Project Facts

  • Cost: $2.1 million

Project Team

  • Contractor(s):
    Oldcastle Southwest Group
    Four Corners Materials

From Monday, April 3, through May 24, 2017, crews treated the surface of Colorado Highway (CO) 41 near the Four Corners area. The project is scheduled for completion by May 24, 2017.

The two-month project extended from the US Highway 160 to the CO 41 junction, and continued on CO 41 for approximately nine and a half miles to the Utah state line. Construction included an asphalt-leveling course, followed by a double chip seal surface treatment of the roadway.

Other work:

  • Fresh highway striping
  • Installation of new guardrails in some areas along CO 41

The maintenance work will help improve and prolong the life of the roadway.