I-70 over Ward Road Bridge Replacement
|
|
Weekly Traffic Impacts & Work Update
|
|
|
Weekly Traffic Impacts - April 7 to April 13
Please be advised of the following traffic impacts, restrictions and planned work for next week for the I-70 over Ward Road Bridge Replacement project in Jefferson County.
|
|
Ongoing Impacts & Planned Work
Sunday, April 7 to Friday, April 12 - westbound I-70 at Ward Road - no planned closures; crews working behind barrier during daytime hours
- No overnight lane or ramp closures are planned on westbound I-70 within the project limits from Sunday to Thursday
- Crews will be working behind barrier with no impacts to traffic
- Daytime hours are 7 a.m. to approx. 6 p.m. Monday to Friday
- The project limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
- A traffic shift is in place on westbound I-70
- Lanes are narrowed and barrier is in place
- Crews will be present in the median and shoulder areas and extreme caution is advised
- Construction schedules are weather dependent and subject to change
Work includes installing concrete pavement and preparing shoulders for placement of road base.
|
|
Monday, April 8 to Friday, April 12 - both directions of Ward Rd/CO 72 under I-70 - periodic daytime lane closures
- Periodic single lane closures switching to double lane closures will exist in both directions of Ward Road under I-70 during daytime hours
- Motorists can also expect changing lane closure conditions as crews switch from side to side during work activities on mainline I-70
- The weekday closures will be taken from approx. 7 a.m. to 6 p.m. Monday to Friday
- The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange)
- Flaggers will be present to manage traffic flows
- Signs and construction devices are in place alerting motorists and pedestrians to the work and closures
- Some Saturday work is expected
- Sidewalk access is limited and caution is advised
- Construction schedules are weather dependent and subject to change
Work includes accessing westbound I-70 during installation of concrete pavement and placement of road base in the shoulder areas.
|
|
Crews placing road base on a section of westbound I-70 prior to concrete paving.
Photography by Adam Baranowski.
|
|
General Travel Impacts, Schedule & Scope of Work
- The project began in February 2023 with anticipated full completion by late 2024
- Periodic overnight lane and ramp closures will be taken in both directions of I-70 at Ward Road (Exit 266) Sunday to Thursday, during certain work activities
- Daytime single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70 Monday to Friday for access to the work zone
- These weekday closures will be in place from 7 a.m. to approx. 6 p.m.
- Some weekend work is expected, with lane closures taken in both directions of Ward Road, as needed
- Ward Road/CO 72 under I-70 will be fully closed during safety critical bridge work, with detours in place
- During full closures of Ward Road or the westbound I-70 on-ramp, motorists will be detoured to Youngfield Ave to access Exit 264 (Clear Creek Drive/32nd Ave) or the Frontage Road to access I-70 via Kipling St
- This state funded project is part of CDOT’s 10-Year Plan to replace two aging bridges on I-70 over Ward Road with a single structure
- This new structure is being built to meet today's standards to support increased traffic on the I-70 corridor
|
|
Nearby Project Impacts
Harlan St Bridge Replacement & Interchange Improvement project
- Impacts include full periodic closures of the Harlan St. interchange, the Exit 270 on and off ramps to westbound I-70, and other lane and road closures within the project's limits
- Motorists will be detoured to Wadsworth Blvd to bypass ramp closures
- This project has an estimated completion date of February 2025
|
|
|
|
|