I-25 Walsenburg Bridge Replacement

Weekly Traffic Impacts & Work Update

 

Weekly Traffic Impacts - March 17 to March 23


Please be advised of the following traffic impacts, restrictions and planned work for next week for the I-25 Walsenburg Bridge Replacement project in Huerfano County.

Weekday Traffic Impacts


Monday, March 18 to Friday, March 22 - both directions of Colorado Highway 10 under I-25 - intermittent daytime lane closures, managed by flagger operations
  • CO 10 under I-25 will remain open until the next phase of safety critical work, with intermittent daytime lane closures in place
  • Lane closures will be taken during working hours, with alternating directions of traffic managed by flagger operations
  • Working hours are half an hour after sunrise to half an hour before sunset, Monday to Friday
  • Some Saturday work is expected
  • CDOT will reclose both directions of the highway during safety critical construction activities
  • All stakeholders will be notified in advance of the next full closure
  • During full closures, detour routes will be posted with up to 10 miles and 7 minutes in additional travel time expected
  • Closures are necessary to maintain safety for the railroads, the construction crews, the surrounding community, and the traveling public
  • The project/closure limits extend from Mile Point 0 to MP .25
  • Construction schedules are weather dependent and subject to change
Work includes forming and pouring pier columns, and driving H-pile beams for the north abutment.
 Recent view of installed H-pile beams for the new southbound I-25 bridge at Exit 50. Photography by Siete, Inc.

Ongoing Traffic Impacts
 

Sunday, March 17 to Saturday, March 23 - 24/7 single lane alignment - both directions of I-25 
  • Both directions of traffic on I-25 are reduced to a single lane within the project limits
  • The lanes have been shifted to the northbound side of I-25 via median crossover detour pavement
  • The project limits extend from MP 51 to MP 49 on I-25 at the approaches to and at Exit 50 in Huerfano County
  • This single lane alignment will remain in place until further notice
  • A width restriction of 12 feet is in place
  • Speeds are reduced to 55 mph
  • The northbound I-25 on and off ramps are open
  • The southbound I-25 on and off ramps are closed (see detail below)
  • Caution is advised
Sunday, March 17 to Saturday, March 23 - 24/7 closure - southbound I-25 on and off ramps
  • The southbound I-25 on and off ramps at Exit 50 are closed, with detour routes in place
  • These ramp closures will remain in place 24/7 for about six months while crews remove and replace the southbound I-25 bridge structure
  • Detour signs will be present alerting motorists to alternate routes
Suggested detour routes during the full closure of the southbound I-25 ramps at Exit 50.

Temporary Playground Closure 


Please be advised that the playground located at S. Grant Ave. and Colorado Ave. is closed while crews replace an underground sanitary sewer line. 
  • The playground will remain closed until further notice
  • The closure is in place to maintain public safety during underground utility work
  • Fencing and signs are present alerting the public to the closure

General Impacts & Scope of Work

  • Work began in March 2023 with expected completion by late 2024
  • Impacts include a single lane alignment in both directions of I-25 during removal and replacement of the southbound I-25 bridge structure
  • 24/7 closure of the southbound I-25 on and off ramps at Exit 50 during removal and replacement of the southbound I-25 bridge
  • Periods of full closure of both directions of CO 10 under I-25, with detour routes in place during safety critical work
  • Weekday lane closures in both directions of CO 10, managed by flaggers
  • Lane closures in both directions of I-25 and on CO 10 below the bridges during various phases of work
  • This state and federally funded infrastructure upgrade project is designed to improve the safety of two aging bridges to support increased traffic on the I-25 corridor
  • Work includes rehabilitating the northbound I-25 bridge deck, building median crossover pavement to shift traffic, and removing and replacing the southbound I-25 bridge structure
  • The new bridge will be built to meet today's standards
  • Other planned work includes widening and improving the on and off ramps, relocating a sanitary sewer line, and adding guardrail, signs, and safety features.

Stay Connected!

 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2024 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204


You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA