CO 47 Microsurfacing in Pueblo
Project complete
            
          About the Project:
Work will take place along Colorado Highway 47 in the northeast area of the City of Pueblo from Mile Point 0 to MP 3. Work will primarily consist of microsurfacing, which is a protective, thin and tough layer of asphalt blended with a finely crushed stone to make a seal coat.
Project Benefits
- Improve and prolong the life of the road surface
 - Smooth road or highway has many important benefits including safety and improved quality for driving experience
 - Cost-effective method to renew the road surface and seal minor cracks and other irregularities
 
Work Schedule:
- Work will last approximately one month
 - Working hours are Sunday through Thursday from 7 p.m. to 6 a.m.
 
Traffic Impacts:
Motorists can expect the following impacts during the period of construction:
- Vehicles will be reduced to a single-lane, alternating traffic intermittently in either direction, throughout the duration of the project
 - Lane closures, guided by flaggers and pilot cars, will have up to five-minute delays
 - The speed limit will be reduced to 55 mph through the work zone
 - There is a 12-foot lane width restriction in place throughout the duration of the project
 - Refer to COtrip.org for real-time travel conditions and road closures
 
Project Facts
- Construction Cost: $1.85 million
 - Contractor: Intermountain Slurry
 - Timeline: June to July 2024
 - Location: CO 47 
- Nearest Town/City: Pueblo
 - Mile Point(s): 0 to 3
 - County: Pueblo
 
 