Weekly Traffic Impacts - April 14 to April 20


Please be advised of the following travel alert, traffic impacts, restrictions and planned work for next week for the I-70 over Ward Road Bridge Replacement project in Jefferson County.

Travel Alert


Sunday, April 14 - full overnight closure - Ward Road/CO 72 on ramp to westbound I-70
  • Starting at 7 p.m. on Sunday, April 14 and lasting until approx. 6 a.m. on Monday, April 15, the Ward Road/CO 72 (Exit 266) on ramp to westbound I-70 will be fully closed
  • The recommended detour route is: south on Ward Rd to W. 44th Ave., south on Youngfield St, and west to W. 40th Ave. to Clear Creek Drive to enter westbound I-70 at Exit 264 (Clear Creek Dr/32nd Ave) - please refer to the map below for details
  • The detour will add approximately 2 miles and 5 minutes to travel times
  • Other detour routes do exist 
  • Motorists can expect delays
  • A single right lane closure on westbound I-70 and double lane closures in each direction of Ward Road under I-70 will also be taken during this overnight period
  • Signs, message boards and devices will be present to alert the public to the closures and alternate routes
  • All construction schedules are weather dependent and subject to change
Work includes sawcutting asphalt and concrete on the north side of westbound I-70.
Recommended detour route (in blue) during full closure of the Ward Road on ramp to westbound I-70.

Ongoing Impacts & Planned Work


Sunday, April 14 to Friday, April 19 - westbound I-70 at Ward Road  - full overnight on-ramp & single right lane closure on Sunday; no impacts while crews work behind barrier during daytime hours Monday to Friday
  • The Ward Road on ramp to westbound I-70 will be fully closed during overnight hours on Sunday, April 14 (see Travel Alert above)
  • A single right lane closure will be taken on westbound I-70 within the project limits during overnight hours on Sunday, April 14
  • The overnight closures will be in place from 7 p.m. to 6 a.m.
  • Monday to Friday, crews will be working behind barrier with no planned impacts to traffic 
  • Daytime hours are 7 a.m. to approx. 6 p.m. Monday to Friday
  • The project limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
  • A traffic shift is in place on westbound I-70
  • Lanes are narrowed and barrier is in place
  • Crews will be present in the median and shoulder areas and extreme caution is advised
  • Construction schedules are weather dependent and subject to change
Work includes sawcutting asphalt and concrete, sealing joints, installing bottom mats of asphalt, and waterproofing the bridge deck.

 

Sunday, April 14 to Friday, April 19 - both directions of Ward Rd/CO 72 under I-70 - overnight double lane closures on Sunday & periodic daytime lane closures Monday to Friday
  • Sunday, April 14 - Double lane closures will be in place in both directions of Ward Road under I-70 during overnight hours concurrent with the full closure of the westbound I-70 on ramp (see Travel Alert above)
  • The closures will be taken from 7 p.m. to 6 a.m.
  • Periodic single lane closures switching to double lane closures will exist in both directions of Ward Road under I-70 during daytime hours Monday to Friday
  • The weekday closures will be taken from approx. 7 a.m. to 6 p.m. Monday to Friday
  • The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange) 
  • Flaggers will be present to manage traffic flows
  • Signs and construction devices are in place alerting motorists and pedestrians to the work and closures
  • Some weekend work is expected
  • Sidewalk access is limited and caution is advised
  • Construction schedules are weather dependent and subject to change
Work includes accessing westbound I-70 during asphalt and concrete sawcutting, sealing joints, and waterproofing the bridge deck.
Crews concrete paving a section of westbound I-70 up to the new Ward Road bridge structure. Photography by Neil Olson.

General Travel Impacts, Schedule & Scope of Work

 
  • The project began in February 2023 with anticipated full completion by late 2024
  • Periodic overnight lane and ramp closures will be taken in both directions of I-70 at Ward Road (Exit 266) Sunday to Thursday, during certain work activities
  • Daytime single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70 Monday to Friday for access to the work zone
  • These weekday closures will be in place from 7 a.m. to approx. 6 p.m.
  • Some weekend work is expected, with lane closures taken in both directions of Ward Road, as needed
  • Ward Road/CO 72 under I-70 will be fully closed during safety critical bridge work, with detours in place
  • During full closures of Ward Road or the westbound I-70 on-ramp, motorists will be detoured to Youngfield Ave to access Exit 264 (Clear Creek Drive/32nd Ave) or the Frontage Road to access I-70 via Kipling St 
  • This state funded project is part of CDOT’s 10-Year Plan to replace two aging bridges on I-70 over Ward Road with a single structure
  • This new structure is being built to meet today's standards to support increased traffic on the I-70 corridor

Nearby Project Impacts


Harlan St Bridge Replacement & Interchange Improvement project
  • Impacts include full periodic closures of the Harlan St. interchange, the Exit 270 on and off ramps to westbound I-70, and other lane and road closures within the project's limits
  • Motorists will be detoured to Wadsworth Blvd to bypass ramp closures
  • This project has an estimated completion date of February 2025

Stay Connected!

 
Webpagecodot.gov/projects/i70-ward-road-bridges
Hotline720.600.4794
Email:
publicinformation@comcast.net
Sign up for Text Alerts: text wardbridges to 8882199094
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2024 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204


You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA