Revised Traffic Impacts - July 30 to Aug. 5
This update replaces the one sent earlier in its entirety.
Please be advised of next week's revised traffic impacts for the I-70 over Ward Road Bridge Replacement project in Jefferson County.
*****
I-70 Closures - Tuesday, Aug. 1 to Thursday, Aug. 3
Tuesday, Aug. 1 - eastbound I-70 - early morning lane closure
- A single lane closure will be taken on eastbound I-70
- The closure will be in place from 3:30 a.m. to 6 a.m.
- The closure limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
- This scheduled closure is weather and supply dependent and subject to change
Work includes mobilizing dirt equipment into the east abutment
*****
Wednesday, Aug. 2 - eastbound I-70 - overnight lane closure
- A single left lane closure will be taken on eastbound I-70
- The closure will be in place from 7 p.m. to 6 a.m.
- The closure limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
- This scheduled closure is weather and supply dependent and subject to change
Work includes hauling dirt for abutment backfill & grading
*****
Thursday, Aug. 3 - eastbound & westbound I-70 - overnight lane closures
- A single left lane closure will be taken on both westbound and eastbound I-70
- The closures will be in place from 7 p.m. to 6 a.m.
- The closure limits are confined to Mile Point 266.5 (Exit 266 Ward Road) to MP 265 (Exit 265 CO 58/Golden)
- These scheduled closures are weather and supply dependent and subject to change
Work includes mobilizing a crane, hauling dirt and preparing crane pads.
*****
Ward Rd/CO 72 Closures - Monday, July 31 to Thursday, Aug. 3. - daytime & overnight closures
Monday, July 31 & Tuesday, Aug. 1 - both directions Ward Rd - daytime lane closures
- Daytime single lane closures switching to double lane closures will exist in both directions of Ward Road/CO 72 under I-70
- The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange)
- The closures will be in place from approximately 7 a.m. to 5 p.m.
- Sidewalk access is limited and caution is advised
- Signs and construction devices are present to manage traffic
- All construction schedules are weather and work dependent and subject to change
Work includes setting forms and rebar for abutments.
*****
Wednesday, Aug. 2 - southbound Ward Rd - early morning & overnight lane closures
- A single lane closure will exist on southbound Ward Road/CO 72 under I-70 from 4 a.m. to approx. 7 a.m.
- Double lane closures will be in place on southbound Ward Rd/CO 72 from 7 p.m. on Wednesday to 6 a.m. on Thursday
- The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange)
- Sidewalk access is limited and caution is advised
- Signs and construction devices are present to manage traffic
- All construction schedules are weather and work dependent and subject to change
Work includes pouring abutments and stripping a pier soffit.
*****
Thursday, Aug. 3 - southbound Ward Rd - overnight lane closures
- A double right lane closure will exist on southbound Ward Road/CO 72 under I-70 from 6 p.m. to approx. 7 a.m.
- The closure limits are confined to MP 0 (44th Ave) to MP .25 (just east of the I-70 interchange)
- The closures will be in place from approximately 6 p.m. to 7 a.m.
- Sidewalk access is limited and caution is advised
- Signs and construction devices are present to manage traffic
- All construction schedules are weather and work dependent and subject to change
Work includes stripping abutments.
*****
|
|