I-70 over Ward Road Bridge Replacement

Weekly Traffic Impacts & Work Update

 

Weekly Traffic Impacts - April 7 to April 13


Please be advised of the following traffic impacts, restrictions and planned work for next week for the I-70 over Ward Road Bridge Replacement project in Jefferson County.

Ongoing Impacts & Planned Work


Sunday, April 7 to Friday, April 12 - westbound I-70 at Ward Road  - no planned closures; crews working behind barrier during daytime hours
  • No overnight lane or ramp closures are planned on westbound I-70 within the project limits from Sunday to Thursday
  • Crews will be working behind barrier with no impacts to traffic
  • Daytime hours are 7 a.m. to approx. 6 p.m. Monday to Friday
  • The project limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
  • A traffic shift is in place on westbound I-70
  • Lanes are narrowed and barrier is in place
  • Crews will be present in the median and shoulder areas and extreme caution is advised
  • Construction schedules are weather dependent and subject to change
Work includes installing concrete pavement and preparing shoulders for placement of road base.

 

Monday, April 8 to Friday, April 12 - both directions of Ward Rd/CO 72 under I-70 - periodic daytime lane closures
  • Periodic single lane closures switching to double lane closures will exist in both directions of Ward Road under I-70 during daytime hours
  • Motorists can also expect changing lane closure conditions as crews switch from side to side during work activities on mainline I-70
  • The weekday closures will be taken from approx. 7 a.m. to 6 p.m. Monday to Friday
  • The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange) 
  • Flaggers will be present to manage traffic flows
  • Signs and construction devices are in place alerting motorists and pedestrians to the work and closures
  • Some Saturday work is expected
  • Sidewalk access is limited and caution is advised
  • Construction schedules are weather dependent and subject to change
Work includes accessing westbound I-70 during installation of concrete pavement and placement of road base in the shoulder areas.
Crews placing road base on a section of westbound I-70 prior to concrete paving. 
Photography by Adam Baranowski.

General Travel Impacts, Schedule & Scope of Work

 
  • The project began in February 2023 with anticipated full completion by late 2024
  • Periodic overnight lane and ramp closures will be taken in both directions of I-70 at Ward Road (Exit 266) Sunday to Thursday, during certain work activities
  • Daytime single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70 Monday to Friday for access to the work zone
  • These weekday closures will be in place from 7 a.m. to approx. 6 p.m.
  • Some weekend work is expected, with lane closures taken in both directions of Ward Road, as needed
  • Ward Road/CO 72 under I-70 will be fully closed during safety critical bridge work, with detours in place
  • During full closures of Ward Road or the westbound I-70 on-ramp, motorists will be detoured to Youngfield Ave to access Exit 264 (Clear Creek Drive/32nd Ave) or the Frontage Road to access I-70 via Kipling St 
  • This state funded project is part of CDOT’s 10-Year Plan to replace two aging bridges on I-70 over Ward Road with a single structure
  • This new structure is being built to meet today's standards to support increased traffic on the I-70 corridor

Nearby Project Impacts


Harlan St Bridge Replacement & Interchange Improvement project
  • Impacts include full periodic closures of the Harlan St. interchange, the Exit 270 on and off ramps to westbound I-70, and other lane and road closures within the project's limits
  • Motorists will be detoured to Wadsworth Blvd to bypass ramp closures
  • This project has an estimated completion date of February 2025

Stay Connected!

 
Webpagecodot.gov/projects/i70-ward-road-bridges
Hotline720.600.4794
Email:
publicinformation@comcast.net
Sign up for Text Alerts: text wardbridges to 8882199094
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2024 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204


You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA