Project Facts

  • Cost: $2.3 million
  • Contractor: Simon Contractors
  • Timeline: May - October 2018
  • Location: Work extends from mile points 50.6 to 54.4 on CO 138, with bridge work taking place around mile point 50.7

Starting Monday, May 21, crews on this project began replacing a bridge on Colorado Highway 138 in Ovid, Colorado, in Sedgwick County—just south of the Nebraska border.

Other work includes:

  • paving the highway;
  • upgrading curb ramps to comply with current Americans with Disabilities Act (ADA) standards; and
  • grading channels near the bridge, and repairing erosion-prevention material (aka, riprap).