CO 145 Curb Ramp Upgrades in Downtown Dolores

Project Facts

  • Cost: $797,000
  • Contractor(s): Medved Global
  • Timeline: April - June 2018
  • Location: CO 145 in downtown Dolores, where the highway meets 2nd through 8th streets, and 14th and 19th streets

Crews on this project upgraded curb ramps at eight locations along Colorado Highway 145 in southern downtown Dolores to best serve accessibility needs.

The new ramps are located where CO 145 meets 2nd through 8th streets, and 14th and 19th streets.

This project was among the first in a larger statewide initiative to improve all curb ramps that CDOT maintains by bringing them up to current Americans With Disabilities Act (ADA) standards.