US 24 Curve Correction in Teller County

Weekly Traffic Impacts & Work Update


Traffic Impacts - Aug. 6 to Aug. 12


Please be advised of the following lane and highway closures and other restrictions for next week for the US 24 Curve Correction project east of Florissant. All schedules are weather dependent and subject to change.

*****
Travel Advisory - Full Daytime Closures US 24 - Aug. 7 to Aug. 9
  • Both directions of US 24 will be fully closed during daytime hours over three consecutive weekdays during paving operations
  • The closures will be in place from 7 a.m. to 7 p.m. on Monday, Aug. 7, Tuesday, Aug. 8 and Wednesday, Aug. 9
  • During the full closures, both directions of traffic on US 24 will be stopped by uniformed traffic control personnel and flaggers and directed to recommended detour routes
  • Emergency access to first responders will be permitted
  • Access to residences within the work zone will be maintained
  • The closure area extends from Florissant to west of Divide (see map)
  • The project limits are Mile Point 272.6 to MP 272.9 and the approach area is from MP 271 to MP 274
  • The full closures are necessary to allow construction crews to pave the highway and add safety features
  • The recommended detour routes will add approximately 10 miles and 7 minutes to travel times
  • Barricades, temporary stop bars, signs and construction devices will also be present to alert motorists to changing road conditions
  • Speeds will be reduced and caution is advised while driving through the local detour roads
  • A width restriction of 10.5 feet exists on US 24 within the work zone for the remainder of the project
  • All schedules are weather dependent and subject to change
Work includes paving and striping.
*****
Daily Lane Closures - Thursday, Aug. 10 & Friday, Aug. 11 - US 24
  • Single lane closures on US 24 will be in place within the work zone 
  • The closures will be taken during daylight hours between approx. 8 a.m. and 8 p.m. on Thursday, and from 8 a.m. to noon on Friday
  • During lane closures, alternating eastbound/westbound directions of traffic will be shifted into the open lane, managed by uniformed traffic control personnel and/or flaggers
  • Motorists can expect delays up to 15 minutes during alternating traffic holds
  • Signs and construction devices will be present to alert motorists to the closures and presence of work crews
  • Speeds are reduced to 40 mph in the work zone
  • Caution is advised
  • All closures are weather and work dependent and subject to change
Work includes striping and adding signs and lane delineators.
Map of the project work zone on US 24 between Florissant and Divide, including detour routes.

General Travel Advisory

  • The project limits extend from Mile Point 272.6 to MP 272.9
  • During single lane closures of US 24, alternating directions of traffic will be managed by uniformed traffic control personnel and/or flaggers
  • Motorists can expect delays up to 15 minutes during traffic holds
  • CDOT has authorized up to five full daytime closures of US 24 (no more than five occurrences) during construction
  • During these full daytime closures of US 24, all traffic will be detoured to recommended routes
  • The project began on May 1 and is expected to last for approx. 75 calendar days, not including delays due to weather events
  • All construction schedules are weather and work dependent and subject to change
Crews preparing the shoulders and roadway on US 24 prior to milling and paving.
Photo by Monica Ramey.

Nearby Project Impacts


Bridge Repair Project - US 24 east of Florissant
  • Crews are repairing two structures between MP 271 and 272
  • Shoulder closures and lane closures will be taken over the course of construction
  • Work is expected to last until September
Please refer to the project webpage for more information.
 

Stay Connected!

 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2023 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W. Howard Place
Denver CO 80204


You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA