Weekly Traffic Impacts - Sept. 3 to Sept. 9
Please be advised of the following lane closures, restrictions and planned work for next week for the I-70 over Ward Road Bridge Replacement project in Jefferson County.
*****
Travel Advisory - Wednesday, Sept. 6 to Thursday, Sept. 7
- Starting at approx. 9 p.m. on Wednesday, Sept. 6 and lasting until 6 a.m. on Thursday, Sept. 7, motorists can expect a double lane closure on eastbound I-70 between CO 58/Golden (Exit 265) and Ward Road/CO 72 (Exit 266)
- A full closure of both directions of Ward Road/CO 72 under I-70 will be in place from approx. 11 p.m. on Sept. 6 until 6 a.m. on Sept. 7
- Single lanes on Ward Road will reopen to traffic by 6 a.m., or as work progresses during the early morning hours
- The westbound I-70 Ward Road on and off ramps will remain open
- The suggested detour route to bypass the Ward Road closure to access westbound I-70 is: W. 44th Ave.to Youngfield St., and west to W. 40th Ave. to Clear Creek Drive to enter westbound I-70 at Exit 264 (Clear Creek Dr/32nd Ave) - see map below
- The detour will add approximately 2 miles and 5 minutes to travel times
- Uniformed traffic control personnel, variable message boards, signs and construction devices will be present to alert motorists to the closures
- Motorists can expect delays and alternate routes are advised
- The closures are necessary to protect the traveling public, the construction crews, and the surrounding community
- All construction schedules are weather and supply dependent and subject to change
Work includes pouring the bridge deck.
*****
Other Traffic Impacts - Sept. 5-8
Tuesday, Sept. 5 to Thursday, Sept. 7 - I-70 - intermittent overnight lane closures
- Intermittent overnight single lane closures will be taken in both directions of I-70 on Tuesday and Thursday for equipment mobilization and access to the site
- The closures will be taken from approx. 7 p.m. to 6 a.m.
- On Wednesday, Sept. 6, a double lane closure will be in place on eastbound I-70 from 9 p.m. to 6 a.m. Sept. 7 during the deck pour
- The closure limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
- Scheduled closures are weather and work dependent and subject to change
Work includes mobilizing equipment, constructing detour pavement, pouring the bridge deck, backfilling abutments and installing conduit.
*****
Tuesday, Sept. 5 to Friday, Sept. 8 - Ward Rd/CO 72 under I-70 - lane closures
- Single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70 during daytime hours Tuesday to Friday
- A full closure of Ward Rd will be in place from 11 p.m. on Wednesday, Sept. 6 to 6 a.m. on Sept. 7, with detour in place (see Travel Advisory above)
- Weekday lane closures will be in place daily from approx. 7 a.m. to 6 p.m. and as needed from 7 p.m. to 6 a.m. Tuesday to Friday
- The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange)
- Sidewalk access is limited and caution is advised
- Signs and construction devices are present to manage traffic
- All construction schedules are weather and work dependent and subject to change
Work includes constructing detour pavement, pouring the bridge deck, backfilling abutments and installing conduit.
|
|