I-70 over Ward Road Bridge Replacement

Weekly Traffic Impacts & Work Update

 

Weekly Traffic Impacts - March 10 to March 16


Please be advised of the following traffic impacts, restrictions and planned work for next week for the I-70 over Ward Road Bridge Replacement project in Jefferson County.

Ongoing Impacts & Planned Work


Sunday, March 10 to Thursday, March 14 - I-70 at Ward Road  - no planned overnight lane or ramp closures - westbound traffic shift in place
  • No overnight lane or ramp closures are planned on I-70 within the project limits
  • Periodic short-term early morning lane closures may exist from 4 a.m. to 6 a.m. Monday to Friday for equipment mobilization
  • The project limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
  • A traffic shift is in place on westbound I-70
  • Lanes are narrowed and barrier is in place
  • Crews will be working behind barrier during daytime hours 
  • Caution is advised
Work includes excavating roadway and installing base course, and forming and pouring barrier and transition sections.

 

Monday, March 11 to Friday, March 15 - both directions of Ward Rd/CO 72 under I-70 - daytime shifting lane closures
  • Single lane closures switching to double lane closures will exist in both directions of Ward Road under I-70 during daytime hours Monday to Friday
  • Motorists can expect changing lane closure conditions as crews switch from side to side during work activities
  • The weekday closures will be taken from approx. 7 a.m. to 6 p.m.
  • The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange) 
  • Flaggers will be present to manage traffic flows
  • Signs and construction devices are in place alerting motorists and pedestrians to the work and closures
  • Some Saturday work is expected
  • Sidewalk access is limited and caution is advised
  • Construction schedules are weather dependent and subject to change
Recent views of overhang, deck edge and rebar installation for the new westbound I-70 bridge over Ward Road. Photography by Neil Olson.

General Travel Impacts & Scope of Work

  • The project began in February 2023 with anticipated full completion by late 2024
  • Periodic overnight lane and ramp closures will be taken in both directions of I-70 at Ward Road (Exit 266) Sunday to Thursday, during certain work activities
  • Daytime single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70 Monday to Friday for access to the work zone
  • These weekday closures will be in place from 7 a.m. to approx. 6 p.m.
  • Some Saturday work is expected
  • Ward Road/CO 72 under I-70 will be fully closed during safety critical bridge work, with detours in place
  • During full closures of Ward Road or the westbound I-70 on-ramp, motorists will be detoured to Youngfield Ave to access Exit 264 (Clear Creek Drive/32nd Ave) or the Frontage Road to access I-70 via Kipling St 
  • This state funded project is part of CDOT’s 10-Year Plan to replace two aging bridges on I-70 over Ward Road with a single structure
  • This new structure is being built to meet today's standards to support increased traffic on the I-70 corridor

Nearby Project Impacts


Harlan St Bridge Replacement & Interchange Improvement project
  • Impacts include full periodic closures of the Harlan St. interchange, the Exit 270 on and off ramps to westbound I-70 and other lane and road closures within the project's limits
  • Motorists will be detoured to Wadsworth Blvd to bypass ramp closures
  • This project has an estimated completion date of February 2025

Stay Connected!

 
Webpagecodot.gov/projects/i70-ward-road-bridges
Hotline720.600.4794
Email:
publicinformation@comcast.net
Sign up for Text Alerts: text wardbridges to 8882199094
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2024 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204


You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA