Summit County — After a successful first part of the construction season, the Colorado Department of Transportation with contractor Zak Dirt will begin phase two of the I-70 Exit 203 Interchange in Frisco project starting this week. As part of this phase, traffic on CO 9 will shift onto the new underpass bridge deck, which was built and poured in phase one of the project.
The I-70 Exit 203 Interchange Project began this spring and reconfigures CO 9, Lusher Court and Dillon Dam Road. The project aims to reduce congestion, improve safety and add bicycle and pedestrian connections in the area.
"Reaching phase two on schedule is a significant milestone for this two-year project," said CDOT Region 3 Transportation Director Jason Smith. "We know construction isn't easy on the traveling public—especially those who pass through this area frequently—but as one of the major gateways into Summit County, this corridor will ultimately offer a safer, smoother experience for drivers, bicyclists, and pedestrians alike."
During phase one, crews focused on the new CO 9 underpass bridge, creating a frontage road that will link Dillon Dam Road and Lusher Court in 2027. Crews installed the bridge’s foundations, girders, deck, wing walls and adjacent retaining walls. Crews have also made stormwater drainage improvements throughout the project, replaced the sanitary sewer between Dillon Dam Road and CO 9, and begun foundation work for widening the existing I-70 bridge at Exit 203.
Phase 2 Traffic Impacts
- During the second phase, a temporary traffic switch will occur at the interchange of I-70, CO 9 and Dillon Dam Road using the recently constructed bridge deck
- Work is expected to occur Monday through Saturday from 7 a.m. to 7 p.m. with occasional weekend work.
- Single and double lane closures are expected on both I-70 and CO 9 during nighttime hours from 7 p.m. to 7 a.m.
- Single and double lane closures are expected on both I-70 and CO 9
Exit 203 Interchange Project Benefits
- Mobility: Interchange improvements will reduce travel delays caused by crashes and congestion for all users, including the freight industry and guests.
- Safety: The project will increase traveler safety for multimodal users, including new bicycle and pedestrian connections across CO 9 and I-70.
Project Information
For additional information about this project:
- Call the project information line at 970-817-8647
- Email the project team at: [email protected]
- Visit the project website at: codot.gov/projects/i70exit203interchangefrisco
Know Before You Go
Travelers are urged to “know before you go.” Gather information about weather forecasts and anticipated travel impacts and current road conditions prior to hitting the road. CDOT resources include:
- Road conditions and travel information: COtrip.org
- Download the COtrip Planner app: bit.ly/COtripapp
- Sign up for project or travel alerts: bit.ly/COnewsalerts
- Check scheduled construction lane closures: bit.ly/laneclosures
- Connect with @ColoradoDOT on social media: X, Facebook, Instagram and YouTube
Remember: Slow For The Cone Zone
The following tips are to help you stay safe while traveling through maintenance and construction work zones.
- Do not speed in work zones. Obey the posted speed limits.
- Stay Alert! Expect the unexpected.
- Watch for workers. Drive with caution.
- Don't change lanes unnecessarily.
- Avoid using mobile devices such as phones while driving in work zones.
- Turn on headlights so that workers and other drivers can see you.
- Be especially alert at night while driving in work zones.
- Expect delays, especially during peak travel times.
- Allow ample space between you and the car in front of you.
- Anticipate lane shifts and merge when directed to do so.
- Be patient!
Download the COtrip App!
The new free COtrip Planner mobile app was designed to meet the growing trend of information on mobile and tablet devices for the traveling public. The COtrip Planner app provides statewide, real-time traffic information, and works on mobile devices that operate on the iOS and Android platforms. Visit the Google Play Store (Android devices) or the Apple Store (iOS devices) to download!