Business Center

Advertisement for Final Settlement

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Colorado Department of Transportation, at 4201 E. Arkansas Ave., Denver, Colorado, 80222, on or before 5 p.m. of the final settlement date listed.

Final Settlement FSA R100-221

PROJECT #FSA R100-221

PROJECT ID #20202

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established December 14, 2016 the date of final settlement with W.L. Contracting, Inc., in Denver, Douglas and Adams Counties. At various Denver Metro locations, furnishing and installing electrical conduit; traffic signal equipment, wiring and electrical systems; fiber optic cable, modems, termination, and splicing; pavement markings, and traffic control to complete ramp metering systems at 11 freeway entrance ramp sites.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 4201 E. Arkansas Avenue, Denver, Colorado, 80222, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

Final Settlement STR 096A-046

PROJECT #STR 096A-046

PROJECT ID #20778

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established January 2, 2017 the date of final settlement with APC Southern Construction, LLC, in Kiowa County. Work consists of structure K-25-N, patching concrete materials to repair structure.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 4201 E. Arkansas Avenue, Denver, Colorado, 80222, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

Final Settlement STA 3921-013

PROJECT #STA 3921-013

PROJECT ID #19163

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established January 4, 2017 the date of final settlement with COULSON EXCAVATING in Weld County. On SH392 Windsor to Lucerne, resurfacing and bridge rehabilitation including full depth reclamation of HMA pavement, HMA, unclassified excavation, removal of asphalt mat, aggregate base course, structure resurfacing and bridge rail, guardrail, striping, signs and seeding.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 4201 E. Arkansas Avenue, Denver, Colorado, 80222, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

FINAL SETTLEMENT SHE R100-217

NOTICE OF FINAL SETTLEMENT

PROJECT # SHE R100-217

PROJECT ID # 20144

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established June 26, 2018 as the date of final settlement with Roadside Traffic Systems, in Adams and Arapahoe Counties. On I-25 and I-70, pavement markings, remove/replace modified epoxy edge lines and preform plastic tape lane lines.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 4201 E. Arkansas Avenue, Denver, Colorado, 80222, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

FINAL SETTLEMENT CC 0341-100

NOTICE OF FINAL SETTLEMENT

PROJECT # CC 0341-100

PROJECT ID # 22349

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established June 29, 2018 as the date of final settlement with Kiewit Infrastructure, in Larimer County. On US 34: NRCS River Restoration work in the Moodie Reach and the West Drake Reach of the Big Thompson Canyon in partnership with the PR US 34 Big Thompson Canyon flood repairs.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 4201 E. Arkansas Avenue, Denver, Colorado, 80222, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

FINAL SETTLEMENT ER 0341-089

NOTICE OF FINAL SETTLEMENT

PROJECT # ER 0341-089

PROJECT ID # 21326

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established June 29, 2018 as the date of final settlement with Kiewit Infrastructure, in Larimer County. On PR US 34 Big Thompson Canyon, Phase 2: Construction of two new mainline structures as part of the PR US 34 Big Thompson Canyon project.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 4201 E. Arkansas Avenue, Denver, Colorado, 80222, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

FINAL SETTLEMENT STU 0252-399

NOTICE OF FINAL SETTLEMENT

PROJECT # STU 0252-399

PROJECT ID # 16602

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established July 9, 2018 as the date of final settlement with Interstate Highway Construction, in Douglas County. On I-25, highway reconstruction including removal of pavement, earthwork, concrete pavement, drainage, lighting, utility relocation, signing, striping, erosion control, guardrail and traffic control.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 4201 E. Arkansas Avenue, Denver, Colorado, 80222, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

FINAL SETTLEMENT STA 0703-437

NOTICE OF FINAL SETTLEMENT 

PROJECT STA 0703-437 

PROJECT ID # 21225 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established November 22, 2018 as the date of final settlement with SEMA Construction Inc., in Jefferson County. On I-70, 32nd Ave. to 44th Ave., 2” mill & SMA overlay, bridge deck rehabilitation for seven structures including class 2 & 3 repairs and waterproofing membrane, expansion joints, guardrail modification, signing and striping.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

FINAL SETTLEMENT STR 133A-046

NOTICE OF FINAL SETTLEMENT 

PROJECT STR 133A-046 

PROJECT ID # 21262 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established November 26, 2018 as the date of final settlement with Oldcastle SW Group Inc., in Delta and Gunnison Counties. On SH 133 from MP 11.43 to MP 23.8, work consists of full width cold bituminous pavement recycled, 2” overlay, shouldering, guardrail upgrades, epoxy pavement markings, mill and fill bridge work and end block modification on structures I-06-O, I-06-V, and I-07-S, fence replacement on structures I-06-O, replacement of joint gland on structure I-07-S, and mill and fill on structures I-07-P and I-07-Q. 

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation.

FINAL SETTLEMENT ER 144A-002

NOTICE OF FINAL SETTLEMENT 

PROJECT ER 144A-002 

PROJECT ID # 20254 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established November 29, 2018 as the date of final settlement with Castle Rock Construction Co., in Morgan County. On SH 144 from MP 5.08 to MP 6.65, work consists reconstructing 1.6 miles of two lane highway using Aggregate Base Course Class 6 with HMA and includes moving the alignment of the roadway away from the South Platte River.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation

FINAL SETTLEMENT NHPP 095A-019

NOTICE OF FINAL SETTLEMENT 

PROJECT NHPP 095A-019 

PROJECT ID # 21806 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established November 30, 2018 as the date of final settlement with Jalisco International Inc., in Adams and Denver Counties. On SH 95/Sheridan Boulevard from 52nd Avenue to 58th Avenue, work consists of asphalt resurfacing, traffic signal pole upgrades, roadway lighting, bridge and deck joint repair, and pedestrian curb ramp upgrades.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation.

FINAL SETTLEMENT NHPP 1602-153

NOTICE OF FINAL SETTLEMENT 

PROJECT NHPP 1602-153 

PROJECT ID # 20705 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established December 4, 2018 as the date of final settlement with A and S Construction Co., in Archuleta and Mineral Counties. On SH 160 from MP 144.29 to MP 158.56, work consists of 2.5” HMA surface treatment, planning, striping, replacing mailboxes and delineators, upgrading guardrails, bridge repairs, patching, mill and fill work, widening, geohazard/culver/ditch improvements.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation.

FINAL SETTLEMENT IM 025A-037

NOTICE OF FINAL SETTLEMENT 

PROJECT IM 025A-037 

PROJECT ID # 20964 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established December 4, 2018 as the date of final settlement with APC Southern Construction Co., in Las Animas County.  On I-25 south of Trinidad from MP 7.5 to MP 12.9, work consists of asphalt resurfacing with milling and overlay, bridge repair, guardrail improvements, weigh in motion improvements, median drainage improvements.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation.

FINAL SETTLEMENT SHE R100-246

NOTICE OF FINAL SETTLEMENT 

PROJECT SHE R100-246 

PROJECT ID # 20878 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established December 4, 2018 as the date of final settlement with WL Contractors., in Adams and Arapahoe Counties.  In Region 1 traffic signal replacement at three intersections: SH 75 & Coal Mine Avenue, I-25 County Line Road (west ramp), and I-70 & Chambers Road (north ramp).

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation.

FINAL SETTLEMENT C 113A-042

NOTICE OF FINAL SETTLEMENT 

PROJECT C 133A-042 

PROJECT ID # 20142 

In accordance with the notice provisions contained in 38‑26‑107 C.R.S. 1973 as amended, the DEPARTMENT OF TRANSPORTATION, STATE OF COLORADO has established December 6, 2018 as the date of final settlement with Anderson Drilling Inc., in Gunnison County. Gunnison County.

Claims containing a verified statement of the amounts due and unpaid must be in the form of a written affidavit and must be received by the CONTROLLER, Department of Transportation at 2829 W. Howard Place, Denver, Colorado, 80204, on or before 5:00 p.m. of the final settlement date above.

Effective July 1, 2013, Colorado Department of Transportation will no longer advertise Notice of Final Settlements in newspapers and will only post Notice of Final Settlement advertisements on CDOT’s website (https://www.codot.gov/business).

Joshua Laipply, P.E., Chief Engineer, Department of Transportation.

Colorado: The Official State Web Portal