US 285/CO 9 Fairplay Intersection Improvements & Bridge Replacement

Weekly Traffic Impacts & Work Update


Weekly Traffic Impacts - March 3 to March 9


Please be advised of the following traffic impacts, restrictions and planned work for next week for the Colorado Department of Transportation's US 285/CO 9 Intersection Improvements and Bridge Replacement project in Park County.

Sunday, March 3 to Saturday, March 9 - US 285 & CO 9 - intermittent overnight lane closures & 24/7 shoulder closures 

  • There are no planned overnight lane closures during this period
  • Changing traffic conditions exist and caution is advised
  • Traffic control activity is present during working hours and after hours
  • Motorists can expect to encounter heavier than normal truck traffic entering and existing the work zone during daytime hours on Wednesday, March 6 during the concrete deck pour
  • Flaggers and devices will be present to manage traffic flows
  • This deck pour is weather dependent and subject to rescheduling to the following week
  • For the duration of the project, motorists can expect intermittent overnight single lane closures in both directions of U.S. Highway 285 and Colorado Highway 9 from 10 p.m. to 6 a.m. on Sunday and from 8 p.m. to 6 a.m. Monday to Thursday, as needed (except holidays) 
  • During these lane closures, alternating directions of traffic will be shifted into the open lane to bypass the closed lane
  • Flaggers, signs, construction devices and light plants will be present to safely manage traffic flows
  • Lane closure distances will not exceed one mile in length
  • Motorists can expect some delays
  • Shoulder closures and lane narrowing exist on both highways within the project limits
  • Working hours are 7 a.m. to 7 p.m. (sunrise to sunset) Monday to Friday & overnight from 10 p.m. to 6 a.m. Sunday and 8 p.m. to 6 a.m. Monday to Thursday
  • Some Saturday work is also expected
  • No closures will be taken during blackout periods (see below)
  • An 11-foot width restriction is in place
  • Barrier and construction devices are present within the work zone
  • All construction schedules are weather and work dependent and subject to change
Work includes pouring the bridge deck (weather permitting), trenching utilities, setting light poles, and installing inlets.

No Closure/Blackout Periods


No lane closures will be in place during the following holiday periods, weekends or events in Fairplay:

Memorial Day Weekend (Friday, May 24 through Monday, May 27)
South Park Trails Marathon (June 2024 - exact dates TBD )
Independence Day Weekend (Thursday, July 4 through Sunday, July 7)

Burro Days (Friday, July 26 through Sunday, July 28)
Living History Days (August 2024 - exact dates TBD)
Labor Day Weekend (Friday, Aug. 30 through Monday, Sept. 2)

 
Recent drone views of the US 285/CO 9 intersection and south on US 285 in Fairplay.
Aerial photography by Stenback Digital Media.


General Project Impacts & Scope of Work

  • The project began in May 2023 and is expected to be complete by late October  
  • The scope of work includes bridge replacement on US 285 just south of the intersection of US 285/CO 9, intersection improvements, drainage line installation, adding ADA curb ramps in Fairplay and Alma, and making other safety and accessibility upgrades
  • The project limits on US 285 extend from Mile Point 181.83 to MP 184.064 in Fairplay
  • Curb ramp replacement work will also be performed in Fairplay on CO 9 from MP 64.7 to MP 70.4, and in Alma from MP 70.4 to MP 70.9
  • Motorists can expect overnight lane closures in both directions of US 285 and CO 9 during construction
  • Shoulder closures and lane narrowing exist throughout the work zone
  • Motorists can expect longer than normal delays at the US 285/CO 9 intersection on weekends, especially Sunday afternoons, due to heavy corridor traffic backups
  • Alternate routes are strongly advised
  • Motorists can bypass the intersection by taking CR 3 or Platte Drive
  • During curb ramp work, shoulder and sidewalk closures can be expected
  • Reduced speeds (45 mph) and a width restriction of 11 feet are in place
  • All construction schedules are weather and work dependent and subject to change

Stay Connected!

 
Project Webpage: codot.gov/projects/us285-co9intersection/about
Hotline: 720.260.7074
Email:
publicinformation@comcast.net
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2024 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204

You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA