • The project began in May 2023 with an anticipated completion date of late October  
  • The scope of work includes bridge replacement on US 285 just south of the intersection of US 285/CO 9, intersection improvements, drainage line installation, adding ADA curb ramps in Fairplay and Alma, and making other safety and accessibility upgrades
  • The project limits on US 285 extend from Mile Point 181.83 to MP 184.064 in Fairplay
  • Curb ramp replacement work will also be performed in Fairplay on CO 9 from MP 64.7 to MP 70.4, and in Alma from MP 70.4 to MP 70.9
  • Motorists can expect overnight lane closures in both directions of US 285 and CO 9 during construction
  • Shoulder closures and lane narrowing exist throughout the work zone
  • Motorists can expect longer than normal delays at the US 285/CO 9 intersection on weekends, especially Sunday afternoons, due to heavy corridor traffic backups
  • Alternate routes are strongly advised
  • Motorists can bypass the intersection by taking CR 3 or Platte Drive
  • During curb ramp work, shoulder and sidewalk closures can be expected
  • Reduced speeds (45 mph) and a width restriction of 11 feet are in place
  • All construction schedules are weather and work dependent and subject to change


Winter Work Schedule

  • Crews will work through the winter months, weather permitting
  • Daytime working hours may be reduced
  • Work activities may be limited, depending on weather conditions and temperatures

Stay Connected!

 
Project Webpage: codot.gov/projects/us285-co9intersection/about
Hotline: 720.260.7074
Email:
publicinformation@comcast.net
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2024 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204

You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA