I-25 Walsenburg Bridge Replacement
|
|
Weekly Traffic Impacts & Work Update
|
|
|
Weekly Traffic Impacts - Dec. 24 to Dec. 30
Please be advised of the following traffic impacts, closures and restrictions for next week for the I-25 Walsenburg Bridge Replacement project in Huerfano County.
**Schedule Reminder - No work will be performed during the holiday week of Dec. 24 to Jan. 1. Crews will return on Tuesday, Jan. 2, 2024.**
|
|
Weekday Traffic Impacts
Monday, Dec. 25 to Friday, Dec. 29 - both directions of CO 10 under I-25 - no planned lane closures
- No closures are planned for this week
- Colorado Highway 10 at the U.S. Highway 160 junction under I-25 will remain open until the next phase of safety critical work, with intermittent lane closures in place
- Lane closures will be taken during working hours, with alternating directions of traffic managed by flagger operations
- Working hours are half an hour after sunrise to half an hour before sunset, Monday to Friday
- Some Saturday work is expected
- CDOT will reclose both directions of the highway during safety critical construction activities
- All stakeholders will be notified in advance of the next full closure
- During full closures, detour routes will be posted with up to 10 miles and 7 minutes in additional travel time expected
- Closures are necessary to maintain safety for the railroads, the construction crews, the surrounding community, and the traveling public
- The project/closure limits extend from Mile Point 0 to MP .25
- All construction schedules are weather and work dependent and subject to change
|
|
Crews drilling caissons for the new southbound I-25 bridge structure.
Photo by Siete, Inc.
|
|
Ongoing Traffic Impacts
Sunday, Dec. 24 to Saturday, Dec. 30 - 24/7 single lane alignment - both directions of I-25
- Both directions of traffic on I-25 are reduced to a single lane within the project limits
- The lanes have been shifted to the northbound side of I-25 via median crossover detour pavement
- The project limits extend from MP 51 to MP 49 on I-25 at the approaches to and at Exit 50 in Huerfano County
- This single lane alignment will remain in place until further notice
- A width restriction of 12 feet is in place
- Speeds are reduced to 55 mph
- The northbound I-25 on and off ramps are open
- The southbound I-25 on and off ramps are closed (see detail below)
- Caution is advised
*****
Sunday, Dec. 24 to Saturday, Dec. 30 - 24/7 closure - southbound I-25 on and off ramps
- The southbound I-25 on and off ramps at Exit 50 are closed, with detour routes in place
- These ramp closures will remain in place 24/7 for about six months while crews remove and replace the southbound I-25 bridge structure
- Detour signs will be present alerting motorists to alternate routes
|
|
Suggested detour routes during the full closure of the southbound I-25 ramps at Exit 50.
|
|
Temporary Playground Closure
Please be advised that the playground located at S. Grant Ave. and Colorado Ave. is closed while crews replace an underground sanitary sewer line.
- The playground will remain closed until further notice
- The closure is in place to maintain public safety during underground utility work
- Fencing and signs are present alerting the public to the closure
|
|
General Impacts & Scope of Work
- Work began in March with expected completion by late 2024
- Impacts include a single lane alignment in both directions of I-25 during removal and replacement of the southbound I-25 bridge structure
- 24/7 closure of the southbound I-25 on and off ramps at Exit 50 during removal and replacement of the southbound I-25 bridge
- Periods of full closure of both directions of CO 10 under I-25, with detour routes in place during safety critical work
- Weekday lane closures in both directions of CO 10, managed by flaggers
- Lane closures in both directions of I-25 and on CO 10 below the bridges during various phases of work
- This state and federally funded infrastructure upgrade project is designed to improve the safety of two aging bridges to support increased traffic on the I-25 corridor
- Work includes rehabilitating the northbound I-25 bridge deck, building median crossover pavement to shift traffic, and removing and replacing the southbound I-25 bridge structure
- The new bridge will be built to meet today's standards
- Other planned work includes widening and improving the on and off ramps, relocating a sanitary sewer line, and adding guardrail, signs, and safety features.
|
|
|
|
|