I-70 over Ward Road Bridge Replacement
|
|
Weekly Traffic Impacts & Work Update
|
|
|
Weekly Traffic Impacts - May 12 to May 18
Please be advised of the following travel advisories, traffic impacts, restrictions and planned work for next week for the I-70 over Ward Road Bridge Replacement project in Wheat Ridge, Jefferson County.
|
|
Travel Advisory - May 12
Sunday, May 12 to Monday, May 13 - Westbound I-70 - Ward Road/CO 72 on ramp to westbound I-70 & various lane closures
- Starting at 7 p.m. on Sunday, May 12 and lasting until approx. 6 a.m. on Monday, May 13, the Ward Road/CO 72 (Exit 266) on ramp to westbound I-70 will be closed, with detour routes in place
- Various lane closures will also be taken on westbound I-70 within the project limits from 7 p.m. on Sunday, May 12 to 6 a.m. Monday, May 13
- The closures are necessary while crews implement a westbound I-70 traffic shift north onto the new bridge structure
- Once implemented, westbound I-70 traffic will be in its final alignment
- The recommended detour route during the ramp closure is: south on Ward Rd to W. 44th Ave., south on Youngfield St, and west to W. 40th Ave. to Clear Creek Drive to enter westbound I-70 at Exit 264 (Clear Creek Dr/32nd Ave) - please refer to the map below for details
- The detour will add approx. 2 miles and 5 minutes to travel times
- Other detour routes do exist
- Motorists can expect delays and alternate routes are advised
- Signs, message boards and construction devices will be present to alert the public to the closures and alternate routes
- Construction schedules are weather dependent and subject to change
Work includes moving temporary barrier, restriping the lanes, and realigning traffic on westbound I-70 at Ward Road.
|
|
Recommended detour route highlighted in blue during the closure of the Ward Road on ramp to westbound I-70.
|
|
Travel Advisory - May 13
Monday, May 13 to Tuesday, May 14 - Eastbound I-70 lane closures & CO 58 on and off ramp closures & single lane closure on westbound I-70
- Starting at 11 p.m. on Monday, May 13, a double right lane closure will exist on eastbound I-70 between Colorado Highway 58/Golden (Exit 265) and Ward Rd/CO 72 (Exit 266)
- The lane closures will be taken from 11 p.m. on Monday, May 13 to 5 a.m. on Tuesday, May 14
- During these closures, the eastbound I-70 off ramp to westbound CO 58 as well as the CO 58 on ramp to eastbound I-70 will be closed, with detours in place (see map below)
- The recommended detour route for CO 58 to eastbound I-70 is: head westbound on I-70 and take Exit 264; follow the detour signs on Youngfield to W. 44th Ave. to enter eastbound I-70 at the Ward Road on ramp
- The recommended detour route to westbound CO 58 from eastbound I-70 is: take Exit 264, follow Youngfield to W. 44th Ave, turn north onto Ward Road to enter the westbound I-70 on-ramp
- A single left lane closure on westbound I-70 will also be taken during this overnight period
- Flaggers, signs and barricades will be present to manage traffic flows and maintain safety
- The detours will add approx. 2 miles and 5 minutes to travel times
- Motorists can expect delays
- Alternate routes do exist
- Construction schedules are weather dependent and subject to change
Work includes removing overhead sign panels.
|
|
Location of CO 58 ramp closures to/from eastbound I-70 and detour routes.
