Overview
-
39.5520374016 -106.135568619
Description of Work | Resurfaces 14 miles of I-70 from milepost 190 to 204 as well as the right lane of eastbound I-70 between milepost 180 and 190. Numerous bridges along the I-70 corridor will also be rehabilitated by repairing expansion joints and bridge decks. |
Project Owner | CDOT |
CDOT Region | 1 |
County | Eagle and Summit |
Estimated Total Project Cost | $10,068,510 |
ARRA Funds | $8,000,000 |
Project Status | Completed |
Start Date | June 1, 2009 |
Completion Date | Summer 2010 |
Percentage Spent | N/A |
Contractor | Asphalt Paving Co. |