I-70 over Ward Road Bridge Replacement

Weekly Traffic Impacts & Work Update

 

Weekly Traffic Impacts - April 28 to May 6


Please be advised of the following travel alert, traffic impacts, restrictions and planned work for next week through the weekend for the I-70 over Ward Road Bridge Replacement project in Wheat Ridge, Jefferson County. 

Travel Alert


Friday, May 3 to Monday, May 6 - continuous closure - Ward Road/CO 72 (Exit 266) on ramp to westbound I-70 & right lane closure
  • Starting at 7 p.m. on Friday, May 3 and lasting until 6 a.m. on Monday, May 6, the Ward Road on ramp to westbound I-70 will be fully closed
  • This extended closure was originally scheduled for April 26-29 but was postponed due to adverse weather conditions
  • The recommended detour route is: south on Ward Rd to W. 44th Ave., south on Youngfield St, and west to W. 40th Ave. to Clear Creek Drive to enter westbound I-70 at Exit 264 (Clear Creek Dr/32nd Ave) - please refer to the map below for details
  • The detour will add approximately 2 miles and 5 minutes to travel times
  • Other detour routes do exist 
  • Motorists can expect delays
  • A single right lane closure on westbound I-70 will also be taken during this extended weekend closure period
  • Signs, message boards and construction devices will be present to alert the public to the closures and alternate routes
Work includes removing asphalt and concrete, preparing subgrade, fast track paving on mainline westbound I-70, and SMA paving the bridge surface.

Ongoing Impacts & Planned Work


Monday, April 29 to Thursday, May 2 - westbound I-70 at Ward Road - no traffic impacts

Friday, May 3 to Monday, May 6 - westbound I-70 at Ward Road - full closure on ramp & right lane closure
  • No impacts are expected Monday to Thursday
  • Starting at 7 p.m. on Friday, May 3 and lasting until 6 a.m. on Monday, May 6, the Ward Road on ramp to westbound I-70 will be fully closed (see Travel Alert above)
  • This extended closure is weather dependent and subject to change
  • The recommended detour route is: south on Ward Rd to W. 44th Ave., south on Youngfield St, and west to W. 40th Ave. to Clear Creek Drive to enter westbound I-70 at Exit 264 (Clear Creek Dr/32nd Ave) - please refer to the map below for details
  • The detour will add approximately 2 miles and 5 minutes to travel times
  • Other detour routes do exist 
  • Motorists can expect delays
  • A single right lane closure on westbound I-70 will also be taken during this extended weekend closure period
  • Signs, message boards and construction devices will be present to alert the public to the closures and alternate routes
  • Work includes removing asphalt and concrete, preparing subgrade, fast track paving on mainline westbound I-70, and SMA paving the bridge surface.
Work includes removing asphalt and concrete, preparing subgrade, fast track paving on mainline westbound I-70, and SMA paving the bridge surface.
Recommended detour route highlighted in blue during the full extended closure of the Ward Road on ramp to westbound I-70.

 

Monday, April 29 to Thursday, May 2 - both directions of Ward Rd/CO 72 under I-70 - no planned daytime lane closures

Friday, May 3 to Monday, May 6 - periodic lane closures concurrent with full extended closure of the Ward Road on-ramp to westbound I-70
  • There are no planned lane closures Monday to Thursday
  • Periodic single lane closures switching to double lane closures may exist in both directions of Ward Road under I-70 concurrent with the full closure of the Ward Road on ramp to westbound I-70 from Friday, May 3 to Monday, May 6
  • The closures will be taken from approx. 7 p.m. on Friday to 6 a.m. on Monday, only as needed
  • The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange) 
  • Flaggers will be present to manage traffic flows
  • Signs, message boards and construction devices are in place alerting motorists and pedestrians to the work and closures
  • Sidewalk access is limited and caution is advised
  • Construction schedules are weather dependent and subject to change

General Travel Impacts, Schedule & Scope of Work

 
  • The project began in February 2023 with anticipated full completion by late 2024
  • Periodic overnight lane and ramp closures will be taken in both directions of I-70 at Ward Road (Exit 266) Sunday to Thursday, during certain work activities
  • Daytime single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70 Monday to Friday for access to the work zone
  • These weekday closures will be in place from 7 a.m. to approx. 6 p.m.
  • Some weekend work is expected, with lane closures taken in both directions of Ward Road, as needed
  • Ward Road/CO 72 under I-70 will be fully closed during safety critical bridge work, with detours in place
  • During full closures of Ward Road or the westbound I-70 on-ramp, motorists will be detoured to Youngfield Ave to access Exit 264 (Clear Creek Drive/32nd Ave) or the Frontage Road to access I-70 via Kipling St 
  • This state funded project is part of CDOT’s 10-Year Plan to replace two aging bridges on I-70 over Ward Road with a single structure
  • This new structure is being built to meet today's standards to support increased traffic on the I-70 corridor

Nearby Project Impacts


Harlan St Bridge Replacement & Interchange Improvement project
  • Impacts include full periodic closures of the Harlan St. interchange, the Exit 270 on and off ramps to westbound I-70, and other lane and road closures within the project's limits
  • Motorists will be detoured to Wadsworth Blvd to bypass ramp closures
  • This project has an estimated completion date of February 2025

Stay Connected!

 
Webpagecodot.gov/projects/i70-ward-road-bridges
Hotline720.600.4794
Email:
publicinformation@comcast.net
Sign up for Text Alerts: text wardbridges to 8882199094
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2024 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204


You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA