CO 9 (Summit Boulevard) Resurfacing in Frisco from I-70 to Main Street

Project Facts

  • Cost: $3.3 million
  • Contractor(s): A & S Construction
  • Timeline: April - September 2018
  • Location: On CO 9 in Frisco, between I-70 and Main Street
March 2018 - Southbound CO 9 Before

Crews on this project have resurfaced an approximate one-mile stretch of Colorado Highway 9 (aka, Summit Boulevard) in Frisco, between I-70 and Main Street. All work was completed in September 2018.

Other work included:

  • reconstructing concrete curb ramps to meet Americans with Disabilities Act (ADA) requirements.
  • repairing concrete on the westbound I-70 roundabout truck apron, and the bridge over I-70.
  • upgrading traffic-signal systems.