Procurement Schedule
Updated August 6, 2015
- Issue Request for LOIs: January 8, 2015
- Issue RFQ: February 26, 2015
- Project briefing meetings: March 16 - March 27, 2015
- Deadline for industry inquiries to RFQ: March 31, 2015
- CDOT responses to industry RFQ inquiries: April 3, 2015
- Final RFQ addendum issued: April 9, 2015
- SOQ due date: April 23, 2015
- Notify short-listed submitters: June 4, 2015
- Debrief RFQ submitters: by request and appointment
- Issue Draft RFP: August 31, 2015
- Final RFP: November 30, 2015
- Design-Build Team Selection: April 2016
- Construction: Summer 2016