Denver Metro Wall Repairs

Denver Wall Repairs Logo

Project Facts

Project Team

  • Contractor(s): Hamilton Construction Company

Project Cost

  • $500,000
I-70 Carr Street MSE Wall Damage

Between February and May 2017, crews repaired damaged retaining and sound walls at nine locations throughout the Denver metropolitan area. Repairs ranged from replacing damaged blocks to culvert cleaning to concrete patching.

The most extensive work occurred at Interstate 70 and Carr Street; the Regional Transportation District Nine Mile Station; and US Highway 287 and Emma Street.

The following locations were repaired as part of this project:

Location

I-70/Carr Street (two sites)
I-25/76th Avenue
US 36/Broadway
I-25/Broadway
Parker Road/Hampden Avenue
RTD Nine Mile Station
I-225/Parker Road
I-25/University Boulevard
US 287/Emma Street (two sites)