|
|
Travel Advisory - May 14
Tuesday, May 14 to Wednesday, May 15 - Eastbound I-70 including CO 58 on and off ramps - full overnight closure
- Starting at 7 p.m. on Tuesday, May 14, a single lane closure will exist on eastbound I-70 between Clear Creek Drive/32nd Ave (Exit 264) and Ward Rd/CO 72 (Exit 266) as well as CO 58 (Exit 265) while traffic control crews place signs, barrier and construction devices
- The single lane closure will switch to a full closure of eastbound I-70 at 11 p.m. on Tuesday, May 14
- The full closure will last from 11 p.m. on Tuesday, May 14 to 5 a.m. on Wednesday, May 15
- During the six-hour closure, all eastbound I-70 traffic will be routed off the interstate at the Clear Creek Drive/32nd Ave off-ramp at Exit 264
- The eastbound I-70 off ramp to westbound CO 58 as well as the CO 58 on ramp to eastbound I-70 will also be closed, with detours in place
- The recommended detour route for eastbound I-70 through traffic is: exit Clear Creek Drive/32nd Ave (Exit 264), follow the detour signs on Youngfield St. to W. 44th Ave., and head east to enter eastbound I-70 at the Ward Road on ramp
- The recommended detour route for CO 58 to eastbound I-70 is: head westbound on I-70 and take Exit 264; follow the detour signs on Youngfield to W. 44th Ave. to enter eastbound I-70 at the Ward Road on ramp
- The recommended detour route to westbound CO 58 from eastbound I-70 is: take Exit 264, follow Youngfield to W. 44th Ave, turn north onto Ward Road to enter the westbound I-70 on-ramp
- Please refer to the map below for all detour route information
- Uniformed traffic control officers, flaggers, signs and barricades will be present to manage traffic flows and maintain safety
- Advanced warning signs and variable message boards will be posted along eastbound I-70 from the US 6 interchange to Clear Creek Drive/32nd Ave. as well as on CO 58 alerting motorists to the closure
- The detours will add approx. 2 miles and 5 minutes to travel times
- Motorists can expect delays
- Alternate routes do exist
- The closure will not impact westbound I-70
- Construction schedules are weather dependent and subject to change
Work includes setting traffic control devices and removing overhead sign bridges/supporting structures from eastbound I-70.
|
|
Detour routes highlighted in blue and purple during the full overnight closure of eastbound I-70 from 32nd Ave. to Ward Road.
|
|
Other Impacts & Planned Work
Monday, May 13 to Friday, May 17 - Eastbound I-70 at Ward Road - no planned lane closures - work performed behind barrier
- Crews will be working on grading and preparing the new eastbound I-70 onsite detour
- Work will be performed during daytime hours behind barrier, with no planned closures
- Regular daytime hours are 7 a.m. to 6 p.m. Monday to Friday
- Signs, message boards and construction devices will be present to alert the public to the closures and alternate routes
- Construction schedules are weather dependent and subject to change
Work includes grading and preparing the new eastbound I-70 onsite detour pavement.
|
|
Monday, May 13 to Friday, May 17 - Ward Road/CO 72 under I-70 - periodic daytime lane closures
- Periodic single lane closures switching to double lane closures will exist in both directions of Ward Road under I-70 during this period
- The closures will be taken from 7 a.m. to 6 p.m. Monday to Friday
- The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange)
- Flaggers will be present to manage traffic flows
- Signs, message boards and construction devices are in place alerting motorists and pedestrians to the work zone and closures
- Sidewalk access is limited and caution is advised
- Construction schedules are weather dependent and subject to chang
|
|
General Travel Impacts, Schedule & Scope of Work
- The project began in February 2023 with anticipated full completion by late 2024
- Periodic overnight lane and ramp closures will be taken in both directions of I-70 at Ward Road (Exit 266) Sunday to Thursday, during certain work activities
- Occasional full overnight closures of each direction of I-70 will be taken within the project limits for certain safety critical work activities
- Daytime single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70 Monday to Friday for access to the work zone
- These weekday closures will be in place from 7 a.m. to approx. 6 p.m.
- Some weekend work is expected, with lane closures taken in both directions of Ward Road, as needed
- Ward Road/CO 72 under I-70 will be fully closed during safety critical bridge work, with detours in place
- During full closures of Ward Road or the westbound I-70 on-ramp, motorists will be detoured to Youngfield Ave to access Exit 264 (Clear Creek Drive/32nd Ave) or the Frontage Road to access I-70 via Kipling St
- This state funded project is part of CDOT’s 10-Year Plan to replace two aging bridges on I-70 over Ward Road with a single structure
- This new structure is being built to meet today's standards to support increased traffic on the I-70 corridor
|
|
Nearby Project Impacts
Harlan St Bridge Replacement & Interchange Improvement project
- Impacts include full periodic closures of the Harlan St. interchange, the Exit 270 on and off ramps to westbound I-70, and other lane and road closures within the project's limits
- Motorists will be detoured to Wadsworth Blvd to bypass ramp closures
- This project has an estimated completion date of February 2025
|
|
|
|
|