I-225 Resurfacing from I-25 to Parker Road
Project Facts
- Goal: Make the road safer by providing a new surface, and upgrading infrastructure to current standards.
- Location: On I-225 from I-25 to Parker Road (mile points 0.38 to 3.85)
- Cost: $9.7 million
- Timeline: June - October 2019
- Contractor: Brannan Sand & Gravel
- Work hours: 8 p.m. - 5:30 a.m., Sunday - Thursday

Crews on this project will resurface I-225 from I-25 to Parker Road. Work will also include:
- upgrading curb ramps to current Americans With Disabilities Act (ADA) standards;
- repairing bridge decks;
- repairing guardrail; and
- replacing overhead signs.