CO 1 Resurfacing in Wellington

Project Facts

  • Cost: $300,000
  • Contractor: Martin Marietta
  • Timeline: August 11-23, 2019
  • Location: CO 1 in Wellington between 1st St and 6th St

Crews on this project have completed the resurfacing of Colorado Highway 1 between 1st and 6th streets in Wellington. Crews began at the railroad crossing west of 1st Street and continued east to 6th Street. The project team estimated the work would take two weeks to complete.

This project will include:

  • milling the roadway surface
  • paving
  • final striping

Schedule & Travel Impacts

  • No further traffic impacts