US 24 west of Limon
-
39.2583098225 -103.728103638
Project Owner | CDOT |
CDOT Region | 1 |
County | Elbert |
Description of Work | Resurfaces 10.8 miles of US 24 in asphalt. |
Estimated Total Project Cost | $6,851,078 |
ARRA Funds | $6,717,078 |
Project Status | Completed |
Start Date | May 2010 |
Completion Date | August 2010 |
Percentage Spent | N/A |
Contractor | APC Southern Construction Co. |