I-70 Eagle Vail Bridges
Project complete
Project Facts
- Cost:
$8.1 million - Average Annual Daily Traffic:
11,000
Project Team
- Contractor(s): Structures, Inc.
Project Overview
Crews on this project repaired and retrofitted bridge joints, the bridge deck, and 600 bridge cracks. They also performed scour mitigation and paved the bridge's deck.
This work will add an estimated 30 years of durability to these bridges.
Construction, which started in April 2016, was scheduled to be complete in July 2016. Work took place five to seven days and nights each week.