I-70 West, Truck Parking Management
-
39.6460146605 -107.072753906
Project Owner | CDOT |
CDOT Region | 1 |
County | Clear Creek and Eagle |
Description of Work | Installs various truck parking management components (electronic signs, closed-circuit cameras, power and communications systems), as identified in the I-70 Mountain Corridor PEIS, to provide notification during inclement weather. |
Estimated Total Project Cost | $2,048,253 |
ARRA Funds | $2,014,973 |
Project Status | Completed |
Start Date | August 10, 2009 |
Completion Date | March 2010 |
Percentage Spent | N/A |
Contractor | Sturgeon Electric Co. |