Phase 3: Southwest Quadrant Improvements US 6 & Wadsworth Boulevard
|
|
Weekly Traffic Impacts & Work Update
|
|
|
Weekly Traffic Impacts - Feb. 4 to Feb. 10
Please be advised of the following traffic impacts, restrictions and planned work for next week for the Phase 3 Southwest Quadrant Improvements at US 6 and Wadsworth Blvd project in Jefferson County.
|
|
General Traffic Impacts
Tuesday, Feb. 6 & Wednesday, Feb. 7 - eastbound US 6 - single overnight lane closures
- Single overnight right lane closures will be taken on eastbound US 6 from Carr St. to the Wadsworth Blvd. interchange during overnight hours on Tuesday and Wednesday
- The closures will be in place from 7 p.m. to 6 a.m.
- The project limits are confined to Mile Point 280.36 to MP 280.84
- Signs and devices are in place to alert residents and motorists to the work zone, closures and restrictions
- All construction schedules are weather dependent and subject to change
Work includes installing temporary barrier and restriping lanes.
Tuesday, Feb. 6 to Saturday, Feb. 10 - W. 6th Ave Frontage Road on-ramp to eastbound US 6 - 24/7 closure till early fall
- A 24/7 closure of the Frontage Road on-ramp to eastbound US 6 at Carr St. will be in place from Tuesday, Feb. 6 until early fall, with detour signage routing motorists to access eastbound US 6 at the interchange
- The closure is necessary to maintain safety during noise wall and auxiliary lane construction
- All construction schedules are weather dependent and subject to change
Work includes removing existing barrier and asphalt, and restriping lanes.
Monday, Feb. 5 to Friday, Feb. 9 - W. 6th Ave Frontage Road Meadowlark Drive to Wadsworth Blvd interchange - daytime lane closures
- Lane closures will be in place during initial work on the roadway
- Closures will be taken from 7 a.m. to 5 p.m. Monday to Friday
- Daily block to block closures will exist once noise wall and auxiliary lane work begins, with minor detours to adjacent side streets
- Flaggers will be present to manage traffic flows
- Signs and devices are in place to alert residents and motorists to the work zone, closures and restrictions
- Local access to driveways will be maintained
Work includes removing existing barrier and asphalt, and restriping lanes.
|
|
Project location and scope of work for the Phase 3 Southwest Quadrant Improvements as part of the overall US 6 & Wadsworth Interchange project.
|
|
General Impacts, Schedule & Scope of Work
- The project began on Jan. 29 and has an anticipated completion date of Jan. 31, 2025
- Periodic overnight lane and ramp closures will be taken on eastbound U.S. Highway 6 between Carr Street and the Wadsworth Blvd. interchange during certain work activities
- These single overnight lane closures on eastbound US 6 will be in place from 7 p.m. to 6 a.m. weekdays and 7 p.m. to 9 a.m. on weekends, as needed
- A 24/7 closure of the Frontage Road on-ramp to eastbound US 6 at Carr St. is in place from Feb. 6 to early fall, with traffic detoured to the Wadsworth interchange to enter eastbound US 6
- Daytime weekday block to block closures along the Frontage Road from Meadowlark Drive to the Wadsworth Blvd off-ramp will exist, with minor detours in place to adjacent side streets
- Flaggers will be present on the Frontage Road as needed during working hours and local access will be maintained
- The project limits on US 6 extend from MP 280.36 to MP 280.84
- The project limits on the Frontage Road south of US 6 extend from just west of Meadowlark Drive to the Wadsworth Blvd off-ramp
- Work on the auxiliary lane and noise walls will progress west to east
- The project limits on Wadsworth Blvd extend from Highland Drive to 4th Ave or MP 12.21 to MP 12.66
- Some overnight and weekend work can be expected later in the project
- This state and federally funded project is the third of a five-phase project to reconstruct the US 6 & Wadsworth Interchange
- This phase is designed to enhance pedestrian connectivity and mitigate traffic noise
- Construction schedules are weather dependent and subject to change
|
|
|
|
|