Bridge Construction Updates
US 36 BRIDGE OVER LOWELL BOULEVARD SCHEDULE
- February-June 2014 – Completed
SHERIDAN BRIDGE SCHEDULE
- February-September 2014 – Completed
BNSF BRIDGE SCHEDULE
- July 2014-March 2015 - Completed
US 36 BRIDGE OVER PROMENADE SCHEDULE
- July-March 2015 - Completed
WADSWORTH PARKWAY AND UPTOWN AVENUE BRIDGE SCHEDULES
December 2013-April 2014
- Aesthetics - Completed
- Structural Concrete Coating - Completed