C-3-0 Accept Weekly Payrolls (Certified Payrolls)

The C-3-0 Accept Weekly Payrolls flowchart and process guides listed on this page outlines the responsibilities of the Subrecipient Project Engineer/Project Manager and CDOT Civil Rights Business Resource Center within the certified payroll discipline area.
This is a graphic representation of the flowchart for C-3-0 Accept Weekly Payrolls. Text version available below.
Flowchart C-3-0 FTA Capital Construction: Accept Weekly Payrolls outlines the roles of the Subrecipient Project Engineer/Project Manager for accepting weekly certified payrolls and the Civil Rights Business Resource Center for conducting a quality control review. Details and information provided in this flowchart is outlined below.


Download C-3-0 Accept Weekly Payroll Flowchart

Flowchart C-3-0: FTA Capital Construction: Accept Weekly Payroll

  1. Start: The prime contractor and subcontractor enter certified payroll. Go to Flowchart 3A-0, Enter Certified Payroll and Prime Approver Role.
  2. Once the certified payroll has been entered for the prime contractor and subcontractors, the prime approver for the prime contractor approves the weekly certified payroll. Go to Flowchart 3A-0, Enter Certified Payroll and Prime Approver Role.
  3. The Subrecipient Project Engineer/Project Manager reviews the certified payroll (Figure 3-1).
  4. Decision Item: Is the certified payroll compliant?
    1. If yes, the Subrecipient Project Engineer/Project Manager continues to step 5.
    2. If no, the Subrecipient Project Engineer/Project Manager continues to step 6.
  5. The Subrecipient Project Engineer/Project Manager accepts the certified payroll in LCPtracker (Figure 3-3).
  6. The Subrecipient Project Engineer/Project Manager rejects the certified payroll in LCPtracker (Figure 3-2).
  7. The Civil Rights Business Resource Center performs a quality control review of the certified payrolls (Figure 3-4).
  8. The process ends.

Process Guides

Graphic representation of a work vest Subrecipient Project Engineer/Project Manager

Graphic representation of a clipboard CDOT Civil Rights Business Resource Center

  • 3-4 This process guide is for the use of the Civil Rights Business Resource Center