US 40 ADA Ramp Upgrades, Grand County & Jackson County

Work this Week

October 26 – 29

Ongoing Traffic Impacts

  • There will be intersection cleanup at various locations in the Town’s of Walden, Hot Sulphur Springs, Winter Park, Granby, Kremmling, and Fraser.
  • The project will be in operation Monday through Thursday from 8 a.m. to 5 p.m.

For more information or to be added to the project update list please call 970-765-8443 email [email protected] It is important that the contractors and the traveling public stay safe during this project, please be aware and obey all traffic signage and restrictions and maintain social distancing from the work zones.

For information about other CDOT projects the public may log on to CDOT'S traveler information website at www.codot.gov, www.cotrip.org or call 511 from anywhere in the state.

About the Project

This project consists of improvements to bring existing curb ramps into compliance with PROWAG requirements. The work to be performed includes improvements to curb ramps, curb and gutter and sidewalks. Curb ramp replacements are located in various areas throughout the towns of Kremmling, Granby, Fraser, Winter Park, Hot Sulphur Springs, and Walden. Grand County, Jackson County. 

Work on this project includes:

Kremmling:

6th St. From Grand/ Eagle Ave. Sidewalk ramps on corners, Westbound, Downtown. Park Ave. from Pine St. to 7th St. Sidewalk ramps on corners, Eastbound

Granby:

Agate Ave. (US HWY 40) from Mesa St. to 6th St. Eastbound, Sidewalk ramps on corners. US HWY 40 from Edgewater Dr. to Thompson Rd., Southbound, Sidewalk ramps on corners (possible on ramp)

Winter Park:

US HWY 40 (Main Street) east and westbound at Kings Crossing RD., High Country Dr., Rosie's Way, Miller Rd., Rendezvous Way, Cooper Creek Way, Vasquez RD., Winter Park Dr. and Village Dr. , On Hwy 40: Old Town Dr., Lakota Trail

Fraser:

US HWY 40 from Park Ave. to First St., Southbound, ramps on corners of intersection

Hot Sulphur Springs:

Byers Ave. from Spring St. to Hemlock St., Eastbound, ramps on corners of intersection.

Walden:

Main St. from 6th St.. to 4th St., ramps on corners of intersection.

Project Facts

  • Cost: $1.7 Million
  • Contractor: KSK, LLC
  • Timeline: May - October 2020
  • Location: US 40 in Grand and Jackson Counties


Proposed Work Schedule

  • Work began Tuesday, May 26, 2020, on 6th Street and Park Avenue in the Town of Kremmling.
  • The general schedule (subject to change) began Tuesday, May 26, 2020, and is expected to be completed late September, weather permitting.
  • Project operation hours are M-Th, 7am - 7pm.
  • Contractors are complying with the latest guidelines set by the State of Colorado for work zones during the COVID-19 response.

Traffic Impacts

  • Travelers by car, bike, wheelchair or foot can expect various lane and sidewalk closures where work zones exist, during daylight hours, Monday through Friday.
  • Sidewalks are likely to be closed overnight or over weekends to allow the concrete to set up.
  • Access to all businesses will be maintained but may be temporarily altered.